OKI PULP & PAPER MILL PROJECT

SUMMARY WEEKLY
Dicipline : Civil Company Name : PT. Kotaminyak Internusa Attachment Target or Plan
Mechanical Area Code : Drawings Plan : 4902
Electrical Contractor Supv : Inspection / Join Survey Actual : 1125
Instrumen OKI Suprv/ PIC : Other Balance : 3777
Date : 06 Juli 2018 : % Target : 20.53%
:

Manpower Total Progress Mei 2018


Quantity Boq Progress
Item Description Unit Boq Remarks
Last Week This Week Up to date Factor Last Week This Week Up to date % Progress

Project Manager I. EXTERNAL LIGHTNING PROTECTION SYSTEM

Site Manager 1 Eritech System 3000 Dynasphere Ea 30 13.00% 7 0 7 3.03%

Project Control 2 Upper Termination Kit Ea 34 4.50% 7 0 7 0.93%

Drafter 3 Ericore Double Shielded Down Conductor Meter 1820 28.60% 326 0 326 5.12%

HSE Project 4 Mast, FRP, Insul, 2M, 60mm OD, Black Ea 34 3.00% 7 0 7 0.62%

Admin 5 Inline Coupling Ea 33 1.80% 7 0 7 0.38%

Kepala Kerja 6 Lower Termination Kit Ea 34 0.60% 7 0 7 0.12%


Total 0 0 0 7 SS Cable Ties for Conductive Cable Clamp Ea 1620 0.80% 315 0 315 0.16%
8 Digital Lightning Event Counter Ea 30 2.90% 7 0 7 0.68%
9 Terminal Box FRP Ea 39 2.10% 7 0 7 0.38%
10 Pipe Support 2" HDG (3M length) Ea 35 0.40% 7 0 7 0.08%
11 Bracket Support, Clamp Support & Accessories Set 33 1.30% 7 0 7 0.28%
12 Accessories & Consumable Lot 30 1.50% 7 0 7 0.35%

II. UPGRADE GROUNDING SYSTEM


13 Coper Bonded, Ground Rod, 5/8" x 10', UL Listed c/w Coupling Ea 102 0.80% 53 0 53 0.42%
14 Ground Clamp Two Hole Cable to Rod c/w SS U Bolt Nut & Washer Ea 92 0.70% 45 0 45 0.34%
15 Cable BC 70mm² Meter 695 1.30% 250 0 250 0.47%
16 Cable NYA 120mm² Meter 121 0.50% 30 0 30 0.12%
17 Grounding Termination Busbar 300x50x6 thickness Copper Ea 39 0.50% 13 0 13 0.17%
18 Ground Inspection Pit 450x450x450 Ea 34 0.50% 14 0 14 0.21%
19 Tower Tripole with Height 20M Set 8 6.70% 1 0 1 0.84%

III. INSTALLATION COST


20 Installation for Lightning & Grounding Protection Lot 39 28.50% 8 0 8 5.85%

Grand Total 4902 100% 1125 0 1125 20.53%

Plant This Week Plant Next Week


S- CURVE
Description Description

OKI PULP & PAPER Lightning Arrester ERICO


120

100

80
Prosentase

60

40

20

0
Weekly 1 Weekly 2 Weekly 3 Weekly 4 Weekly 5 Weekly 6 Weekly 7 Weekly 8 Weekly 9
Progress % 0.00 2.39 12.39 20.53 20.53 20.53 20.53 20.53
Balance % 100 97.61 87.61 79.47 79.47 79.47 79.47 79.47
Target % 100 100 100 100 100 100 100 100