Assignment 3 – Collecting & Distribution of water and Pumps

1. For the distribution network shown below determine the flow in each pipe
and the pressure at A.
    300m
  Elev.
  Pipe Diam.,mm Length,m
15m3/min 3
5m /min P-8 P- 1 355 1000
P-2 P-5 P- 2 405 2000
250m elev.
    P- 3 305 2000
    P- 4 205 1000
P-1 P-4 P-7 P- 5 405 2000
    P- 6 205 2000
3
5m /min 10m3/min 5m3/min P- 7 205 1000
    P- 8 300 150
P-3 P-6

Solution:

o Assume the discharge in each pipe and C = 100, n=1.85, for Hazen William’s Eqn.

    300m
  Elev.
 
15m3/min 5m3/min 10

 
250m elev.
5 5
+ +
10 5 15
LOOp 1 LOOP 2
3
5m /min 10m3/min 5m3/min
5 10

1
 Q  0.54
From Hazen Williams Equation, Head Loss is given by: hf  L 2.63 
 0.278CD 
The Correction factor for each loop is given by:

 hf
Q  
hf
n
QO
Water Supply and urban Drainage Assignments

First Trial

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-1 355 1000 - 10 -11.90 1.19 -7.34  70.03
Loop Pipe 5 D,mm 3.47 L ,m 0.69 Q,m3/min7.66 hf, mQ   hf /Q Q + ∆Q
I P-2 405 2000 1.85 * 14.20
First try P-3 305 2000 P - 4- 5 205 -13.81 1000 2.76 2.34 -2.34 11.71 5.01 3 -3.74
Q  2.6657m / min .
P-4 205 II1000 P - 5- 5 405 -47.79 2000 9.56 5 -2.34 3.47 0.69 -1.08
First try P-6 Σ 205 -70.03 2000 14.20 10 345.04 34.50 3.92
P-7 205 1000 15 365.54 24.37 8.92
Σ 725.76 64.57

725.16
Q  
1.85 * 64.57
Second Trial
Q  6.0706 m 3 / min .

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-1 355 1000 - 7.34 -6.71 0.91 -8.61 25.47
3
Q  
I P-2 405 Loop
2000 Pipe7.66 D,mm 7.64 L ,m Q,m /min6.39 hf, m
1.00 1h.f85
/Q * 10.82
Q + ∆Q
second try P-3 305 2000 P --42.34 205 -3.38 1000 1.45 -2.47 -3.61 -12.95 5.24
Q  1.272m / min
3 -5.24.
P-4 205 II1000 P - 53.74 405 27.92 2000 7.46 -1.08 2.47 -0.20 0.19 -3.85
second try P-6
Σ 205 25.47 2000
10.82
3.92 60.91 15.54 1.15
P-7 205 1000 8.92 139.61 15.65 6.15
Σ 187.37 36.62

187.37
Q  
1.85 * 36.62
Q  2.7657m 3 / min .

Third Trial

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-1 355 1000 - 8.61 -9.02 1.05 -10.20
I P-2 405 2000 6.39 5.46 0.86 4.80 41.02
Q  
Third try P-3 305 2000 - 3.61 -7.55 2.09 -5.20 1.85 * 13.94
P-4 205 1000 5.24 52.13 9.95 3.65 Q  1.5906m 3 / min .
Σ 41.02 13.94

Instructor: Zerihun Alemayehu 2


Water Supply and urban Drainage Assignments

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-4 205 1000 -3.65 -26.68 7.31 -4.69 47.59
P-5 405 2000 -3.85 -2.14 0.56 -4.89
Q  
II 1.85 * 24.74
Third try P-6 205 2000 1.15 6.29 5.47 0.11 Q  1.0398m3 / min .
P-7 205 1000 6.15 70.12 11.40 5.11
Σ 47.59 24.74

Fourth Trial

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-1 355 1000 - 10.20 -12.34 1.21 -10.92
I P-2 405 2000 4.8 3.22 0.67 4.08 18.48
Q  
fourth try P-3 305 2000 - 5.20 -14.85 2.85 -5.92 1.85 *13.79
P-4 205 1000 4.69 42.45 9.05 3.97 Q  0.7244m 3 / min .
Σ 18.48 13.79

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-4 205 1000 -3.97 -31.18 7.85 -4.41
II P-5 405 2000 -4.89 -3.33 0.68 -5.33 15.33
Q  
fourth try P-6 205 2000 0.11 0.08 0.74 -0.33 1.85 * 19.01
P-7 205 1000 5.11 49.76 9.74 4.67 Q  0.4359m 3 / min .
Σ 15.33 19.01

Fifth Trial

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-1 355 1000 - 10.92 -14.00 1.28 -11.21 7.38
P-2 405 2000 4.08 2.38 0.58 3.79 Q  
I 1.85 * 13.64
fifth try P-3 305 2000 - 5.92 -18.87 3.19 -6.21
Q  0.2925m 3 / min .
P-4 205 1000 4.41 37.88 8.59 4.12
Σ 7.38 13.64

Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q Q + ∆Q


P-4 205 1000 -4.12 -33.40 8.11 -4.24
4.28
II P-5 405 2000 -5.33 -3.90 0.73 -5.44 Q  
1.85 * 19.73
fifth try P-6 205 2000 -0.33 -0.61 1.87 -0.44
Q  0.1173m 3 / min .
P-7 205 1000 4.67 42.19 9.03 4.56
Σ 4.28 19.73

Instructor: Zerihun Alemayehu 3


Water Supply and urban Drainage Assignments

Six Trial

Q + ∆Q
Loop Pipe D,mm L ,m Q,m3/min hf, m hf /Q
P-1 355 1000 -11.21 -14.70 1.31 -11.29 1.95
Q  
I P-2 405 2000 3.79 2.07 0.55 3.71 1.85 * 13.49
Six try P-3 305 2000 -6.21 -20.64 3.32 -6.29 Q  0.07814m 3 / min .
P-4 205 1000 4.24 35.22 8.31 4.16 ( negligible)
Σ 1.95 13.49

Q + ∆Q 1.11
Loop Pipe D,m L ,m Q,m3/min hf, m hf /Q Q  
P-4 205 1000 -4.16 -34.00 8.17 -4.18 1.85 * 20.18
II P-5 405 2000 -5.44 -4.06 0.75 -5.47 Q  0.02973m 3 / min .
Six try P-6 205 2000 -0.44 -1.08 2.43 -0.47 ( negligible)
P-7 205 1000 4.56 40.25 8.83 4.53
Σ 1.11 20.18

Final Solution

    300m
  Elev.
15m3/min 5m3/min 10

P-2 P-5 Pipe Q M3/min.


250m elev.
3.71 5.47 P-1 -11.29
 +  + + P-2 3.71
+
P-1 P-4 4.53 P-3 -6.29
11.29
+4.18 P-7
LOOp +1 LOOP 2 P-4 -4.19
3 3 3
5m /min + 10m /min 5m /min P-5 -5.47
6.29+ 0.47 P-6 -0.47
P-3 P-6
P-7 4.53

Head Loss in

o Pipe P – 8 [Q = 10m3/min]
1 1
 Q  0.54  10  0.54
hf  L 2.63 
 150 *  2.63 
 4.05m
 0.278CD   60 * 0.278 * 100 * 0.3 

Instructor: Zerihun Alemayehu 4


Water Supply and urban Drainage Assignments

o Pipe P – 5 [Q = 5.47m3/min]
1 1
 Q  0.54  5.47  0.54
h f  L 2.63 
 2000 *  2.63 
 17.67m
 0.278CD   60 * 0.278 * 100 * 0.3 

o Pipe P - 4[Q = 4.19m3/min]


1 1
 Q  0.54  4.19  0.54
h f  L 2.63 
 1000 *  2.63 
 5.39m
 0. 278CD   60 * 0 .278 * 100 * 0 . 3 

o Pressure on point C

PC  Elev. Re s.  Elev.C  h f P 8  300  250  4.05  45.95m


o Pressure on point B [Assume that all pipe junctions are on the same elevation]

PB  PC  h f P 5  45.95  17.67  28.28m

o Pressure on point A

PA  PB  h fP  4  28.28  5.39  22.89m  Ans.

2. The hourly water demands of a certain community on the day of maximum demand are given in
table 4.fire flow requirement is 1360m3/hr for 6
Time Demand,m3/hr Time Demand,m3/hr
hrs with 450m3/hr from the storage facility. The
0 Midnight 0 1 P.M 484
emergency reserve to compensate for power
1 A.M 197 2 493
failures and other operational problem is
2 197 3 529
3 136 4 522 assumed to be 25% of the total required
4 144 5 622 storage. Calculate the total required storage if
5 227 6 697 pumping period lasts for (a)24 hours and (b) 8
6 302 7 756 hours from midnight to 8A.M.
7 416 8 606
8 584 9 454 Solution:
9 568 10 302
a) Pumping period lasts for 24 hours
10 486 11 266
11 472 0 MN 212 10165
uniformPum pingrate   423.54m 3 per / hr
12 Noon 493 24
Volume of storage = 1345.78 + 490.66 =1836.44m3
Total Required storage = 1836.44 + 0.25*1836.44 + (6*450) =4995.55m3

For 8 hr uniform pumping


For 24 hr uniform pumping [from Midnight to 8AM]  
 
Cumulative Pumping Cumulative Pumping Cumulative  
Time Demand,m3 demand Rate,m3 Pumping ,m3   Rate,m3 Pumping ,m3

Instructor: Zerihun Alemayehu 5


Water Supply and urban Drainage Assignments

Col 6 = Col 9 = (col


col.1 col.2 col.3 col.4 col.5 (col 5-col3) col.7 col.8 8-col3)
0 Midnight 0 0 0 0 0 0 0 0
1 A.M 197 197 423.54 423.54 226.54 1270.63 1270.625 1073.625
2 197 394 423.54 847.08 453.08 1270.63 2541.25 2147.25
3 136 530 423.54 1270.62 740.62 1270.63 3811.875 3281.875
4 144 674 423.54 1694.16 1020.16 1270.63 5082.5 4408.5
5 227 901 423.54 2117.7 1216.7 1270.63 6353.125 5452.125
6 302 1203 423.54 2541.24 1338.24 1270.63 7623.75 6420.75
7 416 1619 423.54 2964.78 1345.78 1270.63 8894.375 7275.375
8 584 2203 423.54 3388.32 1185.32 1270.63 10165 7962
9 568 2771 423.54 3811.86 1040.86 0 10165 7394
10 486 3257 423.54 4235.4 978.4 0 10165 6908
11 472 3729 423.54 4658.94 929.94 0 10165 6436
12 Noon 493 4222 423.54 5082.48 860.48 0 10165 5943
1 P.M 484 4706 423.54 5506.02 800.02 0 10165 5459
2 493 5199 423.54 5929.56 730.56 0 10165 4966
3 529 5728 423.54 6353.1 625.1 0 10165 4437
4 522 6250 423.54 6776.64 526.64 0 10165 3915
5 622 6872 423.54 7200.18 328.18 0 10165 3293
6 697 7569 423.54 7623.72 54.72 0 10165 2596
7 756 8325 423.54 8047.26 -277.74 0 10165 1840
8 606 8931 423.54 8470.8 -460.2 0 10165 1234
9 454 9385 423.54 8894.34 -490.66 0 10165 780
10 302 9687 423.54 9317.88 -369.12 0 10165 478
11 266 9953 423.54 9741.42 -211.58 0 10165 212
0 MN 212 10165 423.54 10164.96 -0.04 0 10165 0

b) Pumping period lasts 8 hours from midnight to 8A.M.

10165
Pumpingrate   1270.625m 3 per1hr
8

Storagerequired  7962m 3

Emergencyrequ.  0.25 * 7962m 3 / hr  1990.5m 3

Firerequir ement  6 * 450m 3 / hr  2700m 3

Total Requirement = 7962 + 1990.5 + 2700

= 12,652.5 m3
Instructor: Zerihun Alemayehu 6
Water Supply and urban Drainage Assignments

3. A small town with a design population of 1600 is to be supplied water at


150liters per capita per day. The demand of water during different periods is
given in the following table:
Time(hr) 0-3 3-6 6-9 9-12 12-15 15-18 18-21 21-24
Demand(1000liters) 20 25 30 50 35 30 25 25

a) Determine the capacity of a service reservoir if pumping is done 24 hours at constant rate.

b) Eight hours from 8 hrs to 16 hrs.

c) Eight hrs from 4 hrs to 8 hrs and again 16 hours to 20hrs.

Solution: [Assume 25% emergency requirement]

Qday-avg. = 1600 * 150 = 240000 liters/day

a) The capacity of service reservoir if pumping is done 24 hrs at constant rate

Time(hr) Row 1 0-3 3-6 6-9 9-12 12-15 15-18 18-21 21-24
Demand(1000liters) Row 2 20 25 30 50 35 30 25 25
Cum.Demand(1000liters) Row 3 20 45 75 125 160 190 215 240
Pumping rate(1000liters) Row 4 30 30 30 30 30 30 30 30
Cum.Pumping rate(1000liters) Row 5 30 60 90 120 150 180 210 240
Row 6=
  R(5)-R(3) 10 15 15 -5 -10 -10 -5 0

Volume of storage = 15 + 10 =25*103m3

Service reservoir = 25,000 + 0.25*25,000 = 31,250Litres

b) Eight hours from 8hrs to 16hrs


240,000liters
Pumpingrate   30,000liters * 4hr  120,000literesper 4hrs
8hr
Time(hr) 0-4 4-8 8 - 12 12 - 16 16 - 20 20 - 24 Total
Demand(1000liters) 28.33 36.67 60 45 36.67 33.33 240
Pumping rate(1000liters) 0 0 120 120 0 0 240
Excess m3(1000liters)     60 75     135

Service reservoir = 135,000 + 0.25*135,000 = 168,750Litres/hr

c) Eight hours from 4 hrs to 8hrs and again 16hrs to 20hrs

Time(hr) 0-4 4-8 8 - 12 12 - 16 16 - 20 20 - 24 Total


Demand(1000liters) 28.33 36.67 60 45 36.67 33.33 240
Pumping rate(1000liters) 0 120 0 0 120 0 240

Instructor: Zerihun Alemayehu 7


Water Supply and urban Drainage Assignments

Excess m3(1000liters)    83.33  83.33   166.66

Service reservoir = 166,660 + 0.25*166,660 = 208,325Litres/hr

4. Find the flow distribution in the gravity supply system through the following
pipe network shown below. use Hazen-Williams formula(c=100).if the
pressure at point A is 490.5Kpa.find the pressure at points B and C.assume all
pipe junctions are at the same elevation.
250 l/s

F 2000m A 2000m
45 l/s 250mm 250mm B
  45 l/s
   
1000m 1000m 1000m
200mm 250mm 200mm
   
   
   
2000m 2000m C
E 150mm D 100mm
40 l/s 80 l/s 40 l/s

Given: C = 100, PA=490.5 kpa

Required: Flow distribution and the pressure at point B and C

Solution: [n=1.85, for Hazen William’s Equation]

o Assume the discharge in each pipe

250 l/s

F 250mm,2000m A 250mm, 2000m


45 l/s 75 75 B
  45 l/s
  + +
1000m 100 1000m 30 1000m
200mm 30 250mm 200mm
   
Loop 1 Loop 2
   
10 10 C

Instructor: Zerihun Alemayehu 8


Water Supply and urban Drainage Assignments

E 150mm,2000m D 100mm,2000m
40 l/s 80 l/s 40 l/s

First trial

Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q


 3.93
AF 250 2000 - 75 -29.92 0.40 -73.81 Q  
I 1.85 * 1.79
FE 200 1000
Loop - 30Pipe -8.13
D,mm 0.27
L ,m -28.81
Q,L/sec h,m hf /Q Q + ∆Q
First try Q f 1.1868L / sec .
DE 150 2000 10AD 8.63250 0.86
1000 11.19
-101.19 -26.05 0.26 -97.39
AD 250 1000II 100AB 25.48250 0.25
2000 101.1975 29.92 0.40 78.80
First try BCΣ -3.93200 1000
1.79 30 8.13 0.27 33.80
DC 100 2000 -10 -62.16 6.22 -6.20
Σ -50.17 7.14
Second trial  50.17
Q  
1.85 * 7.14
Q  3.7982 L / sec .
Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q  1.70
Q  
AF 250 2000 -73.81 -29.04 0.39 -73.32 1.85 * 1.85
I FE 200 1000 -28.81 -7.54 0.26 -28.32 Q  0.4967 L / sec .
Second try DE 150 2000 11.19 10.62 0.95 11.68
AD 250 1000 97.39 24.26 0.25 97.88
Σ -1.70 1.85

Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q


AD 250 1000 -97.88 -24.49 0.25 -97.11  7.26
Q  
II AB 250 2000 78.80 32.78 0.42 79.56 1.85 * 5.11
Second try BC 200 1000 33.80 10.13 0.30 34.56 Q  0.7679 L / sec .
DC 100 2000 -6.20 -25.68 4.14 -5.44
Σ -7.26 5.11

Third trial

Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q  0.34


Q  
AF 250 2000 -73.32 -28.68 0.39 -73.22 1.85 * 1.88
FE 200 1000 -28.32 -7.30 0.26 -28.22 Q  0.0978L / sec .
I Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q
Third try DE 150 2000 11.68 11.51 0.99 11.78
AD 250 1000 -97.21 -24.18 0.25 -97.17
AD 250 1000II 97.11
AB 24.14
250 0.252000 97.21
79.56 33.38 0.42 79.60
Third try Σ
BC 200
-0.34 1.881000 34.56 10.56 0.31 34.60
DC 100 2000 -5.44 -20.10 3.70 -5.40
Σ -0.35 4.67

 0.35
Q  
1.85 * 4.67
Q  0.0405L / sec .
Instructor: Zerihun Alemayehu 9
Water Supply and urban Drainage Assignments

Fourth trial

Loop Pipe D,mm L ,m Q,L/sec hf, m hf /Q Q + ∆Q  0.02


AF 250 2000 -73.22 -28.61 0.39 -73.21 Q  
1.85 * 1.89
FE 200 1000 -28.22 -7.26 0.26 -28.21
Q,L/sec
I
fourth try
Loop Pipe D,mm L ,m Qhf , m0.00572
hf /Q
L / sec .Q + ∆Q
DE 150 2000 11.78
AD 11.69
250 0.991000 11.79
-97.17 -24.16 0.25 -97.17
AD 250 1000II 97.17 24.16 0.25 97.17
 negligible
AB 250 2000 79.60 33.41 0.42 79.60
fourth try Σ
BC 200
-0.02 1.891000 34.60 10.59 0.31 34.60
DC 100 2000 -5.40 -19.83 3.68 -5.40
0.00 Σ 0.00 4.65
Q  
1.85 * 4.65
Q  0.00

Final Solution
250 l/s

F 250mm,2000m A 250mm, 2000m Pipe Q,L/sec.


45 l/s 73.21 79.60 B AF -73.21
  45 l/s FE -28.21
 
+ + DE 11.79
1000m 97.19 1000m 34.60 1000m AD -97.19
200mm 28.21 250mm 200mm AB 79.60
    BC 34.60
Loop 1 Loop 2 DC -5.40
       
11.79 5.40 C
E 150mm,2000m D 100mm,2000m
40 l/s 80 l/s 40 l/s

o Head Loss in Pipe AB [Q = 79.60L/sec.]


1 1
 Q  0.54  79.60  0.54
h f  L 2.63 
 2000 *  2.63 
 33.40m
 0.278CD   1000 * 0.278 * 100 * 0.25 

o Head Loss Pipe BC [Q = 34.60L/sec.]


1 1
 Q  0.54  34.60  0.54
h f  L 2.63 
 1000 *  2.63 
 10.58m
 0.278CD   1000 * 0.278 * 100 * 0.2 

o Pressure on point B [Given that all pipe junctions are on the same elevation]
490.5 10
 PA Alemayehu
PBZerihun
Instructor: h f AB   33.40  16.6m  16.6 * 9.81  162.85 Kpa  Ans
9.81
Water Supply and urban Drainage Assignments

o Pressure on point C

PC  PB  h f BC  16.6  10.58  6.02m  6.02 * 9.81  59.06 Kpa  Ans


PUMP
5. Water has to be supplied to a town having 100000 populations at the rate of 150l/c/d from a
treatment plant 2000m away. the difference in elevation between the lowest water level in the clear
well and the distribution reservoir is 36m.if the demand has to be supplied in 8 hours, determine
the size of the main and the brake horse power of the pump required.asssume C = 120,design
velocity=2.4m/s and pump efficiency = 80%.Neglect minor losses.

Given: Population = 100,000, per capita requirement=150l/c/d, Lpipe=2000m, h=36m,

Demand Supplied in 8 hours=120, design velocity = 2.4m/sec, pump efficiency = 80%

Required: The size of the main and the brake horse power of the pump

Solution: Neglect fire demand

 Maximum day factor and peak hour factor are 1.20 and 1.70 respectively for the population greater than
50,000

15,000,000
Q Day avg  100,000 * 150  15,000,000l / d   15,000m 3 / day
1000
18,000
Q Day  max  15,000 * 1.20  18,000m 3 / day   0.2083m 3 / sec
86,400

25,500
Q peak  hr  15,000 * 1.70  25,500m 3 / day   0.295m 3 / sec
86,400

o Size of main
d 2
QDay  max  VA  V *
4
4Q 4 * 0.2083
d    0.3324m  33.24cm
V 2.4 * 

o Brake horse power of the pump [Total suction head =36m]

1 1
 Q  0.54  0.295  0.54
h f  L 2.63 
 2000 *  2.63 
 67.32m
 0.278CD   0.278 * 120 * 0.3324 

TDH  hs  h f  36  67.32  103.32m

Instructor: Q * Alemayehu
TDH * speificgravity 0.295 *103.32 * 10 11
BHPZerihun
   5.08 Hp
75 * 75 * 0.80
Water Supply and urban Drainage Assignments

6. A centrifugal pump is to operate against a total head of 360Kpa and is to discharge


1.1m3/min.compute the waterpower and motor power assuming an efficiency of 60%.if the
efficiency of an electric motor is 85% and the cost of electricity is 20cents per KWh,compute the
monthly cost f operation if the daily flow is 750m3.

Given: Total head = 360Kpa, Q =1.1m3/min., Efficiency =60%

Required: The water power and motor power and Monthly cost of operation If the efficiency of an electric motor
=85%, cost of electricity =20cents per KWh, daily Flow =750m3

Solution:

o Water Power
1.1 360
Waterpower  WHP  Q * TDH * specificgravity  * *10  0.6728KW
60 9.81
o Motor power

WHP 0.6728
Motorpower  BHP    1.3192KW
  0.6 * 0.85

o Cost to pump 750m3 daily


750m 3 20cents
Costtopump750m 3  3
* (1.3192 KW ) *  299.82cents
1.1 * 60m / hr 1KWh

o Monthly cost to pump 750m3 daily [1 month = 30days]

Monthly cost = 30*299.82cents = 8994.55 cents =8994.55 Birr  Ans.

7. Water from an obstruction well in a confined aquifer is pumped to the ground level by a submerged
borehole pump; an in-line booster pump delivers the water to a reservoir, with the level 20m above
ground level at the well site. the system’s pipe work has the following characteristics:

System Characteristics

Discharge(L/s) 20 30 40 50 60
Head loss (m) 1.38 3.14 5.54 8.56 12.21
Pump discharge(L/s) 0 10 20 30 40
Bore hole pump head (m) 10.0 9.6 8.7 7.4 5.6
Booster pump head (m) 22.0 21.5 20.4 19.0 17.4

Aquifer and well data are as follows: the coefficient of permeability of the aquifer,K = 50m per day;
the aquifer thickness=20m;the radius of the well,r W = 0.15m.

Instructor: Zerihun Alemayehu 12


Water Supply and urban Drainage Assignments

A pumping test suggested that the drawdown was 3m when the abstraction rate was 30L/s.the
water table is 2m below ground level. The draw down is as follows:

Q R 
ZW  ln O 
2kb  rW 
Where q is the abstraction rate in m3 per day, and RO is the radius of influence of the well, which
may be assumed to be linearly related to the abstraction.

Determine the maximum discharge which the combined pumps would deliver to the reservoir.

Given: K= 50m/day = 50/ (24*60*60) = 57.87 x 10-5m/sec, b =20m, r W=0.15m, drawdown =3m,

Q =30L/sec = 30/1000=0.03m3/sec, the water table is 2m below ground level.

Required:MaximumDischarge

Solution:
 R  Z 2kb
ln O   W
 rW  Q
 R  3 * 2 *  * 57.87 * 10 5 * 20
ln O  
 0.15  0.03
 R 
ln O   7.272205217
 0.15 
R O   e 7.272205217 0.15
R O  215.96m  216m

Since, the radius of influence linearly related to the abstraction, thus

Q RO

30L/s 216m  x= 216*20 /30 =144m,

20L/s x?

Discharge(L/s) (1) 20 30 40 50 60
Head loss (m) (2) 1.38 3.14 5.54 8.56 12.21
RO (m) (3) 144 216 288 360 432

Q R 
ZW  ln  O 
2  kb  rW 
ZW(m) (4) 1.89 3 4.16 5.35 6.57
Ground water level from the
ground level (m) (5) 2 2 2 2 2
Reservoir height from the
ground level (m) (6) 20 20 20 20 20

Instructor: Zerihun Alemayehu 13


Water Supply and urban Drainage Assignments

(7) =
Total Head (m) (2)+(4)+(5)+(6) 25.27 28.14 31.7 35.91 40.78

Since Bore hole pump and Booster pump connected in series, thus

Total Head = Bore hole pump head (m) + Booster pump head (m)

Pump Head
Pump discharge(L/s) 0 10 20 30 40
Total Head=bore hole + booster(m) 32.0 31.1 29.1 26.4 23.0

System Head
Discharge(L/s) 20 30 40 50 60
Total Head (m) 25.27 28.14 31.7 35.91 40.78
The maximum discharge which the combined pumps would deliver to the reservoir is 36 L/s

45.0

40.0

35.0

30.0
He a d,H (m)

25.0

20.0

15.0
Pu m p h e a d

10.0 Syste m h e a d

5.0

0.0
Qmax=36 L/s
20 30 40 50 60
Discharge,Q (L/s)

8. Find the flow in each pipe line and the pressure at node JI for the system shown in Fig. P-6.

Pipe Leng, m Dia, mm C 91.4m


P1 67.1 406 120 RB
P2 670.6 305 120 P3
P3 304.8 305 120 J1 Elev.45.7m

P2 Q=21.2 l/sec

P
P1
31.8m H[m]=68.58 - 639.66Q1.5; Q[ m3/s]

Instructor: Zerihun Alemayehu 14


Water Supply and urban Drainage Assignments

RA

Solution:

TDH = HS + hLS + hLd

HS = 91.4 – 31.8 = 59.6m

Head loss suction side [hLS]

1.85 1.85
10.68 L  Q  10.68 * 67.1  Q 
hLS     *   8.19Q 1.85
D 4.866  C  0.406 4.866  120 

Head loss discharge side [hLd]

10.68 *  670.6  304.8  Q 


1.85 1.85
10.68L  Q 
hLd     *   479.36Q 1.85
D 4.866  C  0.305 4.866  120 

TDH = HS + hLS + hLd =59.6 + 8.19Q1.85 + 479.36Q1.85 = 59.6 + 487.55 Q1.85

Since TDH and the head delivered by the pump has to be the same

59.6 + 487.55 Q1.85 = 68.58 - 639.66Q1.5

68.58 – 59.6 =487.55 Q1.85 + 639.66Q1.5

8.98 = 487.55 Q1.85 + 639.66Q1.5

Using trial and error procedure

Q =0.0497m3/sec = 49.7 l/sec

Computation of discharge in each pipe

The head loss in the suction pipe P1


hLS  8.19Q 1.85  8.19 * (0.0497)1.85  0.0317m

Discharge in pipe P1

0.54 0.54
 hf   0.0317 
 0.278 * 120 *  0.406
2.63
Q  0.278CD 2.63      0.04986m 3 / sec  49.86l / sec
 L   67.1 

The head loss in the discharge pipe P2

10.68 *  670.6   0.0497 


1.85 1.85
10.68L  Q 
hLd     *   1.277m
D 4.866  C  0.3054.866  120 

Instructor: Zerihun Alemayehu 15


Water Supply and urban Drainage Assignments

Discharge in pipe P1
0.54 0.54
 hf   1.277 
 0.278 *120 *  0.305
2.63
Q  0.278CD 2.63      0.04988m 3 / sec  49.88l / sec
 L   67.1 

The head loss in the discharge pipe P3

10.68 *  304.8  0.0497 


1.85 1.85
10.68L  Q 
hLd     *   0.5804m
D 4.866  C  0.305 4.866  120 

Discharge in pipe P3
0.54
 hf   Q 
Q  0.278CD 2.63    
 L   1000 
0.54
 0.5804   21.2 
Q  0.278 *120 *  0.305
2.63
     0.02869m / sec  28.69l / sec
3

 304.8   1000 

Assignment 4 – Waste Water and Storm water Collection System


1. A 54 hectare drainage basin containing 26hecare of residential area,with an aveage of 8 dwelling
units per hectare with 4 residents each,20hectare parcel zoned commercial area and 8 hectare open
area.

Waste water generation data

Residential = 120L/resident/day

Commercial = 16200L/hec/day

PeakI & I allowance = 9000L/hectare/day


Instructor: Zerihun Alemayehu 16
Water Supply and urban Drainage Assignments

For the waste water flow data given above determine

a) The average daily flow (ADF) from residential and commercial area.

b) The peak design flow(PDF)for a sewer serving this area taking peaking factor of 4

c) The diameter of the sewer for the above PDF if the ground slope is 1

Given: A tot =54ha, ACommercial=26ha, open area = 8ha


Aresidential=26ha, with an average of 8dwellings units per hectare with 4 residents each

Waste water generation data: Resident = 120l/resident/day, Commercial = 16200l/ha/day,

Peak I & I allowance = 9000l/ha/day,

Solution:

a) ADF of residential area = 26ha*8Du/ha *4res/Du *120l/res/day =99840l/day = 99.84m3/day ADF of


Commercial area = 20ha*16200l/ha/day=324,000l/day = 324m3/day

ADF from Res. &Comm. area = 99.84 + 324 = 423.84 m3/day

b) PDF = PF*ADF +allowance = 4*423.84 + 9*54 =2181.36 m3/day = 0.02525 m3/sec =1.515 m3/min

c) Enter the monograph with Q = 1.515 m3/min and s = 0.01

I read D =179mm  take standard diameter of 150mm,but to have a capacity of 1.515 m3/min ,the slope
has to be steepest i.e. s =0.03

Therefore select larger diameter D = 200mm at s =0.01, Qf =2 m3/min and Vf = 1.07m/sec

 With q/ Qf =1.515/2 = 75.75%, From partial flow diagram,d/D =65% = 0.65

 d = D*0.65 = 200*0.65 = 130mm of depth of flow

 With d/D =65% = 0.65, from partial flow diagram, v/Vf = 110% = 1.1

 v = 1.1* Vf =1.1*1.07 = 1.177m/sec. > Vmin = 0.6m/sec  no problem of sedimentation

Therefore, select D =200m, for slope = 0.01 =1%

2. Using the rational method, compute the design flow and required pipe diameter for the outfall
sewer shown in the figure for a 5-year storm. Take i = 1500/ (t+15) where t is in min. and i in mm/hr
for 5-year return period rainfall intensity. Take travel time of 5min between the inlets and ground
slope of 0.5%.

Given: For 5 –year storm and 5-yr return period


1500
i
 t  15 t is in min and i is in mm/hr

Travel time between inlets = 5min


Area 1
Ground slope = 0.5% = 0.005
Outfall Area 2 A1 =3ha
Required: -Design flow Q Sewer A2 =4ha A C1 = 0.6
te1 = 6 min
-Required pipe diameter for the outfall sewer B C2 = 0.5
Instructor: Zerihun Alemayehu te2 = 7 min 17
Water Supply and urban Drainage Assignments

Solution:

Upstream area [Manhole A]

tC =te1 = 6min, A1 =3ha, C1 = 0.6


1500 CiA 0.6 * 71.43 * 3
i  71.43mm / hr Q   0.35715m 3 / sec
 6  15 360 360
Downstream area [Manhole B] n

A =A1 + A2 = 4 + 3 =7ha  C A  0.6 * 3   0.5 * 4


i i
C 
i 1
n
 0.543
7
A i 1
i

tC ,time from 1 →A → B = te1 + tf = 6 + 5 = 11min tC = 11min [max]

tC ,time from 2 → B = te2 = 7min

1500
i  57.69mm / hr
11  15

CiA 0.543 * 57.69 * 7


Q   0.609m 3 / sec  36.55m 3 / min
360 360

Therefore, design flow of out fall sewer is Q = 36.55m3/min.

Enter the monograph with Q = 36.55 m3/min and s = 0.005

I read D =685mm  take standard diameter of 700mm,but to have a capacity of 1.515 m3/min ,the slope has to be
steepest i.e. s =0.0041

Therefore select larger diameter D = 700mm at s =0.004, Qf =40 m3/min and Vf = 1.71m/sec

 With q/ Qf =36.55/40 = 98.82%, From partial flow diagram,d/D =74.6% = 0.746

 d = D*0.746 = 700*0.746 = 522.2mm of depth of flow

 With d/D =74.6% = 0.746, from partial flow diagram, v/Vf = 112.5% = 1.125

 v = 1.125* Vf =1.71*1.71 = 1.92m/sec. > Vmin = 0.6m/sec  no problem of sedimentation

Therefore, select D =200mm, slope s = 0.005

3. Design the two sewer reaches shown below in figure 2.the design flow for reach 1 is 40L/s and for
reach 2 it is 80L/s. use a minimum cover of 2m.sketch a profile of the street and sewer.

Reach 1,Q = 40L/s Reach 2,Q = 80L/s


MH 1 MH 2 MH 3
Ground Elev. 80m Ground 100m Ground Elev.
350.0m Elev.347.87m 347.0m

Instructor: Zerihun Alemayehu 18


Water Supply and urban Drainage Assignments

Given; Reach 1, Q =40L/sec, Reach 2, Q = 80L/sec, min.cover = 2m

Required; Sketch the profile of street and sewer

Solution:

Reach 1
Q = 40l/sec = 2.4m3/min S = (350 - 347.87)/80 = 0.026625

Enter the monograph with Q = 2.4 m3/min and s = 0.026625

I read D =179mm  take standard diameter of 200mm,but to have a capacity of 2.4 m3/min ,the slope has to be
gentle i.e. s =0.0135

Therefore select larger diameter D = 700mm at s =0.004, Qf =40 m3/min and Vf = 1.71m/sec

If s =0.0135, the rise in height = 0.0135*80 = 1.08m

Difference in ground elevation between two manhole = 350 – 347.87 = 2.13m

Cover = 2.13 – 1.08 = 1.05m < min.cover = 2m not OK!

Therefore with min.cover=2m, fix s =0.0275 and D= 200mm


Enter the monograph with s = 0.0275 and D = 200mm Qf =3.65m3/min and Vf = 1.80m/sec

 With q/ Qf =2.4/3.65 = 65.75%, From partial flow diagram, d/D =58.5% = 0.585

 d = D*0.585 = 200*0.585 = 117mm of depth of flow

 With d/D =58.5% = 0.585, from partial flow diagram, v/Vf = 106.5% = 1.065

 v = 1.065* Vf =1.71*1.80 = 1.92m/sec. > Vmin = 0.6m/sec  no problem of sedimentation

Therefore, select D =200mm, slope s = 0.005

Invert Elevation
Manhole 1

Invert Elev. = ground elev. – Cover – pipe diameter

= 350.0 – 2 – 0.2 = 347.8m

Manhole 1

Invert Elev. = Invert pipe Elev.at MH 1 – fall of sewer

= 347.8 – (0.0275*80) = 345.6m

Reach 2
Q = 80l/sec = 4.8m3/min S = (347.87 - 347.00)/100 = 0.0087

Enter the monograph with Q = 4.8 m3/min and s = 0.0087

Instructor: Zerihun Alemayehu 19


Water Supply and urban Drainage Assignments

I read D =440mm and V = 0.54m/sec,

 Cover = 347.87 - 347.00= 0.87m < min.cover = 2m not OK! And

V=1.92m/sec. > Vmin = 0.6m/sec  problem of sedimentation

Therefore, to get min cover =2m and to resolve problem of sedimentation use D=450mm and S =0.008

 Enter the monograph with s = 0.0275 m3/min and D = 450mm Qf =15m3/min and Vf = 1.62m/sec

 With q/ Qf =4.8/15 = 32%, From partial flow diagram, d/D =40% = 0.4

 d = D*0.4 = 450*0.4 = 180mm of depth of flow

 With d/D =40% = 0.4, from partial flow diagram, v/Vf = 90% = 0.90

 v = 0.90* Vf = 0.9*1.62 = 1.46m/sec. > Vmin = 0.6m/sec  no problem of sedimentation

Therefore, select D =450mm, slope s = 0.008

Invert Elevation
Since, size of pipe of reach 1 and reach 2 are different.Therefore, the crown of reach 1 should be at the
same elevation with the pipe crown elevation of reach 2.

Crown elev.at reach 1 pipe = invert Elev.of reach 1 pipe + pipe diameter

= 345.6 + 0.2 = 345.8m

Manhole 2

Invert Elev. = Crown elev.at reach 1 pipe – pipe diameter

= 345.8 – 0.45 = 345.35m

Manhole 3

Invert Elev. = Invert Elev.at MH 2 – fall of sewer

= 345.35 – (0.008*100) = 344.55m

Check min.cover = Ground elev.at MH3 – crown Elev.at MH3 347 – (344.55+0.45) =2m  OK!

Profile of street and sewer

MH1 Ground Elev.=350.0m

MH2 GroundElev.=347.87m

MH Ground Elev.=347.0m

Instructor: Zerihun Alemayehu 20


Water Supply and urban Drainage Assignments

D=200mm
s= 0.0275
Invert elev.= 347.8m Crown Elev.=345.8m

Invert elev.= 345.6m s= 0.008


D=450mm

Invert elev.= 345.35 m

Invert elev.= 344.55 m

4. Given: 100 person per hectare, Sewage contribution per capita = 375L/d,

Infiltration component =2270 L/ha/d, Minimum diameter = 200mm, n = 0.013

Required: Design the sewer system

Solution: refer figure on the question paper for manhole locations, area and street elevations data

Assumptions
o Per hectare flow is the same

o Cumulative water shed area enter upstream manhole is 35ha


PF  15.05Q 0.167
o Peak factor is calculated using the formula

Residential flow = 100 * 375 =37500 L/ha/d

Infiltration = 2270 L/ha/d

DWF = 37500 + 2270 = 39770 L/ha/d


PF  15.05Q 0.167  15.05 * 39770 0.167  2.57

PWF = 2.57*39770 = 102208.9 L/ha/d= 0.07098m3/min/ha

See Table 4 -1 for Calculation of Sewage Flows and

See Table 4 - 2 for Calculation of Pipe sizes and Velocities

Remarks:

o The pipe sizes which I read it from the monograph (column 7, Table 4- 2) are modified to the next largest
standard pipe size or to a size that accommodates the design flow at a desired depth. These selected sizes
are entered in column 9 of Table 4- 2.

o Note that: For the range of pipe sizes encountered in this problem, a desirable depth of flow is normally
from about half to three-fourths full. Many of the 200mm.minimum diameter pipes, because of the low

Instructor: Zerihun Alemayehu 21


Water Supply and urban Drainage Assignments

flows carried, have the design flow depth that are less than half the maximum depth. this can not be
avoided and does not create a problem as long as cleansing velocities are maintained (all velocities are
greater than 0.6m/sec)

5. Given: 10-yr frequency rainfall, i = 180mm/hr, length of Mh 9 to Mh 10 = 55m,


The rest are measured accordingly

Required: Design a storm drainage system to carry flows from the eight inlet area given in the fig.4

Solution: Refer figure on the question paper

Assumptions

o Assume a 5min.inlet time

o By assumptions clay soil to be predominant in the area, Appropriate c value are assumed

o Street slope is assumed

Table 5-1 Required storm water Inlet Capacities

Col.1 Col.2 Col.3 Col.4 Col.5 Col.6= (3*4*5)/6


Rainfall
Area intensity i Q=CIA/6
Inlet Designation Area (ha) C (mm/hr) (m3/min)
I-1 O 0.40 0.57 180 6.84
I-2 H 2.25 0.35 180 23.63
Instructor: Zerihun Alemayehu 22
Water Supply and urban Drainage Assignments

I-3 M 2.75 0.40 180 33.00


I-4 N 1.27 0.40 180 15.24
I-5 D 2.66 0.40 180 31.92
I-6 C 3.19 0.38 180 36.37
I-7 A 1.93 0.37 180 21.42
I-8 B 1.34 0.42 180 16.88
           

Remarks:

o Beginning at the upstream end of the system, compute the discharge to be carried by each successive
length of pipe, moving downstream. These calculations are summarized in Table 5-2.

o Note that: at each point down stream where a new flow is introduced, a new time of concentration must
be determined as well as new values of c and drainage area size. As the upstream inlet areas are combined
to produce a larger tributary area at some design point, a revised C values representing these combined
areas must be obtained.

For example, in the computation of the flow to be carried by the pipe from M-9 to M-8, the tributary area is A
+ B + c = 6.46ha, and the composite value of C will be

C
Ca i i

0.37 * 1.93  0.42 * 1.34  0.38 * 3.19
 0.38
a i 6.46

o At the design location the value of tC will be equal to the inlet time at I-8 plus the pipe flow time from I-8
to M-9(see table 5-2).

o Using the computed discharge values, select tentative pipe sizes(from Manning Monograph) for the
approximate slopes given in column 8 of Table 5-2.Once the pipe sizes are known, the flow velocities
between input locations can be determined.Normally,these velocities are approximated by computing the
full-flow velocities for maximum discharge at the specified grade.

o These velocities are then used to compute channel flow time for estimating the time of concentration by
using the formula

S
tf 
V * 60

Instructor: Zerihun Alemayehu 23