Concrete pipe culvert 400, 500 and 700 mm diameter (360 degree concrete base) types

shall be protected by concrete (Class-B3 21N/mm2) protection with required


reinforcement bars as indicated in the Drawings.
After excavation the ground, or if required filling up to the specified elevation,
foundation material (crushed stone 0-40) layer shall be introduced and properly
compacted to a thickness as shown in the Drawings, on which the pre-cast concrete pipe
and required surrounded concrete shall be installed in alignment both in horizontal and
vertical position and in elevation.

Excavation, sand base filling, installation of concrete pipes, and back-filling for sand
base type of concrete pipe culvert 400 and 500 mm diameter shall be required as shown
in the Drawing.

5.11 SLAB COVER SETTING

Slab covers shall be installed to open drainage in footpath as shown on the Drawings.
The Slab Cover shall be made with concrete (Class-B3 21N/mm2) and reinforced steel
bars as shown in the Drawing.

5.12 HEAD-WALL

The head wall(s) shall be constructed at the inlet and outlet side(s) of pipe culvert to
connect the culvert with open drainage.

The item of this work shall consist of excavating, laying and connecting portion of pipe
culvert and open drainage, form work and concreting work, back filling and compacting
and other incidental items of work, all in accordance with the Drawings and
Specifications.

6. STREET LIGHTING

6.1 DESCRIPTION

This work shall consist of designing, furnishing all labors, materials and equipment and
installing in place in accordance with the requirement of the Contract. Included in this
work are furnishing, installing of metal posts, electrical wiring, conduits, fittings,
concrete foundation, hand holes, pits and all other materials necessary for operating and
controlling the Street Lighting System as approved by the Consultant.

6.2 MATERIALS REQUIREMENTS

The Contractor shall furnish all materials as designed and specified on the Drawing.

Materials shall be subject to inspection at any time. Failure of the Consultant to note
faulty materials or workmanship during construction shall not relieve the Contractor of
his responsibility for removing or replacing such materials and redoing the work at his
expense.

TS-63
6.3 CONSTRUCTION REQUIREMENT

The Contractor shall submit to the Consultant for approval a list of the all materials and
equipment to be incorporated in the work. The list shall include the name of the
manufacture, size and catalog number of the unit, detailed scale drawings and wiring
diagrams of the system.

The Contractor shall also submit for approval the certifications as follows:

When the manufacturer of materials does not use with an ISO 9000 certification system,
the Contractor shall provide a production certification for each shipment of materials,
which include the following with each production certificate.

1. Date and place of manufacture


2. Test results of material from the same lot and documentation of inspection and
testing system
3. Lot number or other means of cross-referencing to the manufacturer’s inspection
and testing system
4. Manufacturer’s statement that the material complies with all contract requirements
5. Manufacturer’s signature or other means of demonstrating accountability for the
certification

Well in advance of commencement of the work, the Contractor shall submit working
drawings and electrical calculation sheets for power distribution to the Consultant for
his approval, incorporating the actual field conditions into the work. The working
drawings shall indicate, but not limited to, location of lighting pole and ancillary
equipment, concrete foundation with re-bars and anchor bolts for pole, installation of
electrical conduit, wiring and lighting conductor.
Forms for concrete foundation shall be true to lines and grades as approved, and shall
be rigid and securely braced in place. Conduit ends and anchor bolts shall be in proper
position and to proper height and shall be held in place by means of a template until the
concrete placed. The concrete shall be cured for not less than 72 hours.

Each metal pole shall be installed on concrete foundation. The poles shall be set
precisely vertical on each anchor bolt, while the light shall be perpendicular to the road
center.

Specification of LED lighting luminaire shall be as indicated on the Drawings wherein


its expected lifetime shall be 60,000 hours. The Contractor shall submit the drawings
and specification of the proposed products for an approval by the Consultant. Should
the Contractor intends to propose an alternative products equivalent to the original, the
drawings and specification of the alternative products shall be submitted to the
Consultant for his clarification and approval.

The Contractor shall give assistance to the Client on his request by furnishing
documentation required in such application as for power supply to the street lighting
system.

Upon completion of the work, the Contractor shall submit an ‘’As Built’’ or corrected
drawing in detail thereon.

TS-64
1800

1-D12 1-D12 346

1071
300
4-M25 D12
LIGHTINGLAMP 50 180
LED120W

D12

346
300
300
500
1000

180
1-D12

4-M25

1000
4479
1-D12

500
8000

50
300

ANCHOR BOLTS S=1:25

SERVICE DOOR 90x400 AND OPENING


2450

90
4- 30

400
300
680
750
150

GROUND LEVEL
300
75

400
9@150=1350

D16
1500

180
75
150

CONCRETE (24N/mm2)
D12 t22 300
CRUSHER-RUN
70 70
3@120=360
500 BASE PLATE S=1:25
600 Specification
SECTION S=1:50 1.Surface Treatment : Hot dip Galvanized
Note : Quantity and location of Street Lighting shall be finalized and
2.Design Wind Speed : 50m/sec
Street Light Pole Type A approved by the Consultant
(Single-lamp)

THE PREPARATORY SURVEY ON Approved by: Date: TITLE :


MINISTRY OF Drawing No. SL-1
KATAHIRA & CLAUDE E. LANGLEY [MPW]
THE PROJECT FOR Checked by: Date: DETAILED STRUCTURE OF
PUBLIC WORKS ENGINEERS YAMAJUKU [KEI] SCALE AS SHOWN
RECONSTRUCTION(PHASE-2) OF STREET LIGHTING
REPUBLIC OF LIBERIA INTERNATIONAL SOMALIA DRIVE IN MONROVIA
Designed by: Date:
DATE DEC.2017
MAEHATA [KEI]
1800 1800

1-D12 1-D12 346


300

1071
4-M25 D12
50 180
LIGHTINGLAMP LIGHTINGLAMP
LED120W LED120W
D12

346
300
300
500
1000

180
1-D12

4-M25

1000
4479
1-D12

500
8000

50
300

ANCHOR BOLTS S=1:25

SERVICE DOOR 90x400 AND OPENING


2450

90 4- 30

400
300
680
750

300
150

GROUND LEVEL
75

400
11@150=1650

D16
1800

180
CONCRETE (24N/mm2)
t22 300
75
150

D12
CRUSHER-RUN
70 70
3@120=360 BASE PLATE S=1:25
500
600
Specification
1.Surface Treatment : Hot dip Galvanized Note : Quantity and location of Street Lighting shall be finalized and
SECTION S=1:50 approved by the Consultant
2.Design Wind Speed : 50m/sec
Street Light Pole Type B
(Two-lamp)

THE PREPARATORY SURVEY ON Approved by: Date: TITLE :


MINISTRY OF Drawing No. SL-2
KATAHIRA & CLAUDE E. LANGLEY [MPW]
THE PROJECT FOR Checked by: Date: DETAILED STRUCTURE OF
PUBLIC WORKS ENGINEERS YAMAJUKU [KEI] SCALE AS SHOWN
RECONSTRUCTION(PHASE-2) OF STREET LIGHTING
REPUBLIC OF LIBERIA INTERNATIONAL SOMALIA DRIVE IN MONROVIA
Designed by: Date:
DATE DEC.2017
MAEHATA [KEI]
Earth
8 7 12

10 9
404 (Pole insertion Length)
M8 earth bolt M8 bolt
125
2
640 40
6 3 15

Ø60.5
Ø6 welded pin

165

10°
1
1-Ø12 hole


4 LED Power-Unit Drawing for Pole

11

【LED-Lighting equipment】
【Electrical Property】 【LED Specification】 No. Name Material Finish Qty Remarks
Voltage 220V LED color White 1 Body ADC12 Painting 1
0.54A Color temperature 5000K 2 Frame ADC12 Painting
Input-Current Lighting-start 1
Ra 70
60,000-hour progress 0.64A 3 Holder ADC12 Painting 1
LED design life 60,000-hour
60,000-hour average 0.59A Attachment Arm type 4 Front Glass Tempered glass Clear 1 t4.0
Power supply design life 60,000-hour
Input-Power Lighting-start 114W Conformity adapter Ø60.5×120L 5 Hinge SUS304 1
LED number 60 piece
60,000-hour progress 135W Luminous flux 13,940 Lm Weight 10.8kg 6 Adjustable screw SUS304 1 M6
60,000-hour average 124W Finish Acryic resin painting 7 Cable clamp Fiber 1s
【Environmental capability】
Input VA Lighting-start 119.6VA Painting Color N7 8 Terminal Porcelain 1 3P
Operating temperture limits -20℃∼+40℃
60,000-hour progress 141.2VA Packing Silicon rubber 9 Fall prevention wire SUS304 1 Ø3.0 L=300mm
Humidity 85% or more
60,000-hour average 130.4VA Coefficient of wind force 1.0 10 Bolt SUS304 1 M10 W,SW
Lightning surge Nomal:2kv/Common:15kv
Power factor 85% or more Body:IP23 Front:0.07m2 11 Veneer SUS304 Painting 1 t1.2
Area
Waterproof
Frequency 50/60Hz LED-PowerUnit:IP44 Side :0.05m2 12 Pole supporter SPHC Galvanization 1 t6.0

THE PREPARATORY SURVEY ON Approved by: Date: TITLE :


MINISTRY OF Drawing No. SL-4
KATAHIRA & CLAUDE E. LANGLEY [MPW]
THE PROJECT FOR Checked by: Date: DETAIL OF LED-LIGHTING
PUBLIC WORKS ENGINEERS YAMAJUKU [KEI] SCALE AS SHOWN
RECONSTRUCTION(PHASE-2) OF EQUIPMENT
REPUBLIC OF LIBERIA INTERNATIONAL SOMALIA DRIVE IN MONROVIA
Designed by: Date:
DATE DEC.2017
MAEHATA [KEI]

You might also like