HSE Daily Report

PROJECT: DAMMAM INDEPENDENT SEWAGE TREATMEENT PLANT (DMMISTP)

Report No.: DISTP-SPV-HSEDR-005 Date: 24-DEC-2020


Safety Officer: Muhammad Asif

Weather Condition Temperature


Cloudy ☐ Stormy ☐ Clear ☒ Cold ☐ Hot ☐ Rainy ☐ 24o C Dammam

Sr.# Activities in Progress Locations Remarks


a) Inlet Headwork
1 Excavation b) Chlorine Contact Tank Satisfactory
c) Secondary Clarifier D
a) Material Yard
b) Balancing Tack
2 Rigging Not Satisfactory (1)
c) Biological Tank D
d) Primary Clarifier D
Hot Work a) Warehouse
3 Satisfactory
(Welding, Grinding & Cutting) b) Material Yard
4 Working at Height a) Warehouse Satisfactory
a) Balancing Tank
5 Steel Fixing & Shuttering b) Biological Tank D Satisfactory
c) Primary Clarifier D
6 Road Work a) All Site Area In Progress
7 Scaffold Erecting a) Primary Clarifier D In Progress

Incident: Location Description


No
Near Miss
No
HSE Violation:
No
Other:
1- Hazardous activities of rigging at balancing tank: NCR (DISTP-SPV-EPC-NCR-002) has been issued.

HSE Officer: Muhammad Asif


Sign:
Technical Director: Hayder AL-Rawashdeh Sign: