AS PER TENDER DOCUMENTS:

ITEM UNIT COST


DESCRIPTION UNIT QTY TOTAL AMOUNT
NO MATERIAL LABOR OTHERS TOTAL
D1 (MAIN DOOR) SET(S) 1.00 15,000 4,500 2925 22,425.00 22,425.00
MASONRY WALL (CHB INSTALLATION) SQM 1.26 400 180 87 667.00 837.89
MASONRY WALL (FINISH PLASTERING ON
BOTH SIDES) SQM 2.51 250 112.5 54.375 416.88 1,047.36
24,310.24

AS PER DOOR REVISION 1(3PANELS - 2 GLASS SLIDING DOOR, 1 FIXED):

ITEM UNIT COST


DESCRIPTION UNIT QTY TOTAL AMOUNT
NO MATERIAL LABOR OTHERS TOTAL
D1 (MAIN DOOR) SET(S) 1.00 23,625 7,088 4606.88 35,319.38 35,319.38
MASONRY WALL (CHB INSTALLATION) SQM - 1.26 400 180 87 667.00 - 837.89
MASONRY WALL (FINISH PLASTERING ON
BOTH SIDES) SQM - 2.51 250 112.5 54.375 416.88 - 1,047.36
33,434.13

AS PER DOOR REVISION 2(4PANELS - 2 GLASS SLIDING DOOR, 2 FIXED WINDOW):

ITEM UNIT COST


DESCRIPTION UNIT QTY TOTAL AMOUNT
NO MATERIAL LABOR OTHERS TOTAL
D1 (MAIN DOOR) WITH FIXED WINDOW
SIDE PANEL SET(S) 1.00 19,534 5,860 3809.05 29,202.73 29,202.73
MASONRY WALL (CHB INSTALLATION) SQM - 1.26 400 180 87 667.00 - 837.89
MASONRY WALL (FINISH PLASTERING ON
BOTH SIDES) SQM - 2.51 250 112.5 54.375 416.88 - 1,047.36
27,317.49