You are on page 1of 2

PO No.

876 Total Packages 14


PO Name AS-BUILT WEEKLY MONITORING REPORT Total Files 1691
As-Built drawings modifications
for OMP Wells
SHAYBAH FACILITIES Total Files - Remaining 1187
Client CAT WEEK-27 Total Files Completed 143

Date 28-Jun-20 Total Percent (%) Progress 8.5%

%Completed
Completed

Remaining
Total Files

28-Jun-20

29-Jun-20

30-Jun-20
Assigned

1-Jul-20

2-Jul-20
Assigned Manhour
No. Facility Name Batch No. Submission Date Remarks Link Remarks
To Current
Week

1 SHYB-114 TIE-IN (SAB-32) 104 2-Jul-20 Shahid Under Drafting Link 48 158 47 111 30% 6 41

2 SHYB CP (SAB-52) 104 No Native Files

3 SHYB -620 TIE-IN (SAB-69) 104 2-Jul-20 Bobby Under Drafting Link 36 250 0 250 0% 0 0

4 SHYB-701 TIE-IN (SAB-67) 104 2-Jul-20 Boy Under Drafting Link 30 349 8 341 2% 0 8

5 SHYB-702 TIE-IN (SAB-67) 104 2-Jul-20 Basit Under Drafting Link 48 229 8 221 3% 0 8

6 SHYB-44 E&I and PDHMS (SAB-20) 105 2-Jul-20 Gary Under Drafting Link 48 131 7 124 5% 7 0

7 SHYB-73 TIE-IN (SAB-28) 105 2-Jul-20 Ardee Under Drafting Link 46 112 28 84 25% 0 28

8 SHYB-115 TIE-IN (SAB-32) 105 2-Jul-20 Jorge Under Drafting Link 29 132 0 132 0% 0 0

9 SHYB-379 SWC&PDHMS (SAB-76) 105 No Native Files

10 SHYB-912 GI (SAB-28) 105 2-Jul-20 Jess T. Under Drafting Link 25 153 4 149 3% 4 0

11 SAB-72 TO SAB-77 OHPL (SAB-77) 111 No Native Files

12 SHYB-129 OHPL (SAB-124) 102 No Native Files

13 SHYB-157 CP (SAB-50) 102 2-Jul-20 Gary Under Drafting Link - 7 3 4 0% 0 3

14 SHYB-44 OHPL (SAB-20) 102 2-Jul-20 Gary Under Drafting Link - 9 4 5 0% 0 4

15 SHYB-757 CP (SAB-07) 102 2-Jul-20 Gary Under Drafting Link - 11 8 3 0% 0 8

14 SHYB-43 OHPL (SAB-72) 111 2-Jul-20 Miland Under Drafting Link 48 13 0 13 0% 0 0

15 SHYB-45 CP (SAB-21) 111 2-Jul-20 Miland Under Drafting Link - 12 0 12 0% 0 0

16 SHYB-215 TIE-IN (SAB-83) 99 2-Jul-20 Joy Under Drafting Link 48 125 26 99 0% 0 26


PO No. 876 AS-BUILT WEEKLY MONITORING REPORT Total Packages 14
As-Built drawings modifications for OMP Wells SHAYBAH FACILITIES Total Files 1542
PO Name [CAT]
WEEK-28 Total Files Completed 0
Date 05-Jul-20 Total Percent (%) Progress 0.0%

%Completed
Completed
Total Files

28-Jun-20

29-Jun-20

30-Jun-20
Assigned

1-Jul-20

2-Jul-20
No. Facility Name Batch No. Submission Date Assigned To Remarks Link Manhour
Current
Week

1 SHYB-114 TIE-IN (SAB-32) 111 11-Jul-20 Under Drafting Link 158 0 0%

2 SHYB-360 CP (SAB-52) 111 No Native Files

3 SHYB-470 TIE-IN (SAB-43) 111 11-Jul-20 Under Drafting Link 254 0 0%

4 SHYB-501 TIE-IN (SAB-19) 111 11-Jul-20 Under Drafting Link 145 0 0%

5 SHYB-502 TIE-IN (SAB-19) 111 No Native Files

6 SHYB-620 TIE-IN (SAB-69) 111 11-Jul-20 Under Drafting Link 250 0 0%

7 SHYB-701 TIE-IN (SAB-67) 111 11-Jul-20 Under Drafting Link 349 0 0%

8 SHYB-702 TIE-IN (SAB-67) 111 11-Jul-20 Under Drafting Link 227 0 0%

9 SHYB-911 GI (SAB-28) 111 11-Jul-20 Under Drafting Link 159 0 0%


No Native Files & RLM
10 SHYB-167 (SAB-54) OHPL 108 *Native File Rcvd -
Empty
11 SHYB-274, 275 CP (SAB-95) 108 18-Jul-20

11 SHYB-211, 212 CP (SAB-95) 108 18-Jul-20 Transmitted

12 SHYB-107 PDHMS & SWC (SAB-32) 108 18-Jul-20

13 SHYB-213 (SAB-77) 108 18-Jul-20 0 0%

14 SHYB-215 TIE-IN (SAB-83) 108 18-Jul-20 0 0%


No Native Files for
15 SHYB-588 CP (SAB-44) 108
DOCS
14 SHYB-589 CP (SAB-44) 108 18-Jul-20 0 0%

15 SHYB-590 CP (SAB-44) 108 18-Jul-20 0 0%