Professional Documents
Culture Documents
Post Qualification Sample
Post Qualification Sample
Technical Proposal
Bid Security Bid Securing Declaration Passed
signed by Rene G. Janducayan,
East Asia Construction,
Incorporated dated November 26,
2014, notarized by Atty. Jose
Romi S. Marañon, with PTR
#2237486, January 7, 2014
Authority of Signing Official Affidavit signed by Rene G. Passed
Janducayan, East Asia
Construction, Incorporated dated
November 26, 2014, notarized by
Atty. Jose Romi S. Marañon, with
PTR #2237486, January 7, 2014
Organizational Chart East Asia Construction, Passed
Incorporated
Contractor’s Certification on East Asia Construction, Passed
Key Personnel Incorporated
Affidavit of Compliance with Affidavit signed by Rene G. Passed
Labor Laws and Standards Janducayan, East Asia
Construction, Incorporated dated
November 26, 2014, notarized by
Atty. Jose Romi S. Marañon, with
PTR #2237486, January 7, 2014
Affidavit of Compliance with Affidavit signed by Rene G. Passed
IRR-A Sec. 17.7.1 Janducayan, East Asia
Construction, Incorporated dated
November 26, 2014, notarized by
Atty. Jose Romi S. Marañon, with
PTR #2237486, January 7, 2014
Financial Proposal
Bid Prices in Bill of Quantities East Asia Construction, Passed
Incorporated
Detailed Estimates East Asia Construction, Passed
Incorporated
Cash Flow by Quarter and East Asia Construction, Passed
Payment Schedule Incorporated
6. Findings:
[ ] Responsive [ ] Non-Responsive
Noted by:
--------------------------------------------------------------------------------------------------------------------------------
DPWH-INFR-56-101005 Page 2 of 2