Professional Documents
Culture Documents
66000XXXXX
SCHEDULE B
ATTACHMENT III
SCOPE OF WORK
1. REFERENCED DOCUMENTS
The technical scope of WORK is specified in the following Volumes listed below
and includes documents or standards referenced therein or elsewhere in the
Contract:
1.2. In addition to the Scope of WORK defined in this Contract, the scope shall be
in accordance with, but is not limited to, the narratives, calculations,
specifications, drawings, reports, and any other related documents listed and
included in the following Control Log:
2.1.1. The scope of the Project Support Building and the Contractor Camps as
set forth in the Job Specification shall be in accordance with:
B-III-1
MP-IK-LSTK / MP-LSTK / IK-LSPB 04/13
Revised 12/16
Saudi Aramco: Company General Use
SCHEDULE B, ATTACHMENT III CONTRACT NO. 66000XXXXX
2.2. All Project Standards not listed above are included in the Specifications,
Drawings, Reports, or Supplemental Project Documents listed in the above
referenced Drawings Control Log.
The project will provide facilities that deliver Arab Heavy (AH) crude oil, export gas
and condensate from the planned Zuluf Central Processing Facility (ZCPF) to the
designated termination points. This Budget Item (BI) comes in support of the Zuluf
AH crude oil increment program, which aims to develop 600 MBCD of AH crude oil
increment from Zuluf reservoir starting with 300 MBCD in August, 2025 and a full
capacity of 600 MBCD in October, 2025. This BI will also account for 200 MBCD of
AH crude oil from Safaniyah reservoir that is planned to come on-stream in the
future.
The total 800 MBCD increment from Zuluf and Safaniyah will be processed at a new
ZCPF which is planned to come to on-stream Dec. 2025. The scope of this project
covers delivery of the produced hydrocarbons from the proposed ZCPF to its
designated customers by installing following downstream pipelines:
B-III-2
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 12/16
Saudi Aramco: Company General Use
SCHEDULE B, ATTACHMENT III CONTRACT NO. 66000XXXXX
In addition, to the three pipelines, the scope of work also incudes, Main line valve
areas, Jump-over areas, Scraper receiving areas as well as the additional four Surge
Relief Skids (SRS) located in existing brown fields of Ras Tanura Terminal (RTT),
Ras Tanura Refinery (RTR), Ju’aymah Terminal (JT) and Ju’aymah Junction (JJ).
CONTRACTOR shall transport the coated pipes from the coting yard to the site.
CONTRACTOR shall provide the necessary lifting and handling equipment to
be used for the loading of the pipes from the coater yard. CONTRACTOR shall
be also responsible to transport all excess coated pipes from the coating facility
or Job Site to any designated area assigned by the Company.
CONTRACTOR shall provide the water required for the hydrostatic testing of
the mainline pipeline, valves, piping and any other facility that may require
hydrostatic testing per SAUDI ARAMCO standards.
Contractor shall construct evaporation ponds so that when the hydrostatic test
is completed, the water shall be drained to these evaporation ponds. Any other
method of water disposal shall be pre-approved by SAUDI ARAMCO.
4.3.1.
B-III-3
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 12/16
Saudi Aramco: Company General Use
SCHEDULE B, ATTACHMENT III CONTRACT NO. 66000XXXXX
The total number of crews shall increase if the work progress is not in
line with the plan and as directed by the COMPANY Representative for
no additional cost to the COMPANY.
Surveying crew
QA/QC crew
Inspection crew
Right of Way construction crew
Stringing crew
Welding crew
Automatic Ultrasonic Testing (AUT) / X-Ray/ Non-Destructive
Testing (NDT) crew
Coating crew
STOPAQ crew
Trenching / Excavation crew
Roads Crossing crew
Lowering crew
Tie-in crew
Backfilling crew
Berming and Stabilizing crew
Communication crew
Instrumentation crew
Electrical & CP crew
Cleaning & Gauging crew
Hydrostatic test crew (includes Water filling, dewatering, drying
runs)
Safety Crew
The number of sub crews shall be provided in accordance with the site
progress requirement to meet the critical milestones dates as set forth in
Schedule “B”, Attachment II.
B-III-4
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 12/16
Saudi Aramco: Company General Use
SCHEDULE B, ATTACHMENT III CONTRACT NO. 66000XXXXX
Surveying Crew
QA/QC Crew
Site prep crew
Civil and Structural Crew
Prefab crew
Material receipt and inventory crew
Welding crew
X-ray crew
Pipefitting crew
Coating crew
Crane/Heavy lifting crew
Torqueing crew
Tie-In crew
Mechanical crew
Instrumentation crew
Electrical crew
Communications crew
Hydrostatic test crew (includes Water haul, filling, dewatering,
drying)
Safety crew
The number of sub crews shall be provided in accordance with the site
progress requirement to meet the critical milestones dates as set forth in
Schedule “B”, Attachment II.
5.1.1. Photographs.
CONTRACTOR shall apply for and obtain Photo Permits at WORK Site
before photography will be authorized, as described in Attachment 3 of
this Procedure.
B-III-6
MP-LSTK / MP-IK-LSTK / MP-IK-LSPB 04/13
Revised 12/16
Saudi Aramco: Company General Use