You are on page 1of 5

N I TTR

NI R IC
C A CI
C D ALAR
A L AR
AL A R M A N D SAF
ARM SAA FE
F E TY
FETYT SSYS
YS
S TE
TEMM

Improved safety system


in a nitric acid plant
T
he nitric acid production process is a production lines with an overall production
The existing alarm and safety
very demanding process from a safety capacity of 810 t/d of 100 % HNO3. The
system in a nitric acid plant standpoint. Special attention must be original alarm and safety system in the
taken regarding power recovery by the turbo nitric acid plant at Petrokemija consisted of
in Croatia was replaced by a
set and the reactor section. The turbo set is a combination of an electrical relay-based
new microprocessor-based the mechanical equipment that drives the safety system and transistorised alarm
air and nitrous oxide compressors. In the modules. However, over the years, it had
system in order to increase
reactor section, there are special precondi- become very unreliable and it was neces-
the safety requirements tions relating to the exothermal reactions sary to revamp and upgrade it to a new
and to modernise the involving the oxidation of a gaseous mixture microprocessor-based system. The original
of ammonia and air. In order to prevent dis- system provided the following functions,
production process. The astrous consequences and hazards, the which were also required in the new system:
nitric acid production process must be con- ● logic inputs and outputs for the first fail-
main task of such a system
tinuously monitored using control and safety ure sequence;
is to continuously monitor all systems. A control system is considered to ● switching off the motors;

important process parameters be safety related if it provides functions that ● control using NO (normal open) con-
significantly reduce the risk of a hazard, tacts and alarm signal repetition with
and quickly inform operators and in combination with other risk reduction visual and acoustic control.
about potential dangers that measures, reduces the overall risk to a tol-
erable level, or if it is required to function, The existing system was replaced in three
could lead to disastrous maintains or achieves a safe state for the phases: the analysis phase, the imple-
consequences and associated equipment under control. mentation phase, the operation and main-
tenance phase. All three phases were
hazards. The project scope carried out in accordance with the interna-
Petrokemija is a fertilizer producer located tional standard IEC 61508 and IEC 61511
Above: Petrokemija nitric acid in Kutina, Croatia. Nitric acid is produced for the functional safety of safety instru-
plant in Kutina, Croatia. in a dual pressure process in two identical mented systems.

Nitrogen+Syngas 322 | March -April 2013 49


NITRIC ACID ALARM AND SAFETY SYSTEM

Table 1: Main causes and effects for emergency shutdown procedure

Possible causes Effects


Emergency STOP pushbutton in the control room 1. Closing the two electrical solenoid valves at the pipe of the gaseous
ammonia and opening the startup relief valve.
Emergency STOP pushbutton at the local control panel
of the turbo set 2. Closing the extraction valve of the nitric acid from the absorption tower.

Steam turbine overspeed 3. Closing the inlet valve of the quenching water before the steam super
heaters.
Tail gas turbine overspeed
4. The recirculating pump for the steam super heaters is stopped.
Axial displacement of air compressor rotor
5. Emergency shutdown procedure of the turbo set, quick trip, which
Axial displacement of nitrous gas compressor rotor comprises:

Axial displacement of steam turbine rotor 5.1. Closing the steam inlet valve for the steam turbine.

Axial displacement of tail gas turbine rotor 5.2. Opening the relief valve of the air compressor to the atmosphere.

Low pressure of the lubrication oil for the turbo set 5.3. Opening the relief valve of the nitrous gas compressor to the
atmosphere.
Low pressure of the vacuum in the steam turbine
condenser 5.4. Closing the inlet valve for the tail gas turbine.

Low temperature of the tail gas before the DeNOx reactor 5.5. Opening the bypass valve of the tail gas turbine to relieve it.

Low temperature of the tail gas after the tail gas turbine 6. Closing the control valve of the liquid ammonia for the DeNOx system

Fig 1: ESD and alarm system configuration Defects and safety effects in
production
ES/OS OS
operator & engineering station operator station Two different sets of defects were recog-
nised at the Petrokemija plant. Defects
I represents the most serious defects in
production, after which the emergency
shutdown procedure for the whole process
(turbo set and process unit) must be con-
ducted as soon as possible. In the case of
the defects II, the process unit must first
be shut down, while the power recovery
with the turbo set may remain operational
for three minutes to ensure the proper blow
down procedure for all parts of the equip-
industrial ethernet ment and pipes in the nitric acid production
redundant process unit. Both defects I and II result
in the corresponding safety effects in the
AS41 7 H /F
production: the protection of process equip-
ment and process staff in order to avoid
possible hazardous situations. Table 1
shows the main causes and effects of
the emergency shutdown sequence and
ET200M failsafe
DP (redundant)

Table 2 lists the same for the normal


shutdown sequence. Each cause will auto-
standard

ET200M matically and simultaneously trigger all the


effects that are listed in the right-hand col-
ET200M umn of the Tables 1 and 2.
In addition to the already mentioned
PROFIBUS
-

ET200M signal safety causes and effects, there are further


alarm states, trips and interlocks for proc-
ess parameters that trigger an alarm as
a preliminary warning so the operator can

50 Nitrogen+Syngas 322 | March - April 2013


NITRIC ACID ALARM AND SAFETY SYSTEM

Table 2: Main causes and effects for normal shutdown procedure

Possible causes Effects


Very high level of liquid ammonia in the ammonia 1. Closing the two electrical solenoid valve at the pipe of the gaseous
evaporator ammonia and opening the startup relief valve
High pressure of the gaseous ammonia after ammonia
evaporator 2. Closing the extraction valve of the nitric acid from the absorption tower.

Low pressure of the air for the oxidation with the 3. Closing the inlet valve of the quenching water before the steam super
gaseous ammonia heaters.
Malfunction of the boiler feed water recirculation in the
water jackets of the burners 4. Stop of the recirculation pump for the steam super heaters.
Malfunction of the recirculation of the boiler feed water
in the boiler 5. Normal shutdown procedure of the turbo set after 3 minutes, slow trip,
which comprises:
Very high level of the nitric acid in the separator before
the inlet of nitrous gas compressor 5.1. Closing the steam inlet valve for the steam turbine.
Low pressure of the cooling water
Low pressure of the instrumental air 5.2. Opening the relief valve of the air compressor to the atmosphere.

High temperature of the catalytic gauzes


5.3. Opening the relief valve of the nitrous gas compressor to the
Failure of the electrical power atmosphere.
Normal STOP pushbutton in the control room
5.4. Closing the inlet tail gas turbine.
Normal STOP pushbutton at the local control panel of
turbo set
5.5. Opening the bypass valve of the tail gas turbine to relieve it.
Low temperature of the tail gas before the DeNOx reactor
Low temperature of the tail gas after the tail gas turbine 6. Closing the control valve of the liquid ammonia for the DeNOx system.

take the necessary action to prevent an integrity level is 1, which means that the and operator station. It is supplied from
unexpected shutdown. The possible alarm probability of the failure on demand is a new UPS.
states, trips and interlocks are listed in between 10-2 and 10-1 per year with a All the process safety conditions have
Table 3. They refer to both production lines. risk reduction factor of between 10 to 100. been implemented in the SIMATIC Safety
Matrix, which is the basis for the new
Determination of safety instrumented Decision for a new process control alarm and safety system. The key condi-
functions and safety integrity level and safety system tion was the recognition of the first alarm
responsible for the shutdown sequence,
One task when analysing all of the possi- The SIMATIC PCS 7 process control and regardless of whether it is an emergency
ble hazardous process states in the nitric safety system was chosen to replace the or normal shutdown procedure.
acid production at Petrokemija, was gen- old Praxis electrical relay safety and tran- The SIMATIC Safety Matrix was config-
erating the logic diagram that determines sistorised alarm system. ured as engineering (ES) and operator sta-
the recognised causes and consequen- The new SIMATIC PCS 7 alarm and tion (OS). Siemens implemented the cause
tial safety protection effects of the safety safety system from Siemens combines and effect method defined by the Ameri-
equipment and devices. The logic diagram the functionality of a classic distributed can Petroleum Institute in the API RP 14C
represents every possible hazardous state control (DCS) and logical systems in a guideline and safety standards in accord-
listed in Tables 1 and 2. These possible common hardware and software platform ance with IEC 61508 and IEC 61511 pro-
causes are entered in an interactive digital with integrated engineering tools and oper- viding functional safety up to SIL 3.
logic simulator CEDAR LS in order to verify ator interface. Thanks to SIMATIC Safety The operator interface was defined in
the correctness and functionality of the Matrix, it meets safety standards up to the form of the process diagrams, alarm
logic diagram. Safety Integrity Level 3 (SIL3) according to and working groups. The standard and
Other tasks included the identification IEC 61508 and IEC 61511. failsafe I/O modules for the digital/analog
of the safety instrumented functions and The system comprises (see Fig. 1) inputs/outputs of the process variables,
determining the safety integrity level by one redundant central controller SIMATIC including EX protection were installed in
using the risk graph technique in a sys- AS 417-FH with integrated safety func- the four Simatic ET200M I/O racks. Finally
tematic team approach. With the help of tion, four SIMATIC ET200M I/O racks with the new system was connected to all proc-
the risk graph technique the safety instru- redundant PROFIBUS DP interface, indus- ess safety equipment in the field, includ-
mented functions as shown in Table 4 trial Ethernet (system bus, terminal bus), ing new solenoid valves, where the control
have been identified. and operator interface in the form of the voltage has been changed from 380 V to
It can be concluded that the safety combined operator/engineering station 24 V or 220 V.

Nitrogen+Syngas 322 | March - April 2013 51


NITRIC ACID ALARM AND SAFETY SYSTEM

Table 3: This list shows the alarm states, interlocks and trips for common situations in both production lines

Possible alarms, trips and interlocks Processing alarms, trips and interlocks

Low and high level of the liquid ammonia in the ammonia evaporator Audible and visual alarms with the necessary
information such as:
Low temperature of the gaseous ammonia after ammonia evaporator

High temperature of the high pressure steam after super heater 1. alarm condition

Blocked oil filter in the oil system for the turbo set 2. part of the plant affected
High temperature of the oil in the oil system for the turbo set
3. description of the required action
High level of condensate in the steam turbine condenser
4. alarm priority
Low pressure of the instrumentation air
Low temperature of the catalytic gauzes in the burners 5. time of the alarm
Low and high level of the boiler feed water in the steam drum
6. status of the alarm
Low and high level of the nitric acid in the bleaching tower
7. grouping and first-up alarms
Low level of the nitric acid in the oxidation tower
8. has priority over lower grade alarms (e.g. the
High level of the nitric acid in the separator at the inlet of the nitrous gas
high alarm is suppressed when a high-high
compressor
alarm is received)
Low and high level of the nitric acid in the absorption tower
Low and high level of the nitric acid in the condenser of the weak nitric acid 9. suppression of the out of service plant alarms

Low volume flow of the de-mineralized water for the absorption tower 10. suppression of the selected alarms during
certain operating modes
Low pressure of the high and low pressure steam

Low level of the boiler feed water in the reactor 11. automatic load alarm, load shedding and
shelving
Low and high level of the nitric acid in the storage reservoirs for the nitric acid

Malfunction of the boiler feed steam pump

Malfunction of the nitric acid pump for the end users

Malfunction of the nitric acid circulating pump through the oxidation tower

Malfunction of the extraction pump for the weak nitric acid from the condenser of
the weak nitric acid

Malfunction of the extraction pump for the condensate from the condenser of the
steam turbine

Malfunction of the boiler feed water circulating pump

Malfunction of the nitric acid circulating pump through the absorption tower Easy
Malfunction of the de-mineralized water pump for the absorption tower engineering
with Simatic
Low and high temperature of all other process parameters involving all process PCS 7
streams (air, ammonia, nitric acid, steam, etc.)

Table 4: Values of the determined safety instrumented functions in the nitric acid production at Petrokemija

Category of the safety instrumented function Description


The consequential severity of the accident being C2 Injury or occupational illness but no lost time
prevented

The pre-safeguard likelihood of the accident W4 Expected to occur frequently (for example, once a month)

The presence in the hazardous zone F1 Rare to more frequent exposure in the hazardous zone

The probability of avoiding the hazardous event P1 Possible under certain conditions

52 Nitrogen+Syngas 322 | March - April 2013


NITRIC ACID ALARM AND SAFETY SYSTEM

A final dedicated testing and Above: Petrokemija nitric acid


plant in Kutina, Croatia.
training phase
The implementation was followed by test- Right: The absorption tower in
ing according to Tables 1 to 3, realised Petrokemija’s nitric acid plant
according to the guidelines for alarm in Kutina, Croatia
systems such as EEMUA 191 and CHID
Circular CC Tech safety 9 and finally the
SIMATIC Safety Matrix. The upgrade was “The selected alarm and safety system
successfully concluded with a training and is based on the SIMATIC Safety cause &
introduction course for the process staff effects matrix. This method has proven
(a team of 20 operators). From the very to be an extremely effective option for
beginning, the system operated without describing safety functions and for defin-
any malfunctions. ing marginal and shut down conditions,”
The complete project, from the analy- says Mr. Nenad Zecevic, Head of DUKI 1,
sis phase through commissioning and Petrokemija.
validation to training and implementation, “With the upgraded alarm and safety
took approximately one year, and was system, improved safety measures have
completed in January 2011. It was mainly been implemented in the production of
carried out by the process and main- nitric acid at Petrokemija, and it has cre-
tenance staff of Petrokemija. Siemens ated the basis for further improving the
Croatia supported the migration and safe production process in the form of better
commissioning. analysis of the safety issues,” added Mr.
A well-structured project, good engi- Ivan Hoško, Lead Automation Engineer
neering practice of the teams and required DUKI 1, Petrokemija. ■
safety integrity level meant that the
upgrade of the alarm and safety system Acknowledgement
in the nitric acid production at Petrokemija This text is based on the article of Nenad
went smoothly. Zečević, Ivan Hoško and Sven Pavlaković
Further, this project formed the basis published in Kemija u industriji: N. Zečević,
for the replacement of the existing pneu- I. Hoško, S. Pavlaković, Nitric acid revamp
matic control system and for improve- and upgrading of the alarm and protection
ments in the DeNOx system as well as in safety system, Kem. Ind. 61 (4) (2012)
trending and reporting. 205–214.

54 Nitrogen+Syngas 322 | March - April 2013

You might also like