METHOD OF STATEMENT
FOR
STEEL STRUCTURE MULTIPLE LIFTING WORKS
Revision : 0 1 2 3
Prepared by;
Reviewed by:
QA/QC
Reviewed by:
HSE
Reviewed by:
JGC
Reviewed by:
SAPMT
Approved by:
Issue Purpose:
METHOD OF STATEMENT
TABLE OF CONTENTS
1.0 PURPOSE……………………………………………………………………........ 3
2.0 SCOPE……………………………………………..……………….……….3
4.0 RESPONSIBILITIES……………………………………………….……….4
Sheet 2 of 12
METHOD OF STATEMENT
1.0 PURPOSE
1.1 The purpose of this method statement is to provide the requirements and construction
methology or the installation works of steel structure in JAZAN REFINERY and TERMINAL
PROJECT Package 12-Aromatic and Naphtha Area.
2.0 SCOPE
2.1 This method statement shall cover procedure for the installation works of steel
structure in JAZAN REFINERY and TERMINAL PROJECT Package 12- Aromatic and
Naphtha Area. This also includes general requirements for job specifications, quality
assurance workmanship and required safety procedures for the correct implementation and
completion of work.
Sheet 3 of 12
METHOD OF STATEMENT
3.3.1 SATIP-M-001-01 Structural Steel for pipe rack, Steel supports and
Miscellaneous
4.0 RESPONSIBILITIES
1.1 Construction Manager shall be responsible for all HSE matter and to study, analyze and schedule
all construction activities with his department to include manpower and equipment line up as well as
other possible resources required for the successful implementation of the construction work
activities. Study all aspects of work procedure as per DEC/JGC technical scope of work.
1.2 Structural supervisor shall study and review all necessary documents for the installation works in
his area to include, technical scope of work, specification, bill of quantities, planned milestone dates
and construction procedure.
1.3 Structural foreman shall be responsible for the direct work supervision at site to ensure that the
work will be performed in accordance with DEC/JGC Technical Scope of work and latest approved
for construction drawings. He shall monitor the availability of materials in line with his required
schedule.
1.4 The Surveyor shall be responsible to check the verticality alignment of side panel to ensure that all
panels are aligned.
1.5 QC Inspector shall be responsible of monitoring and inspection of the work to ensure that the work
is performed in accordance with DEC/JGC Technical Scope of work and Standards.
1.6 Safety Supervisor / Officer shall be responsible in monitoring safety aspects and ensuring that the
work will be done in accordance with DEC/JGC Safety Standard Procedure. He shall give
reminders or advise to the workers to do the activity safety.
5.0 MANPOWER
5.1 Manpower will consist of the following, but not limited to as listed below.
5.1.1 Supervisor
5.1.2 Foreman
5.1.3 Erector
Sheet 4 of 12
METHOD OF STATEMENT
5.1.4 Surveyor
5.1.5 Rod man
5.1.6 Crane Operator (Aramco Certified)
5.1.7 Man lift Operator (Aramco Certified)
5.1.8 Scaffolder
5.1.9 Safety Supervisor / Officer
5.2.0 Helpers
5.2.1 QC Inspector
7.1.1 When unloading materials delivered to the job site, method of unloading shall be done
enable to minimize damage of painted surface.
7.1.2 Unloaded structural materials should be segregated properly according piece mark
number for immediate identification.
7.1.3 Material that has damage during or after unloading shall be replaced or repaired to the
original condition.
8.0 PREPARATORY WORKS.
Sheet 5 of 12
METHOD OF STATEMENT
8.1 Site access shall be done, and safe access for all intended site vehicles including delivery
vehicle and cranes for the area where to install the steel structure.
8.2 Storage and erection area location of area shall be clean, level and ready.
8.3 Clearing of obstructions, below ground, above ground or any overhead obstructions.
8.5 Using approved and latest drawings, verification of dimension.
8.6 Any unsatisfactory conditions of pedestal and anchor bolts shall be subject for rectification
prior to erection of steel structure.
8.7 Coordinate the availability of materials and accessories in accordance with the proper
sequence of installation works.
8.8 Anticipate any obstruction or interference of installation works, position of the crane and man
lift as per installation plan.
8.9 Man lift shall be used during erection work to removed the sling, bolting and bolt tightening
the bolt.
8.10 Barricade the working area and provide safety caution sign.
8.11 Scaffolds shall be provided with adequate and safe access to and from the work platform.
Sheet 6 of 12
METHOD OF STATEMENT
12.1 Approved work permit should be obtained prior to start any repair works.
12.2 Work Execution shall be carried out in accordance with this method of statement.
12.3 All crew must carried out a safety risk assessment prior to start of any new activity.
12.4 The necessary manpower inclusive of supervisory staff, tools, equipment, materials,
and other resources required must be available and ready to use.
12.5 Workers should wear their PPE’s always.
12.6 Good housekeeping must be maintained in the duration of works.
Sheet 7 of 12
METHOD OF STATEMENT
12.7 Safety Supervisor / Officer shall monitor compliance of entire working crew for the safety
procedure until the work is fully completed.
12.8 DEC/Subcontractors shall make sure that all be incident and injury free.
12.0 ATTACHMENT:
Sheet 8 of 12
METHOD OF STATEMENT
Sheet 10 of 12
METHOD OF STATEMENT
Sheet 11 of 12
METHOD OF STATEMENT
Sheet 12 of 12
METHOD OF STATEMENT
Safety Helmet Face Shield Goggle Barricade Harness Hand Gloves Safety Shoes
Ear Plug Coverall Safety Glasses Work Permit Fire Extinguisher Dust Mask Others
Sheet 13 of 12