Professional Documents
Culture Documents
Push button and switch in the offices for lighting retrofit 18 Dec 2019 Shell
Enclosure
We confirm that the Shop drawing / Enclosure hereby submitted is suitable for the conditions of use Signed
and conforms with the contract specifications and all applicable codes, standards and statutory
Drawing
requirements. We confirm that no variation in the contract sum is implied or claimed by this
submittal sheet. Acceptance of this material submittal does not alter in any way whatsoever our Name: Other
contractual or common obligations and responsibilities. Where the submittal is in any way in
Eyad Mohammed Refai Calculation
variance with the specification, such variations must be identified and brought to the attention of the
project management representative on this form. Project management acceptance will be invalidated Schedule
if such variations are not identified Contract Specification Clause Ref.:
Signature:
Eyad Mohammed Refai
Switch box -water SRM/Shell/STR/MS/001/A 00 18 Dec 2019 GEWISS Switch-Box GW27 041
tight enclosure
switch Visual inspection 00 18 Dec 2019 GEWISS one- way Switch GW20 501
Project Manager REPRESENTATIVE A: Work may C: Revise and Resubmit Work may
DATE RECEIVED proceed not proceed
Signature________________________________Date______
_________