Professional Documents
Culture Documents
Disain Stabilisasi Tanah
Disain Stabilisasi Tanah
Design C B R o f R O A D
STABILIZATION METHOD REPLACEMENT METHOD (RED SOIL)
CBR after stabilization, CBR1= 10.00 % CBR after stabilization, CBR1= 6.00 %
CBR2= 5.48 % CBR2= 0.91 %
CBR original soil, CBR3= 0.95 % CBR original soil, CBR3= 0.91 %
Thickness of stabilization, Z= 58.28 CM Thickness of stabilization, Z= 92.91 CM
Design CBR, DCBR = 4.00 % Design CBR, DCBR = 4.00 %
Design T E M P O R A R Y R O A D
E xa m p l e o f
SOIL STABILIZATION PROPOSAL
for ROAD DESIGN
1. INTRODUCTION
At Karawang West Java, a factory will be constructed soon. We propose the soil stabilization to improve
and increase strength of soil in this area.
Soil stabilization can be is used for :
a. Increasing Bearing Capacity of subgrade. e. Making Separator Layer.
b. Decreasing expansion of expansive soil. f. Making Beam Effect, etc.
c. Reduce the damage caused by settlement.
d. Making Impermeable Layer
2. SOIL CONDITION
There are two kinds of soil at site. We carried out the trial mix of soil stabilization test.
Page 2
Example Road Design
Moisture
Soil Color Content Wet Soaked
Swelling
Density CBR
Soil (1) < Surface> Yellowish 45.00 % 1.737 t/m3 5.10% 1.91%
Brown
Soil (2) <Bottom> Reddish 45.45% 1.722 t/m3 2.53% 1.77%
Brown
According to the "General Guidelines for Road Asphalt Pavement" issued by Japan Road Association, weak
soil (CBR<3%) should be replaced with borrowing material or should be stabilized so that the CBR
exceeds 3%.
For design, 15% is taken as CBR after stabilization and design CBR assuming equals 5 %.
Design CBR :
Page 3
Example Road Design
3
(Z-20) x CBR11/3+ 20 x CBR21/3+ (100-Z) x CBR31/3
=
100
where ,
CBR1 : CBR after stabilization (%)
maximum CBR for stabilized soil should be less or equal 20 %.
CBR2 : CBR for decreasing layer (%)
CBR2 = (CBR1+CBR3)/2
CBR3 : CBR for original soil (%)
Z : Stabilized Thickness (cm)
(CONSTRUCTION) ( DESIGN )
CBR1
Z-20
Stabilized Layer
Z
CBR1
100 100
Decreasing Layer
20
CBR2
Page 4
Example Road Design
Design CBR :
3
(Z-20) x CBR11/3+ 20 x CBR21/3+ (100-Z) x CBR31/3
= > 5%
100
3
(Z-20) x 151/3+ 20 x ((15+1.77)/2)1/3+ (100-Z) x 1.771/3
= > 5%
100
From the above equation, required thickness (Z) of stabilization becomes as follows :
Z= 46.74 cm ~ 50 cm
Page 5
Example Road Design
Considering of the differences between mixing method at site and at laboratory, ratio of strength at
site to that at laboratory is taken = 0.5, so :
Based on the result of CBR test at laboratory and from "Chart Relationship Mixing Rate vs CBR" , required
Agent & Mixing Rate is :
5. CONCLUSION
SOIL (1) <Surface>
Design CBR 5%
CBR of original soil soil 1.91%
Swelling 5.10%
Target CBR after stabilization 15%
Swelling 0.65%
Required strength at CBR= 30 %
laboratory
Stabilizing Agent Soil Stabilization Agent
Slab 20 cm
Thickness of improved 45.29 ~ 50 cm
layer Lean Concrete 10cm
Mixing rate 80 kg/m3
Crushed Stone 15 cm
SOIL (2) <Bottom>
Design CBR 5%
CBR of original soil soil 1.77% Subgrade
Page 6
Example Road Design
By the stabilization of 50cm which aims at the CBR of stabilized layer 15%, it is possible to raise design CBR
to 5% and reduce expansion of expansive soil.
6. CONSTRUCTION WORK
Page 7
Example Road Design
FIELD TEST
ting the types of heavy equipment
used and determining the standard
for job control.
- Compact by roller
- Use crawler of heavy equipment
C O M PACT I N G such as back hoe, bulldozer,
,etc,. for compaction, in case
that the stabilized layer is
still too weak for roller to run.
Page 8
Example Road Design
1) PREPARATORY WORK
(a) Drainage
On condition that construction site has pools or a high groundwater level. it is necessary to trench tempo-
rary drains so as to prevent water from running into the site.
(b) Removal of foreign materials
Before construction. stumps and roots of plants. concrete fragments, boulders, rubbish and so on should be re-
moved.
(c) Control of moisture content
This method, in general. does not require moisture content control. However on condition that soil is too dry
to be hydrated, it is required to add water until the moisture content of soil reaches around optimum.
2) FIELD TEST
In case of a special or large scale project. it is recommended that a field test should be executed for
checking the following items.
(a) Mixing efficiency
Page 9
Example Road Design
Confirm availability and efficiency of the heaviy equipment used for mixing work at site.
Also confirm propriety of the mixing way ( dry mixing or slurry mixing). the mixing rate prescribed by results of
laboratory test and so on.
(b) Applicability
Determine construction method ( especially mixing method), type and number of heavy equipment used and so
on.
(c) Strength of Stabilized Layer
Observe the achievement of target strength.
(d) Influence of construction on environmental factors
Sound the noise, vibration and dust caused by the construction work.
4) SPREADING
Stabilizing agent can be spread by man power (for 40 kg bag) or by back hoe (for 1 ton jumbo bag).
5) MIXING
As the accuracy of mixing is the most important factor of effectiveness of the stabilization. Site supervisor
must control the activities of operators for mixing work as carefully as possible. Conceptionally the powder
Page 10
Example Road Design
of stabilizing agent should become unable to be distinguished from original soil after mixing.
6) GRADING
On finishing mixing. grading should be conducted in advance of compaction. because it is difficult to reform
the undulated of strengthened surface after compaction.
7) COMPACTION
It is possible that delay of compaction work causes less strength than required, so it should be done within
3 hours after mixing. In other word. site work should be scheduled to be completed by compaction every day.
8) CURING
During the construction work the surface should be kept from drying. In case of constructing pavement such
as surface course or upper base course overlying the stabilized layer, it should be made as earliest as possible.
9) CONTROL TEST
Control test is used to confirm that strength reaches the target after the due curing age.
Page 11
Example Road Design
homogenously.
Page 12
Example Temporary Road Design
E xa m p l e o f
SOIL STABILIZATION PROPOSAL
for TEMPORARY ROAD DESIGN
1. INTRODUCTION
Regarding the damage of slope at Cikampek-Cipularang Toll Road project, we proposed the soil stabilization
for solving problem in this project.
Soil Stabilization is used for :
a. Making Separator Layer
b. Making Impermeable Layer
c. Making Beam Effect
d. Increasing Bearing Capacity , etc.
2. GROUND CONDITION
Assumption the ground condition is as follow :
U.C.S. : qu = 0.27 kg/cm2
= 2.7 t/m2
Cohesion c = qu/2 = 1.35 t/m2 (=13.5 kN/m2)
Internal friction angle f = 00
Wet density gt = 1.8 t/m3 (= 18 kN/m3)
Moisture Content w = 53.0 %
3. DESIGN
16m
3 (+16,8) 4
(+50,8)
C E
c =(+16,7)
qu/2 = 1.35 t/m2 (+50,7)
1 (-50,0) 1:2
8m f = 00
gt = 1.8 t/m3
A (-50,1) B (0,1)
a=26.565o
1 (-50,0)
2(0,0) 6 (+50,-
5 (-50,0) Bearing c = qu/2 = 1000 t/m2 20)
Strata f = 400
Page 13
Example Temporary Road Design
gt = 1.9 t/m3
B. PROPOSE OF SOIL STABILIZATION
6m 16m 9m
4 (+16,8) 5 6
10 (+25,+8) (+50,+8)
11 (+25,+7.25)
Soil Stabilization by Humexset (+15.62,+7.25) D (+50,+7)
1:2 C (+16,+7)
8m Target CBR = 20% c = qu/2 = 1.35 t/m2
f = 00
a=26.565o
A (- B (0,+1) gt = 1.8 t/m3
9 (+5,+2)
50,+1) 2 (-6,0)
1 (-50,0) 3 (0,0)
12 (-50,0) Bearing 13 (+50,-20)
7 (-6,-0.5) T 8 (+5,-0.5) Stratac = qu/2 = 1000 t/m2
f = 400
gt = 1.9 t/m3
0.1W
0.2W 0.2W
0.2W 0.2W
0.1W
Page 14
Example Temporary Road Design
Shape Factor
SHAPE CONTI-
FOUNDATION NOUS SQUARE RECTANGULER ROUND
f(0) Nc Nr Nq
0 5.3 0 3
5 5.3 0 3.4
10 5.3 0 3.9
15 6.5 1.2 4.7
20 7.9 2 5.9
25 9.9 3.3 7.6
28 11.4 4.4 9.1
32 20.9 10.6 16.1
36 42.2 30.5 33.6
>40 95.7 114 83.2
therefore :
Page 15
Example Temporary Road Design
qa = 2/3.{1.3x(qu/2)x5.3}
= 2/3.{1.3x(2.7/2)x5.3}
= 6.20 t/m2 < q = 58.9 t/m2
so the original ground must be improved.
3.2.3. S T A B I L I T Y A T S U R F A C E O F I M P R O V E D L A Y E R
(C a l c u l a t i o n o f R e q u i r e d S t r e n g t h)
2r
q
Z" qa
'
SOIL STABILIZATION Z = Depth of
q" Improved
Layer
q"<qa
qa
Thickness of pavement is 30 cm, dispersed tyre load q' is calculated by Boussinesq's equation as follows :
q'= q[1-1/{1+(r/Z')2}3/2] where :
q : contact pressure
r : contact radius
Z': depth dispersed
therefore :
q'= 58.9 [1-1/{1+(0.18/0.3)2}3/2]
= 21.8 t/m2
Where :
qa' : allowable bearing capacity (t/m2) at surface of improved layer .
g1 : unit weight of soil below foundation (t/m3), or submerged unit weight in case of soil being ground
water.
g2 : unit weight of soil above foundation (t/m3), or submerged unit weight in case of soil being ground
water.
c : cohesion (t/m2), assuming internal frictio angle of ground. f= 0o,c =qu/2
a, b : shape factor, for round a = 1.3, b = 0.3
Nc,Nr,Nq : Bearing capacity coefficient
f = 0o,therefore Nc= 5.3,Nr=0,Nq=3.0
Df : penetration depth(m)
B : minimum width of foundation, or diameter incase of round foundation.
Page 16
Example Temporary Road Design
therefore
qa' = 2/3.(1.3x(qu/2)x5.3)
= 2.296 qu
= 2.296 qu < q = 21.8 t/m2
(contact pressure below pavement)
From the above stability condition, required UCS after improvement is as follows :
qu > 9.49 t/m2 = 0.95 kg/cm2 ==> CBR= 20%
Considering of the differences between mixing method at site and at laboratory, ratio of strength at
site to that at laboratory is taken = 0.5, so :
Based on the result of CBR test at laboratory and from "Chart Relationship Mixing Rate vs CBR" , required
Agent & Mixing Rate is :
2r
q
Z" qa
'
SOIL STABILIZATION Z = Depth of
q" Improved
Layer
q"<qa
Page 17
Example Temporary Road Design
qa
The required thickness is calculated by Boussinesq's equation on assumtion that the tyre load is dispersed up
to below allowable bearing capacity of original ground in the improved layer.
q" = q[1-1/{1+(r/Z")2}3/2]
= 58.9 [1-1/{1+(0.18/Z")2}3/2]
< qa = 6.20 t/m2 (Allowable bearing capacity of original ground)
3.1.6. CONCLUSION
Crushed Stone 30 cm
Allowable bearing
capacity of original ground qa= 6.20 t/m2
Subgrade
Stabilization 50 cm
Thickness of pavement 30cm (CBR>20%)
(Crushed Stone)
Original soil
Required strength at
site CBR= 20 %
Thickness of improved 50 cm
layer
Page 18
Example Temporary Road Design
By 30cm crushed stone for pavement and the stabilization of 50 cm of subgrade which aims at the CBR of
stabilized layer to 20%, it is possible to raise bearing capacity of original ground for support dump truck
with 30ton gross weight and 10 tyre.
4. CONSTRUCTION WORK
Page 19
Example Temporary Road Design
- Compact by roller
- Use crawler of heavy equipment
CO MPACTIN G such as back hoe, bulldozer,
,etc,. for compaction, in case
that the stabilized layer is
still too weak for roller to run.
Page 20
Example Temporary Road Design
1) PREPARATORY WORK
(a) Drainage
On condition that construction site has pools or a high groundwater level. it is necessary to trench tempo-
rary drains so as to prevent water from running into the site.
(b) Removal of foreign materials
Before construction. stumps and roots of plants. concrete fragments, boulders, rubbish and so on should be re-
moved.
(c) Control of moisture content
Stabilization method, in general. does not require moisture content control. However on condition that soil is
too dry to be hydrated, it is required to add water until the moisture content of soil reaches around optimum .
2) FIELD TEST
In case of a special or large scale project. it is recommended that a field test should be executed for
checking the following items.
(a) Mixing efficiency
Confirm availability and efficiency of the heaviy equipment used for mixing work at site.
Also confirm propriety of the mixing way ( dry mixing or slurry mixing). the mixing rate prescribed by results of
laboratory test and so on.
(b) Applicability
Determine construction method ( especially mixing method), type and number of heavy equipment used and so
on.
(c) Strength of Stabilized Layer
Observe the achievement of target strength.
(d) Influence of construction on environmental factors
Sound the noise, vibration and dust caused by the construction work.
4) SPREADING
Stabilizing Agent can be spread by man power (for 40 kg bag) or by back hoe (for 1 ton jumbo bag).
5) MIXING
Page 21
Example Temporary Road Design
As the accuracy of mixing is the most important factor of effectiveness of the stabilization. Site supervisor
must control the activities of operators for mixing work as carefully as possible. Conceptionally the powder
of Stabilizing Agent should become unable to be distinguished from original soil after mixing.
6) GRADING
On finishing mixing. grading should be conducted in advance of compaction. because it is difficult to reform
the undulated of strengthened surface after compaction.
7) COMPACTION
It is possible that delay of compaction work causes less strength than required, so it should be done within
3 hours after mixing. In other word. site work should be scheduled to be completed by compaction every day.
8) CURING
During the construction work the surface should be kept from drying. In case of constructing pavement such
as surface course or upper base course overlying the stabilized layer, it should be made as earliest as possible.
9) CONTROL TEST
Control test is used to confirm that strength reaches the target after the due curing age.
Page 22
Example Temporary Road Design
soil stabilization
Page 23
Example Temporary Road Design
q"
Page 24
Example Temporary Road Design
q"
Page 25
Example Temporary Road Design
Page 26
Example Temporary Road Design
homogenously.
Page 27
Example Temporary Road Design
Page 28
Construction Work
CONSTRUCTION WORK
OF SOIL STABILIZATION
1 ton
bag
Page 29
Construction Work
5. COMPACTING
Page 30
Construction Work
ON
Page 31
Construction Work
Page 32