CATHODIC PROTECTION
APR 2021
Nomor Dokumen
JWFP-UGSP-PRS-PRO-001
V SMH
Sonatry
elec eng
07april21
Nomor Dokumen
JWFP-UGSP-PRS-PRO-001
Nomor PO.
4110097189
Halaman 4 dari 7
Revisi Revisi
Hal Hal
A B C 0 A B C 0
1
2
3
4
5
6
7
Halaman 5 dari 7
RANGKUMAN REVISI
Halaman 6 dari 7
DAFTAR ISI
1 INSPECTION AND TEST PLAN ..................................................................................... 7
Halaman 7 dari 7
2 Document Review & Approval send the approval document to main contractor Sample JWFP-UGSP-PRS-DSS-001 As per drawing/catalog sheet P R2 R1
JWFP-UGSP-PRS-GAD-001
b Dimensional / Weight / Type Visually check the anode and package dimension, net and Sample JWFP-UGSP-PRS-DWG-001 As per drawing, Weight and P W2 W2,R2
gross weight, & type/model to follow the specification/ Dimension Tolerance + 3%
approved drawing
c Anode-Cable Connection Measure the resistance between each anode and cable tail Sample ≤ 0,5 Ohm P W2 W2,R2
d Quantitatives Count the quantity of Magnesium Anode as per approved 100% JWFP-UGSP-PRS-LST-002 As per drawing/Bill of Material P W1 W1
Bill of Material
B Test Point Inspection Record Manufacturer's Standard (MS)
a Visual Inspection Visually check Test Station Box (Cover, Support, Terminal, Sample No Damage P W2 W2,R2
Hinge, Lock, Name Plate) to ensure that workman-ship,
good practice, and finished were maintained during
manufacturing
b Dimensional / Size / Type / Model Visually/measure the goods dimension and type/model to Sample JWFP-UGSP-PRS-DWG-002 As per drawing, dimension P W2 W2,R2
follow the specification /approved drawing tolerance ± 5%.
c Quantitatives Count the quantity of Test Station Box as per approved Bill 100% JWFP-UGSP-PRS-LST-002 As per drawing/Bill of Material P W1 W1