You are on page 1of 14

Reliance Project Management System

Job Safety Analysis


For RIL-J3 Electrical Activities
10080-1-HSEF-CHK-CN-001

Issued for Approval

Rev Date Revision Details Prepared Checked Approved


By By By
Pre-Task Briefing

Work Hazards
Required Safety Measures/PPE
Activity Present
1. Material 1.1 Toppling 1.1.1 Pre lifting plan should be
Handling of hydra prepared before start of lifting any
/crane. materials by crane. It is to be
ensured that it should not cross the
SWL of the crane/hydra.
1.1.2 Before starting of
loading/unloading by crane, the
work area soil condition should be
plain, compacted.
1.2 Fall of
material due 1.1.3. Crane/Hydra boom should
to failure of be kept as low as possible during
sling/lifting shifting of material for shorter
tackles distances
1.2.1 Use only good condition,
tested & appropriate lifting gears,
tools and tackles slings etc.
1.2.2 Inspection of all lifting tools
and tackles before inspection.
1.2.3 Inspection of over hoist limit
switches periodically.
1.2.4 Approach area for the
crane/hydra should be obstacle
free, physical condition of the
approach road should be clear at
all time.
1.2.5 Outriggers must be extended
(For Tyre Mounted Cranes).
1.2.6 Hydra/Crane should not be
1.3 Fall of operated without Signal man.
person or 1.2.7 RA Sheet to be completely
material filled before lifting operations.
from Trailer 1.2.8 Ensure the length of lifted
material doesn’t exceed 6mtrs
1.3.1 While unloading of materials,
workmen should get down from
1.4
trailer after fixing of slings or belt
Electrocutio
before lifting the material
n to
1.3.2 Vehicle should be provided
Crane/Hydra
with vertical stoppers to avoid fall
of materials while vehicle

Job Safety Analysis For Electrical Works


movement.
1.4.1During handling the material
shall be ensured that there is no
HT electrical utilities overhead line
above the work spot
1.4.2 Necessary precautions to be
taken to avoid electrocution
1.5.1 Ensure that vehicular
movement is to be restricted
where the shifting or handling of
material is carried out.
1.5 Run over 1.5.2 Display of proper signage at
due to the conspicuous place.
vehicular
movement 1.5.3 Speed limit should be as per
road safety guidelines.
1.5.4 Only licensed/Certified
Operator should operate the
crane/hydra.
1.5.5 Authorized signal man with
wearing reflective jacket should be
employed.
1.5.6 Shall be ensured that none
takes rest below & around the
parked vehicle; wheel Stopper has
to be provided.
1.5.7 Segregation of pedestrian
pathway at work place shall b
ensured wherever practically
possible.
1.6 Hit by
Object/Load 1.5.8 Ensure that Access should be
kept clear at all the time without
obstacles for having safe access in
case emergency
1.6.1 Tag line must be used to
prevent swing of the load during
lifting/ shifting
1.6.2 During shifting or rigging
activity no person should be
allowed near the swinging area,
Safe distance to be maintained &
the area is to be barricaded.

2. 2.1 Damage 2.1.1 Prior inspection and checking


Transforme of of material before lifting.
r and NGR equipment. 2.1.2 Selection of proper tools and
Erection

Job Safety Analysis For Electrical Works


(Power tackles for the right job.
transformer 2.1.3 Periodically validation of
-10080-1-
equipment and operator shall be
SS-EL-005)/
ensured
Distribution
2.2 Human 2.2.1 Appropriate PPE’s should be
transformer
injury. used.
-10080-1-
SS-EL-006 2.2.2 Safe distance shall be
maintained from the equipments
NGR-10080- 2.3 while lifting.
1-SS-EL-45)/ Movement 2.3.1 Stopper shall be provided on
MV/LV of both sides of the transformer’s
Switch transformer Wheel.
board/Bus due to
duct vibration.
2.4.1 The area should be clear of all
Erection 2.4 Fire. combustibles. If the same is not
possible the combustible should be
(MV Switch
covered with Fire Blanket.
gear-10080- 2.4.2 Fire Extinguisher should be
1-SS-EL-001
available within 30 mtrs of the
LV Switch area.
gear-10080-
2.5 Failure 2.5.1 Visual inspection of lifting
1-SS-EL-002
of lifting tools tackles and crane or hydra for
MV/LV tools and any defects before starting the job.
Busduct tackles/cran 2.5.2 Load to be lifted should be
10080-1-SS- e or Hydra. under the SWL of the crane/hydra
EL-013) at given radius.
2.5.3 Selection of the tools and
2.6 Fall of tackles should be as per the lifted
materials/ load.
equipments. 2.6.1 Slinging of the accessories on
the right slinging points with
2.7 Fall of proper slings of right capacity.
person. 2.6.2 tools and tackles should be
selected keeping in mind the
weight of the material to be lifted.
2.7.1 Proper working platfrom
should be available for work at
height activities.
2.7.2 Full body harness to be worn
and well anchored at suitable
points. 100% tie off to be ensured
at all times.
2.8 Collision
2.7.3 Life Line should always be
of loaded
supplemented with Safety Net.
vehicle with
2.7.4 Any Cut outs in the floor
other
should be properly barricaded.
vehicles on
road. 2.8.1 Route for transportation

Job Safety Analysis For Electrical Works


should be predetermined.
2.8.2 Road Closure permit should
be obtained if required.
2.9 Hitting 2.8.2 Only experience and
of lifted validated driver should be
material to deployed.
other nearby
materials/pe 2.8.3 Optimum speed to be
rsons. maintained while moving with
loaded vehicle(20KMPH) on road.
2.8.4 The driver should follow
defensive driving technique.
2.9.1 Guy rope (2 in number in
opposite side of the load) to be
properly tied to the materials to
control its swinging movement.
2.9.2 Validated Riggers and Signal
man to be deployed for the job.
3. Welding 3.1 Electric 3.1.1 Obtain Hot Work Permit
Work Shock. wherever required
3.1.2 Welding machine should be
routed through ELCB.
3.1.3 Proper earthing should be
provided & ensure Panel
validation.
3.1.4 Welders should wear
additional PPE`s like Coverall, Face
Sheild, Fire resistance hand gloves
etc.
3.2.1 Regular inspections of
3.2 Hot welding machine and power cables
splatters. to be done by electrician.
3.3.1 Face shield should be
provided.
3.3 UV& IR
3.3.2 Leather hand gloves, apron,
rays.
hand and leg sleeves.
3.4.1 Ensure sufficient ventilation.
3.4.2 Ensure welding equipment is
in good condition and daily check
3.4 Heat list should be maintained.
3.5.1 The area should be clear of
3.5 Fire all combustibles. If the same is not
Hazards. possible the combustible should be
covered with Fire Blanket.

Job Safety Analysis For Electrical Works


3.5.2 Fire Extinguisher should be
available within 30 mtrs of the
area.
4. Drilling 4.1 Electric 4.1.1 Inspect the Equipment before
Shock each use and commencement of
Shift.
4.1.2 Ensure the Equipment is
double earthed.
4.1.3 Ensure the Equipment is
routed through ELCB (30 mA)

4.2.1 Ensure Equipment is only


operated by workmen having
4.2 relevant trade validation.
Unauthorize
d operation
4.3.1 Use of task suitable PPE like
Face shield, cut resistant gloves
along with mandatory PPE’s.
4.3 Struck by 4.4.1 Ensure selection of drill bit
flying
particles with respect to the material being
drilled.

4.4 Struck by
broken drill 4.5.1 Ensure the Worker is wearing
bit cut resistant hand gloves.

4.5 Cut
injury

5. Gas 5.1 5.1.1 Obtain Hot Work Permit &


cutting Fire/Explosi Ensure combustible materials
works. on. should be removed from the
working area before start of work.
5.1.2 Fire Extinguisher should be
available within 30 mtrs of the
work location.
5.1.3 Compressed cylinders should
be kept in upright position in
proper storage area separately.
5.1.4 Use of additional PPE`s
Coverall, Face sheild, Apron,
5.2 Back fire. Canvas hand gloves.
5.2.1 Flash back arrestor to be used
at both the end of i.e. cutting torch
and cylinder end.
5.3

Job Safety Analysis For Electrical Works


Damaged
hose & 5.3.1 Ensure all accessaries are in
joints. good working condition and record
daily check list.
5.3.2Hose pipes should be checked
with soap solution to know any
leakage before start of work.
5.4 Dragging
of cylinders. 5.4.1 Trolley to be used during
movement of cylinders.
5.5
Absent 5.5.1 Pressure gauge to be fitted
/Damaged with gas cylinders.
pressure
gauge. 5.6.1 Proper ventilation to be
5.6 Poor maintained.
ventilation.
5.7.1 Spatter arrestor like fire
blanket must be used. (If required).
5.7 Spatter. 5.7.2 Proper manual handling
procedure to be followed.
5.8 5.8.2 Always maintain a good
Improper housekeeping.
material
handling.
6. 5.1 Electric 6.1.1 Obtain Hot Work Permit.
Cutting/Grid Shock Grinding Machine power cable
ing works. should be routed through ELCB.
5.1.2 Double insullation should be
provided.
5.2 Struck by
grinding 5.2.1 Guards should be ensured.
wheel. 5.2.2 The grinding wheel should be
checked for the RPM and the
expiry date.
5.3 5.3.1 Only trained and experienced
Unauthorize grinder to be do the job.
d operation. 5.4.1 The grinding machines should
be inspected monthly basis and
5.4 tagged for fit.
Defective 4.5.1 Additional PPE`s
machine.
Coverall,Face shield, Apron, Hard
5.5 Sparks. hand gloves must be used.
7. Cable 6.1 6.1.1 Ensure all the electrical
tray Electrical connections routed through ELCB.
support/Ca shock.
ble tray 6.1.2 Proper earthing should be
erection
provided to welding machine.

Job Safety Analysis For Electrical Works


(10080-1-
SS-EL-46) 6.1.3 Ensure the proper size and
condition of electrical power cable
of welding machine.
6.2 6.2.1 Flash back arrestor should be
Protection used at both end.
of back
flash.
6.3 Injury to 6.3.1 Cutting machine should be
person while used with guard protection and
cutting of proper PPE’s Should be used.
cable tray
support.
6.4 Damage 6.4.1 Sharp edges should be
of cable smoothened by using grinding
insulation machine.
due to sharp
edge of
cable
tray/support
.
6.5 Fall of 6.5.1 Cable tray should be lifted by
materials. using suitable rope and 2 way
chain pulley block.
6.6 Fall of 6.6.1 Full body harness shall be
person. used while working at height and it
must be anchored at two different
rigid support.
6.7 Injury to 6.7.1 Provision of safety goggles
eyes and and welding shield to welder.
hands (transparent opaque black for
during welder and helper)
welding.

6.8 6.8.1 Ensure provision of


Respiratory respiratory nose mask for
ailments due welder/helper.
to inhalation
of welding
fumes.
6.9 Failure 6.9.1 Visual inspection of lifting
of lifting tools tackles for any defects before
machinery starting the job.
,tools and
tackles.
(4) Cable 7.1 Bending 7.1.1 proper capacity of jack to be
laying/Glan of cable jack used.
ding and with cable
Termination drum. 7.1.2 50 mm MS solid bar upto 5
(HV Cables - ton to be used for cable drum

Job Safety Analysis For Electrical Works


10080-1-SS- shaft.
EL-021
LV Power &
Control
Cables -
10080-1-SS-
EL-022)
7.2 Physical 7.2.1 Proper housekeeping of
injury to cable trench to be done before
workmen starting cable laying job.
while cable
laying in
cable trench.
7.3 7.3.1 Metallic Lock out and tag out
Electrical shall be used while doing cable
shock while termination in live panel to avoid
doing any accident.
glanding and
termination
in live panel.
7.4 Fire and 7.4.1 Proper tightness of cable
burnt due to with busbar should be ensured.
loose
connection 7.4.2 Cleaning of the bus chamber
with
busbar . shall be carried out by using hot air
blower.
7.5 Human 7.5.1 Proper PPE’s should be used.
injury while
lifting. 7.5.2 Safe distance shall be
maintained from the equipment
while lifting of cable drum.

7.5.3 House keeping shall be done


on regular basis.
7.6 Failure 7.6.1 Visual inspection of lifting
of lifting tools tackles/ hydra for any defects
tools and before starting the job.
tackles/Hydr
a.
7.7 Fall of 7.7.1 Full body harness to be wear
person from and well anchored at suitable
height. points.
7.8 Hitting 7.8.1 Nylon rope to be properly
of cable tied to the cable drum to control its
drum to swinging movement.
other nearby
materials/pe
rsons.
7.9 Collision 7.9.1 Optimum speed to be
of loaded maintained while moving with

Job Safety Analysis For Electrical Works


vehicle with loaded vehicle(20KMPH) on road.
other
vehicles on
road.
8. Battery 8.1 8.1.1 Correct postive and negative
and it’s Explosion connection should be ensured.
accessories of battery. 8.1.2 Periodically checking of
erection electrolyte and cleaning of
(10080-1- batteries shall be ensured.
SS-EL-009) 8.1.3 Battery should be stored in
well ventilated area.
8.2 Electric 8.2.1 Skilled and validated
shock. electricians to be deployed while
taking readings during charging
and discharging cycle of batteries.
8.2.2 Electricians should donn all
the mandatory and job specific
PPE’s like rubber glover of proper
rating.
8.3 Human 8.3.1 Proper tools should be used
injury. for open the packing box of
batteries.
8.4 Damage 8.4.1 Prior inspection and checking
of of material/batteries to be done
material/ba before lifting.
tteries.
8.5 Saw 8.5.1 Proper housekeeping to be
dust make a maintained.
respiratory 8.5.2 Ensure provision of
problems respiratory nose mask.
and eye
injury. 8.5.3 Provision of safety goggles to
be ensured.
8.6 Fall of 8.6.1 Skilled workmen to be
batteries deployed for lifting of batteries.
while lifting.
9. Lighting 9.1 Fall of 9.1.1 Full body harness to be
work person from ensured at all time while working
(10080-1- height. at height.
SS-EL-37) 9.1.2 Use of proper scaffolding
with hand rail and ladder shall be
installed for climbing with proper
clamping.
9.2 Injury to 9.2.1 Area below the working area
person due should be barricaded.
to fall of
material 9.2.2 Safety net to be provided.
from height.
9.3 9.3.1 Skilled and validated

Job Safety Analysis For Electrical Works


Electrical workmen to be deployed for doing
shock due to the connection.
improper 9.3.2 No naked wire to be used for
connection. electrical connection.
9.3.3 Ensure electrical connections
with proper plug top.
9.4 Injury to 9.4.1 Provision of safety goggles
eyes and and welding shield to welder.
hands (transparent for cutting M/C
during operator/driller and opaque black
cutting,drilli for welder and helper)
ng, welding.
9.5 9.5.1 Ensure provision of
Respiratory respiratory nose mask for
ailments due welder/helper.
to inhalation
of welding
fumes.
10.1 Injury 10.1.1 Excavated soil to be
10. Earthing to person removed at least 2 mtr away from
(10080-1- due to the excavated area.
SS-EL-46) falling in
excavated
area.
10.2 10.2.1 Proper clearance from
Damaged to electrical and mechanical
under department to be taken to avoid
ground any damage of pre laid
cables. underground cable/pipeline.
10.3 Injury 10.3.1 Provision of safety goggles
to eyes and and welding shield to welder.
hands (transparent for cutting M/C
during operator/driller and opaque black
cutting,drilli for welder and helper)
ng, welding.
10.4 10.4.1 Skilled and validated
Electrical workmen to be deployed for doing
shock due to the connection.
improper 10.4.2 No naked cable to be used
connection for electrical connection.
of welding 10.4.3 Electrical connections to be
machine. done using plug top.
10.5 Injury 10.5.1 working area should be
to person barricaded.
due to fall of
material 10.5.2 Safety net to be provided.
from height.
10.6 Failure 10.6.1 Visual inspection of lifting
of lifting tools tackles for any defects before
machinery starting the job.

Job Safety Analysis For Electrical Works


,tools and
tackles.
10.7 10.7.1 Ensure provision of
Respiratory respiratory nose mask for
ailments due welder/helper.
to inhalation
of welding
fumes.
10.8 Fire. 10.8.1 The area should be clear of
all combustibles. If the same is not
possible the combustible should be
covered with Fire Blanket.
10.8.2 Fire Extinguisher should be
available within 30 mtrs of the
area.
11. HV/LV 11.1 11.1.1 The power cable should be
Motor Electrical routed through ELCB. proper
testing and shock. earthing of motor to be ensured.
commission
ing 11.1.2 Working area should be
(HV Motors barricaded properly and
– 10080-1- unauthorised entry should be
SS-EL-003 restricted.
LV Motors –
10080-1-SS- 11.1.3 All testing Equipments shall
EL-004) be calibrated with proper
calibration certificate.

11.1.4 Arrangement of fire


extinguiser shall be made available
near working area with proper
checking/inspection.

11.2 Human 12.2.1 Proper PPE’s should be


injury. used.
12.2.1 Deployed personnel should
keep their body parts away from
any sharp objects to avoid cut
injury.

12. General 12.1 12.1.1 Daily STA should be given to


habit Adopting workers.
short cut
method,negl
igence,
wrong
perception
using cell
phone.

Job Safety Analysis For Electrical Works


12.2 12.2.1 Emergency escape route
casuality/ should be displayed at different
Emergency. places.

12.2.2 Emergency assembly point


should be displayed at different
places.

12.2.3 Emergency contact nos


should be displayed at working
location.

12.2.4 Emergency vehicle should


be available at site.

13. Loading 13.1 Fall of 13.1.1 STA shall be conducted.


& unloading materials/eq
of materials 13.2.1 Use of validated and
uipment
/ inspected tools & tackles and
equipment 13.2 Failure crane/hydra for loading /unloading
of lifting job.
machine or 13.2.1 Ensure workers /
tools & riggers/crane operator are trade
tackles validated and trained engaged in
the job.
13.3 Topling 13.3.1 Use proper tag line during
of loading/unloading work.
truck/trailer
13.3.2 Removal of unauthorized
persons from the work place.
13.3.3 Ensure proper lacing for
loaded materials on the truck.
14 Working 14.1.1 Ensure Tool box talk /STA is
14.1
at Height being carried out about the
Major/Mino
execution of the jobs and about
r injury due
right tools used by the contractor
to fall of
and the hazards related to work
person from
atheight.
height
14.2 14.1.2. Ensure that the Work
Materials permit procedures are followed if
falling from applicable.
height.
14.3 14.1.3 Ensure that Mandatory PPE
Scaffold are being used i.e. full body
collapse. harness, safety helmet, safety
14.4 Electric shoes, hand gloves, safety glasses,
shock reflective jacket etc.

Job Safety Analysis For Electrical Works


14.1.4 To ensure workers are
engaged in height work has been
attended the “Work at Height
Training”.

14.1.5. Life line, fall arrester, full


body harness with double lanyard
and shock obserber, proper
scaffolding, access ladder, safety
net etc. are provided for height
work.

14.2.1 Workers are engaged at


working height shall be trade
validated, trained & experienced.

14.3.1 Trained and competent


Scaffold inspector shall be
deployed for erection &
dismantelling of scafolds.
Name and Siganture Date

Contractor Supervisor/ In
charge
Field Engineer
Lead Engineer
Reviewed by HSE
Representative
Industrial Hygiene(If
required by HSE)
Note: This JSA has been developed through consultation with all personnel
involved in the task outlined in the JSA
Note: This form is referenced in numerous practices

Job Safety Analysis For Electrical Works

You might also like