1. Material 1.1 Toppling 1.1.1 Pre lifting plan should be
Handling of hydra prepared before start of lifting any
/crane. materials by crane. It is to be
ensured that it should not cross the
SWL of the crane/hydra.
1.1.2 Before starting of
loading/unloading by crane, the
work area soil condition should be
plain, compacted.
1.2 Fall of
material due 1.1.3. Crane/Hydra boom should
to failure of be kept as low as possible during
sling/lifting shifting of material for shorter
tackles distances
1.2.1 Use only good condition,
tested & appropriate lifting gears,
tools and tackles slings etc.
1.2.2 Inspection of all lifting tools
and tackles before inspection.
1.2.3 Inspection of over hoist limit
switches periodically.
1.2.4 Approach area for the
crane/hydra should be obstacle
free, physical condition of the
approach road should be clear at
all time.
1.2.5 Outriggers must be extended
(For Tyre Mounted Cranes).
1.2.6 Hydra/Crane should not be
1.3 Fall of operated without Signal man.
person or 1.2.7 RA Sheet to be completely
material filled before lifting operations.
from Trailer 1.2.8 Ensure the length of lifted
material doesn’t exceed 6mtrs
1.3.1 While unloading of materials,
workmen should get down from
1.4
trailer after fixing of slings or belt
Electrocutio
before lifting the material
n to
1.3.2 Vehicle should be provided
Crane/Hydra
with vertical stoppers to avoid fall
of materials while vehicle
4.4 Struck by
broken drill 4.5.1 Ensure the Worker is wearing
bit cut resistant hand gloves.
4.5 Cut
injury
Contractor Supervisor/ In
charge
Field Engineer
Lead Engineer
Reviewed by HSE
Representative
Industrial Hygiene(If
required by HSE)
Note: This JSA has been developed through consultation with all personnel
involved in the task outlined in the JSA
Note: This form is referenced in numerous practices