You are on page 1of 52

APPENDIX D

ASPECTS & IMPACTS

NCC Received
07/12/2016

Form 7.2U.03
Environmental Aspects & Impacts Register

ASPECT DETAILS CRITERIA CONTROLS/RESPONSIBILITIES IMPACT SIGNIFICANCE


(i) Plan of Work in place before any work starts
Asbestos Asbestos removal works Control of Air pollution High (if breach of
(ii) Strictly controlled removal
Removal either in association with Asbestos Land enclosure)
(iii) Enclosures constructed for fibrous asbestos
demolition works or as a Regulations Contamination
Responsibility Low (controls applied)
removal contract
(i) QHSE Manager, Director (Contracts)
Asbestos Manager
(ii) Asbestos Supervisor
(iii) Asbestos Supervisor

NCC Received
(i) Suitable skips line with polythene if required
Disposal of Asbestos removal works Hazardous Land High
(ii) Waste collected by Licensed waste carrier

07/12/2016
Asbestos either in association with Waste Contamination
Responsibility
Waste demolition works or as a Regulations
(i) Asbestos Supervisor
removal contract 2005
(ii) Asbestos Supervisor

(i) Method Statement(s) and COSHH


Disposal of Dismantling/Demolition of Hazardous Land High
Assessments in place before works start
Hazardous contaminated Waste Contamination
(ii) Spill kits available
Chemicals/ vessels/associated Regulations Water
(iii) De-commissioning/cleaning documentation
Substances pipework 2005 Pollution
from Client
COSHH (iv) Waste collected by Licensed waste carriers
Regulations Responsibility
(i) QHSE Manager, Director (Contracts),
Contracts Manager, Site Supervisor
(ii) Safety & Quality Director, Managing Director
(Contracts), Engineering Manager, Site
Manager
(iii) Site Supervisor
(iv) Site Supervisor

Form 7.2U.03
Environmental Aspects & Impacts Register

ASPECT DETAILS CRITERIA CONTROLS/RESPONSIBILITIES IMPACT SIGNIFICANCE


Noise Use of demolition Environmental (i) Demolition of Buildings undertaken with a Nuisance Low/Medium
Plant/Equipment Protection Act suitable method to minimise noise/vibration Noise
Compressors/Generators 1990 (ii) All plant to be effectively silenced, serviced
Part III and maintained
Noise at Work (iii) Compressors and generators to be of super
Regulations silenced type
(iv) Strict Control of working hours to be
maintained
Responsibility
(i) QHSE Manager, Director (Contracts),

NCC Received
Contracts Manager, Site Supervisor
(ii) Plant Manager, Site Supervisor
(iii) Plant Manager, Site Supervisor

07/12/2016
(iv) Site Supervisor

Dust/ Demolition/Dismantling of Pollution (i) Demolition undertaken with suitable methods Air Pollution Medium
Particulate Buildings/Structures Prevention to minimise dust/particulate emissions
emissions Control (ii) Ensure adequate controls in place
Regulations (iii) Damp down as appropriate
Environmental Responsibility
Protection Act (i) QHSE Manager, Director (Contracts),
Contracts Manager, Site Supervisor
(ii) QHSE Manager, Director (Contracts),
Contracts Manager, Site Supervisor
(iii) Site Supervisor

Form 7.2U.03
Environmental Aspects & Impacts Register

ASPECT DETAILS CRITERIA CONTROLS/RESPONSIBILITIES IMPACT SIGNIFICANCE


Pollution Demolition/dismantling Public/Third (i) Ensure spill kits available Air, land and Medium
arising from activities party concerns (ii) Emergency procedures documented and all water pollution
Incidents, Plant Operation personnel given instruction with regards to their
spills leaks or individual actions/responses
fire Responsibility
(i) Safety & Quality Director, Managing Director
(Contracts), Engineering Manager, Site
Manager
(ii) Plant Manager, Site Supervisor
(iii) QHSE Manager, Director (Contracts),

NCC Received
Contracts Manager, Site Supervisor

07/12/2016
Use of Energy Electric, gas and water Economic use of (i) Metered use energy/water with care Resource Medium
usage unsustainable (ii) Ensure all equipment is designed to depletion
resources minimise consumption
Responsibility
(i) Plant Manager, Yard Manager, Site
Supervisor
(ii) Directors, Commercial Manager, Plant
Manager
Use of Fossil Vehicles, plant and Economic use of (i) Vehicles plant and equipment serviced and Resource High
Fuels equipment usage unsustainable maintained to ensure optimum fuel depletion
resources consumption Global
Responsibility warming
(i) Plant Manager, Site Supervisor

Form 7.2U.03
Significance Register
Aspect Scope Significance Score

Severity Probability Duration Legislation Total Significance


1. Waste Oil
2 3 2 4 48 HIGH
2. Old parts-disposed as metal
scrap Yard 1 1 1 2 2 LOW
3. General waste – disposed to
landfill All sites 2 3 2 4 48 HIGH
4. Hazardous waste
Client sites 2 2 1 4 16 LOW
5. Reused timber, bricks &
steelworks Client sites 1 3 1 1 3 LOW
6. Recycled metal, hardcore &
timber Client sites 2 3 2 1 12 LOW
7. Electricity used
Head office 1 3 2 1 6 LOW
8. Mains water
Head office/yard 1 3 2 1 6 LOW
9. Mains water
Client sites 1 4 1 1 4 LOW
10. Diesel used for transport & plant
All sites 2 3 2 4 48 HIGH
11. Parts used for repair

NCC Received
All sites 1 2 1 1 2 LOW
12. Office consumables
All sites 1 3 1 1 3 LOW

07/12/2016
13. Transport & plant replacement
All sites 2 3 2 2 24 MEDIUM
14. Transport exhaust
Sites and road 2 3 2 4 48 HIGH
15. Van sharing
Client sites 1 3 1 2 6 LOW
16. Demolition – nuisance under
normal conditions Client sites 2 3 2 4 48 HIGH
17. Demolition – nuisance under
emergency conditions Client sites 3 2 1 4 24 MEDIUM
18. Dust & noise during demolition
client sites 2 3 1 4 24 MEDIUM
19. Diesel storage – spill under
normal conditions All sites 2 2 1 4 16 LOW
20. Diesel storage – spill under
emergency conditions All sites 2 2 1 4 16 LOW
21. Legislation compliance – during
planning – normal conditions All sites 1 2 1 4 8 LOW
22. Legislation compliance – during
planning – emergency conditions All sites 2 2 1 8 32 MEDIUM
23. Archaeological remains-
emergency conditions Client sites 2 2 1 4 16 LOW
24. Natural features – abnormal &
emergency conditions Client sites 2 2 1 4 16 LOW
25. Emission and pollution due to
Services not disconnected- Client sites 1 2 1 4 8 LOW
26. abnormal conditions
Emission and pollution due to
Services not disconnected- Client sites 2 2 1 4 16 LOW
emergency
27. Emission conditions
and pollution due to sub
contractor activities Client sites 2 2 1 8 32 MEDIUM

Form 7.2U.03
Scoring System

Severity (1 to 3)
1 - Minor - negligible impact, minor resource use or waste generation
2 - Significant - occurs at local level, moderate resource use or waste generation
3 - Major - national or global level, high resource use or waste generation
Probability (1 to 4)
1 - Improbable - may only occur under emergency conditions
2 – Remote - not likely to occur due to controls in place, likely to occur under abnormal conditions
and/or absence of occurrence in past
3 – Possible - likely to occur due to limited controls in place, likely to occur under normal conditions
and/or past history shows occurrence in past
4 –Probable - most likely or certain due to low or no controls, high risk of occurrence under normal
conditions

Duration (1 to 3)
1- Short - impact may only occur under abnormal conditions
2 – Long - occurs frequently but not continuously
3 - Continuous - occurs continuously under normal conditions

NCC Received
Legislation and other (including policy) requirements (1 to 8)
1 - Legislation not applicable

07/12/2016
2 - Legislation applicable but not significant to operation and normally compliant under normal
conditions
4 - Legislation applicable and significant to operation and normally compliant under normal conditions
8 - Legislation applicable and not compliant
Categories of aspects
Score Category
0- 20 Low significance
21- 40 Medium significance
41 and above High significance

Form 7.2U.03
ClientKier Construction MS Title: 402
Client: MS Title:

ASSESSMENTS
(Manual Handling Assessment,
PPE Assessment & COSHH Assessment)

NCC Received
07/12/2016

1 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

MANUAL HANDLING ASSESSMENT 1 of 2

1. MANUAL HANDLING WORKS ON SITE

Lifting, moving, carrying materials of various shapes and sizes from the work area to either the processing area
or to waste/scrap skips.
Such materials are lifted and moved by operatives at ground or working from an approved safe means of access
as described in the method statement for the works.

2. METHOD OF ASSESSMENT

To comply with the Manual Handling Regulations, the Company has carried out an assessment.
To carry out the assessment, the Company have:
 Identified the manual handling operations undertaken by their employees
 Made an appraisal, as far as is reasonably practicable, of all manual handling operations to determine if
there is a risk of injury to employees.
In addition, assessments based upon criteria defined in HSE publication ‘Manual Handling Assessment
Charts’ (INDG383 – 08/03) – these are detailed separately.

NCC Received
3.1 ASSESSMENT

(a) Task

07/12/2016
Involves lifting, twisting stooping and reaching, to manually support materials being removed from the various
buildings/structures.
The Assessment revealed that the task involves excessive movement i.e. lifting lowering and carrying, a degree
of pushing and pulling is required to free members and sheet material etc.
There is also a possibility of sudden movement of the load which would increase the force of the operative’s body.
In most cases the load can be carried close to the body, however, physical effort is required to complete the task.
The task is not process rated, and there are sufficient rest periods.

(b) Load
Loads may have an estimated weight of up to 25 kg.
Loads may have sharp edges and be potentially damaging in circumstances where contact is made.
Although the load can be bulky and unwieldy, and difficult to grasp, it is unlikely to shift when the lifting operations
are in progress

(c) Working environment


There are no extremes of temperature associated on the working site.
Natural ventilation is produced by the nature of the work.
The lighting is good, and, where necessary, task lighting will be utilised to illuminate both the work areas and
access/egress routes. Inclement weather will produce a slippery working surface.

(d) Operative’s individual capacity


The Assessment revealed that there were no operatives with back injury problems or other complaints that
suggest that the operatives could be in the high injury risk category.

(e) Other Factors


Overalls, weather and wet condition of materials to be carried could hinder an operative in respect of movement
and posture.

2 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

MANUAL HANDLING ASSESSMENT 2 of 2

3.2 REDUCTION OF RISK (CONTROL MEASURES)

(a) Task
The task cannot be improved by changing the layout of the workstations – the work layout is imposed by the
building/structure to be demolished.
Space management and the improvement of access/egress can reduce the risks imposed by twisting and
stooping.
Reaching will be minimised by the introduction of access equipment, such as mechanical lifts or working
platforms.
Ensuring that operatives adopt the correct stance reduces the risks associated with pushing and pulling.
Operatives will be trained in lifting techniques, together with good posture techniques.
Physical effort will be reduced by teamwork and splitting the load into manageable members.

(b) Load
Bulky unwieldy loads must be cut into smaller pieces.
Member and sheet materials that are difficult to grasp and materials with sharp edges will be handled by
mechanical means wherever possible.
Abrasive protective gloves will be issued, but are a last resort for handling operations where it is likely that a
sharp edge will be present on the materials to be handled.
Consideration should be given to the provision of mechanical assistance where this is reasonably practicable.

NCC Received
Mechanical assistance involves the use of machines such as telehandlers, 360 excavator equipped with
appropriate attachment.

07/12/2016
(c) Working environment
Task lighting will be used to illuminate the work areas and access/egress routes.
Space constraint can be maximised by an increased awareness of housekeeping and a policy of tidying up
before lifting operations are commenced.
Ensure that satisfactory access and egress routes are available before lifting operations are commenced.

(d) Operative’s individual capacity


There will not be any lifting operations that require unusual strength by operatives.
The operations will be capable of being performed by most fit operatives.

(e) Other Factors


Personal protective equipment should only be used as a last resort, when engineering or other controls do not
prove adequate protection.
Where the wearing of PPE cannot be avoided, consider the risks of manual handling injury.
Considerations may include factors such as:
 Gloves may impair dexterity.
 Overalls may inhibit free movement.

4. CONCLUSION

This assessment provides the employee with information in relation to hazards and risk on the Contract,
The assessment revealed that operatives are exposed to a degree of risk of an injury from manual handling
operations.
Due to the nature of demolition activities it is not possible to totally eliminate such risk. However, implementation
of the control measures detailed will either eliminate or significantly reduce the identified risks, as far as is
reasonably practicable.
Employees’ contribution in the re-design of systems of work will be encouraged.
Control measures detailed in 3.2 are appropriate to reduce the possibility of injury - they are practical steps and
once they have been put in place, they will be periodically reviewed by means of site safety inspections.
This assessment will be periodically reviewed as part of the Company continual improvement process.
Review will also be carried out in the event of new information or changes in legislation.

3 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK REMOVAL OF PLASTERBOARD + MW INSULATION

Placing suitable skips near to the


Control Measures work area + transporting by
telehandler

Colour Band Numerical Colour Band Numerical


RISK FACTORS
(G,A,R or P) Score (G,A,R or P) Score

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G 0 0 G G 0 0

Hand distance from lower back A A 3 3 A A 3 3

NCC Received
Vertical lift region R 3 R 3

Torso twisting/sideways bending Asymmetrical

07/12/2016
R G 2 0 R G 2 0
NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE
trunk/load (carrying)

Postural constraints G G 0 0 G G 0 0

Grip on the load A A 1 1 A A 1 1

Floor surface R R 2 2 G G 0 0

Other environmental factors A A 1 1 A A 1 1

Carry distance G 0 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)

TOTAL TOTAL
12 9 10 5
SCORE SCORE

G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

4 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK SOFT STRIPPING

Demolishing the internal


Control Measures partitions and removing arisings
by mechanical means to the
processing area

Colour Band Numerical Colour Band Numerical


RISK FACTORS
(G,A,R or P) Score (G,A,R or P) Score

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G 0 0 G G 0 0

Hand distance from lower back R R 6 6 G G 0 0

NCC Received
Vertical lift region R 3 G 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
R R 2 2 G G 0 0
NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE
trunk/load (carrying)

Postural constraints G G 0 0 G G 0 0

Grip on the load R R 2 2 G G 0 0

Floor surface R R 2 2 G G 0 0

Other environmental factors R R 2 2 G G 0 0

Carry distance G 0 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)

TOTAL TOTAL
17 16 0 0
SCORE SCORE

G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

5 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

DESHEETING
TASK
(ASBESTOS CEMENT & STEEL SHEETS)

Demolishing the structure and


Control Measures removing arisings by
mechanical means

Colour Band Numerical Colour Band Numerical


RISK FACTORS
(G,A,R or P) Score (G,A,R or P) Score

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency A* A A 4 4 4 G G G 0 0 0

Hand distance from lower back A A A 3 3 3 G G G 0 0 0

NCC Received
Vertical lift region A G 1 0 G G 0 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
trunk/load (carrying)
G A G 0 1 0 G G G 0 0 0

Postural constraints G G G 0 0 0 G G G 0 0 0

Grip on the load A A A 1 1 1 G G G 0 0 0

Floor surface A A A 1 1 1 G G G 0 0 0

Other environmental factors A R A 1 2 1 G G G 0 0 0

Carry distance G 0 G 0

Obstacles en route (carrying only) G 0 G 0

Communication and co-ordination (team handling


only)
G 0 G 0

TOTAL TOTAL
11 12 10 0 0 0
SCORE SCORE

G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

6 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK PROCESSING SCRAP AT WORKFACE

Demolishing the structure and


removing arisings by
Control Measures mechanical means to the
processing area

Colour Band Numerical Colour Band Numerical


RISK FACTORS
(G,A,R or P) Score (G,A,R or P) Score

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency A A A 4 4 4 G G G 0 0 0

Hand distance from lower back R A R 6 3 6 G G G 0 0 0

NCC Received
Vertical lift region R R 3 3 G G 0 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
trunk/load (carrying)
R G R 2 0 2 G G G 0 0 0

Postural constraints A G A 1 0 1 G G G 0 0 0

Grip on the load R R R 2 2 2 G G G 0 0 0

Floor surface R R R 2 2 2 G G G 0 0 0

Other environmental factors A A A 1 1 1 G G G 0 0 0

Carry distance A 1 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)
G 0 G 0

TOTAL TOTAL
21 15 21 0 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

7 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK PROCESSING SCRAP IN PROCESSING AREA

Processing scrap by mechanical


Control Measures means in the processing area

Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G A 0 0 0 G G G 0 0 0

Hand distance from lower back R R R 6 6 6 G G G 0 0 0

NCC Received
Vertical lift region R R 3 3 G G 0 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
trunk/load (carrying)
R R R 2 2 2 G G G 0 0 0

Postural constraints G G A 0 0 0 G G G 0 0 0

Grip on the load R R R 2 2 2 G G G 0 0 0

Floor surface R R R 2 2 2 G G G 0 0 0

Other environmental factors R R A 2 2 2 G G G 0 0 0

Carry distance G 0 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)
G 0 G 0

TOTAL TOTAL
17 16 17 0 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

8 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

ERECTION OF HERAS FENCING


TASK
PANELS FEET

This task is relatively low risk, carrying may be reduced by controlled


Control Measures
use of site vehicle to carry items to installation location

Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G G 0 0 0 G G 0 0

Hand distance from lower back G A G 0 3 0 A A 3 3

NCC Received
Vertical lift region G G 0 0 R 3

Torso twisting/sideways bending Asymmetrical

07/12/2016
G G G 0 0 0 R R 2 2

NOT APPLICABLE

NOT APPLICABLE
trunk/load (carrying)

Postural constraints G G G 0 0 0 G G 0 0

Grip on the load G G G 0 0 0 A A 1 1

Floor surface G G G 0 0 0 G G 0 0

Other environmental factors R R R 2 2 2 R R 2 2

Carry distance A 1 G 0

Obstacles en route (carrying only) G 0 G 0

Communication and co-ordination (team handling


only)
G 0

TOTAL TOTAL
2 6 2 11 8
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by
one person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

9 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK LAYING PAVING SLABS

Transporting the slabs to the work


area by mechanical means
Control Measures (telehandlers, FLT) + using
vacuum type handling equipment
Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency A A A 4 4 4 G G G 0 0 0

Hand distance from lower back R A R 6 3 6 G G G 0 0 0

NCC Received
Vertical lift region R R 3 3 G G 0 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
trunk/load (carrying)
R G R 2 0 2 G G G 0 0 0

Postural constraints A G A 1 0 1 G G G 0 0 0

Grip on the load R R R 2 2 2 G G G 0 0 0

Floor surface R R R 2 2 2 G G G 0 0 0

Other environmental factors A A A 1 1 1 G G G 0 0 0

Carry distance A 1 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)
G 0 G 0

TOTAL TOTAL
21 15 21 0 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by one
person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

10 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

STRIPPING EQUIPMENT/REMOVAL OF PIPEWORK,


TASK
CABLES, ETC.
Removing equipment by mechanical
means to the designated area
Control Measures

Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G 0 0 G G 0 0

Hand distance from lower back R R 6 6 G G 0 0

NCC Received
Vertical lift region R 3 G 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
R R 2 2 G G 0 0
NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE
trunk/load (carrying)

Postural constraints G G 0 0 G G 0 0

Grip on the load R R 2 2 G G 0 0

Floor surface R R 2 2 G G 0 0

Other environmental factors R R 2 2 G G 0 0

Carry distance G 0 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)

TOTAL TOTAL
17 16 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by one
person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

11 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

CHANGING ATTACHMENTS
TASK
(Including handling tools)
With the exception of moving and
positioning the attachments by
Control Measures mechanical means, the fitting activity
must be carried out manually

Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G 0 0

Hand distance from lower back R G 6 0

NCC Received
Vertical lift region R 3

Torso twisting/sideways bending Asymmetrical

07/12/2016
R G 2 0
NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE
trunk/load (carrying)
NOT APPLICABLE

Postural constraints R R 3 3

Grip on the load A G 1 0

Floor surface R R 2 2

Other environmental factors R R 2 2

Carry distance R 3

Obstacles en route (carrying only) A 2

Communication and co-ordination (team handling


only)

TOTAL TOTAL
19 12
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by one
person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

12 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

LOADING/UNLOADING VEHICLES + MOVING


TASK
MATERIALS AROUND SITE
Use of mechanical methods –
genie lifts, telehandler, pallet
Control Measures trucks, FLT’s, etc. eliminates
manual handling
Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency A A A 4 4 4 G G G 0 0 0

Hand distance from lower back A A G 3 3 0 G G G 0 0 0

NCC Received
Vertical lift region R R 3 3 G G 0 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
trunk/load (carrying)
G A A 0 1 1 G G G 0 0 0

Postural constraints G A A 0 1 1 G G G 0 0 0

Grip on the load G G A 0 0 1 G G G 0 0 0

Floor surface R R R 2 2 2 G G G 0 0 0

Other environmental factors R R R 2 2 2 G G G 0 0 0

Carry distance R 3 G 0

Obstacles en route (carrying only) A 2 G 0

Communication and co-ordination (team handling


only)
G 0 G 0

TOTAL TOTAL
14 16 14 0 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by one
person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

13 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

Manual Handling Assessment (MAC) Score Sheet

TASK UNLOADING STATIONERY

Use of mechanical methods –


genie lifts, pallet truck, FLT’s, etc.
Control Measures eliminates manual handling

Colour
Numerical Colour Band Numerical
RISK FACTORS Band
Score (G,A,R or P) Score
(G,A,R or P)

CARRY

CARRY

CARRY

CARRY
TEAM

TEAM

TEAM

TEAM
LIFT

LIFT

LIFT

LIFT
Load weight and lift/carry frequency G G 0 0 G G 0 0

Hand distance from lower back A G 3 0 G G 0 0

NCC Received
Vertical lift region R 3 G 0

Torso twisting/sideways bending Asymmetrical

07/12/2016
G G 0 0 G G 0 0

NOT APPLICABLE
trunk/load (carrying)
NOT APPLICABLE

NOT APPLICABLE

NOT APPLICABLE
Postural constraints G G 0 0 G G 0 0

Grip on the load G G 0 0 G G 0 0

Floor surface G G 0 0 G G 0 0

Other environmental factors G G 0 0 G G 0 0

Carry distance G 0 G 0

Obstacles en route (carrying only) G 0 G 0

Communication and co-ordination (team handling


only)

TOTAL TOTAL
6 0 0 0
SCORE SCORE
G Low risk level A Medium risk level R High risk level P Very high risk level
Vulnerability of special risk Examine tasks closely May expose a significant Must come under close
groups should be proportion of workforce to scrutiny particularly when
considered if appropriate risk of injury entire load supported by one
person

IMPORTANT NOTE Control measures identified will only be implemented where reasonably practicable taking into
account access/space constraints and other safety issues

MAC assessment based upon criteria defined in HSE publication ‘Manual Handling Assessment Charts’ (INDG383 –
01/14)
All assessments detailed MUST be read in conjunction with this Publication and the Manual Handling Assessment

14 of 28
ClientKier Construction MS Title: 402
Client: MS Title:

PERSONAL PROTECTIVE EQUIPMENT (PPE) ASSESSMENT

RISK

IMPACTS, CUTS

COLD/INCLEME

NON-IONISING
STABS, CUTS,

SLIPS, TRIPS,

NT WEATHER

DUST/FIBRES
FALLS FROM

ELECTRICAL
IMMERSION

SPLASHES/
RADIATION

RADIATION
VIBRATION

HEAT/FIRE

VAPOURS
IONISING
GRAZES

SPURTS
BLOWS,
HEIGHT

GASES/
FUMES
NOISE
FALLS
PARTS OF BODY AT
RISK
CRANIUM X X
EARS X X
EYES X X X X
RESPIRATORY TRACT X X X X
FACE X X X X
WHOLE HEAD X X
HANDS X X X X X X X X
ARMS (Parts) X X X

NCC Received
FEET X X X X X

07/12/2016
LEGS (Parts) X X X X X X
SKIN X X X X X X X X X
TRUNK/ABDOMEN X X X X X
WHOLE BODY X X X X X X

OTHER FACTORS WHICH MAY BE RELEVANT IN SELECTION/USE OF PPE


IS A COMBINATION OF PPE (IF APPROPRIATE) A FACTOR? YES/NO

IS PHYSICAL EFFORT A FACTOR IN CHOICE OF PPE? YES/NO

ANY OTHER FACTORS IN CHOICE OF PPE? (SPECIFY) YES/NO

IS VISIBILITY A FACTOR IN CHOICE OF PPE? YES/NO

IS COMMUNICATION A FACTOR IN CHOICE OF PPE? YES/NO

PPE TO MINIMISE THE RISKS IDENTIFIED INCLUDES:

MANDATORY: TASK SPECIFIC:


SAFETY HELMET, SAFETY BOOTS, LIGHT EYE ORI-NASAL MASKS (WITH APPROPRIATE FILTER), DUST
PROTECTION, GLOVES (GENERAL USE, eg RIGGERS), MASK, VISOR (TINTED OR NON-TINTED), GLOVES (TASK
HI-VIS CLOTHING (VEST OR JACKET), WET WEATHER SPECIFIC eg BURNERS GAUNTLETS),
GEAR HARNESS/LANYARD (OR OTHER FALL ARREST
SYSTEM), FR GRADE OVERALLS, DISPOSABLE
OVERALLS
THIS ASSESSMENT TAKES INTO ACCOUNT GENERAL DEMOLITION ACTIVITIES – ADDITIONAL/DIFFERENT PPE
REQUIRED AS A RESULT OF PROCESSES OUTSIDE THE SCOPE OF THIS ASSESSMENT WILL BE DETAILED IN THE
RELATED METHOD STATEMENT AS A SEPARATE ISSUE

IMPORTANT NOTE: PPE IS USED AS THE LAST OPTION OF PROTECTION - NOT THE FIRST. WHEREVER
REASONABLY PRACTICABLE, METHODOLOGY IS SELECTED TO ISOLATE PERSONNEL FROM THE HAZARD AND
RELATED RISK

Assessment by: V W Watson December 2014

15 of 28
ClientKier Construction MS Title: 402
Client: MS Title:
COSHH Products (Operational Substances)
COSHH products on demolition Sites fall into three categories:
i) Products brought onto site for use by Company personnel
ii) Substances generated as a result of Company processes, eg dust, metal fume
iii) Substances present on site left as contamination/residue resulting from Client processes previous to demolition
activities commencing
Categories i) and ii)
COSHH Assessments are carried out by utilisation of Materials Safety Data Sheets (MSDS) or information provided
by other third parties and review of actual usage/generation on sites by Company personnel.
Providing the control measures listed in the appropriate COSHH Assessment are adhered to, it is considered that
the risk from products is as low as is reasonably practicable.
The assessments are reviewed on an annual basis, as part of the Safety, Health and Environmental process, or
sooner if considered necessary/conditions dictate.
Category iii)
Information is provided by the Client, generally Materials Safety Data Sheets, this will be assessed and appropriate
control measures, dependent upon the hazards presented by the substance(s), will be implemented. These control
measures may include, but not be limited to, selection of methodology, use of personal protective equipment (PPE),
disposal of waste.
In the event of a range of substances spread throughout the Site, a site-wide COSHH Assessment will be carried
out.
MSDS will be obtained, either from the Client or other source(s), and details recorded of location(s) of the
substances, Risk and Safety Phrases and brief details of control measures. Details of this information will be
recorded onto a COSHH Assessment (Site Wide).
Upon completion of information input, the QHSE Advisor or other competent person will carry out a review of the
site-wide assessment to establish suitable methodologies and/or control measures commensurate with the risks

NCC Received
the substances present..
Selection of Methodology, PPE and control measures take cognisance of the hazards presented by such
substances. Selection is made so as to minimise risks to all personnel who may be affected by our works to a level

07/12/2016
that is as low as is reasonably practicable.

COSHH Assessment Reference Identified Risks

C01 Oxygen

C02 Propane

C03 Metal Fumes

C04 Dust

C05 Concrete Dust

C06 Gas Oil (Derv)

C07 Mineral Oil

C08 Mineral Wool Insulation

C09 Pigeon Excrement

C10 Acetylene (Dissolved)

C11 Pine Disinfectant

C12 Hygiene Cleaning Fluid (Bleach)

16 of 28
SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C01 OXYGEN Compressed gas oxidant. Strongly supports combustion.


May react violently with combustible materials. Incomplete
combustion may form carbon monoxide.

USAGE OF Processing of steelwork PERSONS Burners/Welders


PRODUCT Welding AT RISK Operatives in vicinity

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Non flammable Suitable extinguishing media:
All known extinguishers can be used
Specific Hazards:
Supports combustion. Non flammable. Exposure to fire may cause
Environmental: containers to rupture/explode. Inform Fire Brigade.
No ecological damage caused by this product. Specific Methods:
To atmosphere in a well ventilated place. If possible stop flow of product. Move container away or cool with
Do not discharge into any place where its accumulation could be water from a protected position.
dangerous. Special Protective Equipment for Fire Fighting:
None.

NCC Received
07/12/2016
Health Effects: First Aid Measures:
On Eyes: Inhalation: Keep victim warm and rested. Call a doctor.
On Skin: Apply artificial respiration if breathing has stopped.
By Inhalation: Continuous inhalation of concentrations higher than Skin Contact:
75% may cause nausea, dizziness, respiratory Eye Contact:
difficulty and convulsion. Ingestion: Ingestion is not considered a possible route of
By Ingestion: exposure.

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task None available

Engineering: (including handling and storage) Personal Protection:


Use no oil or grease. Open valve slowly to avoid pressure shock. Ensure operators understand the hazard of oxygen enrichment. Do
Segregate from flammable gases and other flammable materials in not smoke while handling the product. Wear suitable hand, body and
store. Suck back of water into container must be prevented. Do not head protection. Wear Goggles with suitable filter lenses when use
allow back-feed into the container. Use only specified equipment is cutting/welding. Avoid oxygen (>21%) atmospheres. Ensure
which is suitable for this product, its supply pressure and adequate ventilation. Clothing impregnated with oxygen should be
temperature. Keep away from ignition sources (including static ventilated by walking in fresh open air for 2 minutes.
discharges). Store cylinders upright in open air. Keep container
below 50°C in a well ventilated place. Do not use oxygen as a
substitute for air, nitrogen or any other gas. Always leak check
cylinders when first collected, delivered or used, using an approved
leak detection fluid.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C02 PROPANE Liquefied gas under pressure, extremely flammable, may


contain small concentrations of 1,3 butadiene, which may
cause cancer by inhalation.

USAGE OF Processing of Steelwork PERSONS Burners


PRODUCT AT RISK Operatives in vicinity
RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Extremely flammable Suitable extinguishing media:
All known extinguishers can be used
Specific Hazards:
Exposure to fire may cause containers to rupture/explode. Inform
Environmental: Fire Brigade.
Ensure operators understand the flammability hazard. Hazardous Combustion Products
The hazard of asphyxiation is often overlooked and must be Incomplete combustion may form carbon monoxide.
stressed during operator training. Specific Methods:
Always leak check cylinders when first collected, delivered or used, If possible stop flow of product. Move container away or cool with
using an approved leak detection fluid. water from a protected position. Do not extinguish a leaking gas
flame unless absolutely necessary. Spontaneous/explosive re-

NCC Received
ignition may occur. Extinguish any other fire.
Special Protective Equipment for Fire Fighting:
In confined spaces use self-contained breathing apparatus.

07/12/2016
Health Effects: First Aid Measures:
On Eyes: Contact with the liquid may cause cold burns Inhalation: Keep victim warm and rested. Call a doctor.
and/or frostbite Apply artificial respiration if breathing has stopped.
On Skin: Skin Contact: For liquid spillage – flush with water for at least 15
By Inhalation: Toxic by inhalation. In high concentrations may minutes. Apply a sterile dressing and seek
cause asphyxiation and death. Symptoms may medical advice as soon as possible.
include loss of mobility/consciousness. Victim may Eye Contact: As Skin Contact
not be aware of asphyxiation. In low Ingestion: Ingestion is not considered a possible route of
concentrations may cause narcotic effects. exposure.
Symptoms may include dizziness, headache,
nausea and loss of co-ordination. Remove victim
to uncontaminated area wearing self-contained
breathing apparatus.
By Ingestion: Ingestion is not considered a possible route of
exposure.

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task None available

Engineering: (including handling and storage) Personal Protection:


Ensure equipment is adequately earthed. Suck back of water into Ensure adequate ventilation.
container must be prevented. Purge air from system before Do not smoke while handling product.
introducing gas. Do not allow back-feed into the container. Cylinder Keep self-contained breathing apparatus readily available for
sizes A, B, D and E should remain upright at all times. Use only emergency use
specified equipment which is suitable for this product, its supply
pressure and temperature. Keep away from ignition sources
(including static discharges). Store cylinders upright in open air.
Segregate from acetylene, oxidant gases and other oxidant material
in store. Keep container below 50°C in a well ventilated place.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C03 METAL FUMES Hazard by Inhalation of the fumes

USAGE OF The product is generated as PERSONS Burning operative


PRODUCT a result of the burning AT RISK Operatives in vicinity
process

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Non flammable Not applicable

Environmental:
A variety of cutting operations in the scrap industry have been
subject to environmental monitoring under the auspices of the
British Scrap Federation. In the open air, levels of combustion are
usually below the Occupational Exposure limit but the same
monitoring also revealed that personnel exposure can be between 3
and 50mg/m3. There is a wide difference due to numerous variables

NCC Received
including the stature of the operative, weather conditions, surface
treatment and coatings. Furthermore, the exact composition of
metals to be cut is seldom precisely known. A Local Exhaust

07/12/2016
Ventilation [LEV] system, specifically designed in respect of
individual situations, will be installed if appropriate. However, the
nature of most demolition work usually renders this impractical.

Health Effects: First Aid Measures:


On Eyes: Irritation to eyes Inhalation: Remove patient from exposure to fresh air
On Skin: Skin Contact:
By Inhalation: Inhalation of the fumes can cause irritation of the Eye Contact:
respiratory tract, typical symptoms being a dry Ingestion:
throat; coughing; tightness of the chest; and Pressure Injection:
difficulty in breathing. If these fumes are inhaled
or swallowed, they can lead to systemic poisoning.
By Ingestion:
Chronic: The freshly formed metallic oxide fumes of certain
metals, e.g. copper and zinc (galvanized coating),
can lead to a short-term flu-like illness known as
‘metal fume fever’ or ‘Galvo Flu’. This, however,
rarely leads to serious complications

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
Where possible, cold cut using mechanical methods Not applicable

Engineering: Personal Protection:


The hot cutting operation involves the removal of parental metal. As a mandatory precaution, all operatives will be issued with, and
The fumes generated will consist of the combustion gases, which instructed to use, full Respiratory Protective Equipment [RPE]. The
are mainly carbon dioxide and oxides of nitrogen, along with Company will nominate a responsible person who will carry out
particulate fume which will contain substances derived from the periodic inspections of the RPE. Site management and the
parent metal and any surface treatment or coating such as subordinate line management are instructed to bring any heavily
electroplating, oil or paint. Depending on the metal being cut, other coated or ‘suspect’ material to the attention of the Senior
potentially more hazardous fumes can be produced such as Management.
hexavalent chromium nickel and cadmium.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C04 DUST Hazard by Inhalation

USAGE OF This product is generated as PERSONS Operatives


PRODUCT a result of demolition AT RISK Others in vicinity
processes

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Not applicable Not applicable

Environmental:
Dust (various )is collected, where possible, in a controlled manner
i.e. wet sweeping, bagged and disposed of as solid waste.

NCC Received
Health Effects: First Aid Measures:

07/12/2016
On Eyes: Irritation to eyes Inhalation: Remove to fresh air
On Skin: Skin Contact: Remove contaminated clothing, wash with
By Inhalation: Can cause wheezing, bronchitis and other soap and water
respiratory disorders Eye Contact: Irrigate with eye wash solution or clean
By Ingestion: water, holding the eyelids apart. Continue
Chronic: Dust associated with MEL’s can cause cancers. irrigation for at least 10 minutes
Other: Ingestion: Wash out mouth with water and give to drink

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
The use of local exhaust ventilation and containment will be
considered but this is generally not practical due to the nature of the Not applicable
Company’s work.

Engineering: Personal Protection:


Dust is a generic term for solid particulate matter, composed from OES for dust may be exceeded. Inhalation is controlled by the
various other substances. Dust particles vary in size. Shape and correct selection of respiratory protection i.e. disposable respirator.
colour. Eye contact is controlled by the wearing of dust-proof goggles.
When handling the substancecontact is controlled by wearing
approved PVC lightweight gauntlet gloves.
Suitable eye irrigation solutions should be made available on
workstations.
Simple health surveillance is required. Simple visual examination of
employees hands, by supervisory personnel on a biannual basis.
Discoloration, dryness or other signs of skin deterioration will require
medical attention.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C05 CONCRETE DUST Hazard by Inhalation

USAGE OF This product is generated as PERSONS Operatives


PRODUCT a result of demolition AT RISK Others in vicinity
processes

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Not applicable Not applicable

Environmental:
Dust levels during demolition works are to be kept to a minimum by
careful selection of demolition methods. The short term generation
of high dust levels during activities such as felling etc. are very
difficult to reduce. The long term generation of Concrete Dust from
processing and handling are to be reduced by the use of water
sprays.

NCC Received
07/12/2016
Health Effects: First Aid Measures:
On Eyes: Irritation to eyes Inhalation: Remove to fresh air
On Skin: Can cause irritation Skin Contact: Remove contaminated clothing, wash with soap
By Inhalation: Can cause wheezing, bronchitis and other and water
respiratory disorders Eye Contact: Irrigate with eye wash solution or clean
By Ingestion: water, holding the eyelids apart. Continue
Chronic: irrigation for at least 10 minutes. If irritation
Other: persist, seek medical advice
Ingestion: Give plenty of water or milk to drink

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
The use of local exhaust ventilation and containment will be Not applicable
considered but this is generally not practical due to the nature of the
Company’s work.

Engineering: Personal Protection:


The Concrete Dust contains portland cement and mineral Where the generation of Concrete Dust is not controlled to below
aggregate. Portland cement contains calcium silicates, aluminates, acceptable levels, suitable RPE will be used. This will normally be
ferro aluminates and sulphates. Small amounts of lime and disposable paper respirators, but where it is suspected that these
chlorides are also present together with trace amounts of chromium are not adequate, air samples may be taken.
compounds. Mineral aggregates contain silica and quartz dust. The main source of exposure to Concrete Dust will be during the
Concrete Dust will take the form of grey particles. demolition of reinforced concrete buildings and structures and
during the processing and handling of the resultant arisings.
The main hazard of Concrete Dust is the silica material which
causes silicosis. Once cured, the portland cement does not present
any significant hazards, other than those of a nuisance dust.
Simple health surveillance is required. Simple visual examination of
employees hands, by supervisory personnel on a biannual basis.
Discoloration, dryness or other signs of skin deterioration will require
medical attention.
Client: MS Title:

REF. SUBSTANCE HAZARDS


(AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C06 GAS OIL (DERV) Hazard by Inhalation and contact with eyes and skin

USAGE OF Fuel for plant/vehicles PERSONS Operative


PRODUCT AT RISK

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Extremely Flammable Extinguish with dry powder, foam or water fog. For small fires use
CO².
Never use water jets

Environmental:
Contain spillage, dilute with copious amounts of water and flush to
drain over a long period.

NCC Received
Health Effects: First Aid Measures:

07/12/2016
On Eyes: Irritation to eyes Inhalation: Remove patient from exposure into fresh air
On Skin: Prolonged and repeated skin contact could lead to Skin Contact: Wash affected areas with soap and tepid
dermatitis and possible long term risk of skin water. If irritation persists, seek medical
cancer. advice
By Inhalation: Eye Contact: Irrigate with eye wash solution or clean
By Ingestion: water, holding the eyelids apart. Continue
Chronic: irrigation for at least 20 minutes
Other: Ingestion: Wash out mouth with water; drink plenty of
milk; do not induce vomiting

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task. None available

Engineering: Personal Protection:


Storage should be in open air or well ventilated areas free from When handling, avoid skin & eye contact and inhalation of fumes.
sources of heat. Employees will be issued with suitable gloves, eye protection and
Gas Oil (Derv) should be stored in a secure container with screwed protective clothing.
cap to prevent leakage. The chief source of exposure of Operatives to Gas Oil (Derv) is
Ensure adequate ventilation. Protect from heat, light and during routine servicing and re-fuelling of construction plant,
contamination. machinery and vehicles. The main hazard to employees is by skin
Gas Oils are a complex mixture of Distillate Hydrocarbons or eye contact and in extreme circumstances by ingestion due to
containing aromatics and additives commensurate with their leaks or spillage. Spillage absorbed by sawdust, rags or cotton
required properties, forming a flammable clear or red liquid with a waste etc. constitutes to a considerable fire risk thus creating a
characteristic Hydrocarbon odour. further hazard to all Operatives.
Client: MS Title:

SUBSTANCE HAZARDS
(AND / OR TRADE NAME) +
REF [MANUFACTURER/SUPPLIER]

C07 MINERAL OIL Hazardous by all routes of exposure, especially skin or eye
contact

USAGE OF Lubricating plant/equipment PERSONS Operative


PRODUCT AT RISK

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Extremely Flammable Extinguish with foam, dry powder, CO²
Never use water

Environmental:
This Assessment must be read and understood by all dismantling
Operatives, Plant Fitters and other persons involved in dismantling
of industrial plant and equipment. In case of spillage, contain spill at
source and prevent discharges to sewers and streams.

NCC Received
Health Effects: First Aid Measures:
On Eyes: Irritation to eyes Inhalation: Avoid excessive inhalation. Remove patient
On Skin: Contact may lead to de-fatting of the skin, into fresh air

07/12/2016
dermatitis, oil acne and warty (cancerous growths). Skin Contact: Any cuts, scratches etc. should be promptly
Prolonged and repeated skin contact with used treated. Wash affected skin areas with
oils should be avoided. cleansers provided followed by soap and
By Inhalation: water.
By Ingestion: Eye Contact: Irrigate immediately with copious quantities
Chronic: Potential Carcinogenic of clean water for 5 minutes. Obtain
medical attention if irritation persists.
Ingestion: Seek medical advice

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task None available

Engineering: Personal Protection:


The dismantling of industrial plant and equipment together with the The main hazard to employees is by skin contact with these oils
re-fuelling and routine servicing of construction plant and vehicles usually due to leakage or spillage. During normal handling, the
often exposes the personnel concerned to mineral type oils and priority action is to minimise the possibility of spillage by the use of
greases. suitable containers such as jugs or cans. To reduce chance of
Wherever possible, oil is to be handled in suitable containers and is contact, impervious gloves, overalls and eye shields may be used.
to be drained out of sumps and tanks before these are dismantled or Before protective equipment is worn, it should be checked to see it
handled. is clean and uncontaminated. If clothing becomes soaked in oil, it
should be removed as soon as possible. Any contaminated skin
should be washed with the skin cleansers provided followed by soap
and water. SOLVENTS MUST NOT BE USED. Any contaminated
material or tools should not be placed in overall pockets, due to the
risks of oil soaking through the inside (where it may not be noticed)
and leading to the potential risk of scrotal cancer.
The chief sources of exposure of Operatives and Fitters to mineral
based oils and greases are during the re-fuelling and servicing of
construction plant and vehicles and the handling of contaminated
process plant and equipment in the course of the dismantling work
undertaken with the occasional exposure to oil fumes when hot
cutting work is undertaken on ‘dirty’ metal.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C08 MINERAL WOOL INSULATION Irritant – may cause skin irritation. High dust levels may
irritate the throat and eyes

USAGE OF This product is exposed PERSONS Operative


PRODUCT during demolition activities AT RISK

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Non-combustible Suitable extinguishing media:
Environmental:
Water, foam, dry powder, CO²
No special precautions. Not classified as special waste, and may be
disposed in normal waste landfill. Inert inorganic product with very
small organic content <5.5%. If disposed in landfill it will gradually
decompose and revert to nature inorganic granules or dust with non
known gages, but do not constitute a hazard in normal ventilated
area.

NCC Received
Health Effects: First Aid Measures:
On Eyes: Irritation to eyes Inhalation: Move person to fresh air
On Skin: May cause temporary (but reversible) skin Skin Contact: If irritation occurs wash skin with soap and

07/12/2016
irritation by mechanical action. water
By Inhalation: Can cause wheezing, bronchitis and other Eye Contact: If irritation occurs wash eyes with water
respiratory disorders Ingestion: Drink plenty of water if accidentally ingested
By Ingestion:
Chronic: Dust associated with MEL’s can cause cancers.
Other: On the basis of the evidence of exposure which
occurred over 30 years ago, the international
Agency for Research into Cancer has classified
man made mineral fibre as 'possibly
carcinogenic'.

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
Not possible – result of demolition process Not applicable

Engineering: Personal Protection:


Rockwool products are light brown insulation's which are chemically Cutting and handling may create dust. High dust levels may irritate
composed of mineral wool bonded with 0.3 - 3.3% resin and 0.2% the throat or eyes. The resin poses no known hazard in its cured
mineral oil - dust suppressant/water repellent. Its melting point is in state.
excess of 1000oC and it is insoluble in water. Avoid unnecessary handling of unwrapped product. Ensure
adequate ventilation of workspaces. Keep work areas clean. Use
water sprays to dampen area prior to brushing, or use vacuum
cleaning.
Wear suitable protective clothing and gloves.
Respiratory protection: In confined spaces it is recommended that
disposable face masks complying with EN149 FFP1 or FFP2 should
be used and are suitable for most applications to improve
discomfort.
Hand protection: Cloth, leather or rubber gloves can be worn to
reduce any mechanical irritation affects which may occur.
Eye protection: When working with product above head height, eye
protections to BS EN 166 is advised.
Skin protection: Loose fitting clothing is advised.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C09 PIGEON EXCREMENT Apart from the obvious, it depends on what the birds have
been feeding on (grit from buildings, grain from crops etc.)

USAGE OF A contact as a result of the PERSONS Operative


PRODUCT process AT RISK

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Non-flammable Not applicable

Environmental:
Dispose of to suitable facility

NCC Received
Health Effects: First Aid Measures:

07/12/2016
On Eyes: Irritant Inhalation:
On Skin: Irritant Skin Contact: Wash affected skin area with cleansers
By Inhalation: } See below provided followed by soap and water.
By Ingestion: } See below Eye Contact: Irrigate immediately with copious amounts of
Chronic: clean water for 5 minutes. Obtain medical
Other: The chief sources of exposure of Operatives and attention if irritation persists.
Fitters to Pigeon Excrement is contracting Ingestion: Seek medical advice
Farmers Lung, which is an Asthma like illness;
Salmonella, which leads to food poisoning and
possible dermatitis, skin problems.

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
Not possible – result of demolition process Not applicable

Engineering: Personal Protection:


Employees are expected to maintain a high standard of personal
hygiene at all times, but especially before eating, drinking, smoking,
using the toilet or leaving work.
Taking into account the possible covering of dust, plaster etc, it is
unlikely to be neat.
Wear a facemask to FFP3 standard; either one of the following:
 One shift disposable
 Half face mask with a P3 disposable filter
Wear for one shift, disposable coveralls - some are washable for a
number of times.
Practice good hygiene and shower after every shift of work.
Do not eat, drink or smoke while in this environment.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C10 ACETYLENE (DISSOLVED) Incomplete combustion may form carbon monoxide

USAGE OF Burning PERSONS Burners/Welders


PRODUCT Welding AT RISK Operatives in vicinity

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability:
Extremely flammable Fire Fighting Procedures:
Suitable extinguishing media:
All known extinguishers can be used
Specific Hazards:
Environmental: Exposure to fire may cause containers to rupture/explode.
Try to stop release Specific Methods:
Ventilate area to clean up If possible stop flow of product.
Move container away or cool with water from a protected position.
Do not extinguish a leaking gas flame unless absolutely necessary.
Spontaneous/explosive re-ignition may occur.
Extinguish any other fire.

NCC Received
Special Protective Equipment for Fire Fighting:
In confined spaces use self-contained breathing apparatus.

07/12/2016
Health Effects: First Aid Measures:
On Eyes: Inhalation: Keep victim warm and rested. Call a doctor.
On Skin: Apply artificial respiration if breathing has stopped.
By Inhalation: In high concentrations may cause asphyxiation. Phosphine is a common contaminant of acetylene
Symptoms may include loss of produced from calcium carbide and water, and its
mobility/consciousness. presence should be considered if symptoms of
Victim may not be aware of asphyxiation. irritation develop during acetylene inhalation.
In low concentrations may cause narcotic effects. Skin Contact:
Symptoms may include dizziness, headache, Eye Contact:
nausea and loss of co-ordination. Ingestion: Ingestion is not considered a possible route of
Remove victim to uncontaminated area wearing exposure.
self-contained breathing apparatus.
By Ingestion: Ingestion is not considered a possible route of
exposure.

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task None available

Engineering: (including handling and storage) Personal Protection:


Ensure equipment is adequately earthed. Ensure adequate ventilation.
Avoid contact with pure copper, mercury, silver, bras with greater Wear suitable hand, body and head protection.
than 70% copper. Wear goggles with suitable filter lenses when used in
Suck back of water into container must be prevented. cutting/welding.
Purge air from system before introducing gas. Do not smoke while handling product.
Do not allow back-feed into the container.
Use only specified equipment which is suitable for this product, its
supply pressure and temperature.
Keep away from ignition sources (including static charges).
Segregate from oxidant gases and other oxidant material in store.
Refer to supplier’s container handling instructions.
Keep container below 50°C in a well ventilated place.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C11 PINE DISINFECTANT FLUID Non-Hazardous

USAGE OF It is a general purpose PERSONS Operative


PRODUCT cleaner for disinfecting AT RISK
floors, walls, toilets, drains
and sinks.
RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Non-flammable Not applicable

Environmental:
Contain spillage, dilute with water flush to drain over long period

NCC Received
07/12/2016
Health Effects: First Aid Measures:
On Eyes: Contact with eyes could cause some discomfort Inhalation:
On Skin: Possible allergic skin reactions as a result of Skin Contact: Wash thoroughly with clean water. If
prolonged contact soreness persists seek medical attention.
By Inhalation: Can cause wheezing, bronchitis and other Eye Contact: Wash thoroughly with clean water and seek
respiratory disorders medical advice
By Ingestion: Ingestion could cause some discomfort Ingestion: Give plenty of milk or water to drink. Seek medical
Chronic: advice if discomfort persists.
Other:

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task Not applicable

Engineering: Personal Protection:


A clear liquid of various colours with a sweet pine fragrance. Employees will be informed of the no-hazardous quality of the
Pine Disinfectant Fluid discolours material therefore care must be substance, but that care should still be taken to avoid contact with
taken to avoid spillages and contact with clothing. the eyes. It is therefore important to use safety equipment supplied
by the company.
Wear protective gloves if prolonged contact is likely.
Client: MS Title:

SUBSTANCE HAZARDS
REF. (AND / OR TRADE NAME) +
[MANUFACTURER/SUPPLIER]

C12 HYGIENE CLEANING FLUID (BLEACH) Hazardous by all routes of exposure especially skin or eye
contact

USAGE OF Cleaning (site cabins etc.) PERSONS Operative


PRODUCT AT RISK

RISKS
(FLAMMABILITY, HEALTH & ENVIRONMENTAL)

Flammability: Fire Fighting Procedures:


Extremely flammable Suitable extinguishing media:

Water – if large amounts (chlorine will be liberated)


BA in confined spaces
Environmental:
Contain spillage, dilute with copious amounts of water and flush to
drain over a long period. Chlorine will be liberated.

NCC Received
Health Effects: First Aid Measures:

07/12/2016
On Eyes: Irritates the eyes causing them to become watery Inhalation: Remove patient from exposure into fresh air
On Skin: Risk of irritation Skin Contact: Wash affected areas with soap and tepid
By Inhalation: Irritates the respiratory system causing shortage of water. If irritation persists, seek medical
breath and wheezing advice
By Ingestion: As an injurious substance, can cause internal Eye Contact: Irrigate with eye wash solution or clean
damage and poisoning which can be fatal water, holding the eyelids apart. Continue
Chronic: Can be fatal if swallowed irrigation for at least 20 minutes
Ingestion: Wash out mouth with water and give water;
drink plenty of milk; do not induce vomiting

CONTROL MEASURES
(TO ENSURE RISKS ARE AS LOW AS REASONABLY PRACTICAL)

Elimination: Substitution:
This product is required to carry out the task Use a product with as low a concentration as possible

Engineering: Personal Protection:


The chief source of exposure of operatives to bleach is during To control the risk of exposure of persons to sodium hypo chloride
routine cleaning of toilets/kitchen areas etc. the substance must only be used in well-ventilated locations. The
Bleach is a corrosive substance and, if in contact with acids, Company will issue operatives with/advise them to wear PVC
liberates toxic gas. gloves, protective clothing and suitable eye protection.
Bleach is composed of Sodium Hypo Chloride Solution (15%). It is Contaminated gloves must be washed in tepid water after contact
a translucent greenish yellow liquid with a feint chlorine odour. with sodium hypo chloride. Personal hygiene is paramount. Smoking
and eating is prohibited in areas where sodium hypo chloride is
known to be present. Operatives will be informed of the hazards
associated with Hygiene Cleaning Fluid.
Health and Safety
Executive
Notification of asbestos work
To improve the management of licensed asbestos work through auditing by the asbestos
industry, HSE may share limited data provided on the ASB5 form with trade associations
and relevant bodies. The data shared will be limited to: name of licensee, licence expiry
date, site location, dates of work, nature of work.
Notification No F88843BAFD Date Submitted 29/04/2016 11:54:23

Notification type This is a NEW notification

About you and your licence


Licence number 841600127 Licence expiry date 13/07/2016
Licence holder name KAEFER LTD
Address 63
Portland Street
Mansfield Woodhouse
MANSFIELD
Nottinghamshire
NG19 8BE

NCC Received
Phone no 01623 781200

07/12/2016
Email Address dione.busby@kaefercd.co.uk

Job details
Name of company Total Reclaims Demolition LTD
contracted to
Phone number of
company contracted 01159 632009
to
Contact name at
company contracted Mr Melvyn Cross
to
Site address The Wainwright Academy
Harrop White Road
MANSFIELD
Nottinghamshire
NG19 6TF
Multiple site No, there are not multiple site addresses
addresses
In which local
authority is the site
address (Country, England, Nottinghamshire, Mansfield
Geographical Area
and Local Authority)?
Exact work location
or description of
where on the Nursery Block and Main School
premises work is to
be carried out
Person preparing Mr Andrew Westran Mobile phone 07974 926 804
plan of work Mr Andrew Westran Mobile phone 07974 926 804
Site Supervisor Mr Andrew Westran Mobile phone 07974 926 804

Timing and duration of work


Actual start date of 16/05/2016 Expected finish date 13/07/2016
set up on site of work
Waiver required? No, this notification does not require a waiver
Duration of work (no 43 Job start and finish 8:00 - 15:00 (Friday 8:00
of days) times - 13:00)
Night working No, night working is not Weekend working No, weekend working is
involved not involved
Significant cessation / No, there will not be a significant cessation or pause during the work
pause

About the work


ACM Type Asbestos insulating board
Work to be Removal
undertaken
General condition of Good
the asbestos material

NCC Received
Main type of asbestos ChrysotileAmosite
Details of the type of

07/12/2016
work to be Removal of AIB to Columns, Window Panels and Debris to Walls. Good
undertaken, general Condition. Amosite.
condition and main
type of asbestos
Size of job (area or 310Lm and 280m2
volume)
Minimum number of Maximum number of
persons employed 4 persons employed 6
per shift per shift

Control measures and risks


Control measures Shadow vacuumingDecontaminationEnclosure of work under negative
used to reduce pressureIntact removal of whole AIB panels /tiles etcRPE
exposure
How the work will be
supervised and Using viewing panelsVia CCTVUsing enclosure entry
monitored
Non-asbestos risks No, there are no non asbestos risks that make the asbestos work more
difficult
Special premises No, the asbestos removal is not taking place on special premises

Enforcing authority
The enforcing authority is - HSE
Notifier contact details and declaration
Declaration I declare that an ACoP compliant plan of work has been prepared
Notifier name Mr Andrew Westran Notifier position Supervisor
NCC Received
07/12/2016
Total Reclaims Demolition Ltd

PROJECT ID 402 PROJECT TITLE DATE

PREPARED BY: Joe Childs


RISK ASSESSMENTS
The risk assessments have been carried out in accordance with the Management of Health and Safety at Work
Regulations 1999 (Specifically Regulation 3 – Risk Assessment).
The ethos of our risk assessment and generation of safe systems of work is to apply the principles of prevention, as
detailed within the Management of Health & Safety at Work Regulations 1999, Regulation 4 and Schedule 1, and the
Construction (Design & Management) Regulations 2015 Appendix 1.
The first, and most effective, principle of prevention is to avoid the risk by selection of alternative methods.
This is taken into account when carrying out the risk assessments, selecting appropriate methodologies and
generating the safe system of work.
The risk assessments are supplemented by assessments required by other regulations, these include COSHH, manual
handling and personal protective equipment (PPE)
To enable prioritisation the ratings are numeric – the Risk Rating & Category Matrix identifies the scoring
criteria/definitions and the risk hierarchy

Risk Rating & Category Matrix

NCC Received
ACTIVITY
PERSONS AT
HAZARD INITIAL RISK
MITIGATION APPROACH AND
RESIDUAL RISK
07/12/2016
ID RISK CONTROL MEASURES
S L RR S L
Falls from height;
Falls of materials; No access onto any roof is permitted
Removal of TRD OPS; PC Falls of equipment or throughout this project - if you leave a safe
001 materials from OPS; GENERAL tools 3 4 12 work platform and enter onto a roof you 4 1
height PUBLIC Ejection of broken will be instantly dismissed for gross
out arisings – injury misconduct
to others

Page 1 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Engage specialist contractor to erect full


height scaffold with working lift at eaves
and edge protection to gables; Inspect
debris netting to ensure adequately
enclosing the working lift; Assess weather
Falls from height; conditions - do not permit access if high
Falls of materials; winds or icy conditions; Obtain hand-over
Removal of TRD OPS; PC Falls of equipment or certificate (issue to PC) and ensure scaf-tag
001 materials from OPS; GENERAL tools 3 4 12 completed and displayed; Specialist 2 2
height PUBLIC Ejection of broken contractor to inspect scaffold weekly and
out arisings – injury carry out ALL alterations/reductions.
to others Operatives to use two no. roof ladders for
roof covering extraction works and affix
safety harness to one. Erect exclusion zone
to base of working zone and position
banksmen as required to further control
area
Possible causes of noise in area: Plant operation
– demolition activities.
Plant operation – breaking out; Hand demolition
operations - breaking out;
Delivery vehicles. Soft stripping activities.
TRD supervisor to be issued with 'traffic light'
necklace monitors - to establish controlled
hearing protection zones when 'red' notification
flashes - where these are not available 20m
hearing protection zone to be installed as a
mandatory control around all plant working
zones; Ensure only essential workers are within
the hearing protection zones. Post mandatory
hearing signage at approach points and provide

NCC Received
appropriate hearing protection which relates to
the risk.

07/12/2016
Site works have been assessed based on the
exposure limit and action values published in the
Control of Noise at Work Regulations 2005.
(1) The lower exposure action values are—
(a) a daily or weekly personal noise exposure of
Working in 80 dB (A-weighted); and
TRD OPS Noise exposure; (b) a peak sound pressure of 135 dB (C-weighted).
002 Noisy 4 4 8 2 2
PC OPS Hearing loss; (2) The upper exposure action values are—
environment
(a) a daily or weekly personal noise exposure of
85 dB (A-weighted); and
(b) a peak sound pressure of 137 dB (C-weighted).
(3) The exposure limit values are—
(a) a daily or weekly personal noise exposure of
87 dB (A-weighted); and
(b) a peak sound pressure of 140 dB (C-weighted).
Noise levels are based upon BS 5228-1:2009
Tables D.2 Historic sound level data on
demolition, D.3 Historic sound level data on site
preparation, D6 Historic sound level data on
concreting operations and D7 Historic sound
level data on general site activities.
Times are based on average times for the activity
on SiteTask 1 – Breaking out (D.2 Ref 10)
Task 2 – Excavator (D.3 – Ref 40) Task 3 –
Compressor (D.7 – Ref 27) Task 4 – Hand
held petrol driven disc cutter (D.6 – 53)
As the exposure limit is a daily limit and may
vary, it is deemed that the weekly personal
exposure will not exceed the lower exposure
action value.

Page 2 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Ensure all tools & equipment are suitable for


task, and these tools are put away when not
in use to avoid tripping.
Slippy floor conditions. Leads & hoses kept tidy & away from
TRD OPS Uneven ground. walkways. Walkways should be a suitable
003 Slips, trips & falls
Tripping hazards.
3 4 12 width for access/egress.
1 2
PC OPS
Untidy work areas. Ensure that debris does not build up in areas
where personnel may fall.
Clear any spillages immediately with correct
signage used.

Before work: Obtain manufacturers


vibration levels & safe work timescale info &
insert to TRD permit. Supervisor to ensure
operatives fully trained and equipment in
working order.
Working with
Noise. Noise Zone: Supervisor to establish noise
pneumatic
004
breaker (Jack
TRD OPS Eye injuries. 4 4 16 zone around the area & post notices to warn 2 2
Hand/arm vibrations. others.
Hammer)
Safe Working: Rotation of work force to
ensure no one person exceeds the
manufacturer advised safe working period
on the breaker. Operatives should wear
correct P.P.E. at all times.

Pre-work: Ensure operatives are suitably


trained to handle equipment; with necessary
tool box talk to identify hazards & work tasks.
Correct PPE should be worn.
Inspect tools and ensure inspection certs are
available.
Strained muscles &
Ensure area is clean and that clear access is
torn ligaments.
available.
Safe use of hand Cuts, burns &
005
tools
TRD OPS
abrasions.
3 2 6 Safe Work: Use tool in strict accordance 1 2

NCC Received
with training etc, do not use a tool for a
Slips, trips & falls.
purpose which is not meant.
Electrocution
Ensure access & safe work platform are
available.

07/12/2016
Wires/oils/fuels etc to be secured and stored
safely. Power off when not in use.
End of shift: Store each tool correctly, any
damage should be reported.

Before Starting Work: Mechanical handling


devices to be provided; obstacles en-route
removed. Clean up spillages & waste to
prevent risk of slips/trips during transiting of
materials. Manual handling assessment
required to identify injury avoidance
procedures. Operatives should have relevant
manual handling training and appropraite
PPE, whilst being made aware of any
Strained muscles & hazards which may be present.
torn ligaments. Safe Working: Use lifting/movement aids
Cuts, burns & provided or utilise mechanical/crane
abrasions. extraction procedures. Size reduce
006 Manual handling TRD OPS
Slips, trips & falls.
4 4 16 pipe/steelwork to manageable sections.
2 2
Dropped loads. Dual lifting to be utilised taking into account
Hernias & slipped the weight, size and shape of the load. Pack
discs. loads to ensure stability. Personnel must not
exceed their own lifting capacities – DO NOT
TRY TO IMPRESS YOUR COLLEAGUES.
IF YOU CANNOT PUSH OR PULL IT DO
NOT ATTEMPT TO LIFT IT. Ensure the
load is secure prior to lifting it. If any injury
occurs report immediately to the site
supervisor and seek medical attention.
End of Shift: Ensure load is secure prior to
removal from site etc.

Page 3 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-work: Supervisor & machine operator to


carry out walk around survey. Ensure all
attachments required for work are available
and machinery is in good order, inc. lighting
system.
Exclusion Zone: Erect physcial barriers to
Premature collapse of
exclude unauthorised persons. If entry
all/part of structure.
required then do it from open side, wait until
Debris falling onto
operator acknowledges you, lower bucket
machine operator.
and switch engine off before permitting
Debris falling on
Mechanical entry. Appoint banksman to oversee works
007
demolition
TRD OPS others adjacent to site. 4 4 16 outside project boundary to ensure safe
2 3
Debris falling on other
passage of others etc.
operatives on site.
Safe Working:Ensure machine is large
Premature collapse of
enough to carry out works at arms length, if
the scaffold.
not the machine should be able to safely
reach using a raised working platform
(hardcore base). Ensure auto-throttle is
reduced.
Employ banksman always, establish method
statement and communicate to operatives;
supervise during works.

Pre-Work: Ensure Client has cleared all


chemicals from site. Ensure operatives are
aware of hazards of handling hazardous
waste. Ensure suitable PPE worn at all
times, and operatives to wash hands before
eating/drinking/smoking. Confirm with Client
Cuts, grazes &
that any 'live' services in working area have
abrasions.
been identified.
Contact with sharp
Safe Working: Ensure safe system of work
materials.
is in place, operatives should understand this
010 Soft stripping TRD OPS Slips, trips & falls. 4 4 16 and receive toolbox talks on hazardous
2 3
Foot penetration
areas etc. Also place barriers where soft
injuries.
stripping has resulted in a risk of fall etc.

NCC Received
Contact with chemical
Clear materials from workspace
residue.
progressively.
End of Shift: Remove all tools & inspect for

07/12/2016
damage, remove waste paper from site to
reduce fire risk. If disc cutters/grinders are
used, ensure all operatives are competent
and trained in their use.

Position bowser minimum 10m from


watercourse & use for all re-fuelling
operations. All transactions of fuel will be via
pump transfer with spill kit & drip trays -
gullies to be adequately protected using
absorbent materials. Gloves to be worn at all
times.
Contamination of
Specific area to be designated for re-fueling -
ground, watercourses
sand placed below. Any spillages to be
Maintenance & TRD OPS or drains.
reported directly to supervisor. Fire fighting
011 Refuelling of SUB- Injury to untrained 4 4 16 facilities to be adjacent to fuelling area, all
2 3
Machines CONTRACTOR operatives.
operatives to be made aware of procedures
Fire/Explosion.
& correct usage. These areas to be
Dermatitis.
signposted "FLAME FREE" and "NO
SMOKING"
All operatives to be trained in operation &
maintenance of plant/machinery and hold
current CITB CPCS cards. Weekly
inspection forms to be completed by all
operatives.

Pre-Work:Permit required. Refer to project


specific documents and clarify that no
combustible substances are contained within
- Written confirmation from Client where
necessary.
Ensure gas test/purging of pipework/vessels
Burns to operatives.
is carried out prior to commencement.
Operatives clothing
Inspect currounding vicinity & remove
catching fire.
Oxy/Propane combustible materials where practical. Place
013
cutting
ALL Bottles exploding. 4 4 16 wet material below cutting point when
2 2
Combustible materials
necessary.
or structures catching
Exclusion Zone: Erect physical barriers &
fire.
warning points around hot cutting point.
Safe Working: ALL cutting equipment to be
correctly fitted. Ensure operatives are
competent, trained and supervised during
the task and have completed site safety form
regarding equipment.

Page 4 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Liase with management to assign


access/egress/pedestrian routes; designated
person should be assigned at this boundary
to direct traffic & pedestrians. All operatives
to familiarise themselves with surrounding
Soft
Passage of environment. Arrange for adequate signage
Strip/Demolition
construction traffic. for pedestrian diversion with regards to
works within
Injury to others within parking restrictions etc.
community
014
college/
ALL the vicinity. 4 4 16 Exclusion Zone: No work is to be carried 1 3
Parked cars within the out outside the designated zone. Ensure
Construction site
vicinity. warning signs erected in prominent locations.
/residential
Interaction with others. Safe Working: Ensure all affected by the
environment
works are informed ASAP. All drivers should
be trained and visiting drivers should be
informed of site traffic rules. Vehicles should
not be overloaded, but loads secured and
sheeted.

Safe Working: Use mechanical means i.e.


bob-cat with bucket attachment to load
materials wherever practicable. Use Goods
lift only for removal of waste to ground level.
Be aware of SWL and do not exceed.
Should manual handling be required
Loading of strip TRD OPS Manual handling. minimum of two persons needed for heavier
017
out arisings PC OPS
4 4 16 2 3
Falls of materials. items, adopt correct handling technique.
Assess each item prior to lift and clear transit
route to ensure safe passage. Complete site
safety form.
Ensure that no time is the bucket overloaded
with materials and ensure that no persons

NCC Received
enter the loading zone.

07/12/2016
Pre-Work: Site supervisor to carry out
inspection of structures. Create exclusion
zone to ensure minimum personnel within
this area. Erect adequate protection as
Uncontrolled collapse required.
of or damage to Safe Working: Provide safe working
retaining structure. platforms in the form of scaffold towers or
Demolition of
Injury to persons due MEWP at all times. Clear resultant debris as
property adjacent
021
structure to
ALL to uncontrolled 4 4 16 soon is reasonably practicable to ensure 2 3
collapse. floors/scaffold are not overloaded. Ensure
remain
Ejection of materials no mechanical demolition or tracking or
causing injury to machinery takes place which may affect the
others. retaining section of property. Site supervisor
to act a banksman during all works adjacent
retained structure.
On Completion: Clear all created arisings
away from the retained structure.

Pre-Work: Supervisor/safety advisor to carry


out site induction highlighting to all persons
the cross over hazards. Ensure all
movements are limited to designated routes
and times only. Ensure all new/delivery
operatives are also advised.
Collisions with Safe Working: Appoint banksman to direct
Construction pedestrians/cyclists. all construction traffic over this point. Site
traffic crossing Debris falling onto traffic to limit speed to 10mph. All
022
over pedestrian
ALL
footpath.
4 4 16 movement of materials/debris are to be
1 3
footpath. Damage to checked, covered and secured prior to
paving/roadway. leaving site to ensure skips are not
overloaded etc. Banksman to remove any
debris which may have dropped onto the
footpath and secure the entrance to prevent
trespass by others etc.
End of Shift: Ensure signs and fencing are
checked prior to leaving site.

Page 5 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

ALL WORKS TO BE CARRIED OUT IN


LINE WITH HSG189/2
Pre-Work: Advise all persons that
rooftop access is prohibited. Safe work
platforms in form of MEWP to be
employed. Ensure that floors are clear
and any pits/voids are suitably covered.
Correct PPE at all times (Coveralls,
FFP3 face mask etc.)
Exclusion Zone: Erect physical
Falls onto surrounding barriers to prevent entry by
hazards. unauthorised persons. Erect signs.
Removal of
Falls of broken
asbestos cement Safe Working: Wet spray a/c sheets to
sheeting, edging or
sheets from prevent dust/fibre release during
023
structure by hand
TRD OPS coping materials. 4 4 16 2 3
Falls of equipment or removal operation; do not over spray
employing MEWP as it creates contaminated waste water.
tools.
scissor lift Take extreme care to remove sheets
Release of asbestos
fibres. whole; if breakages occur, damp down
exposed area with hand held spray unit
to contain fibre release. Hand tools only.
Position MEWP beneath direct working
area – do not lean outside working
platform, reposition as work dictates.
Lower and position sheets directly onto
the MEWP no more than 10 sheets
before unloading. Remove and load
directly to contaminated waste skip for
disposal to licensed landfill site.

ALL WORKS TO BE CARRIED OUT IN

NCC Received
LINE WITH HSG189/2.
Pre-Work: Advise all persons that
rooftop access is prohibited. Safe work

07/12/2016
platforms in form of tower scaffold to be
employed. Ensure that floors are clear
and any pits/voids are suitably covered.
Correct PPE at all times (Coveralls,
FFP3 face mask etc.)
Falls from any height Exclusion Zone: Erect physical
onto surrounding barriers to prevent entry by
hazards. unauthorised persons. Erect signs.
Removal of
Falls of broken Safe Working: Wet spray a/c sheets to
asbestos cement
sheeting, edging or prevent dust/fibre release during
sheets from
024
structure by hand
coping materials. 4 4 16 removal operation; do not over spray 2 3
Falls of equipment or as it creates contaminated waste water.
employing tower
tools.
scaffold Take extreme care to remove sheets
Release of asbestos
whole; if breakages occur, damp down
fibres.
exposed area with hand held spray unit
to contain fibre release. Hand tools only.
Position Tower Scaffold beneath direct
working area – do not lean outside
working platform, reposition as work
dictates. Remove and load directly to
contaminated waste skip for disposal to
licensed landfill site.

Pre-Work: Inform all persons and create


exclusion zone down wind. PPE worn at all
times. Ecnlosed areas should be opened to
improve air flow (unless unsafe to do so).
Soft-strip Ensure adequate washing facilities available.
Pigeon carcasses &
operations within Safe Working: If waste build-ups, operatives
faeces - Psittacosis.
structures which to use hand tools and place directly in waste,
032
have been
TRD OPS Slips, trips & falls. 3 3 9 which should be removed from the area
1 3
Enclosed space.
nesting in by progressively. Decontaminate the area using
pigeons spray. Follow strict hygeine procedures.
End of shift: Remove coverall & mask &
dispose of as contaminated. Wet down boots
& gloves and place to one side - wash
hands, face & other exposed areas.

Page 6 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Create exclusion zone using


Heras type fencing - ensure signage
depicting works & hazards are located at
prominent locations.
Site supervisor to liase with all adjoining
properties and assess any additional
protective requirements, which may be
Demolition of Unauthorised access
needed. Erect suitable protection to prevent
structures by others.
injury to pedestrians etc.
033 adjacent to ALL Injury to others within 4 4 16 Safe Working: Site supervisor to carry out
2 3
occupied the vicinity.
environmental monitoring i.e. dust, noise etc.
premesis Damage to property.
on an ongoing basis. Where necessary
works to be carried out by hand working
methods to prevent damage to other
properties.
End of shift: Inspection all site dencing and
repair defects. Secure & disable any
machinery, secure access points.

Pre-Work: Ensure emergency procedure set


out within the Health & Safety Plan/Method is
available and read by all operatives with a
copy readily available. All personnel should
be aware of emergency route and nearest
Fire; exits, also of the location of the various
Removal of TRD OPS Exposure to areas of works and relay info through Tool
asbestos within PC OPS asbesros fibres; Box talk. Use fire retardant polythene.
040
building during SUB-
4 4 16 Safe Working: Keep transit routes clear and
2 2
soft strip. CONTRACTOR Asbestosis / do not carry out any works adjacent to the
Mesothelioma enclosure. Hot cutting to be carried out
under Permit to Work procedures. Fire
fighting equipment to be on hand during all
works where there is risk of fire.
Do not commence soft-strip operations until

NCC Received
clearance certificate is received.

07/12/2016
Erect suitable fencing around perimeter of
site and erect signage depicting dangers of
accessing the area.
Erect full height scaffold to all elevations and
returns required to ensure the safety of
others accessing the adjacent
Unauthorised entry
neighbourhood. Erect toe-boards / netting to
onto site.
prevent injury from dropping materials, tools
044 Public Safety ALL Collision. 3 4 12 etc.
2 3
Unauthorised
Ensure inspection to same is carried out on
operation of plant.
a regular basis and any defects repaired.
Ensure all visitors are escorted and do not
deviate from designated routes.
Ensure all plant is isolated and keys
removed at the end of each shift.

Page 7 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Ensure all locations of drop-


zones are signed and relayed to ALL site
operatives; Prepare drop-zone base with
suitable exclusion zone fencing to segregate
from surrounding area – position debris
netting to same. Allocate control to two
operatives only per drop-zone (if more than
one area is to be used at any one time);
Ensure a direct line of communication is
provided + carry out pre-checks of this
equipment from the highest drop-zone point;
Install (by specialist contractor) edge
protection. Read & understand method
Death / injury – due to
statement.
falls / ejection of
Safe Working: Ensure all safety measures
materials;
are in place; Follow method statement; Two
Drop-zone TRD OPS Manual handling.
045
operations PC OPS Falls from opening.
4 4 16 allocated drop-zone operatives (Work-face 2 4
Controller & Ground Floor controller) to
Dust – respiratory
control ALL operations; carry out continual
issues.
environmental monitoring; Cease works
whenever surrounding/environmental issues
dictate; No hazardous materials to enter the
drop-zone; Ensure all items requiring to
enter the drop-zone have been suitably size
reduced to prevent blockages etc; Cease
works and periodically clear arisings from
ground floor level to prevent a back-log of
arisings.
End of shift: Secure/lock all entry points to
the void and post warning notices advising of
void behind; Clear all combustible materials
from the work area to reduce risk of ignition
issues;

NCC Received
Pre-Work: Check that the Client is aware of
the operation and the likelihood of risk.

07/12/2016
Ensure that sensitive areas are adequately
protected from the works.
Inhalation by Safe Working: Controls to eliminate or
operatives and others. reduce dust emissions should be in place
Dust created Hazardous to and noted on the Safety Plan or Method
053 during demolition surrounding vicinity & 4 2 8 Statements. Employ localised water sprays 2 2
& loading activities works. to areas where dust emissions are noted and
Damage to eyes. sheeting of loads in transit should be
implemented.
Site supervisor to carry out environmental
monitoring during loading works.
Implement and maintain a safe system of
work at all times.

Pre-Work: Don correct PPE/RPE. Carry out


a thorough visual inspection of the area.
Issue with ‘litter pickers’. Carry out tool box
talk highlighting dangers of injection of toxic
materials/health risks etc. Issue operatives
with Sharp Box to enable safe disposal of
any hypodermic needles etc.
Removal of
Safe Working: Where needles etc. are
sharps,
Skin penetration from uncovered they are to be placed immediately
hypodermic
contact with sharps into the self closing Sharp Box provided. Any
needles;
and needles findings are to be reported to the site
Working within
Infection, disease & supervisor. Ventilate all contaminated areas
057 areas suspected
skin disorders from
3 4 12 prior to commencement and use a safe and
2 3
of contamination,
contact with effective detergent and or disinfectant to
i.e. blood
contamination matter clean down.
products, drug
Waste Disposal: Following successful
related materials.
clearance of all areas the Sharp Bin is to be
returned to site supervisor who will arrange
disposal through the drugs rehab unit.
Supervisor: To carry out final inspection and
ascertain that the area is safe before
allowing normal operations to continue.
Record all collection and disposal of
contaminates for Health & Safety File.

Page 8 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: : Inspect surrounding area to


highlight any uneven ground, pits etc. Place
steel plates over pits capable of sustaining
weight of machinery, men & materials.
Ensure certificate held for MEWP. Erect
exclusion zone around works area and post
warning signs. Don PPE/RPE. Instruct all
operatives on the safe method of works and
alert them within on-site training of any
hazards highlighted within the inspection.
Ensure safe access / egress is available at
roof level – cover roof lights / erect edge
Gaining access to Falls from height.
protection to all elevations required. Ensure
height - Overturning of MEWP.
suitable access point from the MEWP onto
070 employing mobile TRD OPS Falls of 3 3 9 the structure is available which does not put
1 3
elevated working tools/equipment being
operatives at additional risk. Assess weather
platform (MEWP) taken with operatives.
conditions - beware of frost etc.
Safe Working: Load - SWL to be known
and displayed. Calculations of weight of
men / equipment to be carried out to ensure
this is not exceeded.
Ensure only competent operator is engaged
to operate MEWP. Mandatory for all
operativesto wear safety harness due to risk
of fall from working platform. Operatives
must clip on to a suitable anchor point before
leaving the safe work platform of the MEWP.

Pre-Work: Collate all info from service


providers and initiate site meeting if
necessary with same to discuss termination

NCC Received
requirements etc. Send written request to all
services providers for termination/diversion
to services to ensure all areas within site

07/12/2016
boundaries are safe. Ensure written
Electrocution;
confirmation is received from service
Release of toxic
providers and issue site with copy of same.
substances;
Safe Working: Obtain Permit to Dig from
Locating buried Overturning of
071
services construction plant;
4 4 16 PC; Carry out careful hand dig to expose 2 3
redundant/remaining services using non-
Damage to services
conductive tools. Mark layout with high
due to plant crossing.
visibility markers. Make all aware of layout –
including visiting drivers/plant operators etc.
Where excavations are required ensure area
backfilled as soon as is practicable of erect
barriers around same to make aware. Where
necessary place steel plates or similar over
areas where plant requires to cross to
ensure damage is prevented.

Pre-Work: Obtain isolation certificate from


appointed Contractor – DO NOT
COMMENCE UNTIL THIS IS RECEIVED.
Ensure 110v supply is installed by appointed
Contractor to each floor of structure and is
suitable tested. Secure all associated cables
to prevent tripping hazards. Carry out
inspection of equipment and ensure all is in
074 Site electrics TRD OPS Electric shock. 4 4 16 good order and has been properly tested in 2 3
accordance with current legislation.
Safe Working: Use low voltage equipment
only on sites and connected to centre tapped
transformer (55v). Never tamper with safety
devices and if equipment is faulty do not use
it – return it to your site supervisor. Ensure
all electrics are fitted by a competent person
only.

Pre-Work: Ensure all fencing is erected by


compotent persons. Access points should be
kept clear, and any traffic dealt with by
Site perimeter Entry by unauthorised banksman.
075 fencing/signage/a ALL persons especially 3 3 9 Safe Working: Site fencing to be checked at 1 3
ccess children start/finish of each day to check no
unauthorised access is possible.
Erect adequate signage to ensure all
persons are warned off the site.

Page 9 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Site supervisor to issue all


operatives with correct PPE (P3 respirators,
disposable coveralls etc.) Ensure all
operatives are aware of the respective
Inhalation by hazards through tool box talk training. Form
operatives; an exclusion zone.
Removal of
076
MMMF
TRD OPS Skin irritation; 3 2 6 Safe Working: Do not double handle the 2 2
Release of fibres into material as this will create excessive fibre
atmosphere. release. Place materials directly into
awaiting bags and seal.
End of shift: Remove coveralls etc. and
place within bag for disposal. Ensure strict
hygiene system is in place.
Fill in your WRAP crushing booklet and
follow the correct WRAP protocol throughout
all works; • Appropriate signage to be
positioned both surrounding the crushing
area and to the crusher itself warning of
prohibited access / no touching etc.; • Place
low level skip to ‘mag-belt’ to collect
materials and prevent access by others due
to crushing / entrapment issues; • Carry out
specific site induction training –
incorporating issues of entrapment/
segregation of ‘picking’ operatives from
crushing operations/emergency stop
procedures etc.;• Operators platform must
Vibration; be kept clean and tidy at all times. Area
Dust inhilation; around the access steps must be kept clear
Crushing of Limbs; of debris and tidy. Rotate operator to
Entanglement; prevent vibration problems and issue with
Crushing
077
operations
TRD OPS Noise; 4 4 16 correct PPE to ensure operatives are warn 2 2
Stability issues for at all times; • Ensure hearing protection is
support worn at all times – THIS IS A MANDATORY
equipment/raised REQUIREMENT; • Operatives must work off

NCC Received
working platform separate platform and stop crusher before
entering onto the unit to release tangled
items. It is prohibited to attempt pulling free
while crusher is operational;

07/12/2016
• All guards removed for maintenance must
be replaced by the fitter before re-starting
machinery. Fitter to be in control of isolation
of plant during maintenance;
• Only trained and competent operatives to
be in control of crusher on/off switch.
• Emergency off switch to be RED and in
prominent position (preferably Bump type
switch);
• Complete appropriate inspection/

Pre-Work: Assess weather, particularly frost


etc. Safe access required to all roof
structures.
Edge Protection: In exceptional cases,
should edge protection not be reasonably
practicable safety harnesses attached to an
appropriate anchorage point on the structure
or via a running line capable of sustaining
2.5 times the weight of the operative are to
be worn.
Falls from height. Safe Working: All safety harness’ and
Safe use of safety Failure of harness. lanyards must conform to the relevant British
080
harness
TRD OPS
Failure of anchor
3 4 12 2 3
& EU Standards and be kite marked. A
point. thorough inspection must be carried out by a
competent person before each use and
findings documented – any damage / fraying
to straps etc. renders the item unsuitable for
use and WILL NOT BE USED. When
unclipping / reclipping of lanyard is required
at height two lanyards must be used to
ensure at all times the operative is suitably
protected from falls.
Ensure equipment is correctly used and PPE
worn at all times.

Page 10 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Site supervisor to carry out


inspection of structures. Create exclusion
zone to ensure minimum personnel within
this area. Erect adequate protection as
required.
Safe Working: Provide safe working
Uncontrolled collapse platforms in the form of scaffold towers or
of or damage to MEWP at all times. Clear resultant debris as
Demolition of
adjacent structures. soon is reasonably practicable to ensure
084 walls by hand TRD OPS
Injury to persons due
3 3 9 floors are not overloaded & clear floor
2 3
working methods.
to uncontrolled periodically. Work from the uppermost
collapse. section down in approx. 1m lifts to prevent
uncontrolled collapse. Ensure no
mechanical demolition or tracking or
machinery takes place which may affect the
adjacent property.
End of shift: Clear all created arisings away
from the retained structure.

Pre-Work: Site supervisor and machine


operators to carry out inspection of
designated access/egress routes and work
area. Create exclusion zone to ensure
minimum personnel within this area. Erect
adequate protection as required. Ensure
competent person operates machinery.
Overturning of mini- Ensure all known hazards are relayed to
digger/skid steer. operator. Ensure roll bar fitted to each unit
Use of Mini-
Injury to operative. and seat belt/harness fitted and worn.
Digger Equipment TRD OPS
085
for clearance PC OPS
Crushing injury to 3 3 9 Ensure stop-block/s in place to any 1 3
operative/others. openings/dropzones.
works
Collision with others. Safe Working: Ensure all persons are
excluded from the works area. Receive
written confirmation of disconnection of

NCC Received
services. When clearing materials ensure all
persons are aware of your location. Wear
issued PPE/RPE.
End of shift: Clear all created arisings to the

07/12/2016
designated loading zones or position neatly
so as not to cause additional hazards.

BEFORE STARTING WORK: Ensure ALL trees


with TPO are protected and locations known.
Site supervisor and machine operator to
carry out walk around survey. Inspect
accessible areas surrounding trees and
ensure operatives excluded from the working
area. Ensure all attachments required for
the works are available, quick-hitch
attachments are fully automatic and all
machinery are in good working order.
Ensure equipment is available and inspected
and cutting operative positioned within a
safe zone away from the working area. Skip
Mechanical Collision with to be placed as close to the working area as
091
Extraction of trees
TRD OPS 3 3 9 1 3
operatives/others; possible to reduce transiting issues; Ensure
banksmen positioned to further control the
area and that all works are contained within
the heras fenced site exclusion
zone;EXCLUSION ZONE: Appoint banksmen
to oversee the works to ensure safe passage
of others etc.SAFE WORKING: Machine
operator to be in direct communication with
banksman. Ensure that the machine is large
enough to carry out the work. tree to be
grasped at high level with grab attachment
and tracked back in a controlled manner to
induce controlled collapse. Establish a safe
system of work (Method Statement) and

Page 11 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Erect suitable signage throughout the site.


Designate a one way internal traffic route
wherever possible.
Ensure speed limit is displayed and adhered
to at all times.
Ensure all visitors to site are not permitted to
enter the site unescorted. Designate
pedestrian only route wherever possible.
Plant movement - Warn drivers of plant through toolbox talks of
Movement of collision with other risk of collision at high risk points.
construction plant; Ensure banksman is in full view of the
TRD OPS
102 traffic plus
PC OPS
Plant movement - 4 3 12 operator at all times. Advise operator not to 1 4
banksman within Collision with track or slew if he cannot see the banksman.
site boundary banksman/operatives/ Ensure all plant is fitted with and use
visitors. reversing alarm, mirrors and hazard beacon.
Any defects to these items are to be
reported immediately to the
foreman/supervisor.
All operatives on site to be issued with and
wear high visibility clothing at all times.
All visitors to be issued with correct PPE and
high visibility clothing for the duration of their
visit on site.

Refer to asbestos survey held in your


site file; Specialist contractor to carry
out removal of ALL asbestos containing
materials from buildings prior to entry
by TRD operatives - obtain clearance
certificates and written confirmation via
client that this has been completed.
TRD OPS; If
ASBESTOS Asbestosis;
suspect materials are uncovered STOP
Undiscoveered OPS; Release of
103 4 4 16 WORK IMMEDIATELY, inform others 2 3

NCC Received
asbestos on site VISITORS; asbestos fibres into
GENERAL around you and vacate the area..
atmosphere;
PUBLIC Report immediately to your supervisor.
Supervisor - report

07/12/2016
immediately to client and contain the
area against access. Contact analyst
direct and arrange for site visit and
sampling - DO NOT RE-ENTER THE
BUILDING UNTIL CONFIRMED BY
ANALYST
BEFORE STARTING WORK: Carry out tool
box talk and advise all persons of no-go area
for those not involved with the works. Safe
work platforms in the form of tower scaffold –
erected as per manufactures
recommendations to be employed. Ensure
floor areas clear and any pits/voids etc. are
suitably covered to prevent overturning of
the access equipment. All operatives to be
Falls from any issued with and don correct PPE/RPE –
height onto Disposable coveralls (elasticated wrists,
surrounding ankles, hoods; FFP3 half face masks;
hazards Safety Helmet; Safety Boots; Gloves; Eye
Removal of
Falls of Protection). EXCLUSION ZONE: Erect
104 Asbestos - Non- TRD OPS 4 4 16 2 3
Licensed Works
equipment or tools physical barriers to prevent entry by
Release of unauthorised persons. Erect signs. SAFE
asbestos fibres WORKING: Once exposed damp down the
Asbestosis/Mesothe material using airless spray unit and once
penetrated carefully remove and place
lioma
immediately into asbestos waste sack.
Clean down area with damp rag/tac rag and
bag as contaminated.
Remove waste sacks and load directly to
contaminated waste skip for disposal to
licensed landfill site.
Ensure all operatives have read and
understand the method statement

Page 12 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Carry out tool box talk and advise


all persons that access onto the roof is
prohibited. Safe work platforms in the form of
tower scaffold units to be employed – to be
erected in accordance with manufacturers
recommendations by competent persons.
Ensure floor areas clear and any pits/voids
Falls from height;
etc. are suitably covered to prevent
Working off Falls of materials;
105
Tower Scaffold
TRD OPS
Falls of equipment or
4 4 16 overturning of the unit. Correct PPE to be 1 3
worn (coveralls & FFP2 face masks).
tools
Exclusion Zone: Erect physical barrier to
prevent entry by unauthorised personnel.
Safe Working: Operatives to position Tower
beneath the direct working area - do not lean
outside this area, dismount and reposition as
work dictates. Ensure all operatives have
read & understood method statement.

All operatives to attend tool box talk on the


potential risk of Weils Disease. All to be
instructed in the need to adhere to a strict
hygiene regime. Any cuts/grazes etc. are to
be suitably sealed and cleaned following
works where risk of contamination is
present. Ensure suitable washing facilities
Working within an
are provided including soap and disposable
environment with Weils disease /
107 TRD OPS 3 3 9 towels etc. Obtain HSE hand-out – 1 3
evidence of rat Leptospirosis
Leptospirosis from your Site Supervisor if
infection.
you start to suffer from any flu-like
symptoms, book in immediately with your GP
and take the hand-out with you and inform
your GP that they are at risk of Weils

NCC Received
Disease from your occupation. Site
Supervisor to inform the company safety rep
immediately on issue of hand-out.

07/12/2016
Pre-Work: Supervisor and machine operator
to carry walk around survey. Voids etc. must
be properly broken out, backfilled and
compacted prior to commencement.
Working area must be levelled &
machinery/attachments in good condition.
Exclusion Zone: Erect physcial barriers to
exclude unauthorised persons. If entry
required then do it from open side, wait until
operator acknowledges you, lower bucket
Dust / Gas explosions. and switch engine off before permitting
Mechanical
Premature collapse of entry. Post warning signs and appoint
demolition of
part or all of structure. banksman to oversee works outside project
buildings/
Debris falling onto boundary.
structures with
122
high reach
ALL machinery operator. 4 4 16 Safe Working: Ensure machine large 2 3
Debris falling on other enough to carry out task at arms length or
excavator and
operatives on site. via a raised working platform.
cracker/shear
Overturning of Establish a safe system of work (Method
attachment.
machine. Statement) and communicate to the
operatives. Carry out demolition in a
methodical manner with sheared materials
removed in a controlled manner.
Employ water spray techniques to reduce
dust levels. Employ a banksman during all
mechanical demolition.
Ensure method statement being followed
and that the TM plan incorporates suitable
protection to reduce plant/pedestrian
interfaces.

Page 13 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: : Ensure all infill brick/block


panels are ‘popped’ through to expose the
steelwork. Carry out walk-round survey of
the steelwork and highlight cross-beams etc.
or hinge-cut points to permit controlled
collapse. Determine the start point to ensure
the elevation which is closest to the
boundary fencing is collapsed into the
footprint of the structure. Ensure the correct
Collapse of steelwork
excavator attachments are available to carry
damaging boundary
out the works i.e grab/shear. Ensure the
fencing;
protective cage is in place to the cab.
Steel ejection outside
Safe Working: Commence works from
exclusion zone;
designated start point. Ensure all
Ejection of steelwork
preparatory works are carried out. Carry out
Demolition of causing injury to
works at jib length to ensure the cab is at the
124 single storey steel ALL machine operator; 3 3 9 greatest distance from the structure. Grasp
1 3
framed structure ‘Kick-back’ of
the structure at the highest point and track
steelwork – causing
back, away from the footprint of the structure
death or major injury
to induce controlled collapse away from
to operative/s during
boundaries etc.
demolition / final size
Clearance: Once at ground level inspect
reduction of steelwork;
and identify areas of steelwork which require
segregation by hot-cutting. To prevent ‘kick-
back’ issues machine operator to grasp
steelwork to be cut at a suitable point to
ensure risk of ignition of oils is prevented but
permit safe cutting of the steelwork by the
operative – this will ensure any energy
(tension) contained within the steelwork is
absorbed by the excavator and prevent
injury to the cutting operative.

Appoint Fire Warden to control any

NCC Received
emergency situation & designate emergency
escape routes at each floor level and erect
appropriate signage / fire points with all

07/12/2016
emergency routes/ fire points/ assembly
points marked..
Fire points to consist of minimum 2
extinguishers of a type relevant to the
working environment.
Where possible position fire hose and/or
water barrels immediately adjacent any
working areas.
Refer to all relevant documentation and
Burns to operatives. following inspection of vicinity to clarify that
Operatives clothing no combustible/explosive substances are
catching fire. contained. Written confirmation from Client
Fire prevention / Bottles exploding. may be needed.
127
control on sites
ALL
Adjacent combustible
4 4 16 Ensure gas test/purging of pipework/vessels
2 3
materials or structures is carried out prior to commencement as
catching fire. required.
Impeded exit. Place wetted material below any cutting point
as necessary.
Ensure all cutting equipment i.e. guns,
Regulators, Spark Arrestors and Pipes are
correctly fitted.
Ensure that all operatives are competent in
their task and have sufficient information,
instruction, training & supervision.
Incorporate fire prevention matters into site
induction for all operatives/visitors to site.
Carry out fire-drill / emergency evacuation
procedure and relay findings to director.
Maintain 'Good Housekeeping'.

Page 14 Form 7.2D.03 - RISK ASSESSMENT


Total Reclaims Demolition Ltd

Pre-Work: Carry out tool box talk and advise


all persons that the area is now a no-go area
for those not involved with the works.
Ensure floor slab is clear to enable easier
clean down following demolition. All
operatives to be issued with and don correct
PPE/RPE (coveralls & FFP3 face masks).
Organise for analytical monitoring to be
carried out by specialist NAMAS accredited
company if large quantity.
Exclusion Zone: Erect physical barriers to
prevent entry by unauthorised persons.
Erect signs.
Falls of equipment or Safe Working: Wet spray a/c sheets to
Removal of tools; prevent dust/fibre release during removal
asbestos cement Release of asbestos operation though take care not to over spray
205 by controlled ALL fibres into atmosphere 4 4 16 sheeting as this will create contaminated 2 3
collapse Exposure to waste water.
procedures operatives and others. Follow the written method statement.
Do not track over the material as this will
create excessive fibre release. Clear the
waste progressively working into the footprint
of the building and load directly to
contaminated waste skip for disposal to
licensed landfill site.
Make safe the structure – lower attachment
to ground level and switch off before entry by
any personnel
Ensure all operatives have read and
understand the method statement.

ALL WORKS TO BE CARRIED OUT IN


LINE WITH HSG189/2
DO's: The operator must visually check that
the pin is in place on the hitch before starting
the work and every time a different

NCC Received
attachment is fitted;
Operators must not use the machine unless
they are satisfied that the quick hitch is
secured in place. If the manufacture

07/12/2016
recommends a shake and rattle of the
bucket as safety check, this activity must be
undertaken within the safe zone with the
bucket at a low level. Only use the quick
hitch attachments for which you have been
specifically trained; Establish a safe zone
free from other personnel on site when
carrying out any detachment or attachment
operations; Follow manufacturers connection
TRD OPS
Failure of quick-hitch procedure at all times; Report any suspect or
Safe use of quick- PC OPS
211 – fall onto 3 4 12 defective quick-hitch couplers immediately to 1 3
hitch devices SUB-
operative/others your supervisor; Log any defects on your
CONTRACTOR
internal inspection record F29;
Supervisor to check quick hitch attachments
before use on site and as part of weekly
inspection.
DONT's: NEVER swing your attachment
over another person;
NEVER let others work beneath your
attachment;
NEVER operate the coupler with the
supplemental safety device in place;
NEVER use retaining pins which have not
been designed for specific use;
NEVER operate an unsafe Coupler – report
it immediately to your supervisor and remove
keys;

Page 15 Form 7.2D.03 - RISK ASSESSMENT

You might also like