3.3 Excavation in Soil with Dozer with lead upto 100 cum 112.00
metres (Excavation for road way in soil by
mechanical means including cutting and pushing the
earth to site of embankment upto a distance of 100
metres (average lead50 metres), including trimming
bottom and side slopes in accordance with
requirements of lines, grades and cross sections.)
3.4 Excavation in Ordinary Rock with Dozer with lead cum 188.00
upto 100 metres (Excavation for roadway in
ordinary rock by deploying a dozer, 80 HP including
cutting and pushing the cut earth to site of
embankment upto a distance of 100 metres
( average lead 50 metres ), trimming bottom and
side slopes in accordance with the requirements of
lines, grades and cross sections.)