Professional Documents
Culture Documents
INTRODUCTION
PROJECT NAME: SUKH CHAYN RESIDENCE ISLAMABAD
LOCATION: ISLAMABAD
PLUMBING AND FIRE FIGHTING (MUGHALS) SUB CONTECTOR: FIZZA DEVELOPERS PVT LTD.
BUILDING STRUCTURE
TWO APARTMENT BUILDINGS JOINT WITH CONNECTING BRIDGES
1ST FLOOR TOTAL APARTMENTS =16 No. (3 BED APT = 8, 2 BED APT = 8)
2ND FLOOR TOTAL APARTMENTS =24 No. (3 BED APT = 8, 2 BED APT = 12, 1 BED
APT =4)
3RD TO 8TH TYPICAL FLOOR EACH FLOOR APARTMENTS =24 No. (3 BED APT = 8, 2 BED APT = 12, 1 BED
APT =4)
9TH FLOOR TOTAL APARTMENTS =16 No. (3 BED APT = 8, 2 BED APT = 8)
ALL PLUMBING FIXTURES, AUTOMATIC WATER LEVEL CONTROLER, ALL WATER PUMPS
FIRE FIGHTING:
ALL PUMPS, VALVES, FIRE HOSE CABINET WITH REEL, SPRINKLERS, ZCV’s, FIRE EXTINGUISHERS, LANDING
VALVES WITH CABINET, BREECHING INLET.
Rain Water (only Shaft No. 28) shall be collect in Rainwater tank, after treated shall
further be used for Irrigation. (Controlled by BMS). Other Rain Water Outlets
(Scupper Drain) sourcing outside, shall have Free Discharge.
U.P.V.C. Pipes shall be used for Soil, Waste, Vent & Rain Water Drainage System &
P.V.C. Class E Pipes shall be used for External Drainage System.
5. IRRIGATION SYSTEM
2 No’s Irrigation Pump Sets shall be used for transferring filtered rain water & waste
water to the Irrigation at External Area.
6. FIRE FIGHTING SYSTEM:
I. FIRE HOSE REAL CABINET SYSTEM
II. Fire SPRINKLER SYSTEM
III. FIRE EXTINGISHERS
IV. FIRE HYDRANT SYSTEM (TWO WAY PILLAR TYPE)
V. DRY RISER SYSTEM LANDING VALVE WITH CABINET
Each building have one overhead water tank and 2 pumps VFD Control in the pent
house floor.
B1 to B3 & 9th Floor Each Floor 6 Nos. FIRE HOSE REAL CABINET
Ground floor to 8th Floor Each Floor 8 Nos. FIRE HOSE REAL CABINET
B3 to 9th Floor All Floors cover with Fire Sprinkler system
Basement Level 03, 02 & 01 is divided into 5 Zones providing ZCV’s (Zone Control
Valve).
Basement Level 03, 02 & 01 is fully covered with Upright Type Sprinklers.
Each Apartment consists of separate Gate Valve for Fire Line & Access Panel at
entrance.
Pent house level 1 & 2 All Bed Rooms covered with Side Wall type Fire Sprinkler.
Dry Type & CO2 Type Fire Extinguishers shall be placed in Corridor’s Area.
K Type Fire Extinguishers shall be used in Kitchen Area.
Auto Dry Powder Ceiling Mounted Fire Extinguisher shall be placed in Electrical
Rooms.
Pendant Type Sprinklers shall be used in Flat’s Entrance Lobby & Passage Way.
2 No’s Separate Wet Risers shall be used from Top Level to each part of the building.
Each floor shall be divided into 2 Zones providing ZCV Assembly.
Fire Test Drain Line for complete system shall be connected to Basement Level 03
Underground Water Tank.
Each building have 1 dry riser landing valve cabinet with canvas hose in the stair
case.
Ground Floor External Area Cover with 2 Way Pillar Hydrant
2 Breeching inlet for fire department connections
2 breeching inlet for dry riser system
Black Steel Seamless Fire Pipes shall be used (Schedule 40, ASTM A53).
9. MISCELLANEOUS Work
UPVC Pipe Sleeves
Core Cutting
Equipment Tagging
Shop Drawings
As Built Drawing
BOTTLENECKS
Testing and Commissioning Of Provided Equipment
Water Supply Piping In Walls
Soil, Waste and Vent Piping Suspended from Slab and shafts
Coordination with other services