Site Engineers:
Site engineers are responsible for all aspects of health and safety on site and are accountable
to the Unit head / Regional manager. Their roles include:
Report any issue affecting health and safety issues at the work sites to the regional manager / unit
head / safety team
Coordinate with end customer / client for the taking work permit and returning work permit
Communicating the work content / hazard involved to working group through the medium of
Toolbox meeting before commencement of work every day
Initiating proactive measures to minimize / eliminate accidents
Reporting in detail in the event of incident
Ensure effective use of appropriate PPE
Ensure the quality of job at all times without any compromise on safety
“Stop Work” in the event of any serious safety violation
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 1 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 11
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 2 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 11
4.3 Operational Sequence of work
Trip Breaker
Lift Interlock to free truck lock
Insert Operating handle
Rotate operating handle clockwise till truck position indicator indicates test
Remove operating handle
Breaker can now be operating with Door closed/open
Trip Breaker
Open Breaker chamber door if closed
Disengage secondary and socket
Decouple the both the coupling pins of lead screw from truck
Slide vermin proofing cover
Pull the truck
Lift the truck - lock and withdraw the truck out of the cubicle
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 3 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 11
INSERTION OF BREAKER TRUCK IN THE CUBICLE AND RACKING INTO SERVICE POSITON
Trip Breaker
Slide vermin proofing covers if wheel path locked
Unlocked shutters if locked
Push Truck to test position till it stops
Engage both the coupling pin of lead screw racking mechanism with truck
Engage secondary plug and socket
Slide back vermin proofing covers
Close breaker chamber door
Lift interlock and insert operating handle
Rotate operating handle anticlockwise till truck position indicator indicates service
Remove operating handle
Breaker can now be operated
5.0 Final Checks & Restoration of work area after completion of work:
Disconnect the temporary supply and remove the barricading tapes
Ensure no loose materials / tools are kept in and around the area
Leave the place by keeping it tidy and clean
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 4 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 11
Personal
Protective
Equipment
YES /
Yes Yes Yes Yes
NO
Personal
Protective
Equipment
YES /
Yes Yes Yes No
NO