1.0 Purpose
This procedure is prepared to carry out various pre- commissioning tests to be conducted in systematic
manner for Wave trap to ensure the healthiness and performance of the Device.
2.0 Scope
This procedure covers the Pre commissioning test for wave trap as for the following
1. Insulation Resistance Value Test
2. Contact Resistance Measurement Test
3.0 Responsibility
Unit Head / Regional managers:
Unit heads / Regional managers have overall responsibility for health and safety management and role
includes:
Planning and scheduling of activities with a view to execute the project
Identify significant health and safety and eliminate or minimize them
Maintaining all legal and statutory requirement
Assist the safety team to conduct the safety training and audit at sites
Ensure all safety rules and regulations are followed at work sites
Site Engineers:
Site engineers are responsible for all aspects of health and safety on site and are accountable to the Unit
head / Regional manager. Their roles include:
Report any issue affecting health and safety issues at the work sites to the regional manager / unit
head / safety team
Coordinate with end customer / client for the taking work permit and returning work permit
Communicating the work content / hazard involved to working group through the medium of
Toolbox meeting before commencement of work every day
Initiating proactive measures to minimize / eliminate accidents
Reporting in detail in the event of incident
Ensure effective use of appropriate PPE
Ensure the quality of job at all times without any compromise on safety
“Stop Work” in the event of any serious safety violation
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 1 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 10
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 2 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 10
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 3 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 10
Contact Resistance Measurement
Connect the earth from CRM kit to earth plate or earth pit
Connect the CRM kit Voltage leads to across the Jumper contact
Connect the CRM kit Current leads to across the jumper contact and keep the Voltage leads
inside the current leads
Ensure the tightness of the connections
Apply the rated current across the jumper contact
Note down the value from CRM kit
Repeat the above steps for all remaining jumper contact
After completion the test Switch off the supply to the CRM kit and disconnect the temporary
connections
Prepared by Approved by
Doc No: VEPL /OHSAS/D11 Rev.No:00 Page 4 of 5
VOLTECH ENGINEERS PRIVATE LIMITED.
OPERATIONAL CONTROL PROCEDURE
OCP NO: 10
5.0 Final Checks & Restoration of work area after completion of work:
Disconnect the temporary supply and remove the barricading tapes
Ensure no loose materials / tools are kept in and around the area
Leave the place by keeping it tidy and clean
Personal
Protective
Equipment
Personal
Protective
Equipment