% Accomplishment
Item No. Particulars Unit Quantity Unit Cost Amount Relative Weight
Previous This Period Total to date
I Site Works sqm. 60.00 129.11 ₱ 7,746.60 0.20% 0.00% 100.00% 100.00%
II Earth Works cu.m. 100.00 826.90 ₱ 82,689.98 2.18% 0.00% 100.00% 100.00%
III Concrete Works cu.m. 33.85 6,857.80 ₱ 232,136.65 6.12% 0.00% 52.93% 52.93%
IV Reinforcing Bars kg. 3491.79 88.17 ₱ 307,871.12 8.12% 0.00% 49.74% 49.74%
VI Roof Framing Works kg. 1164.35 102.20 ₱ 118,996.57 3.14% 39.84% 0.00% 39.84%
VII Steel Works kg. 13231.14 132.14 ₱ 1,748,343.73 46.12% 0.00% 30.00% 30.00%
VIII Roof & Tinsmithry Works lot 1.00 188,654.86 ₱ 188,654.86 4.98% 0.00% 0.00% 0.00%
IX Carpentry Works lot 240.00 553.20 ₱ 132,768.00 3.50% 0.00% 0.00% 0.00%
IX Plumbing Works lot 1.00 16,398.42 ₱ 16,398.42 0.43% 0.00% 0.00% 0.00%
IX Electrical Works outlets 40.00 2,056.16 ₱ 82,246.40 2.17% 0.00% 0.00% 0.00%
IX Tile Works sqm. 77.70 1,516.28 ₱ 117,814.68 3.11% 0.00% 0.00% 0.00%
IX Painting Works sqm. 748.95 319.11 ₱ 238,995.06 6.30% 0.00% 0.00% 0.00%
IX Aluminum Composite Panels Cladding sqm. 36.00 6,562.50 ₱ 236,250.00 6.23% 0.00% 0.00% 0.00%
IX Construction Safety And Health lot 1.00 37,453.53 ₱ 37,453.53 0.99% 0.00% 100.00% 100%
This is to Certify that the above item of works are done in accordance with the approved contract, plans and specifications.
CERTIFICATE OF ACCOMPLISHMENT
% Accomplishment
Relative
Item No. Particulars Unit Quantity Unit Cost Amount
Weight
Previous This Period Total to date
This is to Certify that the above item of works are done in accordance with the approved contract, plans and specifications.
MARGARITA V. REMOLLO
Manager/Owner
ATR CONSTRUCTION