DECEMBER 2020

MONTHLY OPERATIONS &


MAINTENANCE REPORT
Monthly Report of Operations and Maintenance
For Alfil millers for both mills A & B and motor vehicles for the
month of December 2020

January 15th, 2021

GENERAL MANAGER

ALFIL MILLERS LTD

Dear Sir:

The maintenance team is pleased to present the attached Monthly report. Included is a detailed
report of operation and maintenance of Mill B and motor vehicle for the month of December.
The maintenance team welcomes any comments or questions on this report.

Sincerely,

Maintenance team
Executive Summary
The month of December ran well and it was very productive. During last month, we
experienced minor break downs in mill B mainly stitching machines. Majorly, we carried out
prevent maintenance in mill B including general greasing. On motor vehicle side, we have
carried out both preventive and breakdown maintenance on few trucks majority of which had
brake systems faults, air bags and self starters’ failures, though repair of some vehicles is still
pending due to lack of spare parts.
Preventive maintenance done at Mill B
We carried out daily, weekly and monthly prevent maintenance on mill B during the last month
(December), as follows;

1. Daily maintenance included blowing of mill B, draining of condensed vapor from


compressor and daily inspection of mill equipments during production to identify and
rectify any fault before intensification.
2. Weekly maintenance done in May includes;
 Cleaning of magnets in mill A
 Cleaning of air filters on blowers
 Cleaning of inspection glasses for rollers since these are mainly affected by
moisture for Mill B
 Cleaning dampening machine to remove rotten grain
 Blowing of low pressure fans inside mill B to avoid excessive vibrations that may
damage electric motor bearings
3. Other maintenance work done last month includes;
 Installing two new slide rollers on warehouse one gate
 Sealing of water leakages and cleaning gutters on all roof tops of production
facility
 Tightening of loose bolts on all equipments respectively on mill B chassis
 Emptying choked cyclones and aspiration channels
 Topping up blower oil
Operations high light on motor vehicle maintenance

Vehicle NO_ Illustration Operation


UBB 866W We installed three new air
bags

New air bag

We installed new V-arm

New V-arm

We also serviced its


compressor and installed new
piston rings

Compressor
serviced parts

One new dumper was


installed

dumper
UAE 896H Three MS-plates were added
on the leaf springs and one
new center bolt

MS- plates added


to the springs

We removed this container in


order to repair the chassis
which was cracked

One drag link, steering pump


were installed

Drag link
UAW 758D One oil seal, U-bolt and
dumper were installed

Dumper

U-bolt

UAW 821Y The vehicle needs new front


axle and repair of the chassis

UAM 813Y All the panel beating was


scania finished and what is left is
new spare parts for the gear
box
UAQ 475Q The vehicle needs new
hunger for the leaf springs
PERSONNEL

The maintenance team includes one motor vehicle & one maintenance mechanic, one welder,
two technical helpers and turn men for motor vehicles. The one technical helper also works in
production shift changeovers as well. The team work hand in hand to deliver precise results.
The team also works hand in hand with productions team to ensure proper mill maintenance