You are on page 1of 21

Reference Cases Automation

Only Project realized between


2019 and 2021
Reference Cases Light Automation
The below ELCA Light Automation Reference Cases have been realized between 2019 and 2021.
Further references, covering other parts of the ELCA portfolio can be provided upon request

EXPO Main Entrance


Design / Build / Programming / Commissioning of >5’000 DMX lights
Client: Scientechnic

EXPO Australian Pavilion


Design / Build / Test / Commissioning of the lighting Control & BMS system
Client: Australia Embassy

EXPO Luxembourg Pavilion


Design / Build / Test / Commissioning of the lighting Control & BMS system
Client: Luxembourg Embassy

UAE Mosques
Design / Build / Commissioning of a DALI-2 based lighting system in some smaller/mid-size Mosques
Client: Mosques in the UAE
Reference Cases Light Automation
Hudayriat Sports Complex
Design / Build / Commissioning of the DALI-2 based Lighting Control System
Client: Hilalco

ZUMA Restaurant
Design / Build / Test / Commissioning of the Light / Sound and BMS system (refurbish project)
Client: ZUMA Restaurants

Panasonic Training Center


Consult / Design / Build / Commissioning of the Light and Multimedia system
Client: Panasonic UAE
Reference Cases GRMS
Royal Atlantis
880 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: Royal Atlantis

Marsa Al Arab Hotel


486 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: Dubai Holding

Marriott Al Jaddaf
165 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: MFK Trading FZE

Fountain View Hotel


800 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: EMAAR

Ecos Hotel
304 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: HMH
Reference Cases GRMS
Richreit Hotel
299 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: Richreit Real Estate Development

Moevenpick Hotel
486 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: Moevenpick Hotels

Jewel of the Creek


950 room Hotel - Build / Test / Commissioning of Lighting Control and Hotel Automation
Client: Dubai International Real Estate

Taj Hotel & Residences


350 room Hotel - Build / Test / Commissioning of Lighting Control, Hotel Automation and BMS
Client: Taj Hotels

Hilton
564 room Hotel - Test / Commissioning of Lighting Control, Hotel Automation and BMS
Client: Hilton
Reference Cases Engineering Services
Taikun
Consult / Design / Build / Test / Commissioning of the Light and Sound system (refurbish project)
Client: Restaurant Secrets

La Serre
Consult / Design / Build / Test / Commissioning of the Light and Sound system (refurbish project)
Client: Restaurant Secrets

Dubai Opera / The Loft


Consult / Design / Build / Test / Commissioning of the Light and Sound system (refurbish project)
Client: Restaurant Secrets
Reference Cases Industrial Automation
Landmark O Mega DC (largest Warehouse in the Middle East)
Build / Test / Commissioning of the conveyor and electrical infrastructure
Client: Landmark Group / Dematic AG

Adidas Retail Logistics


Build / Commissioning of the Installation of high bay and mobile racking system
Client: Adidas ME / SSI Schäfer

Ocean Fair Warehouse


Build / Commissioning of the Installation of high bay and mobile racking system
Client: Ocean Fair International / SSI Schäfer

FEDEX DAFZA Warehouse


Modification of conveyor control system and panels
Client: FEDEX / ALS Logistics
Reference Cases Control & Protection
Saudi Aramco
Design / Build / Test / Commissioning of Utility & Cyber Security Infrastructure
Client: Saudi Aramco

DEWA SCMS
48 Substaions- Build / Test of the SCMS panels
Client: DEWA

Dubai IHC 132kV LCC Panels


Design / Build / Test of 132kV LCC Panels
Client: GE/DEWA

Dubai Land
Design / Build / Test of 400/132kV Control & Protection panels
Client: DEWA

Outlet City
Design / Build / Test of 132kV Control & Protection panels
Client: Danway/DEWA
Reference Cases Control & Protection
Hassyan Coal
Build / Test of 400/132kV Control & Protection panels
Client: DEWA

MBR Solar Phase B & C


Build / Test of 132kV Control & Protection panels
Client: DEWA

KNPC Substaions
Build / Test of 400/132kV Control & Protection panels
Client: KNPC

Kuwait University W
Build / Test of 400/132kV Control & Protection panels
Client: MEW

Wafra Substation
Build / Test of 400/132kV Control & Protection panels
Client: MEW
Reference Cases Control & Protection
Remote end Modification
Design / Build / Test of 132kV Control & Protection panels
Client: L&T/DEWA

Pakistan Telecom Infrastructure


Build / Test of 132kV Control & Protection panels
Client: LESCO

ASAB Substation
Build / Test of 220kV Control & Protection panels
Client: TRANSCO

BAB Substation
Build / Test of 132/33/11kV Control & Protection panels
Client: ADCO

Muweleah Substation
Build / Test of 132/33/11kV Control & Protection panels
Client: SEWA
Reference Cases Control & Protection
DEWA Station Modification
Build / Test of LCC & Interface panels
Client: Mitsubishi
This is us!

(c) 2019 ELCA Systems LLC August 2020 12


ELCA - a Story of Achievements
Leading Integrator for Hotel
Automation & Smart City

Change in Ownership & Capital Increase 2019


Doubled Revenue YoY 2020
Change Production to Industry 4.0 Standards Major Project Awards in
Industrial Automation
2017 2018 RTU / FMS / Sensor offerings and Energy Production
Certified for Photo Voltaic production
Launch of Shielding Solutions
2015
LCC panel production Management change to Al
ADEWA approval for C&P Mansoori Group
2011
2012
Certified for MV/HV ISO 9001 / 14001
panel production Certification
DEWA C&P Approval 2010
2009 IPH Certification

2008
Foundation as
(c) 2019 ELCA Systems LLC August 2020 13
What we do for you
Energy Consumption Optimization
Micro Grid Solutions

Sustainable Energy Production based on Wind


and Photo Voltaic

Hotel / Lighting / Building Mgmt / Industrial and


Utility Automation

Control & Protection / LCC


Utility Engineering (R/E, Modification)

Shielding Solutions
Vibration / Thermal / Harmonics / Acoustic

(c) 2019 ELCA Systems LLC August 2020 14


Your Turn-Key Solution Partner
Consulting & Project Management
Understand your ideas, processes & requirements and
get the solution delivered

Design & Engineering


Lifecycle Support Design your unique solution,
Ensure the value of the tightly integrated with your
solution over the entire processes & workflows
lifecycle

Training & Ramp-Up Build & Programming


Get your staff trained and Build, program and test the
ensure future staff training solution, in line with the design
(TTT)

Commissioning & Test Logistics & Installation


Bring the solution alive and test the Get your project delivered on time and with
functionality against the specification minimal disturbance of the hotel operation

(c) 2019 ELCA Systems LLC August 2020 15


Our Values – a Strong Foundation

At ELCA, we believe that business


don’t create value, but people do.
We’re committed to strong values,
which shall be reflected in
everything we do.

(c) 2019 ELCA Systems LLC August 2020 16


A selection of Clients

(c) 2019 ELCA Systems LLC August 2020 17


Quality @ ELCA

Staff Selection & Training

Continuous Internal & External QC

Industry 4.0 based Production

ISO 9001 / ISO 14001 certified

Quality Audited Supply Chain

(c) 2019 ELCA Systems LLC August 2020 18


Geographic markets

Our home market are the


Arab Emirates (UAE).

ELCA Systems has realized


projects across the Middle
East and has the expertise
to adopt to new markets

(c) 2019 ELCA Systems LLC August 2020 19


ELCA Sustainability Model
ELCA Management and Staff are committed to
Sustainability Standards & Behavior, based on the
QuEST Sustainability Model

We aim to achieve a balance between


Community, Economics and Environment
(c) 2019 ELCA Systems LLC August 2020 20
At Your Service!

(c) 2019 ELCA Systems LLC August 2020 21

You might also like