Daily Report

Daily Monitoring
DEPTH CORE LITHOLOGI
DATE RIG ID HOLE ID DEPTH RECOVERY (%) EOH (M) REMARKS
FROM TO LENGTH From To Lithologi
RIG-01 BA3_10_03 25 28 3 3 100% 25 28 S.ROCK FINISH 28 M
Finish Waste Saprolite
0,00 1,00 LIMO
BA3_09_04 0 12 12 12 100% 1,00 9,00 SAP Finish 12 M
13/09/2021

9,00 12,00 BRK


RIG-02 Moving
RIG-03 Moving
0,00 1,00 SOIL
RIG-04 BA3_07_02 0 5 5 5 100%
1,00 5,00 LIMO
15,00 18,00 TRMT
RIG-05 BA3_12_06 15,00 21,00 6,00 5,90 99% Finish 21 M
18,00 21,00 BRK
TOTAL 26,00 25,90 99,8%

DRILLING PROGRESS
Depth/Day (M) 21,00
Avg/Day (M) 4,2
Total Kumulatif Depth (M) 1014
Kumulatif Avg Depth/Day (M) 6,34
Total Depth Finish Hole (M) 1012
Total Finish Hole (M) 55
Cancel Hole 8
Plan Hole 124

GMS-05/BA3_12_06/15-21m GMS-04/BA3_07_02/0-5m GMS-01/BA3_09_03/25-28m GMS-01/BA3_10_03/0-5m

GMS-01/BA3_10_03/5-10m GMS-01/BA3_10_03/10-12m