How to Reassemble

Step 1 Install 2 conductors


on the lower side of IGBT.

M8X16 (2 points) M6X16 (6 points)

Step 2 Install 2 conductors on the upper side of IGBT.

M8X16 (2 points)

Step3 Install 18 snubber capacitors.

M6X16
(36 points)

Magnified
Picture
Step 4 Connect gate wires of U phase and install conductors (U).
* Warning Gate wires sequence
G1(R)blue
M8X16(2本) E1(W)blue
G2(R)
E2(W)
Wear antistatic wristbands
for grounding to loosen wires.

*Back of insulation sheet

M6X16 (2 points)

Upset M6X16 (2 points)

Step 5 Connect gate wirings of V phase and install conductors (V). (Refer warning at Step 4).
M8X16 (2 points)

M6X16 (2 points)

Upset M6X16 (2 points)


Step 6 Connect gate wires of V phase and install conductors (V). (Refer warning at Step 4).

M8X16 (2 points)

M6X16 (2 points)
Upset M6X16 (2 points)

Step 7 Install beams. Step 8 Install charging resistors.

Install crimp terminals on both ends of resistor.


Insert spindle screws and install them with M5 nuts.
*Be cautious not to break resistors

M5 nut.
springs

M5X12
(4 points)
M6X14
(2 points)
Step 9 Install conductor on the lower side of capacitor. M8X16

Step 10 Install conductor.

M8X20 (6 points)

Step 11 Install conductor under fuse.

M8X20 (2 points)
Step 12 Install conductor on the middle of capacitor.

M5X14 (14 points),


snubber resistors (7 points)

Magnified
Picture

Step 13 Install conductor.

Magnified

Picture

M8X16 (2 points)
M8X20 (3 points)

Step 14 Install insulation supports.

M5X12 (2 points)

Magnified
Picture
Step 15 Install conductor on the
M4X16 upper side of capacitor. Magnified
Picture

M5X14 (26 points)


Step 16 Install capacitor cover.

M8X16 (4 points)

Step 17 Install fuse block. M5X12 (4 points)


Step 18
Install conductor (W phase).
M8X16 (2 points)
M10X25 (2 points) M8X20 (2 points)

M12X45 (8 points)
Step 19 Install conductor (V phase). Step 20 Install conductor (U phase).

M8X20 (2 points) M10X25 (2 points)

M10X25 (2 points)

Step 21 Install terminal block.

M8X16 M12X35 (3 points)

M5X16 (3 points)
M5X10 (4 points)
Step 22 Install fuse cover. Step 23 Install bolts of conductors
M5X10 (5 points) (P+),(P-).
M8X20 (3 points) M8X16 M8X25 (3 points)

Step 24 Install screws of insulation sheet. Install terminal block (R).


M5X12 (3 points) M4X8 (3 points) Step 25 (2 conductors)

M10X25
(2 points)
M8X16
(2 points)
M5X16
(3 poitns)

Install terminal block (S).


Install conductor (R). Step 27 (2 conductors)
Step 26
M10X25 (2 points) M10X25
M8X16 (2 points) (2 points)
M5X16 M8X16
M12X35 (2 points)
M5X16
(3 points)
Step 28 Install conductor (S). Step 29 Install terminal block (T).
(2 conductors)
M10X25 (2 points) M10X25
M8X16 (2 points) M10X25 (2 points)
M12X35 M8X16 (2 points)
M5X16
(3 points)

Install conductor (T). Step 31 Install conductor.


Step 30

M12X30

M8X16

M10X25 (3 points)

M8X16 (3 points)
M12X35

Step 32 Install terminal block (P1). Step 33 Install conductor (P1).

M12X30
M5X16
M5X16 M12X25
(3 points) M12X35
Step 34 Install input module PCB. Step 35 Install shield of the lower side.

M3X8 Insert terminal. Insert connector.(CN30) M5X10 (6 points)

M5X8 M5X16 (2 points)


M8X16

Step 36 Install shield of the upper side. Step 37 Insert connectors of


M5X10 (7 points) gate, power supply PCB.

Magnified gate PCB Power supply PCB Gate PCB

Connectors for installing gate PCB


Each U.V.W. phase: CN41.CN45.CN46.CN51~CN56
Connectors for installing power supply PCB
CN33.CN34.CN35.CN11.CN13.CN14.CN101
Magnified power supply PCB CN102.CN103.CN16.CN17.CN19.CN23.CN21

Install control PCB and


Step 38 insert connectors(CN8,CN9,CN18).

EP3955 (Control PCB for P/G11) EP4083 (Control PCB for VG7)

M3X8 (1 point) Connector

Step 39 Tie harnesses with cable ties.


Cable ties (4 points)
*(anp bases)

Truss screws M5X10 (5 points)


Step 40 Install key pad case. Step 41 Install key pad panel.

M3X8 M4X8

Step 42 Install front cover.

Truss screws M5X10 (24 points)