19 25 28 33
6
Cabinet Pre Assembly Cabinet After Foaming
Foaming
13
Door Foaming
Door Line
47 34 41
Genral Assembly Line
52 64
Gas Charging Safety Testing Room Packing Line
Test
73 90 78
Problem Detail
Note:- Only Quality Manager and Factory Manager are othorized for Exceptional Release.
In Process Quality Check Points Ref-Production Haier
LEGEND : OK PROBLEM
2 Evaporator Pressing Pressing Time 16 sec/Flat Timer 50 Compressor Fitting Right at defined holes Visual
Proper sponge/No
3 Mid Beam Fitting Quality Gap/No dent/No Visual 51 Condenser Placing Alligned Visual
scratch
Back Line
No Punch/Proper
sweding/not complet
Proper Tight/Not
4 Booster Line Fitting Quality panted/proper flow Visual 52 Condenser Fitting Visual
damaged/Paint OK
of Nitrogen/proper
end rubber fitting
Joints smooth/No
7 Glue Filling Properly filled Visual 55 Welding Joining Visual
Blockage or leakage
Quality Checks
liner fold.
15 Front Body Gap panel not more than Filler Guage 63 Welding Jointing Visual
Blockage or leakag
1mm.
no scratch or dent
dent,scratch,no Pipes Straight/Not
16 Side Body on any side,no Visual 64 Welding Piping standards Visual
pressing Touch
pressing.
Wires
Insulation Safety Test
18 Back Body Pipes & Wires Damaged/Pipes Visual 66 Insulation Resistance 100 MΏ/500 VDC
Resistance Equipment
punched
Safety
Safety Test
19 Back Body dent,scratch D/S/No Pressing. Visual 67 Electric Streangth Electric Streangth 1650 V/Sec
Equipment
Equipment
1mm.
Wires
24 Back Body Pipes & Wires Damaged/Pipes no Visual 72
punched
Properly
27 Foaming Cleaning Foam Cleaning Cleaned,Pipes Visual/By hand 75
punched.
No
28 Stock entry Outer Body D/S/Pipes/Wires/Fo Visual/By Hand 76 Warranty Card Printing & Writing As per Model Visual
am cleaned
Final Packing
Liner
29 Stock entry Inner Body Fold/Yellow/Wires Visual/By Hand 77 Caution Sticker Allignment Straight/Alligned Visual
no Damaged
Base Items(Base
30 fitting,allignment, no lose/alligned Visual/By hand 78 Carton Fitting Standard Straight/Alligned Visual
Plate,feets,hinge)
Quality Checks
Properly/Cleaned,Pi
31 Foaming Cleaning Foam Cleaning Visual/By hand 79 Carton Fitting Standard Straight/Alligned Visual
pes punched.
Condenser &
32 Stock entry Outer Body NoD/S/Pipes/Wires/ Visual/By hand 80 Back Side Tight/Alligned Visual
Compres. Fitting
Foam cleaned
No Liner
33 Stock entry Inner Body Fold/Yellow/Wire Visual/By hand 81 Back Side Piping standards Straight/Alligned Visual
Damaged
cleaned/No dust/No
34 Cleaning Over all cleaning Visual/By hand 82 Back Side Safety Test Cleared Visual
black
Final Product Quality Inspection
35 Thermostat Fitting Not lose/Alligned Visual/By hand 83 Front Body Doors No dent/No Scratch Visual
Connections as per
36 Thermostat Connections Wiring Dia Gram 84 Front Body Doors Alligned Visual
wiring dia gram.
Straight/Tight/No
37 Hinges Fitting Visual/By hand 85 Inner Body Liners No Air/No Punch Visual
Front Line
Paint Problems
38 Doors Fitting No missallignment Visual/By hand 86 Inner Body Cleaning Cleared Visual
As per Packing
42 Thermostat Fitting Not lose/Alligned Visual/By hand 90 Final Confirmation Whole Unit Visual
Standard
Connections must
43 Thermostat Connections be as per wiring dia Wiring Dia Gram 91
Quality Checks
gram.
Straight/Tight/No
44 Hinges Fitting
Paint Problems
Visual/By hand 92 Model:-
Alligned by
45 Doors Fitting Side/Alligned from Visual/By hand 93 Color:-
Front
No Dent/No
46 Doors Condition Scratch/No Short Visual 94 Serial #:-
Foamed
48 96
Note : After Inspection ( ) in `MARK`column of each inspection item and remove the defect,if it is not posible to remove on the process mention it on the Body And
write in problem item table.
HNR (Pvt) Ltd.
Doc No:
Effective Date:
GA Daily Process Audit
NO CHECK ITEM CONTROL ITEM STANDARD VALUE CHECK METHOD Station Mark Associate Name
Thermostat Connections Connections as per wiring dia gram. Wiring Dia Gram
Front Line
Doors Fitting No missallignment Visual/By hand
Back Line
Condenser Placing Alligned Visual
Charging Machine Refrigerant Quantity As per standard for each model Visual
Insulation Resistance Insulation Resistance 100 MΏ/500 VDC Safety Test Equipment
Safety
Refrigerant Leakage Leak Checking less than or equal to 0.1 g/anum Electronic Leak Detector
Checked By
HNR (Pvt) Ltd.
Doc No:
Effective Date:
GA Daily Process Audit
NO CHECK ITEM CONTROL ITEM STANDARD VALUE CHECK METHOD Station Mark Associate Name
Front Line
Hinges Fitting Straight/Tight/No Paint Problems Visual/By hand
Back Line
Condenser Placing Alligned Visual
Charging Machine Refrigerant Quantity As per standard for each model Visual
Insulation Resistance Insulation Resistance 100 MΏ/500 VDC Safety Test Equipment
Safety
Refrigerant Leakage Leak Checking less than or equal to 0.1 g/anum Electronic Leak Detector Leakage Check