Title block is according to standards
¡
Title block font size and type according to standards ¡
Project information (project name, client name, client address, client logo) are correct ¡
with standard font size and type
Drawing specific information (drawing title, engineers names, date) are correct with ¡
standard font size and type
Content: MM/TL
Mechanical systems
System title drawing is provided
¡
System list of drawings, legend and symbol and notes drawing is provided ¡
All essential information such as ducts sizes, pipe sizes, equipment name are indicated ¡
on the drawings
Ducts and pipe sizes are checked, correct and match calculation notes ¡
Equipment, ducts, and pipes Horizontal and Vertical clearances are adequate and ¡
accommodate constructability
System list of drawings, legend and symbol and notes drawing is provided ¡
All essential information such as cable sizes, loop name and number, equipment name ¡
are indicated on the drawings
Warring: Transformer 2000kVA, the investor requires an additional 65% of the load on the first floor, so it is not
allowed to expand the load in the future so transformer has overload capacity