Professional Documents
Culture Documents
ANS-DRL-012
Signature: Signature:
Signature:
Department: Drilling
http://gbrbms.apachecorp.com/
Well Integrity Manual ANS-DRL-012
Contents
Revision History
Distribution List
Preface
List of Abbreviations
Section 1 Introduction
Section 2 Well Lifecycle
Uncontrolled when Printed
Revision History
Distribution List
Copy Copyholder
Preface
Purpose
This manual has been designed in modular-format and each section may be amended
without significantly affecting the other sections. This Revision History should be updated
accordingly whenever any section is amended.
The content of this document will be reviewed for accuracy at 12-monthly intervals as decided
by the Technical Authority.
However, the document control system allows for continuous update of this document. As such,
any user may at any time identify an error or suggest an improvement using an Amendment
Proposal form, which is available electronically on the Apache North Sea BMS website,
or from the HSE Technical Assistant or Data Control Centre (DCC) Supervisor at ODL.
All holders of this document are registered so that they can be sent updates and be kept
informed of changes or reviews.
Responsibility of Copyholders
It is the responsibility of the registered copyholder of controlled hard copy versions to maintain
the accuracy of the document by ensuring that all updates are promptly incorporated and
acknowledged.
Furthermore, the registered copyholder of controlled hard copy versions must at all times
maintain custody of this document unless prior approval is given by the relevant Technical
Authority.
The roles and responsibilities of copyholders and ‘virtual’ copyholders are detailed in Section 1
of the Document Control Procedure (ANS-DCM-001).
List of Abbreviations
Section 1
Introduction
Paragraph Page
1 Introduction 1-1
Table
1.1 UK Well-related Legislation 1-2
1.2 UK Regulation References 1-5
1.3 Industry References 1-6
1.4 Asset-specific Terminology 1-7
Introduction
August 2015 Issue 1 1-i/ii
Well Integrity Manual ANS-DRL-012
1 Introduction
As a prudent Operator and to ensure that its Licence to Operate (LTO) is not compromised,
Apache North Sea Ltd (Apache) must ensure that the requirements of any country-specific
regulations are met. Section 1 has been included to provide all personnel involved in well
operations with outline knowledge of the various regulations in force. It is not intended to be
a full training course but merely to provide an overview of well-related legislation and how
compliance should be met.
Note: Legislation is always subject to change, therefore, users of this section
are encouraged to consult the various websites and current revisions of the
reference documents quoted within this Section 1.
The purpose of this document is to detail the management of well integrity for all of UK
Apache North Sea Ltd’s well-stock and in accordance with the applicable regulation which
requires a ‘lifecycle’ approach, is pertinent to the design, construction, operation
and maintenance of Apache wells in the United Kingdom.
This document is aimed primarily at field personnel involved in the ‘Operational Phase’ of
a well and focuses on the ‘what’ and ‘why’ in relation to well integrity. The ‘how
to’ work instruction documents reside at a lower level in the procedural hierarchy.
Introduction
August 2015 Issue 1 1-1
ANS-DRL-012 Well Integrity Manual
The following documents are undergoing phase-out or revision within Apache but may
still be current at the time of issue of this manual:
• Heritage EM Drilling and Production Procedures Manual (DAPPs)
• Apache Well Integrity Policy and Procedures (FX-0344)
Manual users should, therefore, check to ensure that the documents outlined above are
still in use before referencing.
4 Regulatory Requirements
All UK safety legislation is underpinned by the Health and Safety at Work Act (HASAW)
and all industries in the UK have to comply with its requirements.
In respect of the oil and gas industry, specific legislation is derived from the Piper Alpha
Uncontrolled when Printed
Disaster of 1988 and the subsequent Cullen Enquiry which defined the requirement
for all installations operating on the United Kingdom Continental Shelf (UKCS) to produce
a safety case.
Dove-tailing with the contents of a safety case are several key regulations which must be
complied with and which put the onus on Operators to identify and to manage Major
Accident Hazards (MAHs). Such regulations, some of which are not directly related
to well integrity, are defined in Table 1.1 – how compliance is met is detailed
in individual installation safety cases.
Introduction
1-2 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Introduction
August 2015 Issue 1 1-3
ANS-DRL-012 Well Integrity Manual
Introduction
1-4 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Introduction
August 2015 Issue 1 1-5
ANS-DRL-012 Well Integrity Manual
5 Industry References
Uncontrolled when Printed
Introduction
1-6 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
6 Notes on Terminology
Following the transfer of ExxonMobil Assets to Apache, there has been a mismatch
of terminology which requires to be clarified in order to avoid subsequent incidents
due to confusion. Table 1.4 is intended to fulfil this purpose for the key items in question.
In time it is expected that such terminology will become fully harmonised.
Arm Valve
NASA Non-active Side KWV Kill Wing Valve
Arm
WSO Well Services WSA Well Security
Operator Advisor
TRSCSSV Tubing Retrievable DHSV Downhole
or SCSSV Surface Controlled Safety Valve
Sub-surface Safety
Valve
Introduction
August 2015 Issue 1 1-7/8
Well Integrity Manual ANS-DRL-012
Section 2
Well Lifecycle
Paragraph Page
1 Introduction 2-1
Table
2.1 Well Lifecycle Phases 2-1
2.2 Industry References 2-7
Figure
2.1 Well Operating Compilation/Change Flowchart 2-4
2.2 Typical Well Operating Envelope 2-6
Well Lifecycle
August 2015 Issue 1 2-i/ii
Well Integrity Manual ANS-DRL-012
1 Introduction
UK Legislation – specifically Design and Construction Regulations (DCRs) – requires a
‘Lifecycle Approach’ to the design, construction, operation, maintenance and
abandonment of any well. The UK Goal Setting Regime applies the principles of lifecycle
risk management to all aspects of offshore operation, covering installations, pipelines and
wells. The legislation that specifically applies to well management activities is the DCR,
with its main goal to provide a general framework for ensuring the safe condition of a well
at all stages of its life, including a Scheme of Examination by an independent and
competent person.
The prime purpose of Section 2, therefore, is to map out all activities for ensuring
compliance with legislative and Company standards and to provide an auditable process
to track such compliance.
Uncontrolled when Printed
Well Lifecycle
August 2015 Issue 1 2-1
ANS-DRL-012 Well Integrity Manual
• The well Operator shall ensure that suitable well control and blowout protection
is available, before operations begin
• The well Operator must demonstrate that a well is properly designed and constructed
and adequately maintained
• The information which should be supplied to the Health and Safety Executive (or other
regulatory authorities) with regard to well operations and the frequency of reporting
• The requirement of all personnel involved to co-operate with the well Operator
• The requirements for personnel involved in well operations to be communicated,
trained and supervised
Key principles in respect of the well lifecycle approach are to provide:
• Consistent work practices and review processes for all well-related activities
Uncontrolled when Printed
Well Lifecycle
2-2 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
As a point of note, where a well has been subject to a change of use for any reason
or there is a significant change in operating conditions – eg a sharp increase in H2S
levels or a change in the injected fluids on a Produced Water Re-injection (PWRI) well
etc, then the Drilling Group must be consulted and the WOE reviewed and re-issued
wherever applicable.
WOEs should be reviewed regularly on a frequency determined by the Drilling Manager.
WOE templates are available from the Drilling Group Technical Assistant(s).
Note: As of the issue date of this manual, the generation of Well Operating Envelopes
for Forties Field Wells is currently in progress.
Well Lifecycle
August 2015 Issue 1 2-3
ANS-DRL-012 Well Integrity Manual
Drilling/Completions/Well Operations
Engineer completes Technical Work.
No
Well Lifecycle
2-4 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
WOEs can only be changed by the Drilling Group under the formal Management
of Change (MOC) process.
Well Lifecycle
August 2015 Issue 1 2-5
ANS-DRL-012 Well Integrity Manual
Uncontrolled when Printed
Well Lifecycle
2-6 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
More detailed information on well handover is provided in the Well Handover Procedure
(ANS-SOP-059), located in the Apache Business Management System (BMS) or any
superseding procedure. Template well handover documentation is available on the
‘N’ drive or from the Drilling Technical Assistant(s).
Well Lifecycle
August 2015 Issue 1 2-7/8
Well Integrity Manual ANS-DRL-012
Section 3
Well Integrity Management System
Section 3 Chapter 1
Well Integrity Management System
Paragraph Page
1 Overview 3-1-1
Section 3 Chapter 1
Well Integrity Management System (cont’d)
Table Page
3.1.1 Responsibilities for Well Integrity 3-1-2
3.1.2 Responsibility Coding 3-1-4
3.1.3 Basic Competence Matrix per Position 3-1-5
3.1.4 Industry References 3-1-9
Uncontrolled when Printed
1 Overview
Section 3 focuses on how the system should be managed in respect of:
• Overall policies and philosophies
• Roles and responsibilities
• Guidance on the competencies and training of personnel involved with well integrity
• The SafeWells Well Integrity Management System
• Reporting requirements in respect of well integrity issues
• Well integrity KPIs
• Risk management
• Identification of safety-critical equipment
Uncontrolled when Printed
• Management of Change
• Legislative compliance – well examination
Well
Drilling
Drilling Well Drilling Intervention
Prod Manager Completions Platform
Role/Task OIM OSP Eng Integrity HSE Supt
Manager (Tech Supt Eng
Supt Eng Eng (Refer to
Authority)
Note 3)
Well
Drilling
Drilling Well Drilling Intervention
Prod Manager Completions
Role/Task OIM OSP Eng Integrity HSE Supt Platform Eng
Manager (Tech Supt
Supt Eng Eng (Refer to
Authority)
Note 3)
4 Training Requirements
This manual is not intended to be a training guide for well integrity but instead describes
some of the training necessary for personnel involved in well integrity activities. Obviously,
there are varying degrees of knowledge throughout the Company; for example a Drilling
Engineer may have much more knowledge of well design than a Production Operator
and conversely a Production Operator will have much more knowledge of operating a well
than a Drilling Engineer. Training and competence, therefore, has to be focused on the
position the training candidate is fulfilling.
Paragraph 1 provides an example of subjects to be covered as part of a well integrity
course.
Well
Prod Well
Activity Services Comments
Operator Engineer
Supv
Monitor and report Skill Skill Knowledge
on well pressures
Operate xmas tree Skill Skill Knowledge
and wellhead calves
Operate and test Skill Skill Knowledge
DHSVs/ASVs
Well handover Skill Skill Knowledge
Well integrity maintenance Knowledge Skill Knowledge
and repairs
Uncontrolled when Printed
5 SafeWells System
As of May 2013, the Expro NS Ltd proprietary Well Integrity Management System –
SafeWells – is being introduced to Apache. This system is purpose-built to capture all
well integrity data across all Apache Assets. Personnel involved with well integrity issues
are to be trained in inputting data on their respective Installations.
Full population and use of the system will take some time to complete. The Well Integrity
Engineer should be consulted for details of the system and to arrange for the necessary
training where required.
Management, will define the necessary KPIs for the system for managing the overall well
risk. Such KPIs can include, but are not limited to:
• Percentage of wells with approved Operational Risk Assessments (ORAs) in place,
to continue operations
• Number of overdue integrity tests on safety-critical equipment covered by formal
deferral
• Number of overdue integrity tests on safety-critical equipment not covered by formal
deferral
• Percentage of failed integrity tests on safety-critical equipment
• Number of wells awaiting integrity work
• Number of maintenance deferrals on safety-critical equipment
• Number of incidents due to well integrity
• Number and percentage of green/yellow/orange/red SafeWells level of concern wells
In due course, it is expected that such KPIs will be generated and monitored from within
the SafeWells System – refer to Paragraph 5. The Well Integrity Engineer will collate and
issue all well integrity reports.
8 Safety-critical Equipment
The definition of safety-critical equipment can be defined simply as ‘can cause
or contribute to a Major Accident Hazard (MAH)’. Further guidance on this subject can be
found in Paragraph 13 Industry References.
Safety-critical equipment can, for example, be a gas compressor, with a number
of Safety-critical Elements (SCEs) to be identified and satisfied – eg hydrocarbon
containment, overpressure protection etc.
Clearly, there is significant potential for MAH with certain incidents involving a well.
The majority of well equipment is, therefore, safety-critical and thus subject to the
generation of Performance Standards (PSs) and overall condition management via the
Well Integrity Management System. PSs for Wells are held within the Apache intranet
system; consult with the Well Integrity Engineer for more details.
9 Well Reliability
The system should be monitored for any developing trends in respect of equipment
reliability – for example, several consecutive failures of a particular type of DHSV.
The Well Integrity Engineer shall monitor the system for such trends and report any
issues identified to the Drilling Manager.
Uncontrolled when Printed
12 Management of Change
Significant changes to the Well Integrity Management System should be subject
to the MOC requirements defined in the Apache Drilling and Well Operations Policy
(ANS-DRL-002).
13 Industry References
The following industry references are relevant to this section.
Section 3 Chapter 2
Well Integrity Training and Competence
Paragraph Page
1 Background 3-2-1
1 Background
This document forms the basis for discussion and development of a competency system
covering well integrity. Key points to consider are:
• Require a listing of the main objectives for a well integrity course
• What should be covered in the well integrity training
• The need to include any exercises
• Timing and schedule
• Who to participate and mixture of skills in one group
• Handouts and/or documentation
• Computer based vs classroom-based – or other methods
Uncontrolled when Printed
2 Training Guidelines
(9) Documentation – discuss need for keeping good well integrity records. Discuss and
describe need for Waiver System for operating wells outwith the standard. Provide
a sample.
(10) SafeWells Training – dependent on audience, discuss the main features of SafeWells.
Provide more detailed training for personnel entering data on a routine basis.
Uncontrolled when Printed
Section 3 Chapter 3
Evaluation of Well Integrity Failures/Issues
Paragraph Page
Table
3.3.1 Specific Responsibilities for the Evaluation of
Well Integrity Issues 3-3-3
3.3.2 Well Barrier Hierarchy 3-3-4
3.3.3 Reference Tables Evaluation of Risk 3-3-5
3.3.4 Tubing-specific Scenarios (X = Failure) 3-3-7
3.3.5 Annulus-specific Scenarios (X=Failure) 3-3-7
3.3.6 Most Common Annulus-specific Scenarios specific to
Forties DGL Wells (X=Failure) 3-3-8
3.3.7 Spool (Horizontal) Xmas Tree-specific Scenarios (X=Failure) 3-3-9
3.3.8 Status Summary and Required Actions following Failures 3-3-10
3.3.9 General Scenarios/Conditions – Probability Score 3-3-13
Section 3 Chapter 3
Evaluation of Well Integrity Failures/Issues
(cont’d)
Table Page
3.3.10 Consequence Scoring Table 3-3-19
3.3.11 Consequence Mitigation Scoring Table 3-3-20
Figure
Uncontrolled when Printed
failures.
Readers should be aware that well integrity must be monitored for policy compliance
on a continuous basis. Where compliance cannot be met then the applicable and appropriate
measures to assess the risk of continued operation of a well must be applied. The simple
model depicted below defines the basic process to be applied for all Apache well integrity
issues and more detail is provided within this section.
2 Specific Responsibilities
It is Apache policy to assign the responsibilities as defined below, for all integrity critical
operations. This is a requirement that is in line with the appropriate safety case
submission and is also a requirement of the applicable Apache safety management
systems.
Table 3.3.1 provides the necessary guidance on ‘who does what’ in respect of well
integrity evaluations.
TA (Drilling Manager)
Well Operations
Well Integrity
Team Leader
Drilling HSE
(if onboard)
Discipline
Engineer
Engineer
Engineer
Task
ORA
Supt
OSP
OIM
Task
No
Table 3.3.1 Specific Responsibilities for the Evaluation of Well Integrity Issues
Device Criticality
Function Comments
(Element) Level
TUBING BARRIERS
Tubing Kill Provides access for well kill and Low Normally-closed Manual
Valve/NASA venting to process etc. Valve.
Swab Valve Provides access for well intervention Low Normally-closed Manual
work. Valve.
ANNULUS BARRIERS
Hydraulically Provides Emergency Shutdown High
-Actuated (ESD) well shut-off in the event of
Annulus a major release at surface and also
Valves isolates a well from the gas lift/
process system.
Annular Provides annulus inventory High ASV set between 500 and
Safety protection in the event of surface 1000ft.
Valves release of gas-lift gas. Also provides
(all types) a well barrier in the event of Tubing
to Annulus Communication.
Device Criticality
Function Comments
(Element) Level
ANNULUS BARRIERS
score.
Paragraph 4 – Discusses those general well
Other Well integrity conditions, scenarios
Situations/ and factors which cannot
Scenarios be easily accommodated into
a fixed methodology of
evaluation or assessment.
Paragraph 5 – Discusses those factors which
General although not directly associated
Considerations with a well, can contribute to the
risk if not adequately managed.
Paragraph 5 – Provides general guidance
Guidance on on applying a consequence
Consequence score to well integrity issues.
Scoring
Paragraph 5 – Table 3.3.11 – defines
Consequence consequence scores
for different well types.
Table 3.3.12 – discusses and
provides general guidance on
how mitigation can be applied
and scored.
Paragraph 6 – Provides guidance on the Recommended timescale
Timescale for Well timescales for repairing well for repairs to be completed
Integrity Repairs integrity failures. should be included in any
risk assessment.
Unmitigated
UMV Wing Required and Mandatory
LMV SWAB DHSV
(HMV) (PWV) Actions Probability
Score
X X X Refer to Note 1 6
X X X Refer to Note 2 6
X X Refer to Note 3 5
X Refer to Note 4 3
X X Refer to Note 5 3
X X Refer to Note 5 3
X X Refer to Note 6 3
Uncontrolled when Printed
X Refer to Note 4 2
X Refer to Note 4 2
X Refer to Note 6 1
X Refer to Note 6 1
TAC TAC
Unmitigated
(Hole) in (Hole) in Lower to
Surface and
Gas Lift Gas Lift Upper Required
G-DHSV Casing Mandatory
Tubing Tubing Annulus Actions
Valve Probability
above below Comms
Score
G-DHSV G-DHSV
X X X X Refer to 6
Note 15
X X X Refer to 6
Note 12
X X Refer to 6
Note 15
Uncontrolled when Printed
X X Refer to 4
Note 12
X X Refer to 3
Note 13
X Refer to 2
Note 14
X Refer to 2
Note 16
X Refer to 2
Note 13
Upper
Lower TH to TH to Unmitigated
Tubing Tubing
Tubing NASA/ Xmas Xmas and
Hanger Wing Bonnet Required
DHSV Hanger Manual Tree Tree Mandatory
(TH) Valve Seals Actions
Plug Master Upper Lower Probability
Plug (any)
Leak* Seals Seals Score
Leak
X X X X Note 17. 6
X X X Note 18. 6
X X Note 19 6
X X X Note 20 6
X X Note 21 6
X X Note 18 6
Uncontrolled when Printed
X X X Note 18 6
X X X Note 20 6
X X Note 20 6
X X Note 23 6
X X Note 23 6
X Note 22 6
X X Note 25 6
X Note 23 5
X Note 24 5
X Note 26 3
X Note 26 3
X Note 27 3
Note: Some spool xmas trees have a swab valve installed on the top flange rather than
a second tubing hanger plug within the tubing hanger bore. For evaluation
purposes, this design should be treated as per the second tubing hanger plug
scenario.
manually-operated LMV.
Note 4 Single xmas tree ESD failure. Two Continue to operate well. Schedule
other ESDs available – well not out repairs at earliest opportunity.
of barrier compliance.
For DHSV failures, risk assess
For DHSV failures, downhole on a case-by-case ‘consequence’ basis
protection has been lost. and continue to operate well under ORA
unless risk value ‘RED’.
Note 5 Single ESD failure. Xmas tree Continue to operate well. Schedule
redundancy reduced via manually- repairs at earliest opportunity.
operated LMV.
Note 6 Reduced redundancy in manually- Continue to operate well. Schedule
operated xmas tree valves. repairs at earliest opportunity. Be
cognisant of reduced isolation for well
intervention rig-up.
Note 7 Single surface ESD situation (casing Shut-in well. Risk assess for continued
valve). operation. Execute repairs to remedy
TAC ASAP.
Note 8 Single well barrier situation (tubing Shut-in well. Commence planning
integrity). No ESD functionality should to execute repairs to restore ESD
TAC develop. functionality immediately.
Note 9 Single ESD situation (ASV). Shut-in well. Risk assess for continued
operation. Execute repairs ASAP.
If no TAC, two well barriers exist.
Note 10 TAC failure only, which can be Continue to operate well. Schedule
contained with existing two well repairs at earliest opportunity.
barriers (ASV and surface casing
valve).
surface protection.
Note: Some DGL wells may have an
injection valve installed. Risk
assessment should factor-in
this scenario.
Note 14 Single surface valve situation (casing Shut-in well. Risk assess for continued
valve). operation. Execute repairs to remedy
TAC ASAP or provide other mitigation.
Note 15 Well annulus protection has been Shut-in well. Risk assess. Schedule
compromised. repairs to restore integrity ASAP.
Note 16 Manual valve functionality impaired Risk assess. Continue to operate well.
but no communication from lower Schedule repairs to restore valve
annulus. functionality at earliest opportunity
Note 17 No means of flow shut-off in the event Shut-in well wherever practical.
Spool XTs of a leak at top flange and no safe Ascertain significance of leak via tubing
only means of well intervention unless hanger plugs. Consider best practical
henceforth adequate isolations can be achieved. repair to gain adequate barrier(s). Well
must not be put online until approved
ORA in place,
Note 18 DHSV is only practical ESD barrier Shut-in well. Assess overall well
(single barrier situation). Potential for condition. Execute repairs to restore
loss of containment. well integrity compliance at earliest
opportunity. Well must not be put back
on line unless approved ORA in place.
Note 19 DHSV is only practical ESD barrier Shut-in well. Assess overall well
(single barrier situation). condition. Execute repairs to restore
well integrity compliance at earliest
opportunity. Well must not be put back
on line unless approved ORA in place.
Table 3.3.8 Status Summary and Required Actions following Failures (cont’d)
Table 3.3.8 Status Summary and Required Actions following Failures (cont’d)
Unmitigated and
Well Condition Comments Mandatory
Probability Score
Any single barrier Overall risk value will be driven 6
to atmosphere situation by the ‘consequence’ score –
Uncontrolled when Printed
capability etc. Risk assessments on such wells, should therefore address all aspects
of the wells integrity
• Lower annulus integrity issues (Forties field dual gas-lift wells)
In normal operation, wells with a dual-packer design and with no well integrity issues
would normally operate with the upper annulus filled with inhibited fluid. The lower
annulus would operate with high pressure gas-lift gas present during production.
No pressure change in the upper annulus should occur when the well is on production,
other than that from thermal effects when the well is brought online. Pressure monitoring
should, therefore, identify any leakage from the lower to the upper annulus.
Historically, some Deep Gas Lift (DGL) Wells in the Forties Field have gas-lift tubing
and/or shallow packer failures which have resulted in the upper annulus being filled with
gas-lift gas from the lower annulus at ca 80 to 110barg. Three failure modes have been
identified, namely:
(1) Leaking dual packer.
(2) Hole in the 2 3/8in gas lift tubing string.
(3) Complete failure of the dual packer.
Following assessment, those wells with known gas-lift tubing and/dual packer failures
have had instrument pipework removed from the surface annulus valve and replaced with
a double block and bleed arrangement to reduce the most credible leak paths which can
cause a large volume gas release from the gas-filled upper annulus. It also reduces the
escalation potential from adjacent wells with similar annulus integrity issues by removing the
instrument pipework at risk from a jet flame, should a release occur within the same
eggbox.
When upper to lower annulus failures occur on Forties Field DGL wells, the well
should be shut-in pending formal risk assessment to determine the way-forward
and an Operational Risk Assessment (ORA) issued to continue operation of the well.
In assessing such risks, the Wells Team Safety Engineer and the Drilling Engineering
Supt must always be involved in risk assessments involving DGL lower annulus failures
to ensure the risk remains within the tolerable area and to advise of any necessary
material change to the applicable safety case.
of which have allowable leak rates. Over a period of time, the pressure above
the valve can build up to full well tubing head pressure and thus constitute a hazard.
Due to the substantial volumes of hydrocarbons involved, such a hazard should not
be ignored when evaluating risk
• Subsea wells – while it can be argued that any loss of containment from a subsea
well presents very little risk to personnel, the repercussions from a serious pollution
incident should not be underestimated. In addition, risk to personnel will arise when
a vessel is above a subsea well to carry out any well intervention work. In summary,
while risk values can be reduced for subsea well integrity issues while such wells
are in production, a repeat risk assessment must be carried out when preparing
for any kind of well intervention activity
• Cumulative risk – this is risk introduced by a combination of well integrity issues
within close proximity to each other – eg same eggbox or module. While it is not
practical to quantify the cumulative risk of the varying well integrity problems on an
Installation, due regard must be made for such risk when risk assessing well integrity
issues on an individual well. The wellhead maps (refer to example below) generated
for individual Installations provide Apache Management with a risk overview for each
Installation
Where concerns are raised as to a build-up of cumulative risk, then the Well Integrity
Engineer in the first instance should consult with the Technical Authority for further
guidance on reducing such risk.
• Dropped objects – historically, when evaluating well integrity risks the most common
risk to uncontrolled release has been a dropped object impacting on the xmas tree
or wellhead valves and the associated instrumentation. Risk assessments must
therefore discuss this factor and provide the necessary mitigation and controls
• Human factors – when considering mitigation and controls for well integrity failures and
issues, a key component of risk assessment is to ensure that human factors
are discussed and addressed, particularly with issues where human intervention
is required to initiate a well shutdown in an emergency. In practical terms,
the assessment team should consider key area such as:
− Is access available to close a valve in an emergency situation? Particular attention
should be paid to ensuring that personnel are not put at risk by entering an area
where an uncontrolled release has occurred, to close a valve
− Is the equipment used to effect an emergency shutdown fully functional?
Uncontrolled when Printed
− Do the personnel tasked with effecting the emergency shutdown, know of their
responsibilities? Particular attention should be paid to ensuring that shift and tour
handovers highlight the well integrity issue in question
− Do personnel issuing Permits to Work (PTW) understand the implications of issuing
a PTW adjacent to a well with integrity problems?
Unmitigated and
Mandatory
Well Types Comments
Consequence
Score
Hydrocarbon Producer 6 No distinction made between
Wells gas-lifted, sub-hydrostatic, subsea
or ESP wells at this stage.
Cuttings Re-Injection 3 Consequence raised due to:
Wells (CRI) and
• Potential for abrasive material
Produced Water
in CRI wells
Re-injection (PWRI)
Wells • Potential for low levels of
entrained hydrocarbons in PWRI
Uncontrolled when Printed
wells
Water Injection Wells 3
(above hydrostatic)
Water Injection/PWRI 2 Pressure risk only during injection.
Wells (sub-hydrostatic)
Note: For the avoidance of doubt, the term ‘Unmitigated’ means that no controls,
precautions or special conditions have been applied to the issue in question.
Example – Application
Well Types of Mitigation to Comments
Consequence Score
Gas-lifted producers 5 Removal of gas lift will cause
well to die over time. However,
the presence of gas in the annulus
still constitutes a substantial
hazard unless vented or otherwise
dissipated.
ESP wells 4 Pump shutdown will cause
the well to die.
Free-flowing 6
Uncontrolled when Printed
producers
No change in
consequence apparent.
Subsea wells 4 Consequence (and probability)
score will rise when vessel above
a well and must be re-assessed
for such activities.
Note: In all cases, the Technical Authority (Drilling Manager) must agree with
any published consequence score following mitigation.
In all cases, a well should be monitored for any further failures which take the well out
of barrier compliance.
Repairs are not practical on ASVs unless of the DHSV (retrievable) type.
The general two barrier requirements should be applied to failures on subsea wells,
however due to the location of such wells, providing a repair timescale is impractical and
therefore subsea well failures must be addressed on case by case basis.
As discussed elsewhere, timescales for repair of integrity failures on non-hydrocarbon
wells (water injection wells/disposal wells etc) may be relaxed due to the lower risk
potential. However, it should be recognised that high injection rates and pressures over
a long period may accelerate erosion/corrosion issues. Such wells should be addressed
on a case by case basis.
Uncontrolled when Printed
Section 3 Chapter 4
Risk Assessment Process
Paragraph Page
Table
3.4.1 SafeWells Colour-coding Definitions 3-4-1
Figure
3.4.1 SafeWells Well Barrier Status Diagram 3-4-2
3.4.2 SafeWells Worked Example – First Pass (Initial) Assessment 3-4-2
3.4.3 Colour-coding Categories 3-4-3
3.4.4 Change in Condition Screening Assessment Form 3-4-5
3.4.5 Accompanying Risk Assessment Scoresheet 3-4-6
3.4.6 Wells Risk Assessment Summary Form 3-4-7
3.4.7 Risk Approval Matrix 3-4-8
3.4.8 Final Overall Risk Applied 3-4-9
3.4.9 Risk Assessment Process Flowchart 3-4-11
the Well Integrity Engineer for guidance where necessary. The SafeWells data entry input
is based on the criteria outlined in Table 3.4.1:
• Analyse whether the minimum two well barrier standard is still present on the tubing and
the annulus. This evaluation can be completed by authorised users in the first instance
but all such evaluations must be checked and agreed (‘accepted’) by the Well Integrity
Engineer within the SafeWells system
• Where it can be proven supported by the appropriate justification, that the required
two barrier standard has been met, no further assessment of risk is necessary
and the SafeWells Level of Concern – the Overall Well Risk, updated accordingly.
The Overall Well Level of Concern will now be changed to Normal Operation. Continue
to monitor well integrity. Refer to worked example below:
Overall Well
‘Level of Concern’
Individual Well
Barrier (SCE) Status
• Where the minimum barrier standard is not present or where there are concerns
over a well integrity situation and the Level of Concern is not green, then proceed
to an assessment of risk based on the guidance and criteria defined within Stage 2
onwards
Notes: (1) It should be noted that the First Pass assessment defines the ‘as-found’
integrity status of the individual well barrier elements (SCE) or barriers
only, and does not at this stage, provide the overall risk from continued
operation of the well.
(2) The Well Integrity Engineer may choose to vary the ‘Level of Concern’
up or down following further assessment of the issue in question. For audit
purposes, all such changes must be logged and dated within the SafeWells
system and be accepted/approved at the appropriate level.
Uncontrolled when Printed
Completion of the ORA must be based on the information supplied by the Well Integrity
Engineer or Technical Authority for Wells. It should be noted that the ORA process is part
of the electronic Permit to Work System (ISSOW) and utilises a 5 x 5 risk matrix and
as such, this matrix should be used to allocate overall risk for allowing continued
production or operation of a well with integrity issues.
Installation :
Failure Identified: SCE/Well No :
1 What is the impaired or degraded equipment/system used for?
3 Cumulative Risk - Are there any other SCE’s interdependent with this SCE or SIMOPS activities involved?
(Consider – deferred maintenance on other SCE’, existing ORA‘s, SIMOPS activities event and Current ORA appendix 3, 4 & 5 as
appropriate
4 Specify what MAH are involved: Blowout; Explosion; Fire; Toxic Gases; Release Well Bore Fluids;
Dropped Object uncontrolled Release of Stored Energy ?
6 What measures can we put in place to replace the functionality lost due to impaired or degraded
equipment/system?
Uncontrolled when Printed
7 How effective are these measures likely to be under the circumstances in which they are most needed?
8 Does the proposed change involve changes to the original design impaired or degraded
equipment/system, if so what are they?
9 Does the proposed change involve changes to the original procedures/method if so what are they?
10 Does the proposed change involve changes to the original design equipment, operating procedures and,
personnel are deemed competent to put changes in place?
Equipment:
Procedure:
Training:
12 Under what circumstances could the specified MAH occur associated with the proposed change?
13 Together, are all of these measures sufficient to manage risk effectively, and for how long?
14 Review the proposed changes collectively above and ensure actions taken and agreed relating to
equipment/ procedure/method statement to be used are risk assessed to ALARP to proceed if NOT,
STOP.
1 2 3 4 5 6
6 6 12 18 24 30 36
Mitigation
5 5 10 15 20 25 30
4 4 8 12 16 20 24
3 3 6 9 12 15 18
2 2 4 6 8 10 12
1 1 2 3 4 5 6
1-6 No Performance Standard breach – two (2) un-degraded well barriers to atmosphere confirmed.
NORMAL Some minor failures identified but of low concern. Where significant operational mitigations and
OPERATION controls are required, then the issue of an ORA should be considered.
8-16 Performance Standard not fully met due to degradation of available well barriers but acceptable
DEGRADED mitigations and controls available. Operation can continue subject to application of identified
CONDITION mitigations and controls and issue of approved ORA where deemed necessary. Continue to monitor
integrity status.
18-25 Performance Standard not met. Continued operation may be acceptable with remaining or
Uncontrolled when Printed
IMPAIRED substitute temporary barriers and / or other mitigations and controls. More detailed Safety Study
CONDITION required to justify continued operation. ORA to be raised and approved at appropriate level of
management.
30-36 Performance Standard not met and no mitigations or controls identified at Initial Assessment. Wells
HIGH in this category must be shut-in on available barriers and Emergency Contingency Action initiated
POTENTIAL wherever necessary, to avoid compromising Installation integrity. Operation of the well must not be
resumed until the necessary repairs have been carried out or the well otherwise made safe and
Management Approval obtained.
Approvers
accept the risk. In all cases, the mitigated risk score should be applied not the unmitigated.
Such approvals will be managed via SafeWells based on this matrix.
Input to SafeWells
Once the assessment of risk has been completed and the final scoring (or level
of concern) has been ascertained, the applicable overall colour coding for the well based
on the table below should be applied in SafeWells and the system-generated Reports
sent to the appropriate positions as defined in the matrix above. Refer to worked example
in Figure 3.4.8.
Out-of-hours Arrangements
Outwith office hours only, it may be necessary to carry out a risk assessment without the
full complement of reviewers and approvers being available. In such instances, the risk
assessment may be executed onsite – subject to the following provisos:
• The rule-based process as defined within this section must be complied with in full
to ensure an informed decision is arrived at
• Wherever possible, the onboard Well Services Supervisor must be included in the risk
assessment. Where the Well Services Supervisor is not onboard, then the Duty
Onshore Well Intervention Engineer must be consulted and agree with the risk
assessment outcome
• All documentation from the risk assessment must be emailed to the defined reviewers
and approvers
• The defined reviewers and approvers must review and agree with the risk assessment
outcome at the earliest opportunity
The applicable Installation OIM has responsibility for ensuring the above requirements
are complied with.
• There should be an assessment of individual ORAs and how they may impact
on each other to affect the hazard management process and the overall risk level
for the Installation in question. There should also be consideration and/or evaluation
of other issues that will affect risk – for example, safety critical maintenance backlog,
operational restrictions, weather conditions etc
Yes
Required two (2) well
barriers still present Continue to monitor
and ESD capability well integrity status.
uncompromised?
No
Uncontrolled when Printed
Complete Change in
Condition Screening
Assessment Form
Complete Risk
Assessment and apply
Risk Score. Update
'Safewells’.
No
Management
Shut-in Well. agreement to
continue
production?
Yes
Section 4
Well Integrity Monitoring, Testing
and Maintenance
Paragraph Page
1 Introduction 4-1
Section 4
Well Integrity Monitoring, Testing
and Maintenance (cont’d)
Paragraph Page
Section 4
Well Integrity Monitoring, Testing
and Maintenance (cont’d)
Paragraph Page
Communication 4-39
10.10 Annulus Pressure Diagnostics 4-39
Section 4
Well Integrity Monitoring, Testing
and Maintenance (cont’d)
Table Page
4.1 Examples of Safety-critical Equipment and their Function 4-2
4.2 Well Maintenance Frequencies 4-3
4.3 PPM Deferral Tolerance Chart 4-5
4.4 Responsibilities for PPM Deferrals 4-7
Uncontrolled when Printed
Section 4
Well Integrity Monitoring, Testing
and Maintenance (cont’d)
Figure
4.1 Example Well PPM Deferral Request 4-9
4.2 Typical Xmas Tree and Wellhead Valve Failures 4-18
4.3 Continued Operation with Inline Xmas Tree Valve Failures 4-19
Uncontrolled when Printed
4.4 Continued Operation with Outboard Xmas Tree Valve Failures 4-20
4.5 Continued Operation with Spool Xmas Trees
Integrity Failures 4-21
4.6 Continued Operation with Annulus Valve Failures 4-22
4.7 Continued Operation with Failed DHSV 4-26
4.8 Typical ASV Test Graph 4-28
4.9 Continued Operation with ASV Failure 4-29
4.10 Typical Forties DGL Well Schematic 4-35
4.11 Recommended Alarm Setpoint Guidance 4-38
4.12 Well Integrity Leak Path Diagram 4-40
4.13 Continued Operation with TAC 4-41
4.14 Continued Operation with Casing to Casing Communication 4-42
1 Introduction
This section deals with well integrity monitoring, testing and maintenance requirements
during the operational phase of a well. Work instruction – ie how to do guidance is provided
in other procedures or work instructions.
Where proformas for recording well integrity information are referenced, then such
documents are available from the Well Integrity Engineer, or directly from the SafeWells
System.
Maintenance on xmas trees and wellheads is normally carried out by specialist crews
under Apache supervision. Execution of the necessary integrity testing where venting
to process takes place – eg DHSV/ASV/xmas tree/wellhead valve inflow testing
etc, should be carried out by Production Operations personnel.
When failures have been identified it is important to:
Uncontrolled when Printed
• Identify the problem area by analysing what has happened by gathering as much
information on the failure as possible
• Ascertain if the required two barriers to atmosphere are in still in place
• Ascertain if the minimum one Surface ESD and one Downhole ESD (DHSV)
are still available
• Ascertain if replacement barriers can be activated or if further mitigation can
be applied
Throughout this section, therefore, readers are provided with a range of tools to analyse
problem areas in the field and to have the necessary information to hand when
discussing with the Well Integrity Engineer in the first instance. In all cases, the Well
Integrity Engineer should be notified/consulted on any well integrity failures identified.
Accountability for compliance with this section rests with the Installation OIM as Well
Owner during the operational phase.
Pressure- Pressure-
Equipment Comments
Containing Controlling
Tubing/Casing X
Xmas Tree Valves X X
DHSV/ASV X X
Production Packer X
be verified to ensure that it continues to meet its PS, hence the need to pressure test such
equipment.
3 Maintenance Strategies
The table in Appendix 4A discusses and defines the Maintenance Strategies for various
types of well – eg Water Injection, Long-term Shut-in (LTSI) etc. The purpose of the table is
to ensure that effort is not wasted on carrying out maintenance on wells which
do not require it – eg LTSI wells do not require xmas tree valves to be greased
on the same frequency as an active well. Over-greasing will only result in grease being
pumped into the well causing future problems for well intervention.
(3) All deferrals are documented and are tracked through to closeout.
In addition, during PPM work, there will be instances where certain maintenance routines
are impractical to carry out due to various reasons and exceptions to the standard PPM
work instruction is necessary. Typical and practical examples would be:
• Situations where wellhead bleeder plugs are seized or otherwise inoperable. Such
a failure may result in a well having to be killed and plugged to effect a repair resulting
in a low risk benefit/high cost scenario
• Re-occurring non-critical failures, where repair is impractical or where the cost would
outweigh the risk benefits gained – for example, failure of a 13 3/8in wellhead void
pressure test. As the 13 3/8in casing/void does not normally provide hydrocarbon
containment, such a failure may constitute a low risk if there are no other issues which
compromise the overall integrity of the well – for example, 13 3/8in x 9 5/8in casing
communication etc
The majority of problem areas are of low risk to wellbore integrity and provided there
is ongoing surveillance to ensure compliance with the required two barrier policy (as with
all wells) and there are no other critical well integrity issues to consider, the repair of such
problems can be deferred for a period of time dependent on the risk.
For this type of deviation or exception, the PPM work instruction should be modified
to suit, under the deferral process as defined within this section.
Mandatory Requirements
• Maintenance on production wells already operating with significant well integrity failures
should not be deferred unless absolutely necessary, as any further deterioration
in the equipment may go unidentified for the period of deferral. In such situations,
it may be more prudent to issue an ORA to maintain maximum focus on this type
of well. The Drilling Manager as Technical Authority has the final decision on whether
an ORA is required
• The tolerance or Grace Period for the execution of well-related PPMs is based
on the guidance provided in the Apache Maintenance and Inspection Deferral
Procedure (ANS-MTC-004). As well-related PPMs are deemed safety-critical
(10% tolerance) and are generally based on a 6-monthly and 12-monthly frequency,
the tolerance for such work is therefore 18 days and 36 days from the scheduled
start date respectively. If work cannot be completed within this tolerance date,
then a PPM Deferral Request must be raised and approved. Table 4.3 provides
a graphical representation
this category.
Production-critical 12% of frequency
Maintenance
General Maintenance 15% of frequency
• Deferral periods must be identified on the Deferral Form and must be based on risk
assessment. For long-term low-risk deferrals or exceptions – for example, where
a full PPM cannot be executed for various reasons – a review of well status must
be made at each scheduled PPM or at 6-monthly intervals whichever is comes sooner
As risk is proportionate to the exposure time, a further risk assessment must
be carried out if the deferral is renewed for any reason. A second deferral must be
approved by the Technical Authority (Drilling Manager).
• PPM Deferral documentation should be held within the SafeWells System
• A statement on whether and how, compliance with the two barrier policy is achieved
and maintained. The past history of the well in respect of integrity failures should
be included in this statement
• Whether the request constitutes a repeat deferral
• Any ongoing mitigation or surveillance required. As discussed previously, for some
issues, it may be more prudent to issue an Operational Risk Assessment (ORA) also,
to ensure the necessary level of surveillance and mitigation is applied. The Wells
Team will provide guidance in this respect wherever applicable
• PPM Deferral Request validity period. This period should be based on the level
of risk and whether it will be feasible or practical to repair the problem. For example
some problems may only be repaired when a well is being worked-over and thus
may be required to be kept open
• What actions are required to close out the PPM Deferral Request
Uncontrolled when Printed
A hazard evaluation should then be carried out by the Wells Team to ascertain
and formalise the level of exposure. The PPM Deferral Request together with the applicable
hazard evaluation documentation should be reviewed internally within the Wells Team
and then sent to the OIM for review prior to final approval. The OIM must be satisfied that all
documentation is in order and that the well is safe to operate.
Once the OIM has agreed with all aspects of the PPM Deferral Request then they should
approve as per the Table 4.4.
5.2 Responsibilities
Responsibilities for compilation and issue of PPM Deferral Requests are as defined in the matrix below.
Onshore
Well Well
Task Offshore Platform Well Drilling
Task OIM OSP Integrity Services
No WSS Engineer Intervention Manager
Engineer Supt
Engineer
001 Overall Safety of the Well A R C C C C C C
002 Well Status Reporting to A R R C C C C I
Wells Team
003 Compilation of PPM Deferral A R C R R C I I
Request
004 Technical Review and C C R R R R* R A
Acceptance of PPM Deferral
Request
005 Approval for Issue A/R C C C C I C C
* R = Well Integrity Engineer has responsibility for ensuring that any PPM Deferral Requests outwith the green or yellow risk status
are risk-assessed and approved as per Section 3, Chapter 4 Risk Assessment Procedures.
Pass – this means that the device in question has a) met the required leak rate
Performance Standard (PS); and b) is fully functional.
Degraded – this means that the device is impaired in some respect and the PS is not fully
met. This could either be the leak rate is higher than the pass criteria but lower than
the fail criteria, and/or the functionality is impaired in some respect – eg valve closure
time outwith the PS but within acceptable limits as determined by risk assessment.
A probability of failure score will be applied to those devices or safety-critical
component(s) categorised as degraded (refer to Section 3, Chapter 3 Evaluation of Well
Integrity Failures/Issues for more details).
Fail – this means that the device does not meet the required PS and serves no purpose
as a well barrier or isolation. This would include devices which fail to function on demand.
• Tubing/casing
comms with
control line
• Unable to
maintain C/L
pressure
ASVs <1907scf/hr Ditto above.
Tubing to Annulus API 14H Std • Refer to
Communication Paragraph 6.4
Volumetric
(TAC)
calculation
Casing to casing API 14H Std • Refer to
communication Section 10
Volumetric
calculation
Step Action
1 Apply required pressure.
2 Allow 5-minute stabilisation period prior to commencing pressure test,
ensuring that pressure does not drop below 95% of required test pressure
before monitoring begins.
3 Monitor pressure for minimum 15 minutes.
Test Criteria
Pressure test Due to the higher test pressures (ca 4000psi)
involved than that for inflow testing, the allowable
leak rate is a maximum 5% drop from the applied
pressure (stabilised) over a period of 15 minutes.
Acceptable communication rates between tubing and primary annulus are based on API
RP 14B, which defines allowable leakage across a downhole safety valve, and is widely
regarded as an industry standard.
For gas leak paths the acceptable communication is defined as 900scf/hr and for liquid
systems it is defined as 6.3gal/hr.
Communication checks should be conducted as described in platform-specific procedures,
which provide the necessary work instruction for such work.
To simplify the calculation, worst case values for z = 0.85 may be assumed.
The allowable change in pressure during the test (dPa) (psi) is then:
0.85 Q.T .t 21.63 T .t
dPa = =
35.37 V V
Uncontrolled when Printed
For the normal range of test fluids and well conditions c = 3 x 10-6psi-1. API RP 14B
recommends an acceptable fluid leak of 6.3gal/hr.
The allowable change in pressure (dP) (psi) which this leakage per hour equates
to can therefore be calculated as:
6 .3
dPa =
42 x 3 x 10 −6
50 000
dPa =
Uncontrolled when Printed
V
or for pressure measured over time t (hrs):
50 000 t
dPa =
V
The flowcharts in Paragraph 8 are intended to provide field personnel with the necessary
guidance to provide an initial assessment of the failure and for onshore personnel
to analyse whether the well can be kept online, or secured due to safety concerns.
It is recognised that the flowcharts do not address every combination of failure mode
and in such instances, field personnel should liaise with the Well Integrity Engineer or
Onshore Well Services Team.
Programme issued by the Wells Team together with a competent person to supervise the
repair operation. Refer to Section 3 of this manual in respect of roles and responsibilities.
Any deviation from this standard must be approved by the Drilling Manager.
Sequence Equipment
1 DHSV (if being tested)
2 Lower master valve
Uncontrolled when Printed
Where new or replacement xmas tree or wellhead valves or other components have
been installed or where pressure containment has been breached pressure testing
should be performed to the 1.1 Maximum Expected Wellhead Pressure (MEWP)
as defined in the Apache Drilling and Well Operations Policy (ANS-DRL-002).
In the event of a failure, gate valves should have grease or sealant re-injected into
the relevant ports as applicable, be cycled a number of times and then re-tested. If a valve
produces similar leakage rates for three successive tests it should be rescheduled
for inspection or overhaul. The direction of leakage should be determined.
Regular testing provides integrity assurance for normal platform operations (in-service
wells) only. Where well intervention is to be conducted, more stringent leak testing
criteria should be applied to ensure isolation from the well bore prior to breaking
containment.
Failure Diagnostics
The following flowcharts provide operating personnel with the required steps to take
following identification of a xmas tree valve failure issue or anomaly. Where such
an issue has been identified, the Well Integrity Engineer must be informed/consulted
for further advice.
Where the defined standard closure times cannot be met, the actual best closure time
achieved must be reported to the Well Integrity Engineer for the necessary risk assessment
to be completed.
Figure 4.3 Continued Operation with Inline Xmas Tree Valve Failures
Figure 4.4 Continued Operation with Outboard Xmas Tree Valve Failures
Figure 4.5 Continued Operation with Spool Xmas Trees Integrity Failures
DHSVs on dead and shut-in wells are normally tested every 12 months.
Note: The well is closed in at surface, allowing it to build up to full tubing head pressure
before the DHSV is closed. After closing the valve, the tubing above the DHSV
is then bled off at a controlled rate to the lowest practical value and the resultant
pressure buildup in the tubing is monitored.
Integrity testing of the DHSV consists of three main requirements and all three
requirements should be met to warrant a pass:
(1) Correct functioning of the DHSV – the DHSV closes upon release of control line
pressure. The DHSV remains open when control line pressure is applied.
(2) Inflow testing of the valve itself – will provide tubing protection, within an allowable
leak rate, when closed.
(3) Inflow test of the DHSV control line – there is no communication with either the tubing
or annulus pressures and the correct operating pressure can be maintained.
• As the majority of wells are gas lifted, it should always be possible to charge a well
with sufficient pressure to enable a differential to be applied, to allow a meaningful test
to take place
• Slam shut tests are not recommended
• DHSV testing should be carried out immediately prior to xmas tree maintenance
and well intervention operations. This removes the requirement to test the DHSV
on a separate occasion maximising well uptime. It is also preparation for some of the
valve maintenance
• Many water injection, ESP and PWRI wells go on to vacuum when closed-in due
to low reservoir pressure. Subsequently, in such wells where there is no pressure
to check the integrity of the valve (ie water injectors and dead wells) the regular testing
programme should still take place to confirm that control line pressure can
be maintained and that the well has no capability of maintaining hydrocarbon flow
to surface. Functionality of the DHSV can and should be checked for correct operation
by connecting a low-volume pump to the control line and observing: a) the pressure
response of the DSHV opening; and/or b) the volume of fluid returns from the control
line when the DHSV is closed
• The integrity testing of DHSVs in water injection wells is carried out, wherever possible,
by measuring the leak rate directly (ie measured volume of water). This is only applicable
if the well can sustain a significant supercharging effect for the duration of the test
Proformas for DHSV integrity testing are available within the SafeWells System
Uncontrolled when Printed
Based on the equations specified in Appendix G of API RP 14B, it shows the pressure
build-up/leak rates, which are allowable above a closed DHSV during a 15 minute test.
Table 4.9 is only applicable to Forties Wells. For Beryl Wells, a formula spreadsheet is
available to check allowable leak rates on a case by case basis based on individual well
volumetric calculations. Refer to references in Paragraphs 6.2 and 6.4 for further details.
If necessary, consult the Well Integrity Engineer for advice on this issue.
When the ASV is closed and the gas above the ASV vented, the gas will cool rapidly
until venting stops and the surface casing valve is closed again. Once venting stops
and the valve is closed, the gas left above the ASV will heat up causing an increase
in pressure to occur. This effect can often be misconstrued as a failed test. It is important,
therefore, to ensure that sufficient time is provided for thermal stabilisation to take place,
before commencing the inflow test. The rate of change in pressures should, therefore,
be logged throughout the test to identify the when the stabilisation period has ended and
the test can be commenced. It should be noted that experience has shown that such
tests can sometimes take up to 5 or 6 hours to complete.
The chart below illustrates an example of this effect. Where there is doubt as to the validity
of an ASV inflow test, the Well Integrity Engineer should be called for advice.
Uncontrolled when Printed
• If hydrocarbons are identified, a decision on the requirement for remedial action will
be made on the change in risk associated with the presence of those hydrocarbons,
depending on the zone, inventory and the rate of influx. The initial requirement will
be to identify the rate of influx. This will be carried out by bleeding the annulus to zero
or as close to zero as practical and carrying out a PBU over 1 hour
‘C’
Criteria ‘A’ ‘B’
(if enclosed)
Annulus operating pressure (bar) Set limit 35 Set limit 25 Set limit 10
Top-up test (bar) 35 25 10
Potential increased pressure 155bar max 35 25
in the event of annulus
(gas lifted
communication
case)
Resultant operating ranges 35 to 155 25 to 35 10 to 25
to compare with API 6A gauge
range criteria
Best fit gauge range 0 to 200 0 to 60 0 to 25
Uncontrolled when Printed
Exception is Beryl Alpha Well A83 ‘A’ annulus – retain 10k gauge on A annulus only.
A83 has 10K Cameron tree installed.
Notes: (1) For Forties DGL wells with pressurised upper annulus, the best-fit range
should be selected on the basis of the maximum possible annulus
pressure with a similar requirement for ESP wells.
(2) DHSV supply pressure gauges should accommodate system test
pressures against the API criteria.
(3) Tubing head/xmas tree mounted bore pressure gauges: Range should not
be less than the pressure rating of the xmas tree.
Sequence of Venting
The following should be observed to minimise the risk of collapse of the internal casings:
• The tertiary (‘C’) annulus should be at zero pressure before venting the secondary
annulus
• The secondary (‘B’) annulus should be at zero pressure before venting the primary
annulus
CAUTION: IN WELLS WITH INJECTION VALVES, PARTICULAR CARE SHOULD
BE TAKEN TO ENSURE THAT THE PRIMARY ANNULUS AND
THE TUBING ARE VENTED DOWN SIMULTANEOUSLY TO MINIMISE
THE RISK OF TUBING COLLAPSE. IF NECESSARY, CONSULT
THE WELL INTEGRITY ENGINEER FOR ADVICE ON THIS ISSUE.
Note: Due to welI design, it is not possible to monitor and bleed down the tertiary and
Uncontrolled when Printed
Forties Dual Gas Lift (DGL) wells should be topped up and tested on a quarterly basis
unless otherwise advised.
For Forties single-string wells ONLY, the following test pressures apply:
For Forties Dual Gas Lift (DGL) wells ONLY, the following test pressures apply:
Note: The primary annulus on ESP wells should not be pressure tested unless
specifically requested by onshore support due to the risk of explosive
decompression in the ESP power cable. Such wells however, should still be
topped up on the same frequency as other Forties wells.
As with other types of integrity failure, the decision to continue operation of a well with
a failed casing seal hanger or void pressure test and/or the presence of hydrocarbons in
void must be made on a risk basis.
13 Management of Change
The Management of Change (MOC) process defined in the Apache Drilling and Well
Operations Policy (ANS-DRL-002) should be applied where change is necessary.
14 Industry References
The following industry references can be consulted for further advice and information:
Appendix 4A
Recommended Maintenance Strategies
Uncontrolled when Printed
Discussion on Maintenance
Well Type Discussion on Integrity Aspects Recommendations
Strategies
Active Oil and Gas Constitute the largest risk to Require optimum integrity on such wells. Continue with existing PPM scope and
Producers/Injectors personnel in the event of Maintenance to be kept within defined frequencies.
uncontrolled release. frequency.
Long-term Shut-in Oil Consequences of an uncontrolled Xmas trees on this type of well do not Omit greasing from PPM schedule.
and Gas Producers release no different than active oil require regular greasing as functioning
Continue with standard integrity testing
(open to reservoir) and gas producers. of valves is not frequent enough
regime. Consider plug/kill if no long-term
to deplete the grease reservoirs
use for well and thus eliminate need for
within the valve(s).
full PPM.
Long-term Shut-in Oil Such wells present low Ensure that PWV has sufficient integrity Grease and integrity test TKV and PWV
and Gas Producers/ risk/consequence of uncontrolled to isolate ingress of hydrocarbons into only if ingress from process apparent.
WI/PWRI wells release. However, such wells may xmas tree. If well status such that xmas
(NOT open to become charged up from process tree can be removed with barriers in
reservoir – plant if TKV or PWV integrity poor. place, then no requirement to retain
ie plugged/killed) full integrity on xmas tree (other than
TKV/PWV as noted).
Subsea Oil and Gas Consequences of an uncontrolled Newer style xmas trees – ie Skene/ Consider deferment for extending PPM
Producers/Injectors release more of an environmental Nevis/Buckland/Bacchus – do not frequency on a case-by-case basis.
issue than a risk to personnel. require regular greasing. Thus majority Base decision on failure history and
ESDVs provide the major of PPM scope can be completed from risk. Consider future well intervention
protection to platform personnel. Platform. requirements also.
However, be aware of minimum
For older subsea wells – eg SPS/plain
integrity requirements for any
Jane xmas trees – greasing is required.
future well interventions.
Discussion on Maintenance
Well Type Discussion on Integrity Aspects Recommendations
Strategies
Water Injection Wells In an uncontrolled release, water Adequate integrity required on xmas tree Consider deferment for extending PPM
(above hydrostatic) would be the released fluid and wellhead valves due to pressure frequency on a case-by-case basis. Base
therefore explosion risk is zero. hazard. Consider also erosion/corrosion decision on failure history and evidence
However, pressure presents issues. of corrosion/erosion.
a hazard to personnel.
Produced Water Such wells are generally PPM scope and frequency can be Consider deferment for extending PPM
Re-injection (PWRI) sub-hydrostatic, however relaxed, provided no history of major frequency on a case-by-case basis.
Wells hydrocarbons up to ca 600ppm integrity failures apparent. Consider also Base decision on failure history and
may be entrained in produced erosion/corrosion issues. evidence of corrosion/erosion. If flowline
water, although not deemed to to hydrocarbon process still attached,
be a major hazard. ensure TKV/PWV integrity adequate.
Water Injection Wells Consequence of an uncontrolled PPM scope and frequency can be Consider deferment for extending PPM
(sub-hydrostatic) release once injection pressure relaxed, provided no history of major frequency on a case-by-case basis. Base
removed is minimal. integrity failures apparent. Consider also decision on failure history and evidence of
erosion/corrosion issues. corrosion/erosion.
Section 5
Subsea Well Integrity
Paragraph Page
1 Introduction 5-1
2 Scope 5-1
Section 5
Subsea Well Integrity (cont’d)
Paragraph Page
Table
Uncontrolled when Printed
Figure
5.1 Typical Vertical Dual-bore Tree 5-12
5.2 Typical Valve Configuration for a Vertical Dual-bore Xmas
Tree 5-13
5.3 Typical Horizontal or Spool Tree 5-14
5.4 Typical Valve Configuration for a Horizontal or Spool Tree 5-15
5.5 Bacchus Xmas Tree 5-15
5.6 Sequence Hydraulic Control 5-16
5.7 Direct Hydraulic Control 5-18
5.8 Electro–hydraulic Control 5-18
5.9 Typical Control Room Screen 5-19
5.10 Beryl Area Subsea Facilities 5-24
5.11 Bacchus Field Subsea Facilities 5-25
5.12 Horizontal (Spool) Xmas Tree Valve Schematic 5-29
5.13 Information Flow Requirements 5-34
Section 5
Subsea Well Integrity (cont’d)
1 Introduction
The execution of subsea Planned Maintenance (PM) obviously requires a well
to be shut-in to carry-out the required work. Significant volume losses can, therefore, occur
either from in-efficiencies either prior to, or during the work in question. This procedure
is intended to convey those best practices applicable to minimising well downtime
and subsequently, production losses.
It should be noted that the best practices noted in this procedure are intended
to supplement those already defined in other sections of this manual.
2 Scope
This procedure covers the execution of all subsea PM work within Apache. The scope
Uncontrolled when Printed
does not extend to the execution of wellwork on subsea wells but does discuss the integrity
aspects of aspects of planning for subsea well interventions together with providing
definitions on what it constitutes.
The definitions below are intended to identify and clarify roles and responsibilities
for such situations.
Engineer (Onshore)
Platform Engineer
Completions and
Well Intervention
Subsea Projects/
Ops Engineering
Drilling Manager
Superintendent
Superintendent
Maintenance
(if Offshore)
Subsea
WSS
OSP
OIM
No Task
Engineer (Onshore)
Platform Engineer
Completions and
Well Intervention
Subsea Projects/
Ops Engineering
Drilling Manager
Superintendent
Superintendent
Maintenance
(if Offshore)
Subsea
WSS
OSP
OIM
No Task
Engineer (Onshore)
Platform Engineer
Completions and
Well Intervention
Subsea Projects/
Ops Engineering
Drilling Manager
Superintendent
Superintendent
Maintenance
(if Offshore)
Subsea
WSS
OSP
OIM
No Task
The following activities may be considered to be well entry dependent on the particular
equipment design and configuration. In all cases, discussion and agreement on a case-by-
case basis must take place between the Drilling and the Subsea Projects and Operations
Uncontrolled when Printed
Groups, to determine:
• Whether a well (well entry) programme is required
• Whether the work can be performed under a subsea intervention work programme
with the review and concurrence of the Wells Team (refer to Paragraph 4.3)
Key issue for all parties is to ensure that any exposure to the wellbore when performing
the work is safely managed and controlled utilising the most applicable and competent
personnel, thus minimising the hazard of uncontrolled flow from a well and/or pressure
hazards for divers.
Table 5.4 describes the activities that are considered subsea interventions or well
entry where ownership can lie either with the Wells Team or the Subsea Projects and
Operations Group, depending on the implications for maintaining well integrity.
The following well entry operations require the swab valve to be operated and/or additional
pressure barriers to be installed and therefore the Wells Team shall be the responsible
function in all cases:
• Installation or deployment of equipment capable of operating xmas tree swab valves,
such as the subsea wireline lubricator system
• Work performed on a well using a subsea wireline lubricator from a DSV or workover
riser from MODUs
• Subsea well suspension or abandonment where the reservoir has not been fully isolated
as per company or country-specific regulatory requirements, and thus constitutes
a potential hazard
• Tree valves
• Emergency shutdown valves
Any work on the platform control unit that controls the operation of the subsea tree
and other items of downhole equipment, involving the disconnection or reconnection
of control umbilicals.
Subsea tree valve greasing.
Any work performed on subsea structures such as visual inspection, opening doors
for planned intervention or releasing sliding legs.
Any operations that are performed on subsea umbilicals including connection and
disconnection between the tree and outboard of the first valve on the platform topsides.
This includes any subsea tree control piping and cabling.
Any pipeline work, which can be defined as all operations between the tree flowline
connectors and the subsea risers at the operating platform, including:
• Any non-visual work performed at the tree/guidebase to flowline interface, such
as the connection or disconnection of the flowline
• Any non-visual work performed on the chemical injection lines such as connection
or disconnection
Any diving work in the categories above when a part of well construction, well
intervention and abandonment work or activities.
The Wells Team and the Subsea Projects and Operations Group must therefore discuss
and agree on what type of work programme is required to execute the planned work.
5 Equipment/Well Design
5.1 General Well Design
There are significant differences between surface (platform) and subsea wells – mainly in
respect of wellhead/casing and tree design. Detailed descriptions of such differences are
not within the scope of this section.
Xmas Trees
There are several designs of subsea trees in use with Apache and personnel involved with
subsea wells must study their particular xmas trees and configurations before carrying out
any planned maintenance.
Figure 5.2 Typical Valve Configuration for a Vertical Dual-bore Xmas Tree
Horizontal/Spool Trees
Horizontal or spool trees (terminology dependent on manufacturer) differ from vertical
trees in that they have no inline valves on the tree – all tubing and annulus valves being
outboard of the vertical bores to the production tubing and the annulus. An internal tree
cap and crown plug are installed in the tree bore to provide the necessary barriers
to the atmosphere when the non-pressure retaining debris cap is installed.
Horizontal trees are designed to allow drill pipe access through the tree via drilling BOPs
and riser installed on top of the xmas tree. The wellbore can be entered once
the internal tree cap and crown plug have been pulled through the BOPs.
Introduction
There are several different designs of control system for subsea wells. Each system has
advantages and disadvantages and there may be a mixture of different control system
types in one field.
A basic knowledge of how each system works is necessary for readers to understand the
implications of control system operability on well integrity. For more detailed information,
readers are directed to the Subject Matter Experts (SMEs) within the Company.
Sequence Control
This method of control operates on the basis of the tree/wellhead valves functioning
by increasing and decreasing the hydraulic control pressure to sequence the valves open
Uncontrolled when Printed
and closed. This system is generally a retro-fit utilised on older wells where
the original system has developed reliability issues – such as, electro-hydraulic systems
where the electrical function has been lost, etc.
The following are the advantages and disadvantages of a sequence hydraulic control
system:
Advantages
• Increase in range of operability over direct control (typically 5 to 8km, 3 to 5 miles)
• No influence on umbilical size given increase in control functions (manifold at the far end)
• Usually open loop hydraulics (appropriate for expeditious hydraulic shutdown)
Disadvantages
• Increased complexity
• Hydraulic sequence control pod complexity
• Hydraulic fluid management
• Unable to pressure test function individually
• No process information of remote facility
When carrying out integrity tests with wells on such a system, it may not be possible
to integrity test individual valves on the tree/wellhead and it may only be practical
to ascertain that the valves in question are functioning and that there is no flow into
the flowline via the Production Wing Valve (PWV). This is termed a gross flow test. Where
such situations occur, it is prudent to carry out a risk screening exercise to ensure:
Uncontrolled when Printed
• That there is adequate protection for the host platform – such as flow from the reservoir,
can be contained within the well
• The risk to personnel in executing well intervention work can be minimised
Gross flow tests should be recorded in SafeWells as an adhoc test.
When planning well interventions on wells with sequence control, due regard must
be made for the fact that individual valves have not been fully tested as well barriers
and that further testing may be required once the workover control system from
the intervention vessel or MODU, has been hooked up and is functional. For information,
installation of the workover control system will bypass the sequence control and restore
operation of individual valves.
Contingencies must, therefore, be built into the applicable well intervention programme
with the assumption that individual valves may not integrity-test as desired. This will
avoid un-necessary downtime having to deal with detailed wellwork programme changes.
Advantages
• Simple to implement
• Robust in operation
• Good for control close to the pump – eg 500 to 750m
• Pressure testing of individual functions
• Usually closed loop hydraulics unless configured for local vent
Disadvantages
• Slow for operation at a distance
• Increase in umbilical size – ie a core for each function
• Hydraulic fluid management
• Limited in range of operation
• No process information of facility
Uncontrolled when Printed
Electro-hydraulic Control
This is the most common form of subsea well control system and involves a combination of
electrical and hydraulics to function the various tree and wellhead valves. The Subsea
Electrical Module (SEM) fitted close to the tree or manifold provides the necessary signals
to operate the hydraulics supplied by the host platform via an umbilical, to individual valves.
Advantages
• Increase in range of operability over sequence control (typically 10 to 100km)
• No influence on umbilical size given increase in control functions (manifold
at the far end)
• Can be either open or closed loop hydraulics (as appropriate for required performance
criteria)
• Process information retrieved from remote location
• Operation and control of complimentary equipment (pig detectors etc)
Disadvantages
• Electro hydraulic control pod complexity
• Hydraulic fluid management
Uncontrolled when Printed
Introduction
The schematic below illustrates a typical control room mimic-screen with a subsea tree
and its associated valving, pressure transducers and others.
In practice, however, experienced personnel are usually able to observe valve closure
when executing PMs by careful observation of pressure fluctuations within the tree
together with visual indication – usually a coloured LED, in the host platform control
room. control room indications alone should not be viewed as guaranteeing that
a valve has functioned closed.
Annulus Venting
Venting of an annulus would normally be executed by closing the production master
Uncontrolled when Printed
valve and opening the Crossover Valve (XOV) to the tree and then subsequently
venting to the flowline via the open production wing valve. Care must be taken to ensure
that the annulus pressure is always higher than the tubing pressure before opening
the XOV, to avoid influx from the tubing to the annulus and alarm setpoints should be set
accordingly. Care should also be taken to avoid venting under high differential pressure,
in order to avoid hydrate formation.
Hydrate Risk
In the North Sea, due to the cooling effect of the sea, some subsea wells may be at a high
risk of forming hydrates, particularly around the xmas tree and the gas lift lines
in a gas-lifted well.
Note also the potential for hydrate formation when venting an annulus at high differential
pressures and velocities particularly at startup.
Well startup and shut-in procedures should, therefore, address the potential for hydrates
and provide steps to avoid hydrates forming.
These facts should be recognised when operating subsea wells or planning maintenance
activities and the necessary hydrate prevention precautions should be followed.
Personnel involved with the integrity of subsea wells should be aware of the potential
for trapped annulus issues. An annulus is trapped when cement or settled mud solids
extend above the previous casing shoe. Due to subsea well design where only the primary
annulus can be vented any trapped fluids can cause a buildup in annulus pressure
as a well heat up. This creates the potential for burst or collapsed casing or which may also
impact on the integrity of the production tubing resulting in uncontrolled flow of reservoir
fluid with obvious Health Safety and Environment (HSE) and cost implications. Typical
mitigations can include:
• Leave cement below previous casing shoe – challenging in deviated wells or reservoirs
near shoe
• Leave compressible fluid in trapped annulus
• Burst disk or foam wrap
• Vacuum insulated tubing
• Ensuring that the annulus pressure is always higher than the tubing pressure when
opening the XOV to vent down an annulus
• A Heritage EM Survey on wells with potential for trapped annulus is available from
the Wells Team ‘N’ drive or contact the Well Integrity Engineer for such information
Co-ordination of Activities
If a dive support vessel is required for performing maintenance on subsea wells, adequate
time must be set aside for procurement of such a vessel. It is recommended that planning
for such work should commence around 26 weeks before planned execution.
All groups involved with subsea work (Instruments/Production Ops/Subsea Projects
etc) should review, those PM routines which require a well to be shut in to execute,
and ensure that wherever practical such routines are completed at the same time,
thus avoiding multiple well shut-ins.
Job Planning
When preparing for planned maintenance on a subsea well, adequate control room
personnel must be available to support the work.
Planned Preventative Maintenance (PPM or PM) routines should be tailored to suit
the service and criticality of each well, to avoid excessive downtime in executing
maintenance work. Therefore on a periodic basis, the status of each well (long-term
shut-in/suspended/change of use etc) versus the maintenance work being carried out
should be reviewed.
While the maintenance frequency for subsea wells is defined as 24 months (+ 1 month
before being backlogged), it is recognised that it is not cost-effective to mobilise a Dive
Support Vessel (DSV) specifically for carrying out valve greasing and visual inspection
on individual subsea wells. Therefore this work would normally be carried out when
a DSV is mobilised for other more critical subsea work. Best efforts should, therefore,
be made to plan subsea well maintenance into routine or unplanned DSV schedules
wherever practical. Where the defined frequency of maintenance cannot be complied
with due to the reasons defined above, then the applicable management of change
documentation and risk screening should be completed.
In all cases, and in alignment with regulatory expectations, the period between visual
inspections should not exceed 5 years.
Servicing Requirements
Servicing requirements will vary depending on the make and type of valve or component
in operation. General servicing requirements at work instruction level is provided in
manufacturers' service manuals or rig books.
Good engineering judgement based on practical experience taking into account the issues
described throughout this section has been applied in setting the preferred acceptable leak
rate of 200psi over 15 minutes for all tree and wellhead valves.
In situations where the API 14 criteria has to be applied, and due to the various
configurations of subsea xmas trees and associated equipment resulting in a wide range of
downstream test volumes, it is necessary to quote values on an individual well basis.
Note that certain well-specific PPM work instructions may indeed quote such volumes
and acceptable leak rates based on such data. As defined elsewhere therefore,
the requirements of the well-specific PPM or Well Operating Envelope (WOE) will over-ride
the preferred standard of 200psi.
When applying the API 14 B standard and as with platform wells, the acceptance criteria
is based directly on the formula presented in API recommended practice, and as presented
in this section.
• However, to avoid any damage to non-equalising valves, individual well records should
always be consulted to check whether the valve is self-equalising or non-equalising,
prior to carrying out any integrity testing. On wells with non-equalising valves, the tubing
will have to be re-pressured to well tubing head pressure prior to attempting to re-open
the valve after integrity-testing
9 Well Barriers/Isolations
Well Barriers/Isolations
The barrier requirements for subsea wells are essentially no different from that for platform
or surface wells and the general two barrier requirement still applies, as defined
in other references such as the Apache Drilling and Well Operations Policy
(ANS-DRL-002).
pollution incident – and financial – cost to repair or deal with. However, the costs to the
Company both in terms of reputation and financial outlay must not be underestimated and
as a prudent Operator, best efforts should be directed at ensuring no well integrity incidents
occur during the life of a subsea well.
While in-service wells present little risk to personnel, the execution of well intervention
operations of any description on a subsea well, increase that risk substantially as soon
as a vessel arrives over that well. The removal of tree caps and subsequent heavy
lift operations can introduce high consequence events should there be, for example
a dropped object incident.
Other Considerations
The following general notes in relation to subsea wells are intended to supplement
the aforementioned notes.
Any downtime incurred on such wells can result in substantial costs, both in terms
of volume losses and in vessel or MODU day-rates.
As subsea wellwork is executed by the Wells Team the following best practices apply to
both. However, Production Operations have responsibility for ensuring compliance when
requested.
It is strongly recommended that all relevant valves are functioned and integrity tested
prior to any vessel or MODU being mobilised. This work must be completed well
in advance of vessel/MODU mobilisation to ensure any failures identified can be dealt
with by the Engineer(s) compiling the applicable well programme. This will help avoid
any high-cost vessel/MODU downtime while attempting to obtain the necessary well
barriers or isolations for installing well intervention or well control equipment.
Particular attention must therefore be paid to the following:
Target well barriers – ie the well to be worked on, has adequate barriers for the
installation of well intervention or well control equipment. Such barriers should address
both the tubing and annulus well integrity requirements.
On manifold-type or flowbase systems, valves or systems with any communication
to the target well must be integrity-tested to ensure no ingress of hydrocarbons
can jeopardise the timely installation of intervention or well control equipment on the well.
While any vessel is onsite over a subsea well for well intervention, consideration must
be given to the proximity of other subsea wells in the field with a view to carrying
out any tree and wellhead maintenance or other inspection/maintenance tasks on the
well or associated structures – even where the maintenance tasks are not scheduled
for execution. Use of the well intervention vessel or MODU for such tasks concurrently
with well intervention work, can realise substantial cost-savings over a standalone
mobilisation.
Therefore on fields where template structures exist or where the wells are in close
proximity to each other, an evaluation of the location of all surrounding or adjacent
wells – specifically the distance between the target well and adjacent wells, should
be compiled and cross-checked against the operating range of any ROVs or divers.
Adjacent Wells
In situations where adjacent wells are at risk from, for example dropped objects, due
Uncontrolled when Printed
to ongoing well intervention work, then the integrity status of such wells MUST be
previously known or otherwise ascertained. Therefore a full campaign of integrity checks
should be executed PRIOR (at least 1 month before) to the arrival of the vessel to avoid
lost time addressing such issues. Any deficiencies noted during such checks – eg failed
tree valves etc, MUST be accounted for when planning the work in question and the
necessary risk assessments completed, or alternative well barriers/isolation requirements
noted and addressed.
A documented record of adjacent well integrity results MUST be provided in the
applicable project interface document.
Overview
Appendices 1 and 2 provide examples of work instruction (proforma) which can be tailored
to suit individual subsea wells. This proforma must be based on tree and wellhead
design/type and must reflect actual well status at the time of work execution.
In addition to the proforma described above, various tools are available to assist
in generation of these proformas with respect to valve configuration and pressure
transducer configuration etc (refer to Appendix 5C – Subsea Xmas Tree Valve Status
Tool Example).
The proformas must be completed during execution of the planned maintenance with
all relevant data being accurately logged. Should the proforma in question prove
to be unsuitable during execution of the PM – for example, a pressure transducer proves
Uncontrolled when Printed
References
(1) Apache Drilling and Well Operations Policy (ANS-DRL-002).
(2) Oil and Gas UK – Guidelines for the Suspension and Abandonment of Wells.
Permanent Abandonment
The actions taken to ensure the permanent isolation from surface and from lower
pressured zones, of exposed permeable zones, fluids and pressures in any well that will
not be re-entered.
Suspension
Also referred to as temporary abandonment. Actions taken prior to leaving a well to ensure
adequate isolation of permeable zones, fluids and pressures in any well that will be
re-entered or abandoned at a later date. It should be noted that regulatory authorities may
impose a time limit on how long a subsea well can be suspended for,
and personnel should be aware of any such requirements.
Inspections
Based on regulatory expectations, all suspended subsea wells should be inspected
on a regular basis – normally 4 years – with a maximum of 5 years between inspections
to allow for the necessary vessel planning work to take place on a cost-effective basis.
In addition, and as with active subsea wells, such inspections should be scheduled
whenever any adjacent work is taking place in the same area, irrespective of when the last
inspection has been carried out.
Uncontrolled when Printed
13 Industry References
The following industry references are relevant to this section.
Appendix 5A
Subsea Well PPM Proforma Template –
Vertical Dual Bore XT
Uncontrolled when Printed
Appendix 5B
Subsea Well PPM Proforma Template –
Horizontal XT (S66 Example)
Uncontrolled when Printed
Appendix 5C
Subsea Xmas Tree Valve Status Tool Example
(Template available from Well
Integrity Engineer)
Uncontrolled when Printed
Appendix 5D
Example Subsea Equipment ER
Reference Chart
Uncontrolled when Printed
Section 6
Corrosion, Scale, Wax and Corrosion
Management (Production Chemistry)
Chapter 1 Erosion/Corrosion
Chapter 2 Production Chemistry
Uncontrolled when Printed
Section 6 Chapter 1
Erosion/Corrosion
Paragraph Page
1 Introduction 6-1-1
6 Elastomers 6-1-9
6.1 Definition of Elastomers 6-1-9
6.2 Elastomers used in the Oil Industry 6-1-9
6.3 Major Seal Failure Modes 6-1-11
6.4 Seal Selection Process 6-1-11
Figure
6.1.1 The Electrical Circuit 6-1-3
Erosion/Corrosion
August 2015 Issue 1 6-1-i/ii
Well Integrity Manual ANS-DRL-012
1 Introduction
This chapter provides an overview of erosion, corrosion and flow assurance considerations
which can impact on well integrity throughout the lifecycle of the well and outlines how
knowledge of the material properties and chemical processes which can occur in a well
can help ensure well integrity. This is not only important during the operational phase
of a well: loss of integrity, degraded material properties and loss of flow assurance
can also significantly impact on the ability to undertake intervention work, suspend and
abandon the well and prevent loss of containment to the environment, post-abandonment.
The first step towards delivery of well integrity is through material selection to ensure that
all the components in a well will retain physical integrity throughout the planned life of the
well. Material selection choices will be based on knowledge of:
• Operating conditions
Uncontrolled when Printed
Erosion/Corrosion
August 2015 Issue 1 6-1-1
ANS-DRL-012 Well Integrity Manual
Restricted access to all or parts of the well due to chemical deposits can limit downhole
inspection and monitoring, prevent well intervention to remediate integrity problems
or temporarily suspend the well and can result in more technically challenging and
ultimately more costly well abandonment. Chemical treatments pumped downhole for
well stimulation, dissolving chemical deposits or remediating well souring can, due
to their chemical nature, present an aggressive corrosion threat to the completion.
Process chemical treatments may also impact well integrity if, for example, lapses
in oxygen scavenger dosing of injection water results in excursions of oxygen to the point
where use of plain carbon steel tubulars in injection wells will not be not cost effective
due to premature loss of integrity. Similarly, poor microbiological control of injection
water can result in reservoir souring and eventual production well integrity issues due
to H2S corrosion. It is key, therefore, that production chemistry management and well
integrity management strategies are aligned.
The following sections give a high-level overview of basic corrosion physics and production
Uncontrolled when Printed
chemistry issues and products which need to be appreciated in order to deliver well
integrity through design (material selection) and mitigation by control of operating
parameters, production chemistry management and well intervention throughout the life
of the well. Readers should, therefore, be alert to the presence of corrosion/erosion
causation factors and their effect on well integrity.
Erosion/Corrosion
6-1-2 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Uncontrolled when Printed
The electrical circuit consists of three parts. These are shown diagrammatically
in Figure 6.1.1 and consist of:
(1) The Anode
Is the portion of the metal surface that is dissolving or corroding. For iron this
can be represented by the chemical reaction:
Fe ⇒Fe2+ + 2 electrons
(2) The Cathode
Is the portion of the metal surface at which the electrons formed by the anodic
reaction are consumed. There are many cathodic reactions that can occur depending
on the composition of the solution.
For an acid the cathodic reaction would typically be:
2H+ + 2 electrons ⇒ H2 ↑(gas)
(3) The Electrolyte
Is the electrically conductive solution such as an aqueous salt solution, in contact
with the metal surface through which the electrical current (or electrons), necessary
to support the corrosion process, flows.
In the case where there is no externally applied electrical current, the anodic
and cathodic reactions are balanced, ie there will be no ‘total’ current flow measured.
The reasons why some areas of the metal surface act as anodes whereas others
act as cathodes, are complex. A major factor is inhomogeneity in the metal surface
and/or electrolyte. In general corrosion, the anodes and cathodes will be randomly
distributed over the surface and will move during the corrosion process. In localised
corrosion, eg pitting, the anodes will be restricted to certain, small areas.
Erosion/Corrosion
August 2015 Issue 1 6-1-3
ANS-DRL-012 Well Integrity Manual
Erosion/Corrosion
6-1-4 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
where the iron sulphide scale is damaged or is not present. In practice, this type of H2S
corrosion has practical significance when H2S partial pressure is </= 0.3kPA per 0.05psi
and <pH <5.5.
Of greater importance, at the relatively low H2S levels often found in downhole fluids,
is the mechanism known as Sulphide Stress Cracking (SSC). In general, all
environments containing water and H2S are covered by the term sour. However, by
convention, in the field of corrosion in the oil and gas industry only environments where
SSC can occur, as defined in NACE Standard MR-0175 (metals for SSC and stress
corrosion cracking resistance in sour oilfield environments), are designated as being sour.
SSC occurs as a result of the entry of atomic hydrogen into the metal.
Aqueous corrosion will produce atomic hydrogen, which would normally tend to recombine
via the reaction:
2H+ 2 electrons ⇒ H + H ⇒H2 ↑ (gas)
These hydrogen gas molecules are too large to enter the metal and are thus not harmful
to it. However, hydrogen sulphide is thought to discourage the recombination of hydrogen
atoms to form H2 gas and hence encourages the entry of atomic hydrogen into the metal.
Once in the metal the atomic hydrogen will diffuse to trap sites, where it will lead to a local
increase in the stress and/or a reduction in the strength of the metal lattice. For a material
under load, there is evidence to suggest that the atomic hydrogen will concentrate near
stress concentrators and may give rise to crack initiation at such points, hence leading
to a brittle like fracture. This type of cracking can occur quite rapidly. Thus, even
if materials are only to be exposed to sour conditions for short periods of time, they must
be resistant to SSC.
3.3.3 Oxygen
The presence of dissolved oxygen can have a marked influence on the corrosion of oil field
goods. High corrosion rates can result even at relatively low concentrations of dissolved
oxygen (much less than 1ppm). Acceptable levels can go from 20ppb to 10ppb in ageing
assets. In this process iron is converted by a corrosion reaction to oxides and/or
hydroxides. The cathodic reaction in this case is:
O2 + 2H2O + 4 electrons ⇒ 4OH-
Erosion/Corrosion
August 2015 Issue 1 6-1-5
ANS-DRL-012 Well Integrity Manual
The corrosion rate in oxygenated near-neutral solutions is often controlled by the rate
at which oxygen can diffuse to the cathodic areas on the metal surface to support
the corrosion reaction. As such, the corrosion rate will be increased by flow, etc. Oxygen
corrosion is not normally a problem with produced fluids, as they contain no dissolved
oxygen. However, it can be a significant issue in water-based drilling muds, completion
brines, etc. In such cases it may be necessary to control the dissolved oxygen content,
eg using oxygen scavengers. Another area where oxygen corrosion can be a significant
issue is in injection water systems, in which case care must be taken to reduce
the oxygen to acceptable levels – eg using gas stripping or vacuum degassing.
Halide ions can cause localised corrosion damage to materials used for downhole
equipment in the form of corrosion pitting and/or crevice corrosion. In addition, they
can increase the corrosion damage resulting from the effect of other corrodents.
Halide ions can also give rise SCC of susceptible materials, principally austenitic stainless
steels. This type of cracking will normally only occur at elevated temperatures, typically
above 50°C (120°F) for austenitic stainless steels, and under the action of tensile stresses.
This can also include residual stresses from mechanical working.
SCC can be defined as crack initiation and growth in an alloy caused by the conjoint
action of corrosion and tensile stress. This cracking can occur at stresses well below
the yield strength. The mechanism by which this occurs is not fully understood, but
it requires the presence of certain specific alloy/environment combinations, eg austenitic
stainless steel in chloride containing solutions. The result of SCC is that normally ductile
materials can suffer from catastrophic, apparently brittle, failures.
Erosion/Corrosion
6-1-6 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
of oxygen ingress into the system, cracking may occur at lower temperatures.
Chloride stress corrosion cracking manifests itself as branched long cracking (usually
transgranular) which when initiated will propagate and can result in rapid failure.
3.4.4 Erosion-Corrosion
Erosion can be defined in a variety of ways, but is essentially the wastage of materials
due to the mechanical removal of the material surfaces by flowing environments. Such
wastage is most extreme when solids (such as sand) are present in the environment.
Corrosion-erosion can occur in environments that have the potential to be both erosive
and corrosive. The erosion and the corrosion can either be independent, in which case
the total wastage is the sum of the wastage produced by each mechanism in isolation,
or synergistic, in which case the total wastage is greater than the sum of the independent
processes of erosion and corrosion.
Erosion/Corrosion
August 2015 Issue 1 6-1-7
ANS-DRL-012 Well Integrity Manual
As a result of tests on carbon steel in the presence of carbon dioxide, the Erosion/Corrosion
Research Centre, University of Tulsa have identified three regimes in corrosion/erosion
wastage:
Scaling Regime
In this regime the semi-protective corrosion product layer is retained on the metal surface,
affording some protection. This is the normal situation for solids free conditions, or more
benign corrosion-erosion conditions.
Pitting Regime
In this regime the solid particles prevent scales/surface films forming at impingement
points on the metal surface, whilst scale/surface films form on the rest of the surface.
This leads to localised corrosion (pitting) damage. Corrosion in the bare impingement
areas can be significantly more aggressive in terms of metal penetration rate than for
general wastage. Some scales/surface films can act as cathodic areas, significantly
accelerating the corrosion rate in the relatively small anodic bare impingement
areas. This occurs at conditions intermediate between scaling or general wastage.
Corrosion (pitting) rates up to twice that anticipated for un-filmed conditions have been
observed. Pitting is more damaging than general corrosion, as it can result in penetration
in much shorter times and is more difficult to detect. This is an aspect that should
be borne in mind when selecting materials for downhole service, particularly corrosion-
resistant alloys.
Crevice corrosion is the localised damage that can result at a narrow gap or crevice
between two adjacent components. The local environment produced within a crevice
can be quite different to the bulk fluid environment, leading to corrosion damage
that could not be predicted from the general fluid composition. The crevice may
be between two similar materials, two different materials (in which galvanic corrosion
may also play a role), or even between a metal and a non-metal (eg elastomers).
An important factor in determining whether crevice corrosion will occur is the size of the
gap. Crevice corrosion is often exacerbated at higher temperatures. Corrosion-erosion
is sometimes confused with flow-enhanced corrosion, where the flow regime leads
to enhanced mass transport of corrosion products and reactants. Corrosion-erosion in the
absence of solids is taken to refer to enhanced wastage due to the physical rupture of the
protective, corrosion-product layer by energetic fluid flow regimes and the consequential
corrosion. The mechanical removal of inhibitor might also be defined as a form
of corrosion-erosion.
Erosion/Corrosion
6-1-8 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
4 Detection of Erosion/Corrosion
As is so often the case, erosion/corrosion is detected when a failure occurs – eg sudden
tubing to annulus communication or structural failure etc. The importance of regular
and accurate monitoring and reporting of key erosion/corrosion causal factors as described
in this section, should not be underestimated.
Well Operating Envelopes (WOE) set out the operating limits for a well and as such,
include the limits for erosion/corrosion causation factors such as H2S/CO2 etc. Where such
causal factors are known to exist, there are various tools (callipers) on the market which
can gauge the extent of any erosion/corrosion.
5 Materials Selection
Uncontrolled when Printed
6 Elastomers
6.1 Definition of Elastomers
The terms elastomer and rubber refer to polymeric materials which possess the ability
to recover from applied stress over a significant deformation range. A wide range
of elastomer material types or classes is available to cope with particular service
requirements. These classes are normally referred to by the name of the polymer which
is used, ie nitrile, Viton, Aflas, etc.
Within these classes it is possible to compound specific grades to yield individual
performance characteristics, each grade being manufactured from a mixture of ingredients
that comprises the base rubber, reinforcement (eg carbon black), curing agents, and other
additives (eg lubricants, anti-oxidants etc).
A large number of possible ingredients are available for compounding and this leads
to an infinite number of potential compounds. The art of the rubber supplier is to optimise
the properties of the compound to suit the particular performance requirements.
Erosion/Corrosion
August 2015 Issue 1 6-1-9
ANS-DRL-012 Well Integrity Manual
6.2.5 Perfluoroelastomers
Perfluoroelastomers (FFKM), (Kalrez from DuPont and Chemraz from Greene Tweed),
have exceptionally good chemical resistance and are chemically unaffected by most
oilfield environments.
Mechanical properties are not particular good, however, and anti-extrusion backup devices
should always be used.
Erosion/Corrosion
6-1-10 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Many FFKMs also show poor low temperature sealing properties and some have
limitations with amine corrosion inhibitors. Specific grade selection must take this into
account as required. Normal long-term service temperature range is 0 to 230°C
(30 to 445°F).
In addition, several plastic materials are often used as anti-extrusion backup rings,
eg PTFE, PEEK and Ryton. These are not normally subject to chemical attack in oilfield
service. These materials are not elastomeric and cannot be used as primary seals unless
they are spring or pressure energised, ie PTFE or PEEK O-rings will not seal.
6.3.1 Extrusion
Under certain combinations of temperature, pressure and seal housing dimensions,
an elastomer seal can be extruded into the gap it is meant to seal. This can cause
mechanical damage often referred to as peeling or nibbling. The simplest corrective action
for this is the use of plastic or metal anti-extrusion devices in seal design, eg PTFE or
PEEK backup rings.
Erosion/Corrosion
August 2015 Issue 1 6-1-11
ANS-DRL-012 Well Integrity Manual
Erosion/Corrosion
6-1-12 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Section 6 Chapter 2
Production Chemistry
Paragraph Page
1 Summary 6-2-1
2 Introduction 6-2-1
4 Wax 6-2-7
4.1 Description of Wax 6-2-7
4.2 Impact of Wax on Flow Characteristics of Crude Oil 6-2-8
4.3 Testing Philosophy 6-2-8
4.4 Crude Oil Pretreatments 6-2-9
5 Asphaltenes 6-2-9
5.1 Description of Asphaltenes 6-2-9
5.2 Asphaltene Precipitation 6-2-11
5.3 Determining the Risk of Asphaltene Deposition 6-2-11
5.4 Operational Variables Effecting Asphaltene Deposition 6-2-12
Production Chemistry
August 2015 Issue 1 6-2-i
ANS-DRL-012 Well Integrity Manual
Section 6 Chapter 2
Production Chemistry (cont’d)
Paragraph Page
6 Hydrates 6-2-12
6.1 Description of Gas Hydrates 6-2-12
6.2 Gas Hydrates Problems 6-2-13
6.3 Prevention Methods/Options 6-2-13
Uncontrolled when Printed
7 Emulsions 6-2-15
Table
6.2.1 Industry References 6-2-18
Figure
6.2.1 Examples of Scale Deposits 6-2-2
6.2.2 Variability of Crude Oil Pumpability Data 6-2-8
6.2.3 Hypothetical Structures for Asphaltenes Derived from
Oils Produced in Different Parts of the World 6-2-10
6.2.4 Gas Hydrate Snow 6-2-13
6.2.5 Hydrate Formation Curves 6-2-14
Production Chemistry
6-2-ii August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
1 Summary
This section describes the behaviour of production, injection or treatment fluids through
the lifecycle of a production or injection well. It explains the various production problems
which arise from interaction of production or injection fluids from scale, wax, asphaltene,
hydrates, hydrogen sulphide, water wetting and emulsions. A description of each individual
problem is detailed and the chemistry which causes them along with predictive measures
and possible solutions.
2 Introduction
Downhole production chemistry concerns the behaviour of produced, injected or treatment
fluids through the lifecycle of the production or injection well. Understanding the interaction
Uncontrolled when Printed
of fluids with the reservoir matrix as well as changes in fluids behaviour during the
production or injection process is essential to avoid production losses and maintain flow
assurance.
Although the completion engineer might not be expected to be an expert in production
chemistry, it is important to understand the basic principles of fluids behaviour and the
potential consequences of interactions and changes including:
• Formation damage due to fluids/rock interactions causing wettability changes, and fines
migration
• Mixing of incompatible fluids causing scale and emulsions
• Precipitation of solids due to changes in pressure and temperature
• Corrosivity and erosional corrosion caused by fluids acidity or high rates
In general, prevention or avoidance of production chemistry related problems
is the preferred strategy. Remedial treatments can be expensive and can lead to further
problems. Increasing use of subsea facilities with reduced access increases the cost
of remedial work.
However, there are certain instances where a remedial strategy might prove more cost
effective such as the use of scale dissolvers to manage a low calcium carbonate scaling
risk in a platform well.
In conjunction with other discipline specialists it is the completions engineer’s role to:
• Assess potential risks from available data including fluids analysis
• Generate additional data further analysis and modelling
• Assess impact of risks on production and lifecycle costs
• Determine optimum strategies/solutions to obviate or minimise impact
• Document experience and share lessons learned
To minimise the size of this document and to ensure ongoing access to regularly updated
and expanding data sources, the format provides merely an introduction and overview
of each production chemistry topic. For more detailed information, readers are directed to
the applicable contacts within Apache.
Production Chemistry
August 2015 Issue 1 6-2-1
ANS-DRL-012 Well Integrity Manual
3 Mineral Scale
3.1 Description Of Scale
Uncontrolled when Printed
Oilfield scale is generally thought of as the carbonates or sulphates of the alkaline earth
metals calcium, strontium and barium. However, complex salts of iron such as the sulphides,
hydrous oxides and carbonates may also form solid deposits that give similar problems.
As production moves into hotter and higher pressure environments, even common salt
(halite) can deposit, often in tonne quantities.
The deposition of mineral scales is dependent on a number of variables including:
(1) Degree of supersaturation (ie, concentration above the solubility limit) of scaling ions
in the water.
(2) Absolute temperature and the rate of temperature change.
(3) Degree of agitation during formation of scale crystals.
(4) Size and number of seed crystals.
(5) Presence of impurities.
(6) Change in pH of solution.
(7) Changes in pressure.
(8) Relative volumes of incompatible waters.
Common oilfield scales form in one of two ways. First, a change in conditions such
as temperature or pressure can promote carbonate scale to precipitate from a formation
water. Secondly, two incompatible waters mixing (eg a formation water with seawater)
can promote sulphate scale.
Iron scales (sulphides when production is sour, hydrous oxides when production is sweet)
often reflect corrosion in the system, with iron originating from the pipework or vessels
in the system itself. However, some formation brines naturally contain significant levels
of dissolved iron in the reduced ferrous state, which can lead to problems under some
circumstances.
Production Chemistry
6-2-2 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Drilling the first well in a new prospect can be particularly hazardous. There is no way
of knowing accurately the chemistry of the formation water that will be encountered
and often a more dense mud than is actually required will be used to reduce the chance
of kickbacks. There is, thus, an increased risk of invasion and formation damage due
to scale subsequently resulting in very high skin factors. In the extreme, productive zones
could be entirely blocked off. Obtaining representative water samples as soon as possible
are important to assess the consequences of drilling mud filtrate invasion in future wells.
Production Chemistry
August 2015 Issue 1 6-2-3
ANS-DRL-012 Well Integrity Manual
Once water is first produced, process equipment such as heat exchangers, valves,
pumps, filters and all associated pipework are at risk. Solubility limits of mineral salts
may be exceeded by changing the temperature and pressure, or by mixing incompatible
waters. The latter possibility may arise from a process operation (sand-washing,
desalting, etc) or because waters from different wells are mixed in the production system.
This last point is particularly important even if a well which has suffered sea water
breakthrough does not suffer damage, the water which that well produces is unlikely to be
compatible with pure formation water and mixing such waters in the production system is
sooner, or later, bound to cause problems.
Production Chemistry
6-2-4 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
inhibitors into production systems is commonly practised, and batch squeezes of production
wells is now a routine operation.
A good scale inhibitor must be:
• Efficient – ie it must be able to inhibit the scale in question, irrespective of the
mechanisms operating
• Stable – it must be sufficiently stable under the conditions imposed
• Compatible – it must not interfere with the action of other oilfield chemicals, nor
be affected itself by them. Compatibility in this sense is understood to include direct
chemical interaction and mechanistic antipathy
• Cost effective
In order to optimise the field performance, a chemical must be deployed correctly.
For example, injection of a scale inhibitor into a production header is wasted if it does
not contact incompatible waters before they mix in the production system. In some cases
it may be necessary to install continuous injection facilities downhole to ensure proper
deployment of scale inhibitor.
After a well suffers seawater breakthrough, scale formation could occur in the near
wellbore region, across perforations or in the tubing. While downhole injection
of an inhibitor may protect the tubing, squeeze treatments may be needed to ensure
protection of perforations and near-wellbore. In this technique production is stopped
and a concentrated solution of scale inhibitor is pumped into the well and out into
the formation. After a shut-in period of usually 6 to 24 hours, production is resumed,
and the scale inhibitor leaches back into produced fluids, giving protection against scale
formation until the scale inhibitor is exhausted, when the well is re-squeezed.
Note: Scale squeezes introduce cold fluid into a well which can cause enough
movement in the well tubulars to unseat a retrievable packer. Therefore, when
planning a scale squeeze, programme originators should be cognisant of this
effect and design the work accordingly. In some cases it has been necessary
to heat up the fluids being used for a scale squeeze, before pumping into a well.
Production Chemistry
August 2015 Issue 1 6-2-5
ANS-DRL-012 Well Integrity Manual
Production Chemistry
6-2-6 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Chelation or sequestration is the formation of soluble metal ion complexes in the presence
of substances which would normally give a precipitate. The process of chelation
is illustrated below:
Consider a system in which barium sulphate scale is present. In water/brine the solubility
of barium sulphate is in the range 5 to 50mg/l. There are, therefore, some barium ions
in solution:
BaSO4 --- > Ba2+ + SO42-
Ba2+ +L--->BaL
L = chelating agent
Calcium carbonate scale can be dissolved by hydrochloric acid treatments, however
the dissolving of barium sulphate scale remains a challenge to the industry although
some good results have been obtained with treatments using temperature and chemical
Uncontrolled when Printed
agitation.
4 Wax
Although wax rarely impacts Apache wells due to the higher temperatures, it is important
to understand the mechanisms of wax formation and deposition, the prediction of waxing
tendency and preventative and remedial options in order to contribute to the development
of a wax management strategy should it be required.
The presence of wax in a well can limit well intervention work and can affect the
functionality of key safety-critical devices – eg DHSV and xmas tree valves etc.
Production Chemistry
August 2015 Issue 1 6-2-7
ANS-DRL-012 Well Integrity Manual
In a single phase system, the presence of gas can be beneficial by reducing the viscosity,
the pour points and the gel strength. In a two phase system, the oil properties have a lesser
impact on pipeline pressure drops than the effect of flow regime.
Therefore, it is important to understand not only the characteristics of the oil, but also
the operating conditions of flow, temperature and pressure, and whether gas is present
(ie two-phase (gas/liquid) flow).
Production Chemistry
6-2-8 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
5 Asphaltenes
Uncontrolled when Printed
Production Chemistry
August 2015 Issue 1 6-2-9
ANS-DRL-012 Well Integrity Manual
As with wax and scale issues, the presence of asphaltenes can limit well intervention
work and can affect the functionality of key safety-critical devices – eg DHSV and xmas
tree valves etc. The removal of asphaltenes from a well by mechanical means is very
difficult although some success has been achieved by chemical treatments with
for example – xylene. It should be noted however that such chemicals have health
and environmental concerns when used offshore.
Uncontrolled when Printed
Figure 6.2.3 Hypothetical Structures for Asphaltenes Derived from Oils Produced
in Different Parts of the World
In crude oils, the asphaltenes are not normally present in true solution. They have a very
strong tendency to associate with themselves and resins and form aggregates.
One theory suggests that asphaltenes are present in a micellar state in which there
is a central core consisting of very high molecular weight asphaltenes with many
condensed aromatic rings. This is surrounded by a region of sheets of lower molecular
weight asphaltenes and resins strongly bound by electrostatic forces. As the distance
from the central core increases, the number of condensed aromatic rings falls and there
is a gradual transition to less polarity and less aromaticity. The result is an onion-like
structure with layers of resins surrounding further layers of resin-like asphaltenes surrounding
a central asphaltene core.
Others suggest that asphaltenes do not exist as cumbersome aggregates, but as single
asphaltene molecules stabilised in solution by resins through hydrogen bonding.
Production Chemistry
6-2-10 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
the stabilising layers to be removed can result in the unpeptized asphaltene molecules
or micelle flocculating and forming a deposit. The stabilising effect of resins can
be illustrated by the nature of the asphaltene precipitate formed when n-alkanes are added
to a crude oil. Lighter alkanes can only remove some of the lighter outer resins which more
closely resemble alkanes in structure. Longer alkane chain lengths are able to remove
more of the peptizing resins, resulting in a precipitate with a lower molecular weight. Higher
alkanes produce a precipitate containing a lower percentage of resins and consequently
less precipitate.
The nature of the crude oil itself also has an effect. An aromatic oil will be a good solvent
for the peptised asphaltenes while a paraffinic crude will be a poor solvent. The risk
of asphaltene deposition is, therefore, a result of not only the amount of asphaltene and
resin material in the oil, the but also of the solvency power of the oil for its asphaltenes.
Crudes that are aromatic in nature and have a high resin content will be less liable
to asphaltene deposition.
Asphaltene deposits can appear hard and coal-like, or more sticky and tar-like. The nature
of the deposits is determined by the crude oil and the conditions under which precipitation
occurred. For instance, if all stabilising resins are stripped away and asphaltenes
precipitate, they will be composed of the high molecular weight, highly condensed core
species. These pack closely together leading to a very hard deposit. If asphaltenes
are precipitated by lighter n-alkanes, fewer of the peptising resins may be removed.
The resultant deposit may be a very viscous sticky fluid that can contain entrained oil.
Production Chemistry
August 2015 Issue 1 6-2-11
ANS-DRL-012 Well Integrity Manual
The solvency of a crude for its asphaltenes can be determined via either a flow through
cell apparatus or using a laboratory titration technique. The main stages of assessing
the risk of asphaltene deposition in a well are:
• Sampling
• Determination of asphaltene and resin content
• Determination of the molecular weight of the asphaltene and resins
• Determination of flocculation onset
• Modelling
deposition in a well, including temperature, pressure, gas lift, acid stimulations, miscible
gas injection, electric fields and commingling different crudes. The mechanism and impact
of these are not within the scope of this section.
6 Hydrates
6.1 Description of Gas Hydrates
Hydrocarbon gas and liquid water can combine to form crystalline solids which resemble
wet snow or ice under conditions of high pressure and low temperature. Joule Thomson
cooling effects due to pressure drops are a key cause of hydrate formation in wells
and process systems particularly during shut-down or startup operations. These solids
are called gas hydrates or more correctly Natural Gas Hydrates (NGH). The crystal
structure is composed of cages of hydrogen bonded water molecules which surround
guest hydrocarbon gas molecules such as methane, ethane and propane.
Gas hydrates are unusual in that they behave as solutions of gases in crystalline solids
rather than as chemical compounds. No strong chemical bonds are formed between
the hydrocarbon and the water molecules. The ratio water molecules to gas molecules
can lie within the range 5.7 to 19. For methane hydrate (5.7 ratio), 15 wt% of the hydrate
is methane gas. NGH exists in two crystal structures type I (small cavity) and type II (large
cavity). The two structures are composed of different ratios of 12, 14 and 16-faced water
cages.
It should be noted that it is not necessary for a free gas phase to be present as long
as the hydrate formers are present in the system.
Production Chemistry
6-2-12 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Figure 6.2.4 shows hydrate snow being removed from a condensate flowline. (Photograph
courtesy of Deepstar.)
Uncontrolled when Printed
Production Chemistry
August 2015 Issue 1 6-2-13
ANS-DRL-012 Well Integrity Manual
Production Chemistry
6-2-14 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
6.4.2 Anti-agglomerates
Anti-agglomerates (AAs) also known variously as hydrate dispersants, hydrate slurry
additives and Hydrate Growth Inhibitor (HGI). AAs work by suspending hydrate crystals
in the oil or condensate phase, thus dispersing hydrates and preventing agglomerations
into solid plugs. Some AAs, such as Baker Petrolite’s RE-4136, are surfactants which
attach to hydrate particles and disperse them as they form. Other AAs, such as IFP’s
Emulfip, are emulsifiers. Emulsifying AAs function by forming a tight water-in-oil emulsion
which limits hydrate crystal size by separating the water and ultimately the hydrates into
small droplets.
Uncontrolled when Printed
AA inhibitors will be operationally more complex due to having to deal with transport
of a slurry. There will also be issues about decomposing the hydrate slurry at the
receiving facility and achieving good water/oil separation. The current AA products (Shell
chemistries) are based on quaternary ammonium chemistry and have some toxicity issues.
7 Emulsions
Emulsions can reduce production due to their high viscosities and may cause formation
damage both in production and injection wells. An emulsion is a stable dispersion
of two immiscible liquids (eg oil/water), in which one phase (dispersed phase) exists
as fine droplets suspended in the other phase (continuous phase). The water in-oil emulsion
is more common and problematic than the oil-in-water emulsions.
Production Chemistry
August 2015 Issue 1 6-2-15
ANS-DRL-012 Well Integrity Manual
Injecting brines or acid into a formation with highly surface-active crudes (asphaltic
or paraffinic) can produce severe emulsion blockage which is very difficult to treat.
Including the proper combination of anionic or nonionic surfactants in treating fluids
and using a spearhead of a suitable aromatic solvent can prevent such problems.
The compatibility studies, specified in API RP 42, should be conducted on all completion
stimulation and injection fluids to evaluate the emulsion risks.
Production Chemistry
6-2-16 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Production Chemistry
August 2015 Issue 1 6-2-17
ANS-DRL-012 Well Integrity Manual
9 Industry References
Production Chemistry
6-2-18 August 2015 Issue 1
Well Integrity Manual ANS-DRL-012
Section 7
Other Well Integrity Considerations
Paragraph Page
1 Introduction 7-1
Table
7.1 Industry References 7-4
Figure
7.1 Simple Line Diagram on Measuring Wellhead Movement 7-3
1 Introduction
The following are issues which personnel operating wells should be aware of.
2 Well Startup/Shutdown
It is important to ensure that well startup and shutdown is managed efficiently and
effectively, to avoid either damage to the well components or to the reservoir itself.
Key risk areas are:
• The formation of hydrates due to large pressure drops when opening up a well
• A rapid increase in well temperature causing a pressure increase in the annulus
(or annuli)
Uncontrolled when Printed
Lateral movement of wells should also be monitored and any excessive movement
investigated – particularly where chocks have been installed to steady conductor
movement as on Beryl Bravo, where several instances of conductor movement have
been identified in recent years. The loss of any conductor chocks should, therefore,
be reported to the Well Integrity Engineer for further investigation.
Subsea wellhead growth is the term used for axial movement of the wellhead relative
to its wellhead initial position at the mudline. Wellhead growth is caused by the forces
exerted on the growth wellhead by:
• Thermal expansion of tubulars tied back to the wellhead
• Increasing pressure within the annuli between the tubulars
Changes in temperature from initial installed conditions can cause thermal stresses in the
casing. The casing is constrained axially at the top of the cement and at the wellhead.
The temperature increase from production elongates the casing and attempts to make
Uncontrolled when Printed
the high pressure wellhead move axially upward relative to the low pressure wellhead.
If the high pressure wellhead is locked to the low pressure wellhead, this axial constraint
causes a compressive force to be generated within the casing.
Increased well temperatures also cause the expansion of fluids in the annuli between
tubulars, which results in a pressure increase. The pressure increase acts on the underside
of the casing hangers, as well as on the tubulars. The effect of the compressive stresses
in individual tubulars and pressures in the annuli exert an upward force on the wellhead.
If the production casing (attached to the high pressure wellhead housing) is not cemented
all the way to the mudline, then the high pressure wellhead can move relative to the low
pressure housing (if not latched together), rising above its initial position at the mudline.
The axial forces that act on the locking mechanism between the low pressure and high
pressure wellhead housings should be considered when choosing the rating of the locking
mechanism.
The key inputs used to predict wellhead growth are the cement tops for the casing
(defines strain in each casing string), applied tension, and the well temperature when
producing (defines the temperature change from the initial conditions that cause thermal
stresses and annulus fluid expansion). If wellhead growth occurs, it affects the flowline
and other subsea equipment on the sea floor but not attached to the well.
5 Sand Management
The presence of sand in a well can result in erosion of equipment and the failure
of pressure-controlling equipment (xmas tree valves/DHSVs etc) to close on demand.
6 Monitoring of Conductors
While having no pressure-containment purpose, conductors contribute significantly to the
structural integrity of a well and as such should be monitored for any deterioration in
condition. Subsequently, Apache Projects Group have a surveillance programme in place
to monitor conductor condition.
7 Industry References
The following industry references should be consulted for further information.
Section 8
Well Suspension, Temporary Abandonment
and Permanent Abandonment
Paragraph Page
1 Introduction 8-1
2 Definitions 8-1
Uncontrolled when Printed
Table
8.1 Suspended Subsea Well Categorisation 8-4
8.2 Industry References 8-6
1 Introduction
Quoting the requirements under the UK Design and Construction Regulations (DCR):
‘Operators are to ensure that a well is designed, modified, constructed, equipped,
operated, suspended and abandoned that:
(1) So far is as reasonably practicable there shall be no unplanned escape of fluid
the well.
In addition, Operators are required to ensure that a well is so designed and constructed
that, so far as is reasonably practicable:
(1) It can be a suspended or abandoned in a safe manner.
(2) After its suspension or abandonment, there can be no unplanned escape from
it or from the reservoir to which it led.’
Uncontrolled when Printed
It is not intended to define any specific Apache technical requirements within this section
as the quoted Oil and Gas UK – Guidelines for the Suspension and Abandonment
of Wells (‘the Guidelines’), together with other Apache policies and procedures
as referenced within this manual, provide all the guidance necessary. However, key points
of note in respect of non-technical issues – eg record keeping/reporting/well categorisation
etc, are provided within this section to ensure that all necessary legislative requirements
are met in full.
2 Definitions
Definitions are provided by the Guidelines as follows in italics.
It is important to recognise and outline key risk areas in respect of well integrity up until
the point where full abandonment is completed and a well poses no further integrity risk.
• The operating status of the Subsea Control System must be known. During ROV
inspection, valves should be functioned and tested wherever practical to do so
• The operating status of any pressure transducers must be known. In some cases
the majority of transducers may be non-operational
Work programmes will have to take these issues into account (refer to Section 5 Subsea
Well Integrity).
5 Record Keeping
The legislation requires that records of all wells are kept for a minimum of 6 months after
full abandonment. In practice, all well records are archived offsite.
Category Definition
1 The well has been sufficiently suspended that final abandonment only
Uncontrolled when Printed
6 Well Examination
The legislation (DCR Reg 18) requires that all suspended and temporarily-abandoned
wells are subject to well examination on a regular basis until permanently-abandoned
(P&A).
Apache requires that such wells are examined on a regular basis as with other wells.
The schematics described in Paragraph 5.2 should be utilised for well examination
purposes. Records of well examination activities must be kept on file.
7 Industry References
The following industry references should be consulted when planning and executing well
suspension and abandonment activities.
Appendix 8A
Sample Suspension Schematic
Uncontrolled when Printed