You are on page 1of 24

Name of Work: DEVELOPMENT OF OIL JETTY TO HANDLE LIQUID

CARGO AND SHIP BUNKERING TERMINAL AT OLD KANDLA ON


“BOT” BASIS

Concessioning Authority : Deendayal Port Trust

Concessionaire : Kandla Oil Terminal Pvt.

Independent Engineer : PROF.R.SUNDARAVADIVELU,FNAE


Institute chair professor,
Member BOG IIT Madras (2018-2019)
Member Research Council CRRI
Department of Ocean Engineering, IIT Madras

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering
IIT Madras.
Kandla Oil Terminal
Deendayal Port Trust Pvt.Ltd. 1
1. INTRODUCTION
2. SCOPE OF WORK
3. OVERALL SITE LAYOUT
4.PROJCT SITE AND LOACTION
5.PLAN OF JETTY
6.SCHEDULE OF WORK
7. DESIGN REVIEW STATUS
8. STATUS OF PROGRESS OF WORK
9. SITE PHOTOS

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Deendayal Port Trust Department of Ocean Engineering
IIT Madras.
2
Project Name Development of Oil Jetty to handle liquid cargo and Ship Bunkering
Terminal at Old on BOT basis
Concessioning Deendayal Port Trust
Authority (Client)
Concessionaire Kandla Oil Terminal Private Limited
(Contractor)
Project Start Date 11.12.2020

Project End Date 11.12.2022


IE Project Start Date 01.01.2021

IE Project End Date 11.06.2023 (Construction period 24 months plus Observation period 6 months)

No of staff as per 4 Project Engineer, 1 Senior Project Officer


contract
No of staff present at 3 Project Engineer, 1 Senior Project Officer
site
Bills claimed Total IE Bill Amount=Rs.1,30,00,000.00 plus applicable GST for 30 months.
Bill Claimed: Jan to April’2021=Rs.2,070,900.00.
Bill Submitted: May and June’2021=Rs.8,14,200.00
Invoice submitted: July 2021= Rs. 4,07,100.00
Prof. R. SUNDARAVADIVELU. F.N.A.E,,
Deendayal Port Trust Department of Ocean Engineering
IIT Madras. 3
 The scope of work for project to be carried out by the
Independent Engineer.
Role and Functions of the Independent Engineer
i. Review of the Designs and Drawings;
ii. Review, inspection and monitoring of Construction Works;
iii. Conducting Tests on completion of construction and issuing
Completion/ Provisional
Certificate;

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Department of Ocean Engineering
Deendayal Port Trust IIT Madras.
4
Site:

Construction of Approach Jetty, Berth and Tank Farm Facilities.

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Deendayal Port Trust Department of Ocean Engineering
IIT Madras.
5
View of Over all site Layout

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering Deendayal Port Trust
IIT Madras.
6
Prof. R. SUNDARAVADIVELU.
F.N.A.E, 7
Project Location
Prof. R. SUNDARAVADIVELU.
F.N.A.E, 8
 LAYOUT

Prof. R. SUNDARAVADIVELU.
F.N.A.E, 9
 Schedule of Work

Prof. R. SUNDARAVADIVELU.
F.N.A.E, 10
Sl.No Document List of documents Received mail Review time IITM KOTPL reply
Name date (days) comments sent

1 Tank 1).PESO doc-Dwg List 19.02.2021- 21 12.02.2012 -


farm 18:31 hrs
facilities 2).Schedule
Considerations

3). L2 Schedule

4).Tank farm soil


report-2017

5)Document
Transmittal-
KOTPL-TF-JY-
1001

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Deendayal Port Trust Department of Ocean Engineering
11
IIT Madras.
Sl.No Document List of documents Received mail Review time IITM comments KOTPL
Name date (days) sent date reply

2 Boundary 1).Design Basis 25.02.2021- 21 1)18.03.2021 1.Redesign


wall Report Boundary 18:41 hrs received on
documents wall 24.03.21.
for Tank 2). Co-ordinates- 2)23.04.2021
farm KOTPL-DWg- 2.Redesign
facilities BW-1001-REV- received on
0-SH-1 24.04.21
3) .Column layout-
KOTPL-DWG-
BW-1001-REV-
0-SH-2
4) .Plan, Section &
Elevations- Approved on
KOTPL-DWG- 10.05.2021
BW-1001-REV-
0-SH-3

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Department of Ocean Engineering
12
Deendayal Port Trust IIT Madras.
Sl. Document List of documents Received mail Review time IITM comments KOTPL
No Name date (days) sent date reply

2 Boundary 5) Footing & Plinth 25.02.2021- 21 1)18.03. 2021 1.Redesign


wall beam details - 18:41 hrs 2)23.04.2021 received on
documents for KOTPL-DWG- 24.03.21.
Tank farm BW-1001-REV- 2.Redesign
facilities 0-SH-4 received on
6) Pile Single column- 24.04.21
KOTPL-DWG-
BW-1001-REV-
0-SH-5
7) Pile double
column-KOTPL-
DWG-BW-1001-
REV-0-SH-6

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Department of Ocean Engineering
13
Deendayal Port Trust IIT Madras.
Sl. Document List of documents Received mail Review time IITM comments KOTPL reply
No Name date (days) sent date

2 Boundary 8) Pile design 25.02.2021- 21 1)18.03. 2021 1.Redesign


wall reference 18:41 hrs 2)23.04.2021 received on
documents document 24.03.21.
for Tank farm 9) Document 2.Redesign
facilities Transmittal- received on
KOTPL-TF-JY- 24.04.21
1002

3 Land 1).Design Report for 02.03.2021- 21 24.04.2021 -


Development Land 18:18 hrs
Design Development
Report,draw 2). KOTPL-DWG-FL-
ings for Tank 1002-Filling
farm Layout Approved on
facilities 3). KOTPL-DWG- 12.07.2021
GP-1003-Gate
Pillar

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Department of Ocean Engineering
14
Deendayal Port Trust IIT Madras.
Sl. Document List of documents Received Review IITM KOTPL
No Name mail date time comments reply
(days) sent date

3 Land 4) Amendment to 02.03.2021- 21 24.04.2021 -


Developme tank farm soil 18:18 hrs
nt Design report -
Report, KOTPL
Drawings Borehole
for Tank Location as
farm per M.K.Soil
facilities report
(KOTPL-
DWG-GL-BH-
1023)
5) Document
Transmittal-
KOTPL-TF-
JY-1003

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Deendayal Port Trust Department of Ocean Engineering
15
IIT Madras.
Sl. Document List of documents Received mail Review time IITM comments KOTPL reply
No Name date (days) sent date

4 Terminal 1) Terminal Layout - 05.04.2021- 21 24.04.2021 27.04.2021


Layout for KOTPL-DWG-TL- 21:02 hrs
Tank farm 2001
facilities 2) 2) Documental
Transmittal-
KOTPL-TF-TL-
2001
3) Compliance to 27.04.2021 04.05.2021
OISD 244
4) TERMINAL 27.04.2021 21 05.05.2021
LAYOUT-
KOTPL-DWG-TL-
2001 - Rev 1 Approved on
07.07.2021

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Deendayal Port Trust Department of Ocean Engineering
IIT Madras.
16
Sl.N Document List of Received Review IITM KOTPL reply
o Name documents mail date time comments
(days) sent date

5 Berth Layout 1) KOTPL -DWG- 29.04.2021 21 07.05.2021 26.05.2021


JY-BL-1003 - 21:02 hrs
Rev -0

2) LAYOUT- 26.05.2021 21 12.07.2021


OPTION-1 (1) 10:42
3) LAYOUT-
OPTION-2 (1)
4) LAYOUT-
OPTION-3 (1)
5) Note on
Design vessel
size (1)

Prof. R. SUNDARAVADIVELU.
F.N.A.E, 17
Sl. Document Name List of Received mail Review time IITM KOTPL reply
No documents date (days) comments sent
date

6 DBR JETTY 1) ACM- 1 JULY 21 21 27.07.2021


and KOTPL- 15:36 Hrs
FUGRO REPORT DOC-DBR-
003-REV-B
2) 20-130789-
KANDLA
PORT-RPT-
01
3) 20-130789-
KANDLA
PORT-RPT-
02 - Vol 2

7 SCHEDULE KOTPL-L2 13 AUGUST


Schedule - 21
Updated
12.8.2021

Prof. R. SUNDARAVADIVELU.
F.N.A.E, 18
• Site clearance for land fill is in progress.
• Work order for landfill work is issued
• Materials samples for landfill is taken from quarry and testing will be conducted
on 18.08.2021.

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering Deendayal Port Trust
IIT Madras.
19
Site clearance work in progress

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering Deendayal Port Trust
IIT Madras.
20
View of Site visit of IE team

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering Deendayal Port Trust
IIT Madras.
21
View of Quarry

Prof. R. SUNDARAVADIVELU. F.N.A.E,


Department of Ocean Engineering Deendayal Port Trust
IIT Madras.
22
Collection of quarry samples

23
Thank You

Prof. R. SUNDARAVADIVELU. F.N.A.E,,


Department of Ocean Engineering
Deendayal Port Trust IIT Madras.
24