You are on page 1of 145

JINKA TOWN ROAD PROJECT

Contents
 ENGINEER’S ESTIMATE
 UNIT RATE BREAKDOWNS
 SUMMARIZED INPUTS FOR BREAKDOWNS
JINKA TOWN ROAD PROJECT

ENGINEER’S ESTIMATE
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1

GRAND SUMMARY
Contract Name: Construction of JINKA TOWN ROAD PROJECT
Alternative 1

DIVISION Description DIVISION TOTAL AMOUNT ETB


1000 General 776,400.18
2000 Site Clearance 467,925.35
3000 Drainage 34,989,800.99
4000 Earthworks and Material Stabilization 13,098,611.14
5000 Subase, Road base and Gravel Wearing Course 8,967,344.35
6000 Surface Treatments and Bituminous Surfacings 18,771,183.18
7000 Rigid Pavement Not Applicable
8000 Structures 23,503,892.31
9000 Ancillary Works 352,495.40

(A) Total of Series 100,927,652.90


(B) Specified provisional sums included within the Series -
(C) Total of Series less Specified Provisional Sums (A-B) 100,927,652.90
(D) Estimated detailed Engineering Design cost (5% of A) 5,046,382.64
(E) Total of Series + Design Cost = (A+D) 105,974,035.54
(F) Add Value Added Tax (VAT) (15% of E) 15,896,105.33
(G) Grand Total (E+F) 121,870,140.87

Stadia Engineering Works Consultant Plc Page 1 of 1


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1
Pay Item No. Description Unit Quantity   Rate   Amount 
DIVISION 1000 GENERAL
1400
ACCOMMODATION, SERVICES, AND ATTENDANCE FOR THE ENGINEER'S STAFF
14.01 L. Sum                  -
Office Building Complete as specified including furniture.(Tables 1409/1 and 1409/5)
Laboratory Building Complete as specified including furniture. (Tables 1409/4 and
14.02 L. Sum                  -
1409/6)
14.03  Items measured and paid for by the Lump sum
a Office Equipment as specified as per Table 1409/2  L. Sum                  -
Laboratory Equipment as specifies as required and specified in Tables 1409/3 (a), (b), (c) 
b L. Sum                  -
and/or (d)
14.04 Services
a Fixed Costs L. Sum                  -
b Maintenance and Services for offices and laboratories. Month                  -
14.05 Vehicles for Engineer and his staff
b Vehicle Type B No.                  -
Provision of fuel and lubricants and the servicing, maintenance, and repair of
14.06
vehicles for the Engineer and his staff
b Fuel, service and maintain vehicle  , Type B Veh-mth                  -
Fuel, service and maintain vehicle in excess of 3,000 km for any vehicle in any one 
e km                  -
Calendar month, vehicle Type B
14.07 Attendance upon the Engineer and his staff
a Driver for the Engineer's vehicles Man-mth                  -
b Chainman and Laborers Man-mth                  -
c Laboratory Assistants Man-mth                  -
d Cleaners Man-mth                  -
e Watchman/Security Man-mth                  -
14.08 Additional Offices and laboratory equipment ordered by the Engineer
Prov. 
a                        -
Additional  equipment ordered by the Engineer Sum
Laboratory testing to be carried out in external laboratories as instructed by the Engineer Prov. 
b                        -
Sum
c Percentage allowed for overhead and profit on items 14.08 (a) and (b) %                        -
Building, House Type, complete, as specified, including fixtures furniture and 
14.09
equipment (Tables 1409/7 and 1409/8) 
a Type A housing No.                  -
b Type B housing No.                  -
c Type C housing (Blocks) No.                  -
d Type D housing  No.                  -
14.10 Items measured by number
a Air conditioning units No.                  -
14.11 Temporary facilities of the Engineer
a Office fully fitted, furnished and equipped including all services Month                  -
b Laboratory fully fitted, furnished and equipped including all services Month                  -
c Housing Accommodation fully fitted, furnished and equipped including all services
i Type A houses Month                  -
ii Type B houses Month                  -
d Vehicles including all operating costs
ii Type B Month                  -
e Survey Equipment  Month                  -
14.12 Communication Equipment for the Engineer 
b SIM card for mobile phone (work-related usage) No.                  -
c Airtime for work-related SIM card Month                  -
1500 TRAFFIC MANAGEMENT
15.01 Temporary Diversions
a Construction of diversions km                  -
b Maintenance of Diversion km                1.30           172,087.46           223,713.70
c Reinstatement of Diversion km                  -
d Traffic Management – full width km                  -
e Traffic Management – half-width  km                  -
1600 Social, Health, Safety and Environmental Protection and Mitigation Measures 
16.01 Preparation of Management Plans
a Site Environmental and Social Management Plan (SESMP) L. Sum                  -
b Health and Safety Management Plan (HSMP)  L. Sum                  -
16.02 Provision of Occupational Health and Safety Equipment with Worker Training L. Sum                  -
Provision of a suitably equipped and staffed Clinic in the main construction camp;
16.03 and the provision of first aid equipment, kits and medical supplies, sick bay and a L. Sum                  -
suitable ambulance service at all camps on the site 
Watering of the road under construction, temporary diversions, and access and haul
16.04 Km                4.29           128,831.35           552,686.48
roads at settlement areas 
16.05 STD and HIV/AIDS Prevention and Control Programme 

Conducting Knowledge, Attitude and Practice (KAP) surveys, preparation of action


plans on STD and HIV/AIDS alleviation measures, provision of information and Prov. 
a                        -
educational materials, counselling and testing services and establishment and Sum
training of peer educators and Anti-AIDS Committees 
b Percentage allowed for overhead and profit on item 16.05 (a) %                        -

Stadia Engineering Works Consultant Plc Page 1 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1
Pay Item No. Description Unit Quantity   Rate   Amount 
16.06 Liaison with Communities and Local Authorities 
Establishment and management of a Project Liaison Committee (PLC) including the  Prov. 
a                        -
organization of public meetings and project related notices to the Community Sum
b Percentage allowed for overhead and profit on item 16.06 (a) %                        -
16.07 Complimentary Interventions
Provision for the inclusion of complimentary interventions to the contract as agreed and  Prov. 
a                        -
directed by the Client Sum
b Percentage allowed for overhead and profit on item 16.07 (a) %                        -
1000 General -TOTAL (Carried forward to Summary)           776,400.18

DIVISION 2000 SITE CLEARANCE 
2100 Clearing and Grubbing
21.01 Clearing and Grubbing ha                9.99             46,816.85           467,925.35
21.04 Removal and storage of selected vegetation
Cost of removal, storage, protection and replanting in a protected and fenced-off area of  Prov. 
a
selected vegetation Sum
b Charge on provisional sum of item 21.04(a) %
2200
Demolition, Removal, Disposal or storage of Existing structures and installations
22.06 Removal of existing concrete and masonry structures 
a Plain concrete m3
b Reinforced concrete m3
c Masonry Structures - mortared m3
d Masonry Structures - dry m3
2000 SITE CLEARANCE -TOTAL (Carried forward to Summary)           467,925.35

DIVISION 3000 DRAINAGE
3100 OPEN DRAINS, CASCADES, BANKS, DYKES AND SUB-SOIL DRAINS
31.01 Excavation for Open Drains 
a Excavating soft material, irrespective of depth m3       22,523.52                    90.04        2,027,972.88
b Excavating Hard material to any depth m3            100.00                  200.82             20,082.37
3
31.05 Banks and dykes m                  -
3200 Culverts and Appurtenant Structures
32.01 Excavation
a Excavating soft material, irrespective of depth m3         2,151.10                  105.01           225,892.96
b Excavation in hard material irrespective of depth m3              79.42                  223.14             17,721.57
32.02 Backfilling
a Using the excavated material m3            339.68                    58.06             19,721.77
b Using  Imported selected material m3            699.34                  138.98             97,194.64
32.03 Concrete pipe culverts
a On class A Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m
b On class B Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m            148.00               3,754.49           555,665.05
32.07 Cast in situ Concrete and Form work (C-30)
a Grade C-30 concrete for culverts(box/sand), inlet and outlet structures and skewed ends including formwork, fals work, joints and class F2 surface finish
m3            215.89               5,064.46        1,093,352.41
32.1 Steel reinforcement
b High tensile steel reinforcement for culverts  t              22.65             33,583.39           760,821.76
32.12 Removing existing Structures
c Removing existing class 'B' stone masonry m3              25.00                  181.92               4,548.00
32.14 Removing and stocking existing prefabricated culverts
b Removing and stocking existing corrugated iron sheet pipe of size 1450mm m              26.00                  678.91             17,651.67
32.16 Service Ducts
a Ordinary pipes (150mm diameter steel pipes)  m            400.00                  288.04           115,215.60
b Split pipes (150mm diameter steel pipes) m
32.17 Duct marker blocks (Precast RC Blocks)  No.              32.00                  711.70             22,774.46
32.18 Chambers for ducts No.
3300 Kerbing, Channeling, Open Chutes, Downpipes, and Lining of Open Drains
33.01 Kerbing
a Concrete kerbing (precast or in-situ concrete)
i  Class 25/20 Concrete Curbing (size .45m X .17m) m       11,298.40                  400.14        4,520,954.41
ii  Class 25/20 Concrete Curbing (size .20m X .25m) m         6,188.39                  251.09        1,553,863.59
33.03 Chutes 
Concrete Chute (Class 20/20 precast concrete trapezoidal paved waterway) including 
a m
Formwork
b Masonry Stone Chute (Rectangular) m               2,623.38
33.09 Concrete lining for open drains
Cast in-situ concrete lining (Class 20/20 concrete for Rectangular open drain) including 
a m3
Formwork (with U2 surface finish)

Stadia Engineering Works Consultant Plc Page 2 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1
Pay Item No. Description Unit Quantity   Rate   Amount 
33.17 Paved Drains in Urban Areas and Reinforced Drain Covers 
a U-shaped drains in urban areas (as per Drawings)
i Stone Masonry (Class B U-shaped Masonry – Internal size 1m  depth by 0.8m width) m3               1,608.20
b Reinforced Concrete Drain Covers (as per Drawings)
i Pedestrian crossing covers (Class 25/20 RC Concrete – size 1.6mX1.0mX0.15m) No.         4,896.00                  998.70        4,889,642.09
ii Vehicle crossing covers (Class 25/20 RC Concrete – size 1.6mX0.5mX0.20m) No.
iii Vehicle crossing covers (Class 25/20 RC Concrete – size 1.6mX1.0mX0.20m) No.            544.00               1,666.95           906,822.10
3400 Stone Pitching, Masonry, Precast Concrete Block and Riprap 
34.01 Stone Pitching
b Grouted pitching
i For outlet & inlet of culverts  m2            198.00                  248.45             49,192.53
ii For Road side drains m2                  -                  248.45
iii For Ditch on benches and paved furrow ditch  m2                  285.71
34.02 Riprap 
a Packed riprap (Class 3) m3            108.10                  360.00             38,916.00
b Dumped riprap (Class 3) m3         1,679.00                  360.00           604,440.00
34.03 Stone Masonry Walls
b Cement-mortared stone walls m3         8,811.14               1,608.20      14,170,085.01
34.04 Concrete Pitching
Pre-cast concrete blocks for side walk pavement (300x300x60mm Pre-colored concrete 
c m2         5,548.98                  590.61        3,277,270.09
block on sand base including any jointing work)
3000 DRAINAGE -TOTAL (Carried forward to Summary)      34,989,800.99

DIVISION 4000 EARTHWORKS AND MATERIAL STABILIZATION
4100 Preparation of Roadbed
41.01 Preparation of Road bed and protection of earth works
b Removal of unsuitable material  m3         5,618.86                    79.80           448,379.64
41.02 Road bed preparation and compaction m3       14,533.73                    55.76           810,387.77
41.04 Investigation at deep cuts sections
Prov. 
a
Fixed cost  Sum
b Percentage allowed for overhead and profit on item 41.04(a) %
4200 Roadway and Borrow Excavation
42.01 Cut and borrow to fill 
a m3       60,645.19                  129.45        7,850,785.49
Cut to fill/embankment compaction to minimum of 95% of Modified AASHTO density,T-180
b Borrow to fill/embankment,compaction to minimum of 95% AASHTO T-180 m3            100.00                  164.44             16,444.19
c Rock fill (as specified in sub-clause 4404) m3         3,647.17                  294.17        1,072,879.34
Improved subgrade compacted to 95% of modified AASHTO density (a  compacted  
d m3         6,418.50                  176.32        1,131,705.68
thickness  not exceeding  200  mm  and  not  less  than  100mm)
42.03 Cut to spoil 
a Common (normal) excavation to spoil m3       21,861.50                    80.87        1,768,029.01
b Hard rock Excavation m3                  -
43.01 Reinstatement of borrow areas
a Rock (hard) material ha
b Common (normal or soft) material ha
44.04 Side fills or Fill-flattening m3
4000  EARTHWORKS AND MATERIAL STABILIZATION- TOTAL (Carried forward to 
     13,098,611.14
Summary)

DIVISION 5000 SUBBASE, ROAD BASE AND GRAVEL WEARING COURSE 
5100 Sub-Bases
51.01 Sub-base layer constructed from gravel or crushed stone
a Gravel sub-base (unstabilised gravel) compacted to
95% of modified AASHTO density (a  compacted  thickness  not 
i m3       12,879.13                  262.35        3,378,822.40
exceeding  200  mm  and  not  less  than  100mm)
5200 Road Bases (excluding bituminous bases)
52.01 Base layer construction
c Crushed-stone base compacted to:
100% of modified AASHTO density (a  compacted  thickness  not 
ii m3         8,558.00                  653.02        5,588,521.95
exceeding  200  mm  and  not  less  than  100mm)
5000 SUBBASE, ROAD BASE AND GRAVEL WEARING COURSE -TOTAL (Carried 
       8,967,344.35
forward to Summary)

DIVISION 6000 SURFACE TREATMENTS AND BITUMINOUS SURFACINGS 
6100 BITUMINOUS PRIME COAT
61.01 Prime coat 
a MC-30 cutback bitumen  l       48,180.00                    40.04        1,929,212.94
6200 Tack Coat
62.01 Tack coat
a Stable-grade bitumen emulsion (30%) l
6300  SURFACE SEALS
63.02 Double surface seal using
b 20 mm and 10 mm aggregate(150/200 penetration grade bitumen) m2
63.07 Variations in the rate of application of bituminous binder 
g 150/200 penetration grade bitumen l                    25.52
63.08 Variation in the rate of application of chippings

Stadia Engineering Works Consultant Plc Page 3 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1
Pay Item No. Description Unit Quantity   Rate   Amount 
b 20 mm chippings m3                  477.79
d 10 mm chippings  m3                  477.79
6400 Asphalt Road Base and Surfacing's
64.02 Asphaltic surfacing
a 50mm Asphaltic surfacing with penetration grade 85/100  bitumen m2       48,180.00                  349.56      16,841,970.25
64.05 Binder variations of 50/70 penetration grade bitumen t              25,778.25
6000 SURFACE TREATMENTS AND BITUMINOUS SURFACINGS - TOTAL (Carried 
     18,771,183.18
forward to summary)

DIVISION 8000 STRUCTURES  
8100 Foundations for Structures
81.01 Additional foundation investigations 
Prov. 
a
Fixed cost  Sum
b Percentage allowed for overhead and profit on item 81.01(a) %
81.02 Excavation of materials
a Excavating soft material, irrespective of depth m3         6,205.47                  110.11           683,275.15
b Excavation of  hard materials irrespective of depth m3         1,521.97                  240.74           366,392.51
81.05 Backfill to excavations utilizing :
a Material from the excavation m3                  -
b Imported material m3         2,886.52                  245.87           709,701.49
c Hand laid rock embankment m3
81.08 Foundation fill 
a Rock fill m3
c Compacted granular fill m3
8200 Falsework, Formwork, and Concrete Finishes
82.01 Formwork 
a  Formwork for Class F1 surface finish m2
b  Formwork for Class F2 surface finish m2         1,840.00                  851.08        1,565,982.51
8300 Steel Reinforcement for Structures
83.01 Steel reinforcement for structure 
a Steel bars
i Grade 60 Reinforcement Steel t               37.50             34,757.89        1,303,420.89
ii Grade 40 Reinforcement Steel t               62.80             33,583.39        2,109,036.91
8400 Concrete for Structures
84.01 Cast in situ concrete
a Class 30/20 concrete in all Reinforced Concrete Structures m3            690.85               3,266.49        2,256,651.36
b Class 25/20 concrete in all Reinforced Concrete Structures m3
c Class 15/20 concrete in lean concrete m3              26.95               2,570.71             69,272.29
d Cyclopean concrete underneath foundation footing m3         1,213.17               2,570.71        3,118,697.70
Bridge Bearings, Parapets, Railings, Footways, No-fines Concrete, Water-proofing
8700
and Drainage for Structures
87.03 Elastomeric Bearing No.              16.00             11,470.53           183,528.50
87.07 Concrete parapet  m              50.00                  685.12             34,256.07
87.13 Expansion joints
a Expansion joint with 20mm filler m              43.00                  365.89             15,733.06
87.16 a Joint sealant, 20mm deep grouted polysulphide sealant m              43.00                  182.87               7,863.53
87.19 Drainage pipes and weep holes
a Drainage pipes:
i Dia. 100mm PVC pipe  No.
b Weep holes
i Dia. 200mm PVC pipe m            211.20                    82.96             17,520.70
87.23 Crushed Stone in drainage Strips m3            237.60                  575.16           136,657.57
8900 Stone Masonry Structures
89.01 Stone masonry walls
b Cement-mortared stone masonry walls (Class "B" Stone Masonry) m3         6,580.77               1,660.28      10,925,902.09
81000 Mechanically Stabilized Earth
810.01 Supply and erection of MSE structure
Gabion wall facing as shown on the drawings (including rock fill, connection wires, 
a m2
Geotextile filter for drainage behind gabion wall facing, and other accessories)
b Polymeric (Geogrid) Reinforcements m2
Drainage at interface of backfill and in-situ soil (including Longitudinal Perforated Drainage 
c m2
Pipe, Transverse Outlet Pipe and geotextile filter, as shown on drawings)
810.02 Fill material in MSE structures m3                  367.29
8000 STRUCTURES - TOTAL(Carried forward to summary)      23,503,892.31

DIVISION 9000 ANCILLARY WORKS
9100 Gabions and Mattresses
91.01 Foundation trench excavation and backfilling
a In solid rock (material requiring blasting)  m3                  -                  240.74
b Excavation (common) in all other classes of material m3                  -                  110.11
c Backfilling m3
91.02 Surface preparation for bedding m2                  -                    49.17
91.03 Gabions and Mattresses                   -
a Gabion boxes                  -
Gabion boxes (galvanized, wire dia 2.7mm, box size (2x1x1) and mesh size 100x120mm, 
i m3
diaphragm spacing 1m)
Gabion boxes (galvanized, wire dia 2.7mm, box size (1.5x1x1) and mesh size 100x120mm, 
ii m3
diaphragm spacing 1m)                  -
91.04 Filter Fabric (Terram 1000 or equivalent) m2                  -

Stadia Engineering Works Consultant Plc Page 4 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 1
Pay Item No. Description Unit Quantity   Rate   Amount 
9200 DELINEATORS, MARKERS AND KILOMETRE POSTS
92.01 Delineators, markers (guide posts) and kilometer posts
b Guide Posts (reinforced concrete C- 20) No.
c Kilometer posts (reinforced concrete C- 20) No.                6.00                  803.77               4,822.60
9300 Guardrails
93.01 Galvanized guard rails on steel post m            200.00                  494.17             98,833.51
9400 ROAD SIGNS
Sign faces with painted background. Symbols, lettering and borders in Engineering
94.01 grade retro-reflective material with signboard constructed from aluminum alloy of
thickness 2mm
a Traffic signs
i Area not exceeding 2 m² m2              38.07               1,572.79             59,875.98
ii Area exceeding 2 m² m2
94.02 Sign Supports
a  Concrete Class C 20/20 No.
b  Steel  No.              47.00                  555.79             26,122.08
94.03 m3                2.82               2,662.35               7,507.82
Concrete in road sign footings including excavation and backfilling (Class 15/20)
9500 Road Traffic Markings, Road Studs and Traffic Calming
95.01 Paint (thermoplastic road marking)
a White lines (broken or unbroken) (width of 100mm) km                5.98             12,506.72             74,790.16
b Yellow lines (broken or unbroken) (width of 100mm) km                5.98             12,506.72             74,790.16
c White lettering and symbols  m2              46.00                  125.07               5,753.09
95.02 Variation in rate of application: 
a White paint l                    50.54
b Yellow paint l                    50.54
c Glass beads Kg                    35.10
95.04 Traffic Calming
a In situ asphalt Speed Bumps (Single Bump 10m wide and 0.1m thick as per drawing)  m
b In situ asphalt Rumble Strips (classification of set of 4 strips specified) m
9600 Landscaping and Grassing
96.01 Stockpiling of Topsoil m3
96.02 Preparation of areas for grassing:
a Top-soiling  m3
b Provide and apply chemical fertilizers (type) t 
96.03 Grassing: 
a Planting of grass cuttings  ha
b Seeding  ha
96.04 Replacement or replanting of trees and growth management No.
96.05 Reinstatement of construction sites
Prov. 
a
Reinstatement of camp sites Sum
Prov. 
b
Reinstatement of plant sites and storage sites Sum
c Percentage allowed for overhead and profit on item 96.05 (a) & (b) %
9900 Footways and Masonry and Concrete Safety Barriers
99.02 Safety Barrier
a Masonry m
b Precast Concrete as per drawing m
9000 ANCILLARY WORKS - TOTAL  (Carried forward to summary)           352,495.40

Stadia Engineering Works Consultant Plc Page 5 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

GRAND SUMMARY
Contract Name: Construction of JINKA TOWN ROAD PROJECT
Alternative 2

DIVISION Description DIVISION TOTAL AMOUNT ETB


1000 General 673,147.70
2000 Site Clearance 549,527.44
3000 Drainage 40,284,928.74
4000 Earthworks and Material Stabilization 19,618,815.63
5000 Subase, Road base and Gravel Wearing Course 10,575,064.16
6000 Surface Treatments and Bituminous Surfacings 20,559,471.49
7000 Rigid Pavement Not Applicable
8000 Structures 25,567,535.26
9000 Ancillary Works 439,634.82

(A) Total of Series 118,268,125.24


(B) Specified provisional sums included within the Series -
(C) Total of Series less Specified Provisional Sums (A-B) 118,268,125.24
(D) Estimated detailed Engineering Design cost (5% of A) 5,913,406.26
(E) Total of Series + Design Cost = (A+D) 124,181,531.51
(F) Add Value Added Tax (VAT) (15% of E) 18,627,229.73
(G) Grand Total (E+F) 142,808,761.23

Stadia Engineering Works Consultant Plc Page 1 of 1


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity   Rate   Amount 
DIVISION 1000 GENERAL
ACCOMMODATION, SERVICES, AND ATTENDANCE FOR THE 
1400
ENGINEER'S STAFF
Office Building Complete as specified including furniture.(Tables
14.01 L. Sum                   -
1409/1 and 1409/5)
Laboratory Building Complete as specified including furniture. (Tables
14.02 L. Sum                   -
1409/4 and 1409/6)
14.03  Items measured and paid for by the Lump sum
a Office Equipment as specified as per Table 1409/2  L. Sum                   -
Laboratory Equipment as specifies as required and specified in Tables 
b L. Sum                   -
1409/3 (a), (b), (c) and/or (d)
14.04 Services
a Fixed Costs L. Sum                   -
b Maintenance and Services for offices and laboratories. Month                   -
14.05 Vehicles for Engineer and his staff
b Vehicle Type B No.                   -
Provision of fuel and lubricants and the servicing, maintenance, and
14.06
repair of vehicles for the Engineer and his staff
b Fuel, service and maintain vehicle  , Type B Veh-mth                   -
Fuel, service and maintain vehicle in excess of 3,000 km for any vehicle in 
e km                   -
any one Calendar month, vehicle Type B
14.07 Attendance upon the Engineer and his staff
a Driver for the Engineer's vehicles Man-mth                   -
b Chainman and Laborers Man-mth                   -
c Laboratory Assistants Man-mth                   -
d Cleaners Man-mth                   -
e Watchman/Security Man-mth                   -
14.08 Additional Offices and laboratory equipment ordered by the Engineer

a Prov. Sum                         -
Additional  equipment ordered by the Engineer
Laboratory testing to be carried out in external laboratories as instructed by 
b Prov. Sum                         -
the Engineer
c Percentage allowed for overhead and profit on items 14.08 (a) and (b) %                         -
Building, House Type, complete, as specified, including fixtures 
14.09 furniture and 
equipment (Tables 1409/7 and 1409/8) 
a Type A housing No.                   -
b Type B housing No.                   -
c Type C housing (Blocks) No.                   -
d Type D housing  No.                   -
14.10 Items measured by number
a Air conditioning units No.                   -
14.11 Temporary facilities of the Engineer
a Office fully fitted, furnished and equipped including all services Month                   -
b Laboratory fully fitted, furnished and equipped including all services Month                   -
Housing Accommodation fully fitted, furnished and equipped including all 
c
services
i Type A houses Month                   -
ii Type B houses Month                   -
d Vehicles including all operating costs
ii Type B Month                   -
e Survey Equipment  Month                   -
14.12 Communication Equipment for the Engineer 
b SIM card for mobile phone (work-related usage) No.                   -
c Airtime for work-related SIM card Month                   -
1500 TRAFFIC MANAGEMENT
15.01 Temporary Diversions
a Construction of diversions km                   -
b Maintenance of Diversion km                 0.70            172,087.46            120,461.22
c Reinstatement of Diversion km                   -
d Traffic Management – full width km                   -
e Traffic Management – half-width  km                   -
Social, Health, Safety and Environmental Protection and Mitigation 
1600
Measures 
16.01 Preparation of Management Plans
a Site Environmental and Social Management Plan (SESMP) L. Sum                   -
b Health and Safety Management Plan (HSMP)  L. Sum                   -
Provision of Occupational Health and Safety Equipment with Worker
16.02 L. Sum                   -
Training
Provision of a suitably equipped and staffed Clinic in the main
construction camp; and the provision of first aid equipment, kits and
16.03 L. Sum                   -
medical supplies, sick bay and a suitable ambulance service at all
camps on the site 
Watering of the road under construction, temporary diversions, and
16.04 Km                 4.00            138,171.62            552,686.48
access and haul roads at settlement areas 
16.05 STD and HIV/AIDS Prevention and Control Programme 
Conducting Knowledge, Attitude and Practice (KAP) surveys, preparation of 
action plans on STD and HIV/AIDS alleviation measures, provision of 
a information and educational materials, counselling and testing services and  Prov. Sum                         -
establishment and training of peer educators and Anti-AIDS Committees 

b Percentage allowed for overhead and profit on item 16.05 (a) %                         -

Stadia Engineering Works Consultant Plc Page 1 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity   Rate   Amount 
16.06 Liaison with Communities and Local Authorities 
Establishment and management of a Project Liaison Committee (PLC) 
a including the organization of public meetings and project related notices to  Prov. Sum                         -
the Community
b Percentage allowed for overhead and profit on item 16.06 (a) %                         -
16.07 Complimentary Interventions
Provision for the inclusion of complimentary interventions to the contract as 
a Prov. Sum                         -
agreed and directed by the Client
b Percentage allowed for overhead and profit on item 16.07 (a) %                         -
1000 General -TOTAL (Carried forward to Summary)            673,147.70

DIVISION 2000 SITE CLEARANCE 
2100 Clearing and Grubbing
21.01 Clearing and Grubbing ha 11.74              46,816.85            549,527.44
21.04 Removal and storage of selected vegetation
Cost of removal, storage, protection and replanting in a protected and 
a Prov. Sum
fenced-off area of selected vegetation
b Charge on provisional sum of item 21.04(a) %
Demolition, Removal, Disposal or storage of Existing structures and
2200
installations
22.06 Removal of existing concrete and masonry structures 
3
a Plain concrete m
b Reinforced concrete m3
c Masonry Structures - mortared m3
d Masonry Structures - dry m3
2000 SITE CLEARANCE -TOTAL (Carried forward to Summary)            549,527.44

DIVISION 3000 DRAINAGE
3100
OPEN DRAINS, CASCADES, BANKS, DYKES AND SUB-SOIL DRAINS
31.01 Excavation for Open Drains 
3
a Excavating soft material, irrespective of depth m 27,916.60                     90.04         2,513,555.06
b Excavating Hard material to any depth m3 291.91                   200.82              58,621.52
3
31.05 Banks and dykes m -
3200 Culverts and Appurtenant Structures
32.01 Excavation
3
a Excavating soft material, irrespective of depth m 1,985.69                   105.01            208,522.76
b Excavation in hard material irrespective of depth m3 39.71                   223.14                8,860.79
32.02 Backfilling
a Using the excavated material m3 420.40                     58.06              24,408.37
3
b Using  Imported selected material m 1,373.72                   138.98            190,919.77
32.03 Concrete pipe culverts
a On class A Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m
b On class B Bedding
i 36'' diameter R.C pipe m
ii 42'' diameter R.C pipe m
iii 48'' diameter R.C pipe m 201.00                3,754.49            754,653.22
32.07 Cast in situ Concrete and Form work (C-30)
a Grade C-30 concrete for culverts(box/sand), inlet and outlet structures and skewed ends including formwork, fals work, joints and class F2 surface finish
m3 274.11                5,064.46         1,388,231.98
32.1 Steel reinforcement
b High tensile steel reinforcement for culverts  t 27.94              33,583.39            938,462.21
32.12 Removing existing Structures
c Removing existing class 'B' stone masonry m3 25.00                   181.92                4,548.00
32.14 Removing and stocking existing prefabricated culverts
b Removing and stocking existing corrugated iron sheet pipe of size 1450mm m 26.00                   678.91              17,651.67
32.16 Service Ducts
a Ordinary pipes (150mm diameter steel pipes)  m 425.00                   288.04            122,416.57
b Split pipes (150mm diameter steel pipes) m
32.17 Duct marker blocks (Precast RC Blocks)  No. 34.00                   711.70              24,197.87
32.18 Chambers for ducts No.
Kerbing, Channeling, Open Chutes, Downpipes, and Lining of Open
3300
Drains
33.01 Kerbing
a Concrete kerbing (precast or in-situ concrete)
i  Class 25/20 Concrete Curbing (size .45m X .17m) m 13,018.40                   400.14         5,209,197.14
ii  Class 25/20 Concrete Curbing (size .20m X .25m) m 6,830.00                   251.09         1,714,966.51
33.03 Chutes 
Concrete Chute (Class 20/20 precast concrete trapezoidal paved waterway) 
a m
including Formwork
b Masonry Stone Chute (Rectangular) m                2,623.38
33.09 Concrete lining for open drains
Cast in-situ concrete lining (Class 20/20 concrete for Rectangular open 
a m3
drain) including Formwork (with U2 surface finish)

Stadia Engineering Works Consultant Plc Page 2 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity   Rate   Amount 
33.17 Paved Drains in Urban Areas and Reinforced Drain Covers 
a U-shaped drains in urban areas (as per Drawings)
Stone Masonry (Class B U-shaped Masonry – Internal size 1m  depth by  3
i m                1,608.20
0.8m width)
b Reinforced Concrete Drain Covers (as per Drawings)
Pedestrian crossing covers (Class 25/20 RC Concrete – size 
i No. 5,940.00                   998.70         5,932,286.36
1.6mX1.0mX0.15m)
Vehicle crossing covers (Class 25/20 RC Concrete – size 
ii No.
1.6mX0.5mX0.20m)
Vehicle crossing covers (Class 25/20 RC Concrete – size 
iii No. 660.00                1,666.95         1,100,188.58
1.6mX1.0mX0.20m)
3400 Stone Pitching, Masonry, Precast Concrete Block and Riprap 
34.01 Stone Pitching
b Grouted pitching
i For outlet & inlet of culverts  m2 343.07                   248.45              85,235.47
2
ii For Road side drains m -                   248.45
iii For Ditch on benches and paved furrow ditch  m2                   285.71
34.02 Riprap 
3
a Packed riprap (Class 3) m 108.10                   360.00              38,916.00
b Dumped riprap (Class 3) m3 1,679.00                   360.00            604,440.00
34.03 Stone Masonry Walls
b Cement-mortared stone walls m3 9,433.42                1,608.20       15,170,836.39
34.04 Concrete Pitching
Pre-cast concrete blocks for side walk pavement (300x300x60mm Pre-
c m2 7,066.98                   590.61         4,173,812.51
colored concrete block on sand base including any jointing work)
3000 DRAINAGE -TOTAL (Carried forward to Summary)       40,284,928.74

DIVISION 4000 EARTHWORKS AND MATERIAL STABILIZATION
4100 Preparation of Roadbed
41.01 Preparation of Road bed and protection of earth works
b Removal of unsuitable material  m3 74,506.24                     79.80         5,945,531.88
41.02 Road bed preparation and compaction m3 17,882.69                     55.76            997,122.86
41.04 Investigation at deep cuts sections
a Prov. Sum
Fixed cost 
b Percentage allowed for overhead and profit on item 41.04(a) %
4200 Roadway and Borrow Excavation
42.01 Cut and borrow to fill 
Cut to fill/embankment compaction to minimum of 95% of Modified 
a
AASHTO density,T-180 m3 48,499.70                   129.45         6,278,498.27
b Borrow to fill/embankment,compaction to minimum of 95% AASHTO T-180 m3 100.00                   164.44              16,444.19
3
c Rock fill (as specified in sub-clause 4404) m 4,828.32                   294.17         1,420,335.53
Improved subgrade compacted to 95% of modified AASHTO density (a  
3
d compacted  thickness  not exceeding  200  mm  and  not  less  than   m 7,915.50                   176.32         1,395,655.73
100mm)
42.03 Cut to spoil 
a Common (normal) excavation to spoil m3 44,083.68                     80.87         3,565,227.18
b Hard rock Excavation m3 44,083.68                   211.13
43.01 Reinstatement of borrow areas
a Rock (hard) material ha
b Common (normal or soft) material ha
3
44.04 Side fills or Fill-flattening m
4000  EARTHWORKS AND MATERIAL STABILIZATION- TOTAL 
      19,618,815.63
(Carried forward to Summary)

DIVISION 5000 SUBBASE, ROAD BASE AND GRAVEL WEARING 
COURSE 
5100 Sub-Bases
51.01 Sub-base layer constructed from gravel or crushed stone
a Gravel sub-base (unstabilised gravel) compacted to
95% of modified AASHTO density (a  compacted  thickness  not 
i m3 15,189.00                   262.35         3,984,813.68
exceeding  200  mm  and  not  less  than  100mm)
5200 Road Bases (excluding bituminous bases)
52.01 Base layer construction
c Crushed-stone base compacted to:
100% of modified AASHTO density (a  compacted  thickness  not 
ii m3 10,092.00                   653.02         6,590,250.47
exceeding  200  mm  and  not  less  than  100mm)
5000 SUBBASE, ROAD BASE AND GRAVEL WEARING COURSE -
      10,575,064.16
TOTAL (Carried forward to Summary)

DIVISION 6000 SURFACE TREATMENTS AND BITUMINOUS 
SURFACINGS 
6100 BITUMINOUS PRIME COAT
61.01 Prime coat 
a MC-30 cutback bitumen  l 52,770.00                     40.04         2,113,004.70
6200 Tack Coat
62.01 Tack coat
a Stable-grade bitumen emulsion (30%) l
6300  SURFACE SEALS
63.02 Double surface seal using
2
b 20 mm and 10 mm aggregate(150/200 penetration grade bitumen) m
63.07 Variations in the rate of application of bituminous binder 
g 150/200 penetration grade bitumen l                     25.52

Stadia Engineering Works Consultant Plc Page 3 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity   Rate   Amount 
63.08 Variation in the rate of application of chippings
b 20 mm chippings m3                   477.79
3
d 10 mm chippings  m                   477.79
6400 Asphalt Road Base and Surfacing's
64.02 Asphaltic surfacing
2
a 50mm Asphaltic surfacing with penetration grade 85/100  bitumen m 52,770.00                   349.56       18,446,466.79
64.05 Binder variations of 50/70 penetration grade bitumen t               25,778.25
6000 SURFACE TREATMENTS AND BITUMINOUS SURFACINGS - 
      20,559,471.49
TOTAL (Carried forward to summary)

DIVISION 8000 STRUCTURES  
8100 Foundations for Structures
81.01 Additional foundation investigations 
a Prov. Sum
Fixed cost 
b Percentage allowed for overhead and profit on item 81.01(a) %
81.02 Excavation of materials
a Excavating soft material, irrespective of depth m3 8,186.36                   110.11            901,387.68
3
b Excavation of  hard materials irrespective of depth m 1,521.97                   240.74            366,392.51
81.05 Backfill to excavations utilizing :
3
a Material from the excavation m -
b Imported material m3 3,642.52                   245.87            895,577.33
c Hand laid rock embankment m3
81.08 Foundation fill 
3
a Rock fill m
3
c Compacted granular fill m
8200 Falsework, Formwork, and Concrete Finishes
82.01 Formwork 
a  Formwork for Class F1 surface finish m2
b  Formwork for Class F2 surface finish m2 1,840.00                   851.08         1,565,982.51
8300 Steel Reinforcement for Structures
83.01 Steel reinforcement for structure 
a Steel bars
i Grade 60 Reinforcement Steel t  37.50              34,757.89         1,303,420.89
ii Grade 40 Reinforcement Steel t  62.80              33,583.39         2,109,036.91
8400 Concrete for Structures
84.01 Cast in situ concrete
3
a Class 30/20 concrete in all Reinforced Concrete Structures m 690.85                3,266.49         2,256,651.36
b Class 25/20 concrete in all Reinforced Concrete Structures m3
3
c Class 15/20 concrete in lean concrete m 26.95                2,570.71              69,272.29
d Cyclopean concrete underneath foundation footing m3 909.88                2,570.71         2,339,023.27
Bridge Bearings, Parapets, Railings, Footways, No-fines Concrete,
8700
Water-proofing and Drainage for Structures
87.03 Elastomeric Bearing No. 16.00              11,470.53            183,528.50
87.07 Concrete parapet  m 50.00                   685.12              34,256.07
87.13 Expansion joints
a Expansion joint with 20mm filler m 43.00                   365.89              15,733.06
87.16 a Joint sealant, 20mm deep grouted polysulphide sealant m 43.00                   182.87                7,863.53
87.19 Drainage pipes and weep holes
a Drainage pipes:
i Dia. 100mm PVC pipe  No.
b Weep holes
i Dia. 200mm PVC pipe m 211.20                     82.96              17,520.70
3
87.23 Crushed Stone in drainage Strips m 237.60                   575.16            136,657.57
8900 Stone Masonry Structures
89.01 Stone masonry walls
b Cement-mortared stone masonry walls (Class "B" Stone Masonry) m3 8,050.00                1,660.28       13,365,231.09
81000 Mechanically Stabilized Earth
810.01 Supply and erection of MSE structure
Gabion wall facing as shown on the drawings (including rock fill, connection 
2
a wires, Geotextile filter for drainage behind gabion wall facing, and other  m
accessories)
b Polymeric (Geogrid) Reinforcements m2
Drainage at interface of backfill and in-situ soil (including Longitudinal 
2
c Perforated Drainage Pipe, Transverse Outlet Pipe and geotextile filter, as  m
shown on drawings)
810.02 Fill material in MSE structures m3                   367.29
8000 STRUCTURES - TOTAL(Carried forward to summary)       25,567,535.26

DIVISION 9000 ANCILLARY WORKS
9100 Gabions and Mattresses
91.01 Foundation trench excavation and backfilling
a In solid rock (material requiring blasting)  m3 -                   240.74
3
b Excavation (common) in all other classes of material m -                   110.11
c Backfilling m3
91.02 Surface preparation for bedding m2 -                     49.17
91.03 Gabions and Mattresses  -
a Gabion boxes -
Gabion boxes (galvanized, wire dia 2.7mm, box size (2x1x1) and mesh size 
i m3
100x120mm, diaphragm spacing 1m)
Gabion boxes (galvanized, wire dia 2.7mm, box size (1.5x1x1) and mesh 
ii m3
size 100x120mm, diaphragm spacing 1m) -

Stadia Engineering Works Consultant Plc Page 4 of 5
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Pay Item No. Description Unit Quantity   Rate   Amount 
2
91.04 Filter Fabric (Terram 1000 or equivalent) m -
9200 DELINEATORS, MARKERS AND KILOMETRE POSTS
92.01 Delineators, markers (guide posts) and kilometer posts
b Guide Posts (reinforced concrete C- 20) No.
c Kilometer posts (reinforced concrete C- 20) No. 6.00                   803.77                4,822.60
9300 Guardrails
93.01 Galvanized guard rails on steel post m 360.00                   494.17            177,900.32
9400 ROAD SIGNS
Sign faces with painted background. Symbols, lettering and borders in
94.01 Engineering grade retro-reflective material with signboard
constructed from aluminum alloy of thickness 2mm
a Traffic signs
i Area not exceeding 2 m² m2 35.24                1,572.79              55,417.13
2
ii Area exceeding 2 m² m
94.02 Sign Supports
a  Concrete Class C 20/20 No.
b  Steel  No. 44.00                   555.79              24,454.72
Concrete in road sign footings including excavation and backfilling 3
94.03 m 2.61                2,662.35                6,948.73
(Class 15/20)
9500 Road Traffic Markings, Road Studs and Traffic Calming
95.01 Paint (thermoplastic road marking)
a White lines (broken or unbroken) (width of 100mm) km 6.60              12,506.72              82,544.32
b Yellow lines (broken or unbroken) (width of 100mm) km 6.60              12,506.72              82,544.32
2
c White lettering and symbols  m 40.00                   125.07                5,002.69
95.02 Variation in rate of application: 
a White paint l                     50.54
b Yellow paint l                     50.54
c Glass beads Kg                     35.10
95.04 Traffic Calming
In situ asphalt Speed Bumps (Single Bump 10m wide and 0.1m thick as per 
a m
drawing) 
b In situ asphalt Rumble Strips (classification of set of 4 strips specified) m
9600 Landscaping and Grassing
3
96.01 Stockpiling of Topsoil m
96.02 Preparation of areas for grassing:
a Top-soiling  m3
b Provide and apply chemical fertilizers (type) t 
96.03 Grassing: 
a Planting of grass cuttings  ha
b Seeding  ha
96.04 Replacement or replanting of trees and growth management No.
96.05 Reinstatement of construction sites
a Prov. Sum
Reinstatement of camp sites
b Prov. Sum
Reinstatement of plant sites and storage sites
c Percentage allowed for overhead and profit on item 96.05 (a) & (b) %
9900 Footways and Masonry and Concrete Safety Barriers
99.02 Safety Barrier
a Masonry m
b Precast Concrete as per drawing m
9000 ANCILLARY WORKS - TOTAL  (Carried forward to summary)            439,634.82

Stadia Engineering Works Consultant Plc Page 5 of 5
JINKA TOWN ROAD PROJECT

UNIT RATE BREAKDOWNS


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No : 

Activity No :  a  Category: Sub-Component  ADP=  March 21, 2017


Activity Name:  Borrow Material Production Scope: Material Production                       686.00   M3   Result:                34.74   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.IV 1 8.00 102.31 818.51 81.08
2 Helper II 1 8.00 23.87 190.99 18.92
3
4
Labour Sub-total              1,009.49                      -                                    8.64 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2
3
Equipment Sub-total          2,080.71             10,672.75           5,972.91                                91.36 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            11,682.24           5,972.91 

Average daily production (ADP) = 686.00 M3


Activity operational cost per crew day / ADP = 17.03 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 22.99 Birr/m3
Activity replacement cost per crew day / ADP = 8.71 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 11.75 Birr/m3
Total Activity Unit Rate =                        34.74 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 1 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  b Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Select Material Production Scope: Material Production                       560.00   M3   Result:                42.56   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.IV 1 8.00 102.31 818.51 81.08
2 Helper II 1 8.00 23.87 190.99 18.92
3
4
Labour Sub-total              1,009.49                      -                                    8.64 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2
3
Equipment Sub-total          2,080.71             10,672.75           5,972.91                                91.36 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            11,682.24           5,972.91 

Average daily production (ADP) = 560.00 M3


Activity operational cost per crew day / ADP = 20.86 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 28.16 Birr/m3
Activity replacement cost per crew day / ADP = 10.67 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 14.40 Birr/m3
Total Activity Unit Rate =                        42.56 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 2 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  c Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Quarry Rock Production Scope: Material Production                       480.00   M3   Result:              187.73   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Quarry Foreman 1 8.00 56.84 454.73 11.35
2 St.eq.opI 1 8.00 22.74 181.89 4.54
3 Powder Man I 1 8.00 30.69 245.55 6.13
4 Equ.op.IV 1 8.00 102.31 818.51 20.43
5 Helper I 1 8.00 18.76 150.06 3.75
6 Labor Foreman 1 8.00 17.05 136.42 3.41
7 Labour I 20 160.00 12.62 2,018.99 50.40
8
Labour Sub-total              4,006.15                      -                                    7.87 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 37.63
2 Air Compressor 600CFM 16.00 377.78 18.65 396.43 6,044.45 298.41 21.31
3 Drill, Self Prop, Crawler Type 4500 Kg 16.00 727.88 599.01 1,326.89 11,646.14 9,584.13 41.06
4 Hand Tools
Equipment Sub-total          3,804.03             28,363.34         15,855.44                                55.73 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Ammonium Nitrate Kg 60.00 180.00 10,800.00 58.31
2 Power Jell Kg 90.00 2.25 202.50 1.09
3 Electrical Detonator No 65.00 16.00 1,040.00 5.61
4 Cord m 16.00 180.00 2,880.00 15.55
5 Connecting wire m 12.00 300.00 3,600.00 19.44
6 Bits & Drills No
Material Sub-total            18,522.50                      -                                  36.40 
Total Cost per crew day            50,891.99         15,855.44 

Average daily production (ADP) = 480.00 M3


Activity operational cost per crew day / ADP = 106.02 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 143.13 Birr/m3
Activity replacement cost per crew day / ADP = 33.03 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 44.59 Birr/m3
Total Activity Unit Rate =                      187.73 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 3 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  d Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Scope: Material Production                       240.00   M3   Result:              442.71   Birr/m3 
Rock Crushing -Surface & concrete  Aggregate

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 22.15
2 Equ.op.III 1 2.00 39.79 79.58 2.42
3 Driver III 3 20.00 36.38 727.56 22.15
4 St.eq.opI 1 8.00 22.74 181.89 5.54
5 Mechanic II 1 8.00 51.16 409.25 12.46
6 Helper I 1 8.00 18.76 150.06 4.57
7 Labour I 10 80.00 12.62 1,009.49 30.73
Labour Sub-total              3,285.40                      -                                    5.62 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 1.99
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 27,459.56 18,558.17 8,901.40 62.35
3 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 3.29
4 Dump truck,6*4 (12m3) 12M3 20.00 481.75 104.04 104.04 9,635.00 2,080.75 32.37
Equipment Sub-total        30,433.90             29,764.41         12,281.19                                50.88 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Stone M 106.02 33.03 240.00 25,445.99 7,927.72 100.00
2 - -
Material Sub-total            25,445.99           7,927.72                                43.50 
Total Cost per crew day            58,495.81         20,208.91 

Average daily production (ADP) = 240.00 M3


Activity operational cost per crew day / ADP = 243.73 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 329.04 Birr/m3
Activity replacement cost per crew day / ADP = 84.20 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 113.68 Birr/m3
Total Activity Unit Rate =                      442.71 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 4 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  e Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Rock Crushing -Base Aggregate Scope: Material Production                       260.00   M3   Result:              435.35   Birr/m3 

 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 17.19
2 Equ.op.III 3 24.00 39.79 954.93 22.56
3 Driver III 3 22.00 36.38 800.32 18.90
3 St.eq.opI 1 8.00 22.74 181.89 4.30
4 Mechanic II 1 8.00 51.16 409.25 9.67
5 Helper I 1 8.00 18.76 150.06 3.54
6 Labour I 10 80.00 12.62 1,009.49 23.85
Labour Sub-total              4,233.51                      -                                    6.76 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 1.08 591.65 496.23 1,087.88 640.96 537.58 2.08
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 3,432.45 18,558.17 8,901.40 60.14
3 Loader, Crawler 2-2.5 M3 1.08 979.60 802.82 1,782.42 1,061.23 869.72 3.44
4 Dump truck,6*4 (12m3) 12M3 22.00 481.75 104.04 585.79 10,598.50 2,288.82 34.35
Equipment Sub-total          6,888.53             30,858.85         12,597.52                                49.25 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Stone M3 106.02 33.03 260.00 27,566.49 8,588.37 100.00
2
3
Material Sub-total            27,566.49           8,588.37                                43.99 
Total Cost per crew day            62,658.85         21,185.89 

Average daily production (ADP) = 260.00 M3


Activity operational cost per crew day / ADP = 241.00 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 325.34 Birr/m3
Activity replacement cost per crew day / ADP = 81.48 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 110.00 Birr/m3
Total Activity Unit Rate =                      435.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 5 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  f Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Rock Crushing -Sub Base Aggregate Scope: Material Production                       280.00   M3   Result:              413.42   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 21.38
2 Equ.op.III 1 2.33 39.79 92.84 2.73
3 Driver III 3 22.89 36.38 832.66 24.46
3 St.eq.opI 1 8.00 22.74 181.89 5.34
4 Mechanic II 1 8.00 51.16 409.25 12.02
5 Helper I 1 8.00 18.76 150.06 4.41
6 Labour I 10 80.00 12.62 1,009.49 29.66
7
Labour Sub-total              3,403.76                      -                                    5.31 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 2.33 591.65 496.23 1,087.88 1,380.52 1,157.87 4.46
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 3,432.45 18,558.17 8,901.40 59.93
3 Dump truck,6*4 (12m3) 12M3 22.89 481.75 104.04 585.79 11,026.72 2,381.30 35.61
Equipment Sub-total          5,106.11             30,965.40         12,440.57                                48.34 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Stone M3 106.02 33.03 280.00 29,686.99 9,249.01 100.00
Material Sub-total            29,686.99           9,249.01                                46.35 
Total Cost per crew day            64,056.16         21,689.58                              100.00 

Average daily production (ADP) = 280.00 M3


Activity operational cost per crew day / ADP = 228.77 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 308.84 Birr/m3
Activity replacement cost per crew day / ADP = 77.46 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 104.57 Birr/m3
Total Activity Unit Rate =                      413.42 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 30% void & waste for quarry rock hauling calculation
* 0.5Km free hauling distance for quarry rock hauling operation

Stadia Engineering Works Consultant Plc Page 6 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  g Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Hot Mix Production (AC - 60/70) Scope: Material Production                       200.00   M3   Result:           4,439.00   Birr/m3 
*(Central Mix Plant)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Batch plant Sup. 1 8.00 86.40 691.19 15.98
2 Equ.op.III 1 4.00 39.79 159.15 3.68
3 Welder II 1 8.00 45.47 363.78 8.41
4 Mechanic III 1 8.00 71.62 572.96 13.25
5 Elec. III 1 8.00 71.62 572.96 13.25
6 Helper II 5 40.00 23.87 954.93 22.08
7 Labour I 10 80.00 12.62 1,009.49 23.34
Labour Sub-total              4,324.46                      -                                    0.69 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 4,351.53 2,366.60 1,984.93 9.67
2 Asphalt Plant 130-150TPH 8.00 2,669.98 435.31 24,842.31 21,359.81 3,482.50 87.24
3 AC Welder, Diesel 300-400AMP 4.00 189.56 16.19 823.00 758.24 64.76 3.10
Equipment Sub-total        30,016.84             24,484.65           5,532.18                                  3.90 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Bitumen - AC-60/70 Kg 19.10 - 27,600.00 527,022.00 - 88.08
2 Chip Aggregate M3 262.13 91.80 272.00 71,298.39 24,968.25 11.92
Material Sub-total          598,320.39         24,968.25                                95.41 
Total Cost per crew day          627,129.50         30,500.43 

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 3,135.65 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 4,233.12 Birr/m3
Activity replacement cost per crew day / ADP = 152.50 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 205.88 Birr/m3
Total Activity Unit Rate =                   4,439.00 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 7 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  h Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Hot Mix Production (AC - 80/100) Scope: Material Production                       200.00   M3   Result:           5,605.38   Birr/m3 
*(Central Mix Plant)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Batch plant Sup. 1 8.00 86.40 691.19 16.28
2 Equ.op.III 1 2.00 39.79 79.58 1.87
3 Welder II 1 8.00 45.47 363.78 8.57
4 Mechanic III 1 8.00 71.62 572.96 13.50
5 Elec. III 1 8.00 71.62 572.96 13.50
6 Helper II 5 40.00 23.87 954.93 22.50
7 Labour I 10 80.00 12.62 1,009.49 23.78
Labour Sub-total              4,244.88                      -                                    0.53 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 2.00 591.65 496.23 2,175.77 1,183.30 992.46 11.89
2 Asphalt Plant 130-150TPH 3.00 2,669.98 435.31 9,315.87 8,009.93 1,305.94 80.49
3 AC Welder, Diesel 300-400AMP 4.00 189.56 16.19 823.00 758.24 64.76 7.62
Equipment Sub-total        12,314.63               9,951.47           2,363.16                                  1.24 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Bitumen - AC-80/100 Kg 26.00 - 27,600.00 717,600.00 - 90.96
2 Chip Aggregate M3 262.13 91.80 272.00 71,298.39 24,968.25 9.04
Material Sub-total          788,898.39         24,968.25                                98.23 
Total Cost per crew day          803,094.74         27,331.41 

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 4,015.47 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 5,420.89 Birr/m3
Activity replacement cost per crew day / ADP = 136.66 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 184.49 Birr/m3
Total Activity Unit Rate =                   5,605.38 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 8 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  i Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Pipe Production(Dia.36) Scope: Material Production                         15.00   Each   Result:           1,419.03   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason II 2 16.00 32.40 518.39 16.43
2 St.eq.opI 1 8.00 22.74 181.89 5.76
3 Bar Sett.I 2 16.00 30.69 491.11 15.56
4 Helper I 3 24.00 18.76 450.18 14.27
5 Labour I 15 120.00 12.62 1,514.24 47.98
Labour Sub-total              3,155.81                      -                                  20.52 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 4.00 42.64 8.28 50.92 170.56 33.10 65.48
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 34.52
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total                 260.48              186.84                                  1.69 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.35 6,690.06 - 55.94
2 Binding wire Kg 32.00 6.25 200.00 - 1.67
3 Cement Quintal 255.78 14.58 3,729.27 - 31.18
4 Sand m3 461.54 1.62 747.69 - 6.25
3
5 Crushed Aggregate M 243.73 84.20 2.43 592.27 204.62 4.95
Material Sub-total            11,959.29              204.62                                77.78 
Total Cost per crew day            15,375.58              391.46 

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,025.04 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,383.80 Birr/each
Activity replacement cost per crew day / ADP = 26.10 Birr/each
Total Repl. unit cost including 35% overhead & profit = 35.23 Birr/each
Total Activity Unit Rate =                   1,419.03 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 9 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  j Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Pipe Production(Dia.42) Scope: Material Production                         15.00   Each   Result:           1,908.02   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason II 3 24.00 32.40 777.58 17.02
2 St.eq.opI 1 8.00 22.74 181.89 3.98
3 Bar Sett.I 3 24.00 30.69 736.66 16.13
4 Helper I 4 32.00 18.76 600.24 13.14
5 Labour I 23 180.00 12.62 2,271.36 49.73
Labour Sub-total              4,567.74                      -                                  22.02 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 4.00 42.64 8.28 50.92 170.56 33.10 65.48
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 34.52
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total                 260.48              186.84                                  1.26 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.47 8,948.67 - 56.21
2 Binding wire Kg 32.00 12.50 400.00 - 2.51
3 Cement Quintal 255.78 18.90 4,834.24 - 30.37
4 Sand m3 461.54 2.10 969.23 - 6.09
3
5 Crushed Aggregate M 243.73 84.20 3.15 767.76 265.24 4.82
Material Sub-total            15,919.90              265.24                                76.73 
Total Cost per crew day            20,748.12              452.08 

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,383.21 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,867.33 Birr/each
Activity replacement cost per crew day / ADP = 30.14 Birr/each
Total Repl. unit cost including 35% overhead & profit = 40.69 Birr/each
Total Activity Unit Rate =                   1,908.02 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 10 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  k Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Pipe Production(Dia.48) Scope: Material Production                         15.00   Each   Result:           2,704.24   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason II 4 32.00 32.40 1,036.78 16.91
2 St.eq.opI 1 8.00 22.74 181.89 2.97
3 Bar Sett.I 4 32.00 30.69 982.21 16.02
4 Helper I 6 48.00 18.76 900.36 14.69
5 Labour I 30 240.00 12.62 3,028.48 49.41
Labour Sub-total              6,129.72                      -                                  20.76 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 5.00 42.64 8.28 50.92 213.21 41.38 70.34
2 Concrete Vibrator 5 HP 4.00 22.48 2.43 24.91 89.91 9.74 29.66
3 Pipe Molds - 120.00 - 1.20 144.00
4 Hand Tools
5
Equipment Sub-total                 303.12              195.12                                  1.03 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.78 14,815.34 - 64.13
2 Binding wire Kg 32.00 12.50 400.00 - 1.73
3 Cement Quintal 255.78 22.68 5,801.09 - 25.11
4 Sand m3 461.54 2.52 1,163.08 - 5.03
3
5 Crushed Aggregate M 243.73 84.20 3.78 921.31 318.29 3.99
Material Sub-total            23,100.81              318.29                                78.22 
Total Cost per crew day            29,533.66              513.41 

Average daily production (ADP) = 15.00 Each


Activity operational cost per crew day / ADP = 1,968.91 Birr/each
Total Oper. unit cost including 35% overhead & profit = 2,658.03 Birr/each
Activity replacement cost per crew day / ADP = 34.23 Birr/each
Total Repl. unit cost including 35% overhead & profit = 46.21 Birr/each
Total Activity Unit Rate =                   2,704.24 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 11 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  l Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Guide Post Production Scope: Material Production                         30.00   Each   Result:              395.53   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total              1,077.70                      -                                  12.45 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3
4
Equipment Sub-total                 130.24                21.42                                  1.51 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.91 420.92 5.65
2 Cement Quintal 255.78 8.21 2,099.44 28.20
3 Crushed Aggregate M3 243.73 84.20 1.37 333.43 115.19 4.48
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,231.32 56.83
5 Lumber m3 10,000.00 0.04 360.00 4.84
Material Sub-total              7,445.11              115.19                                86.04 
Total Cost per crew day              8,653.05              136.61 

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 288.44 Birr/each
Total Oper. unit cost including 35% overhead & profit = 389.39 Birr/each
Activity replacement cost per crew day / ADP = 4.55 Birr/each
Total Repl. unit cost including 35% overhead & profit = 6.15 Birr/each
Total Activity Unit Rate =                      395.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 12 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  m Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  KM Post Production Scope: Material Production                         30.00   Each   Result:              395.53   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total              1,077.70                      -                                  12.45 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3
4
Equipment Sub-total                 130.24                21.42                                  1.51 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.91 420.92 5.65
2 Cement Quintal 255.78 8.21 2,099.44 28.20
3 Crushed Aggregate M3 243.73 84.20 1.37 333.43 115.19 4.48
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,231.32 56.83
5 Lumber m3 10,000.00 0.04 360.00 4.84
Material Sub-total              7,445.11              115.19                                86.04 
Total Cost per crew day              8,653.05              136.61 

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 288.44 Birr/each
Total Oper. unit cost including 35% overhead & profit = 389.39 Birr/each
Activity replacement cost per crew day / ADP = 4.55 Birr/each
Total Repl. unit cost including 35% overhead & profit = 6.15 Birr/each
Total Activity Unit Rate =                      395.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 13 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  n Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  HCB Production Scope: Material Production                       160.00   Each   Result:                  7.28   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 5.00 17.05 85.26 31.06
2 Labour I 2 15.00 12.62 189.28 68.94
3
Labour Sub-total                 274.54                      -                                  31.83 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 HCB Machine 5.00 - - - - -
2
Equipment Sub-total                        -                        -      
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.72 332.31 56.51
2 Cement Quintal 255.78 1.00 255.78 43.49
3
4
Material Sub-total                 588.09                      -                                  68.17 
Total Cost per crew day                 862.63                      -   

Average daily production (ADP) = 160.00 Each


Activity operational cost per crew day / ADP = 5.39 Birr/each
Total Oper. unit cost including 35% overhead & profit = 7.28 Birr/each
Activity replacement cost per crew day / ADP = - Birr/each
Total Repl. unit cost including 35% overhead & profit = - Birr/each
Total Activity Unit Rate =                          7.28 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 14 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  o Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Sand Production Scope: Material Production                         28.00   M3   Result:              385.88   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.III 1 8.00 39.79 318.31 67.96
2 Helper I 1 8.00 18.76 150.06 32.04
3
4
Labour Sub-total                 468.37                      -                                    9.07 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 100.00
2
3
4
Equipment Sub-total             941.88               4,698.07           2,836.94                                90.93 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day              5,166.44           2,836.94 

Average daily production (ADP) = 28.00 M3


Activity operational cost per crew day / ADP = 184.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 249.10 Birr/m3
Activity replacement cost per crew day / ADP = 101.32 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.78 Birr/m3
Total Activity Unit Rate =                      385.88 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 15 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  p Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Sand Hauling Scope: Material Production                    1,129.41   M3   Result:                62.39   Birr/m3 
* 10.5km freehaul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.III 10 77.02 39.79 3,064.51 100.00
2
3
4
Labour Sub-total              3,064.51                      -                                    7.47 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 12.46
2 Dump truck,6*4 (12m3) 12M3 69.02 481.75 104.04 585.79 33,250.18 7,180.61 87.54
3
4
Equipment Sub-total          1,673.67             37,983.39         11,150.47                                92.53 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day            41,047.90         11,150.47 

Average daily production (ADP) = 1,129.41 M3


Activity operational cost per crew day / ADP = 36.34 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 49.07 Birr/m3
Activity replacement cost per crew day / ADP = 9.87 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 13.33 Birr/m3
Total Activity Unit Rate =                        62.39 Birr/m3

Stadia Engineering Works Consultant Plc Page 16 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  q Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Formwork - Minor Drainage Scope: Drainage                         32.00   M2   Result:              239.73   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carp. Foreman 1 8.00 64.80 518.39 20.68
2 Driver III 1 2.00 36.38 72.76 2.90
3 Carpenter II 3 24.00 54.57 1,309.61 52.25
4 Labour I 6 48.00 12.62 605.70 24.17
5
6
Labour Sub-total              2,506.46                      -                                  45.52 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total             514.88                  853.51              176.24                                15.50 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 8.00 800.00 - 37.27
2 Lumber m3 10,000.00 0.13 1,280.00 - 59.64
3 Nails kg 26.50 2.50 66.25 - 3.09
Material Sub-total              2,146.25                      -                                  38.98 
Total Cost per crew day              5,506.22              176.24 

Average daily production (ADP) = 32.00 M2


Activity operational cost per crew day / ADP = 172.07 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 232.29 Birr/m2
Activity replacement cost per crew day / ADP = 5.51 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/m2
Total Activity Unit Rate = 239.73 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole & lumber 2 1/2 times

Stadia Engineering Works Consultant Plc Page 17 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  r Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Duct Marker Blocks Production Scope: Material Production                         30.00   Each   Result:              223.98   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 30.38
2 Bar Sett.I 1 8.00 30.69 245.55 22.78
3 Labour I 5 40.00 12.62 504.75 46.84
4
Labour Sub-total              1,077.70                      -                                  21.96 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 2.00 42.64 8.28 50.92 85.28 16.55 65.48
2 Concrete Vibrator 5 HP 2.00 22.48 2.43 24.91 44.96 4.87 34.52
3 Pipe Molds - - 1.20
4
Equipment Sub-total                 130.24                21.42                                  2.65 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.38 174.46 4.71
2 Cement Quintal 255.78 3.40 870.16 23.52
3 Crushed Aggregate M3 243.73 84.20 0.57 138.20 47.74 3.73
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.11 2,058.48 55.63
5 Lumber m3 10,000.00 0.05 459.00 12.40
Material Sub-total              3,700.30                47.74                                75.39 
Total Cost per crew day              4,908.24                69.16 

Average daily production (ADP) = 30.00 Each


Activity operational cost per crew day / ADP = 163.61 Birr/each
Total Oper. unit cost including 35% overhead & profit = 220.87 Birr/each
Activity replacement cost per crew day / ADP = 2.31 Birr/each
Total Repl. unit cost including 35% overhead & profit = 3.11 Birr/each
Total Activity Unit Rate =                      223.98 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 18 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  s Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         12.00   M3   Result:           3,124.94   Birr/m3 
Class A bedding (Class 20/20 concrete)
*(Grade 20)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total              4,174.40                      -                                  15.71 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 60.36
2 Concrete Vibrator 5 HP 16.00 22.48 2.43 24.91 359.66 38.95 20.35
3 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 19.30
4 Hand Tools
Equipment Sub-total              1,767.68              325.47                                  6.65 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 43.20 11,049.70 - 53.58
2
2 Formwork m 172.07 5.51 23.57 4,055.68 129.82 19.67
3 Sand m3 461.54 7.20 3,323.08 - 16.11
3
4 Crushed Aggregate M 243.73 84.20 9.00 2,193.59 757.83 10.64
Material Sub-total            20,622.04              887.65                                77.63 
Total Cost per crew day            26,564.12           1,213.12 

Average daily production (ADP) = 12.00 M3


Activity operational cost per crew day / ADP = 2,213.68 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,988.46 Birr/m3
Activity replacement cost per crew day / ADP = 101.09 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.48 Birr/m3
Total Activity Unit Rate = 3,124.94 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 19 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  t Category: Sub-Component  ADP=  March 21, 2017
Activity Name:  Rock Crushing -Chip Aggregate Scope: Material Production                       200.00   M3   Result:              477.79   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mat. Prod. Sup. 1 8.00 90.95 727.56 23.00
2 Equ.op.III 1 1.67 39.79 66.31 2.10
3 Driver III 3 17.00 36.38 618.43 19.55
4 St.eq.opI 1 8.00 22.74 181.89 5.75
5 Mechanic II 1 8.00 51.16 409.25 12.94
6 Helper I 1 8.00 18.76 150.06 4.74
7 Labour I 10 80.00 12.62 1,009.49 31.92
Labour Sub-total              3,163.01                      -                                    6.03 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 0.83 591.65 496.23 906.57 493.04 413.53 1.76
2 Crusher Plant 51-100 TPH 8.00 2,319.77 1,112.67 27,459.56 18,558.17 8,901.40 66.14
3 Loader, Crawler 2-2.5 M3 0.83 979.60 802.82 1,485.35 816.33 669.01 2.91
4 Dump truck,6*4 (12m3) 12M3 17.00 481.75 104.04 - 8,189.75 1,768.63 29.19
Equipment Sub-total        29,851.48             28,057.29         11,752.57                                53.52 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Stone M3 106.02 33.03 200.00 21,204.99 6,606.44 100.00
2 - -
Material Sub-total            21,204.99           6,606.44                                40.45 
Total Cost per crew day            52,425.29         18,359.01 

Average daily production (ADP) = 200.00 M3


Activity operational cost per crew day / ADP = 262.13 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 353.87 Birr/m3
Activity replacement cost per crew day / ADP = 91.80 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 123.92 Birr/m3
Total Activity Unit Rate =                      477.79 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 20 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  15.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Maintenance of Diversion Scope: Traffic Management                           0.70   km   Result:       172,087.46   Birr/Km 
*5 Km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 4.00 73.89 295.57 7.89
2 Equ.op.IV 1 8.00 102.31 818.51 21.84
3 Equ.op.III 6 44.00 39.79 1,750.70 46.72
4 Equ.op.II 1 8.00 28.42 227.36 6.07
5 Helper I 1 8.00 18.76 150.06 4.00
6 Labour I 5 40.00 12.62 504.75 13.47
7
Labour Sub-total              3,746.95                                  6.10 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 8.00 808.70 794.52 1,603.22 6,469.63 6,356.13 15.67
2 Water truck,6*4 20000Lits 24.00 422.98 145.63 568.61 10,151.50 3,495.08 24.58
3 Roller,Vibrator,2Drums 8 ton 6.00 478.94 281.42 760.36 2,873.64 1,688.50 6.96
4 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 11.46
5 Dump truck,6*4 (8m3) 8M3 40.00 426.76 88.12 514.88 17,070.29 3,524.90 41.33
Equipment Sub-total          4,534.95             41,298.28         19,034.46                                67.18 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Select Material m 20.86 10.67 787.50 16,428.15 8,722.69 100.00
2
Material Sub-total            16,428.15           8,722.69                                26.72 
Total Cost per crew day            61,473.39         27,757.15 

Average daily production (ADP) = 0.70 km


Activity operational cost per crew day / ADP = 87,819.12 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 118,555.82 Birr/Km
Activity replacement cost per crew day / ADP = 39,653.07 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 53,531.65 Birr/Km
Total Activity Unit Rate =               172,087.46 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Gravelling of detour with 15cm thick & 7.5m wide


*Considering 30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 22 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  21.01 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Clearing and Grubbing Scope: Site Clearance                           1.10   ha   Result:         46,816.85   Birr/ha 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 14.71
2 Equ.op.IV 1 8.00 102.31 818.51 33.10
3 Equ.op.III 2 8.77 39.79 348.77 14.11
4 Helper I 1 8.00 18.76 150.06 6.07
5 Driver III 3 16.21 36.38 589.52 23.84
6 Labour I 2 16.00 12.62 201.90 8.17
Labour Sub-total              2,472.54                                  9.46 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 45.10
2 Loader, Wheel 2-2.5 M3 8.77 591.65 496.23 1,087.88 5,186.19 4,349.78 21.91
3 Dump truck,6*4 (12m3) 12M3 16.21 481.75 104.04 585.79 7,806.93 1,685.96 32.99
Equipment Sub-total          3,754.38             23,665.87         12,008.65                                90.54 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            26,138.41         12,008.65 

Average daily production (ADP) = 1.10 ha


Activity operational cost per crew day / ADP = 23,762.19 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 32,078.96 Birr/ha
Activity replacement cost per crew day / ADP = 10,916.95 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 14,737.89 Birr/ha
Total Activity Unit Rate =                 46,816.85 Birr/ha
Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 26 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  22.06(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Demolishing Plain concrete Scope: Site Clearance                         30.00      Result:              474.94    Br / m3  

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 18.48
2 Labour I 8 62.00 12.62 782.36 81.52
3 - -
4
Labour Sub-total                 959.70                                13.03 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 - - -
4 -
Equipment Sub-total              6,405.10           3,189.43                                86.97 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
3
4
Material Sub-total                        -                        -      
Total Cost per crew day              7,364.80           3,189.43 

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 245.49 Br / m3
Total Oper. unit cost including 35% overhead & profit = 331.42 Br / m3
Activity replacement cost per crew day / ADP = 106.31 Br / m3
Total Repl. unit cost including 35% overhead & profit = 143.52 Br / m3
Total Activity Unit Rate =                      474.94 Br / m3

Stadia Engineering Works Consultant Plc Page 27 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  22.06(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Demolishing Reinforced concrete Scope: Site Clearance                         18.00      Result:              808.60    Br / m3  

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 14.94
2 Labour I 10 80.00 12.62 1,009.49 85.06
3 - -
4
Labour Sub-total              1,186.84                                15.63 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 - - -
4 -
Equipment Sub-total              6,405.10           3,189.43                                84.37 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
3
4
Material Sub-total                        -                        -      
Total Cost per crew day              7,591.94           3,189.43 

Average daily production (ADP) = 18.00


Activity operational cost per crew day / ADP = 421.77 Br / m3
Total Oper. unit cost including 35% overhead & profit = 569.40 Br / m3
Activity replacement cost per crew day / ADP = 177.19 Br / m3
Total Repl. unit cost including 35% overhead & profit = 239.21 Br / m3
Total Activity Unit Rate =                      808.60 Br / m3

Stadia Engineering Works Consultant Plc Page 28 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  22.06(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Scope: Site Clearance                         20.00      Result:              874.40   Birr/m3 
Demolishing Masonry Structures - mortared

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.IV 1 8.00 102.31 818.51 44.78
2 Labour I 10 80.00 12.62 1,009.49 55.22
3 -
Labour Sub-total              1,828.00                                22.57 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Crawler Type 1.76M3 8.00 784.05 606.71 1,390.76 6,272.37 4,853.67 100.00
2 Hand Tools
3
4
5
Equipment Sub-total          1,390.76               6,272.37           4,853.67                                77.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day              8,100.38           4,853.67 

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 405.02 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 546.78 Birr/m3
Activity replacement cost per crew day / ADP = 242.68 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 327.62 Birr/m3
Total Activity Unit Rate =                      874.40 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 29 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  22.06(d) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Demolishing Masonry Structures - dry Scope: Site Clearance                         30.00      Result:              582.93   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.IV 1 8.00 102.31 818.51 44.78
2 Labour I 10 80.00 12.62 1,009.49 55.22
3 -
Labour Sub-total              1,828.00                                22.57 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Crawler Type 1.76M3 8.00 784.05 606.71 1,390.76 6,272.37 4,853.67 100.00
2 Hand Tools
3
4
5
Equipment Sub-total          1,390.76               6,272.37           4,853.67                                77.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day              8,100.38           4,853.67 

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 270.01 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 364.52 Birr/m3
Activity replacement cost per crew day / ADP = 161.79 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 218.42 Birr/m3
Total Activity Unit Rate =                      582.93 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 30 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  31.01(a) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Open Drain Excavation (in soft) Scope: Drainage                       120.00   m3   Result:                90.04   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.III 1 8.00 39.79 318.31 67.96
2 Helper I 1 8.00 18.76 150.06 32.04
3
4
Labour Sub-total                 468.37                      -                                    9.07 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 828.35 4,698.07 2,836.94 100.00
2
Equipment Sub-total              4,698.07           2,836.94                                90.93 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
3
4
Material Sub-total                        -                        -      
Total Cost per crew day              5,166.44           2,836.94 

Average daily production (ADP) = 120.00 m3


Activity operational cost per crew day / ADP = 43.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 58.12 Birr/m3
Activity replacement cost per crew day / ADP = 23.64 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 31.92 Birr/m3
Total Activity Unit Rate =                        90.04 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 31 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  31.01(b) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Open Drain Exc. (in Hard) (Extra-over) Scope: Drainage                       100.00   m3   Result:              200.82   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 19.52
2 Equ.op.III 2 12.00 39.79 477.46 25.62
3 St.eq.opI 1 8.00 22.74 181.89 9.76
4 Labour I 4 32.00 12.62 403.80 21.67
5 Labour II 4 32.00 13.64 436.54 23.43
Labour Sub-total              1,863.47                      -                                  16.39 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 49.42
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 17.95
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 31.79
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.84
5 Hand Tools
Equipment Sub-total              9,507.32           3,505.04                                83.61 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
3
4
Material Sub-total                        -                        -      
Total Cost per crew day            11,370.79           3,505.04 

Average daily production (ADP) = 100.00 m3


Activity operational cost per crew day / ADP = 113.71 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 153.51 Birr/m3
Activity replacement cost per crew day / ADP = 35.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 47.32 Birr/m3
Total Activity Unit Rate =                      200.82 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 32 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.01(a) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Minor Structures Excavation (in Soft) Scope: Drainage                       150.00   m3   Result:              105.01   Birr/m3 
*0.5Km free-haul to waste
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 21.05
2 Equ.op.III 2 12.00 39.79 477.46 23.03
3 Helper I 1 8.00 18.76 150.06 7.24
4 Labour I 10 80.00 12.62 1,009.49 48.68
5
6
Labour Sub-total              2,073.56                      -                                  24.46 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 73.35
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 26.65
3 Hand Tools
4
5
Equipment Sub-total              6,405.10           3,189.43                                75.54 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day              8,478.65           3,189.43 

Average daily production (ADP) = 150.00 m3


Activity operational cost per crew day / ADP = 56.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 76.31 Birr/m3
Activity replacement cost per crew day / ADP = 21.26 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 28.70 Birr/m3
Total Activity Unit Rate =                      105.01 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 34 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.01(b) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         90.00   m3   Result:              223.14   Birr/m3 
Minor Structures Exc. (in Hard) (Extra-over)
*0.5Km free-haul to waste
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 19.52
2 Equ.op.III 2 12.00 39.79 477.46 25.62
3 St.eq.opI 1 8.00 22.74 181.89 9.76
4 Labour I 4 32.00 12.62 403.80 21.67
5 Labour II 4 32.00 13.64 436.54 23.43
Labour Sub-total              1,863.47                      -                                  16.39 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 49.42
2 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 17.95
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 31.79
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.84
5 Hand Tools
Equipment Sub-total              9,507.32           3,505.04                                83.61 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day            11,370.79           3,505.04 

Average daily production (ADP) = 90.00 m3


Activity operational cost per crew day / ADP = 126.34 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 170.56 Birr/m3
Activity replacement cost per crew day / ADP = 38.94 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 52.58 Birr/m3
Total Activity Unit Rate =                      223.14 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material

Stadia Engineering Works Consultant Plc Page 35 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.02(a) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         70.00   m3   Result:                58.06   Birr/m3 
Backfilling using the excavated material
*using the excavated material
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 6.05
2 Helper I 2 16.00 18.76 300.12 13.32
3 Labour I 18 144.00 12.62 1,817.09 80.63
4
5
Labour Sub-total              2,253.63                      -                                  81.47 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Plate Compactor - 48.00 10.68 5.09 15.77 512.64 244.24 100.00
2 Hand Tools
3
Equipment Sub-total               15.77                  512.64              244.24                                18.53 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
3
Material Sub-total                        -                        -      
Total Cost per crew day              2,766.27              244.24 

Average daily production (ADP) = 70.00 m3


Activity operational cost per crew day / ADP = 39.52 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 53.35 Birr/m3
Activity replacement cost per crew day / ADP = 3.49 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 4.71 Birr/m3
Total Activity Unit Rate =                        58.06 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 36 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.02(b) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         70.00   m3   Result:              138.98   Birr/m3 
Backfilling using  Imported selected material
*using imported material of 10 km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 5.85
2 Equ.op.III 1 2.00 39.79 79.58 3.41
3 Helper I 2 16.00 18.76 300.12 12.86
4 Labour I 18 144.00 12.62 1,817.09 77.88
5
6
Labour Sub-total              2,333.21                      -                                  40.82 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 0.20 591.65 496.23 1,087.88 118.33 99.25 7.97
2 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 57.50
3 Plate Compactor - 48.00 10.68 5.09 15.77 512.64 244.24 34.53
4 Hand Tools
5
Equipment Sub-total          1,618.53               1,484.49              519.73                                25.97 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Select Material m 20.86 10.67 91.00 1,898.36 970.60 100.00
2
3
Material Sub-total              1,898.36              970.60                                33.21 
Total Cost per crew day              5,716.06           1,490.33 

Average daily production (ADP) = 70.00 m3


Activity operational cost per crew day / ADP = 81.66 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 110.24 Birr/m3
Activity replacement cost per crew day / ADP = 21.29 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 28.74 Birr/m3
Total Activity Unit Rate =                      138.98 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 37 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(a)(i) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  36'' diameter R.C pipe installation on class A  Scope: Drainage                         11.00      Result:           3,160.08   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 21.00
2 Mason I 2 16.00 22.17 354.69 17.06
3 Equ.op.III 1 7.00 39.79 278.52 13.40
4 Labour I 10 80.00 12.62 1,009.49 48.55
5
Labour Sub-total              2,079.24                      -                                    9.08 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.41
2 Dump truck,6*4 (8m3) 8M3 3.00 426.76 88.12 514.88 1,280.27 264.37 34.30
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.29
4
Equipment Sub-total              3,732.32           2,290.00                                16.29 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.28 71.05 - 0.42
2 Sand m3 461.54 0.04 18.46 - 0.11
3
3 Class A Bedding m 2,213.68 101.09 2.59 5,733.42 261.83 33.53
4 Pipes (Dia. 36) No 1,025.04 26.10 11.00 11,275.43 287.07 65.94
Material Sub-total            17,098.36              548.90                                74.63 
Total Cost per crew day            22,909.92           2,838.90 

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 2,082.72 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,811.67 Birr/m
Activity replacement cost per crew day / ADP = 258.08 Birr/m
Total Repl. unit cost including 35% overhead & profit = 348.41 Birr/m
Total Activity Unit Rate =                   3,160.08 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 18km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 38 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(a)(ii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  42'' diameter R.C pipe installation on class A  Scope: Drainage                         11.00      Result:           3,854.39   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 18.33
2 Mason I 2 16.00 22.17 354.69 14.89
3 Equ.op.III 1 7.00 39.79 278.52 11.69
4 Labour I 13 104.00 12.62 1,312.34 55.09
5
Labour Sub-total              2,382.09                      -                                    8.37 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 62.69
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.05
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.26
4
Equipment Sub-total              3,774.99           2,298.81                                13.27 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.35 88.81 - 0.40
2 Sand m3 461.54 0.05 23.08 - 0.10
3
3 Class A Bedding m 2,213.68 101.09 3.15 6,973.08 318.44 31.27
4 Pipes (Dia. 42) No 1,383.21 30.14 11.00 15,215.28 331.53 68.23
Material Sub-total            22,300.26              649.97                                78.36 
Total Cost per crew day            28,457.34           2,948.78 

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 2,587.03 Birr/m
Total Oper. unit cost including 35% overhead & profit = 3,492.49 Birr/m
Activity replacement cost per crew day / ADP = 268.07 Birr/m
Total Repl. unit cost including 35% overhead & profit = 361.90 Birr/m
Total Activity Unit Rate =                   3,854.39 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 39 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(a)(iii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  48'' diameter R.C pipe installation on class A  Scope: Drainage                         11.00      Result:           4,806.76   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 18.33
2 Mason I 2 16.00 22.17 354.69 14.89
3 Equ.op.III 1 7.00 39.79 278.52 11.69
4 Labour I 13 104.00 12.62 1,312.34 55.09
5
Labour Sub-total              2,382.09                      -                                    6.60 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 62.69
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.05
3 Plate Compactor - 8.00 10.68 5.09 15.77 85.44 40.71 2.26
4
Equipment Sub-total              3,774.99           2,298.81                                10.45 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.42 106.58 - 0.36
2 Sand m3 461.54 0.06 27.69 - 0.09
3
3 Class A Bedding m 2,213.68 101.09 3.69 8,168.47 373.03 27.26
4 Pipes (Dia. 48) No 1,968.91 34.23 11.00 21,658.02 376.50 72.29
Material Sub-total            29,960.75              749.53                                82.95 
Total Cost per crew day            36,117.83           3,048.34 

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 3,283.44 Birr/m
Total Oper. unit cost including 35% overhead & profit = 4,432.64 Birr/m
Activity replacement cost per crew day / ADP = 277.12 Birr/m
Total Repl. unit cost including 35% overhead & profit = 374.12 Birr/m
Total Activity Unit Rate =                   4,806.76 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 40 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(b)(i) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  36'' diameter R.C pipe installation on class B  Scope: Drainage                         11.00      Result:           2,450.02   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total              1,877.34                      -                                  10.88 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total              3,700.23           2,263.19                                21.45 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.28 71.05 - 0.61
2 Sand m3 461.54 0.04 18.46 - 0.16
3
3 Select Material m 20.86 10.67 14.92 311.25 159.14 2.67
4 Pipes (Dia. 36) No 1,025.04 26.10 11.00 11,275.43 287.07 96.57
Material Sub-total            11,676.19              446.20                                67.67 
Total Cost per crew day            17,253.76           2,709.40 

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 1,568.52 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,117.51 Birr/m
Activity replacement cost per crew day / ADP = 246.31 Birr/m
Total Repl. unit cost including 35% overhead & profit = 332.52 Birr/m
Total Activity Unit Rate =                   2,450.02 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 41 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(b)(ii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  42'' diameter R.C pipe installation on class B  Scope: Drainage                         11.00      Result:           2,639.89   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total              1,877.34                      -                                  10.02 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total              3,700.23           2,263.19                                19.75 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.35 90.28 - 0.69
2 Sand m3 461.54 0.05 15.61 - 0.12
3
3 Select Material m 20.86 10.67 16.77 23.19 178.87 0.18
4 Pipes (Dia. 42) No 1,383.21 30.14 11.00 13,029.94 331.53 99.02
Material Sub-total            13,159.02              510.40                                70.23 
Total Cost per crew day            18,736.59           2,773.59 

Average daily production (ADP) = 11.00


Activity operational cost per crew day / ADP = 1,703.33 Birr/m
Total Oper. unit cost including 35% overhead & profit = 2,299.49 Birr/m
Activity replacement cost per crew day / ADP = 252.14 Birr/m
Total Repl. unit cost including 35% overhead & profit = 340.40 Birr/m
Total Activity Unit Rate =                   2,639.89 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 7.2km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 42 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.03(b)(iii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  48'' diameter R.C pipe installation on class B  Scope: Drainage                         11.00   m   Result:           3,754.49   Birr/m 
Bedding

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 23.25
2 Mason I 2 16.00 22.17 354.69 18.89
3 Equ.op.III 1 7.00 39.79 278.52 14.84
4 Labour I 8 64.00 12.62 807.60 43.02
5
Labour Sub-total              1,877.34                      -                                    6.76 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 63.96
2 Dump truck,6*4 (8m3) 8M3 3.10 426.76 88.12 514.88 1,322.95 273.18 35.75
3 Plate Compactor - 1.00 10.68 5.09 15.77 10.68 5.09 0.29
4
Equipment Sub-total              3,700.23           2,263.19                                13.33 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 0.42 106.58 - 0.48
2 Sand m3 461.54 0.06 27.69 - 0.12
3
3 Select Material m 20.86 10.67 18.48 385.51 197.11 1.74
4 Pipes (Dia. 48) No 1,968.91 34.23 11.00 21,658.02 376.50 97.66
Material Sub-total            22,177.80              573.61                                79.90 
Total Cost per crew day            27,755.37           2,836.80 

Average daily production (ADP) = 11.00 m


Activity operational cost per crew day / ADP = 2,523.22 Birr/m
Total Oper. unit cost including 35% overhead & profit = 3,406.34 Birr/m
Activity replacement cost per crew day / ADP = 257.89 Birr/m
Total Repl. unit cost including 35% overhead & profit = 348.15 Birr/m
Total Activity Unit Rate =                   3,754.49 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering an average hauling distance of 13.26km for pipe hauling by dump truck from production sites.
* free haul distance of 10 km for select material

Stadia Engineering Works Consultant Plc Page 43 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.16(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Service Duct using ordinary pipes (150mm  Scope: Drainage                         20.00   m   Result:              288.04   Birr/m 
diameter steel pipes) 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total                 419.03                      -                                  10.03 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total             514.88                  426.76                88.12                                10.21 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Steel Pipes (Dia. 150mm) No 1,000.00 3.33 3,333.33 - 100.00
2
Material Sub-total              3,333.33                      -                                  79.76 
Total Cost per crew day              4,179.12                88.12 

Average daily production (ADP) = 20.00 m


Activity operational cost per crew day / ADP = 208.96 Birr/m
Total Oper. unit cost including 35% overhead & profit = 282.09 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate =                      288.04 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 44 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.16(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Service Duct using split pipes (150mm diameter  Scope: Drainage                         20.00      Result:              468.04   Birr/m 
steel pipes)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total                 419.03                      -                                    6.12 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total             514.88                  426.76                88.12                                  6.23 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Split Pipes (Dia. 150mm) No 1,800.00 3.33 6,000.00 - 100.00
2
Material Sub-total              6,000.00                      -                                  87.65 
Total Cost per crew day              6,845.79                88.12 

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 342.29 Birr/m
Total Oper. unit cost including 35% overhead & profit = 462.09 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate =                      468.04 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 45 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.17 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Duct marker blocks Scope: Drainage                         20.00   No.   Result:              711.70   Birr/each 
*including class C-concrete footing
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 6.54
2 Labour I 15 120.00 12.62 1,514.24 72.63
3 Mason I 2 16.00 22.17 354.69 17.01
4 Equ.op.III 1 2.00 39.79 79.58 3.82
5
6
Labour Sub-total              2,084.92                      -                                  21.35 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 41.90
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 58.10
3 Hand Tools
4
Equipment Sub-total              1,018.41              584.35                                10.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 1.32 607.17 9.11
2 Cement Quintal 255.78 9.21 2,355.40 35.35
3 Crushed Aggregate M3 243.73 84.20 1.75 427.52 147.70 6.42
4 Duct marker blocks No 163.61 2.31 20.00 3,272.16 46.11 49.12

Material Sub-total              6,662.24              193.81                                68.22 


Total Cost per crew day              9,765.57              778.16 

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 488.28 Birr/each
Total Oper. unit cost including 35% overhead & profit = 659.18 Birr/each
Activity replacement cost per crew day / ADP = 38.91 Birr/each
Total Repl. unit cost including 35% overhead & profit = 52.53 Birr/each
Total Activity Unit Rate =                      711.70 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 46 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  32.18 Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Chambers for ducts Scope: Drainage                           7.00      Result:           9,791.11   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 9.36
2 Driver III 1 2.50 36.38 90.95 1.95
3 St.eq.opI 1 8.00 22.74 181.89 3.90
4 Mason I 2 16.00 22.17 354.69 7.60
5 Carpenter I 2 16.00 40.93 654.81 14.04
6 Carpenter II 1 8.00 54.57 436.54 9.36
7 Labour I 20 160.00 12.62 2,018.99 43.27
8 Bar Sett.I 2 16.00 30.69 491.11 10.53
Labour Sub-total              4,665.50                      -                                    9.50 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 60.36
2 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 19.30
3 Concrete Vibrator 5 HP 16.00 22.48 2.43 24.91 359.66 38.95 20.35
4 Hand Tools
5
Equipment Sub-total              1,767.68              325.47                                  3.60 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.49 2,073.18 4.86
2 Cement Quintal 255.78 40.43 10,340.44 24.22
3 Crushed Aggregate M3 243.73 84.20 6.74 1,642.23 567.35 3.85
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.28 5,296.77 12.41
5 Formwork m2 172.07 5.51 135.66 23,342.94 747.17 54.67
6
Material Sub-total            42,695.57           1,314.52                                86.91 
Total Cost per crew day            49,128.76           1,639.99 

Average daily production (ADP) = 7.00


Activity operational cost per crew day / ADP = 7,018.39 Birr/each
Total Oper. unit cost including 35% overhead & profit = 9,474.83 Birr/each
Activity replacement cost per crew day / ADP = 234.28 Birr/each
Total Repl. unit cost including 35% overhead & profit = 316.28 Birr/each
Total Activity Unit Rate =                   9,791.11 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 47 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.01(a)(i) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Class 25/20 Concrete Curbing (size .45m X  Scope: Drainage                       155.00   m   Result:              400.14   Birr/m 
.17m)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total              4,174.40                      -                                    9.43 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total              1,928.98              372.20                                  4.36 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.19 1,931.54 5.06
2 Cement Quintal 255.78 41.85 10,704.39 28.04
3
3 Crushed Aggregate M 243.73 84.20 6.28 1,530.03 528.59 4.01
2
4 Formwork m 172.07 5.51 139.50 24,003.68 768.32 62.89
5
6
Material Sub-total            38,169.65           1,296.91                                86.21 
Total Cost per crew day            44,273.02           1,669.10 

Average daily production (ADP) = 155.00 m


Activity operational cost per crew day / ADP = 285.63 Birr/m
Total Oper. unit cost including 35% overhead & profit = 385.60 Birr/m
Activity replacement cost per crew day / ADP = 10.77 Birr/m
Total Repl. unit cost including 35% overhead & profit = 14.54 Birr/m
Total Activity Unit Rate =                      400.14 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 48 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.01(a)(ii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Class 25/20 Concrete Curbing (size .20m X  Scope: Drainage                       240.00   m   Result:              251.09   Birr/m 
.25m)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total              4,174.40                      -                                    9.71 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total              1,928.98              372.20                                  4.49 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.80 2,215.38 6.00
2 Cement Quintal 255.78 48.00 12,277.44 33.28
3
3 Crushed Aggregate M 243.73 84.20 7.20 1,754.87 606.27 4.76
2
4 Formwork m 172.07 5.51 120.00 20,648.33 660.92 55.96
5
6
Material Sub-total            36,896.03           1,267.19                                85.81 
Total Cost per crew day            42,999.41           1,639.38 

Average daily production (ADP) = 240.00 m


Activity operational cost per crew day / ADP = 179.16 Birr/m
Total Oper. unit cost including 35% overhead & profit = 241.87 Birr/m
Activity replacement cost per crew day / ADP = 6.83 Birr/m
Total Repl. unit cost including 35% overhead & profit = 9.22 Birr/m
Total Activity Unit Rate =                      251.09 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 49 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.03(a) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Concrete Chute (Class 20/20) including  Scope: Drainage                       100.00      Result:              493.50   Birr/m 
Formwork

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8 -
Labour Sub-total              4,174.40                      -                                  11.73 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total              1,928.98              372.20                                  5.42 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.80 2,215.38 7.52
2 Cement Quintal 255.78 43.20 11,049.70 37.49
3
3 Crushed Aggregate M 243.73 84.20 7.20 1,754.87 606.27 5.95
2
4 Formwork m 172.07 5.51 84.00 14,453.83 49.04
5 - -
6
Material Sub-total            29,473.79              606.27                                82.84 
Total Cost per crew day            35,577.16              978.46 

Average daily production (ADP) = 100.00


Activity operational cost per crew day / ADP = 355.77 Birr/m
Total Oper. unit cost including 35% overhead & profit = 480.29 Birr/m
Activity replacement cost per crew day / ADP = 9.78 Birr/m
Total Repl. unit cost including 35% overhead & profit = 13.21 Birr/m
Total Activity Unit Rate =                      493.50 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 50 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.09(a) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Concrete lining (Class 20/20) including  Scope: Drainage                         12.00      Result:           2,883.21   Birr/m3 
Formwork

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 9.36
2 Driver III 1 2.50 36.38 90.95 1.95
3 St.eq.opI 1 8.00 22.74 181.89 3.90
4 Mason I 2 16.00 22.17 354.69 7.60
5 Carpenter I 2 16.00 40.93 654.81 14.04
6 Carpenter II 1 8.00 54.57 436.54 9.36
7 Labour I 20 160.00 12.62 2,018.99 43.27
8 Bar Sett.I 2 16.00 30.69 491.11 10.53
Labour Sub-total              4,665.50                      -                                  18.84 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total              1,928.98              372.20                                  7.79 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 1.91 880.62 4.85
2 Cement Quintal 255.78 17.17 4,392.25 24.18
3
3 Crushed Aggregate M 243.73 84.20 2.86 697.56 240.99 3.84
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.22 4,139.83 22.79
2
5 Formwork m 172.07 5.51 46.80 8,052.85 257.76 44.34
6
Material Sub-total            18,163.11              498.75                                73.36 
Total Cost per crew day            24,757.60              870.95 

Average daily production (ADP) = 12.00


Activity operational cost per crew day / ADP = 2,063.13 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,785.23 Birr/m3
Activity replacement cost per crew day / ADP = 72.58 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 97.98 Birr/m3
Total Activity Unit Rate =                   2,883.21 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 51 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.17(b)(i) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Pedestrian drain covers (Class 25/20 -  Scope: Drainage                         30.00   No.   Result:              998.70   Birr/each 
1.4mX1.2mX0.15m)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total              3,202.42                      -                                  15.21 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total              1,966.12              758.16                                  9.34 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 3.02 1,395.69 8.79
2 Cement Quintal 255.78 27.22 6,961.31 43.82
3
3 Crushed Aggregate M 243.73 84.20 4.54 1,105.57 381.95 6.96
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.32 6,071.14 38.22
5 Lumber m3 10,000.00 0.04 351.00 2.21
6
Material Sub-total            15,884.72              381.95                                75.45 
Total Cost per crew day            21,053.26           1,140.11 

Average daily production (ADP) = 30.00 No.


Activity operational cost per crew day / ADP = 701.78 Birr/each
Total Oper. unit cost including 35% overhead & profit = 947.40 Birr/each
Activity replacement cost per crew day / ADP = 38.00 Birr/each
Total Repl. unit cost including 35% overhead & profit = 51.30 Birr/each
Total Activity Unit Rate =                      998.70 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 52 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.17(b)(ii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Pedestrian drain covers (Class 25/20 -  Scope: Drainage                         30.00      Result:           1,102.23   Birr/each 
1.6mX1.2mX0.15m)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total              3,202.42                      -                                  13.74 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total              1,966.12              758.16                                  8.44 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 3.46 1,595.08 8.80
2 Cement Quintal 255.78 31.10 7,955.78 43.88
3
3 Crushed Aggregate M 243.73 84.20 5.18 1,263.51 436.51 6.97
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.36 6,938.45 38.27
5 Lumber m3 10,000.00 0.04 378.00 2.08
6
Material Sub-total            18,130.82              436.51                                77.82 
Total Cost per crew day            23,299.36           1,194.67 

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 776.65 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,048.47 Birr/each
Activity replacement cost per crew day / ADP = 39.82 Birr/each
Total Repl. unit cost including 35% overhead & profit = 53.76 Birr/each
Total Activity Unit Rate =                   1,102.23 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 53 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  33.17(b)(iii) Category: Mechanized+Labour intensive  ADP=  March 21, 2017
Activity Name:  Vehicle drain covers (Class 25/20 - Scope: Drainage                         30.00   No.   Result:           1,666.95   Birr/each 
1.6mX1.2mX0.20m)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 10.22
2 Bar Sett.I 1 8.00 30.69 245.55 7.67
3 Labour I 5 40.00 12.62 504.75 15.76
4 Labor Foreman 1 8.00 17.05 136.42 4.26
5 Labour I 15 120.00 12.62 1,514.24 47.28
6 Mason I 2 16.00 22.17 354.69 11.08
7 Equ.op.III 1 3.00 39.79 119.37 3.73
8
Labour Sub-total              3,202.42                      -                                    8.97 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 17.35
2 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.15
3 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 43.41
4 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 30.09
5 Hand Tools
Equipment Sub-total              1,966.12              758.16                                  5.51 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.61 2,126.77 6.97
2 Cement Quintal 255.78 41.47 10,607.71 34.74
3
3 Crushed Aggregate M 243.73 84.20 6.91 1,684.68 582.02 5.52
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.82 15,611.51 51.13
5 Lumber m3 10,000.00 0.05 504.00 1.65
6
Material Sub-total            30,534.67              582.02                                85.52 
Total Cost per crew day            35,703.21           1,340.18 

Average daily production (ADP) = 30.00 No.


Activity operational cost per crew day / ADP = 1,190.11 Birr/each
Total Oper. unit cost including 35% overhead & profit = 1,606.64 Birr/each
Activity replacement cost per crew day / ADP = 44.67 Birr/each
Total Repl. unit cost including 35% overhead & profit = 60.31 Birr/each
Total Activity Unit Rate =                   1,666.95 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 54 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  34.01(b)(i) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         50.00   m2   Result:              248.45   Birr/m2 
Stone Pitching for outlet & inlet of culverts 
m2
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason II 1 8.00 32.40 259.19 9.59
2 Driver III 1 4.00 36.38 145.51 5.39
3 Mason I 4 32.00 22.17 709.37 26.25
4 Labour III 8 64.00 15.35 982.21 36.35
5 Labour I 6 48.00 12.62 605.70 22.42
6
Labour Sub-total              2,701.99                      -                                  32.63 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 3.00 481.75 104.04 585.79 1,445.25 312.11 77.36
2 Water truck,6*4 20000Lits 1.00 422.98 145.63 568.61 422.98 145.63 22.64
3 Hand Tools
Equipment Sub-total          1,154.39               1,868.23              457.74                                22.56 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 6.00 1,534.68 - 41.35
2 Sand m3 461.54 1.50 692.31 - 18.65
3
3 Stone M 106.02 33.03 14.00 1,484.35 462.45 40.00
Material Sub-total              3,711.34              462.45                                44.81 
Total Cost per crew day              8,281.56              920.19 

Average daily production (ADP) = 50.00 m2


Activity operational cost per crew day / ADP = 165.63 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 223.60 Birr/m2
Activity replacement cost per crew day / ADP = 18.40 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 24.85 Birr/m2
Total Activity Unit Rate =                      248.45 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 20 km free haul of masonry stone

Stadia Engineering Works Consultant Plc Page 55 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  34.03(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Cement-mortared stone walls Scope: Drainage                           8.00   m3   Result:           1,608.20   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 4.00 54.57 218.27 7.95
2 Equ.op.III 1 3.00 39.79 119.37 4.35
3 Mason I 5 40.00 22.17 886.72 32.30
4 Carpenter II 1 4.00 54.57 218.27 7.95
5 Labour II 5 40.00 13.64 545.67 19.88
6 Labour I 8 60.00 12.62 757.12 27.58
Labour Sub-total              2,745.42                      -                                  32.37 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 2.00 481.75 104.04 585.79 963.50 208.07 61.96
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 38.04
3 Hand Tools
Equipment Sub-total          1,673.67               1,555.15              704.31                                18.33 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 8.40 2,148.55 - 51.38
2 Sand m3 461.54 2.02 930.46 - 22.25
3 Stone M3 106.02 33.03 10.40 1,102.66 343.53 26.37
Material Sub-total              4,181.67              343.53                                49.30 
Total Cost per crew day              8,482.24           1,047.84 

Average daily production (ADP) = 8.00 m3


Activity operational cost per crew day / ADP = 1,060.28 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 1,431.38 Birr/m3
Activity replacement cost per crew day / ADP = 130.98 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 176.82 Birr/m3
Total Activity Unit Rate =                   1,608.20 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 20 km free haul distance for masonry stone

Stadia Engineering Works Consultant Plc Page 56 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  34.04(c) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Drainage                         96.00   m2   Result:              590.61   Birr/each 
Pre-cast concrete blocks for side walk pavement 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 5.33
2 Labour I 8 64.00 12.62 807.60 31.53
3 Mason I 8 64.00 22.17 1,418.75 55.38
4 Equ.op.III 1 5.00 39.79 198.94 7.77
5 -
6 -
Labour Sub-total              2,561.71                      -                                    6.23 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 74.26
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 25.74
3 Hand Tools - -
4 - -
5
Equipment Sub-total              2,298.68              848.72                                  5.59 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 12.48 5,760.00 15.87
2 Cement Quintal 255.78 16.90 4,321.66 11.91

3 300x300x60mm Pre-colored concrete block m2 273.00 - 96.00 26,208.00 - 72.22


4 -
5 -
6
Material Sub-total            36,289.66                      -                                  88.19 
Total Cost per crew day            41,150.05              848.72 

Average daily production (ADP) = 96.00 m2


Activity operational cost per crew day / ADP = 428.65 Birr/each
Total Oper. unit cost including 35% overhead & profit = 578.67 Birr/each
Activity replacement cost per crew day / ADP = 8.84 Birr/each
Total Repl. unit cost including 35% overhead & profit = 11.94 Birr/each
Total Activity Unit Rate =                      590.61 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling
* Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 57 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  41.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Removal of unsuitable material and replacement  Scope: Earth Work                       585.67   m3   Result:                79.80   Birr/m3 
with suitable material
* including 0.5 Km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 24.30
2 Equ.op.IV 1 8.00 102.31 818.51 33.64
3 Equ.op.III 3 22.97 39.79 914.08 37.57
4 Labour II 1 8.00 13.64 109.13 4.49
5
Labour Sub-total              2,432.87                                  9.88 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 48.08
2 Dump truck,6*4 (12m3) 12M3 18.83 481.75 104.04 585.79 9,068.94 1,958.50 40.86
3 Loader, Wheel 2-2.5 M3 4.15 591.65 496.23 1,087.88 2,454.45 2,058.60 11.06
4
5
Equipment Sub-total          3,754.38             22,196.14           9,990.01                                90.12 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            24,629.01           9,990.01 

Average daily production (ADP) = 585.67 m3


Activity operational cost per crew day / ADP = 42.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 56.77 Birr/m3
Activity replacement cost per crew day / ADP = 17.06 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 23.03 Birr/m3
Total Activity Unit Rate =                        79.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Considering 40% loose factor

Stadia Engineering Works Consultant Plc Page 58 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  41.02 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Road bed preparation and compaction Scope: Earth Work                       586.00   m3   Result:                55.76   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 26.08
2 Equ.op.IV 1 8.00 102.31 818.51 36.11
3 Equ.op.III 1 8.00 39.79 318.31 14.04
4 Equ.op.II 1 6.00 28.42 170.52 7.52
5 Helper I 1 8.00 18.76 150.06 6.62
7 Labour II 2 16.00 13.64 218.27 9.63
Labour Sub-total              2,266.82                      -                                  15.12 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 8.00 808.70 794.52 1,603.22 6,469.63 6,356.13 50.83
2 Roller,Vibrator,2Drums 8 ton 6.00 478.94 281.42 760.36 2,873.64 1,688.50 22.58
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 26.59
4
5
Equipment Sub-total          2,932.19             12,727.11           9,209.65                                84.88 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            14,993.93           9,209.65 

Average daily production (ADP) = 586.00 m3


Activity operational cost per crew day / ADP = 25.59 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 34.54 Birr/m3
Activity replacement cost per crew day / ADP = 15.72 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 21.22 Birr/m3
Total Activity Unit Rate =                        55.76 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *The grader scarifies 15cm of road bed material after top soil removal & place it again

Stadia Engineering Works Consultant Plc Page 59 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Cut to fill Scope: Earth Work                    1,200.00   m3   Result:              129.45   Birr/m3 
* upto 2 Km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 7.23
2 Equ.op.IV 4 29.99 102.31 3,068.81 37.54
3 Equ.op.II 2 10.00 28.42 284.20 3.48
4 Equ.op.III 9 67.90 39.79 2,701.84 33.05
5 Helper I 2 16.00 18.76 300.12 3.67
6 Labour I 10 80.00 12.62 1,009.49 12.35
7 Labour II 2 16.00 13.64 218.27 2.67
Labour Sub-total              8,173.88                                10.55 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 18.68
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 9.77
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 6.91
4 Dump truck,6*4 (12m3) 12M3 41.90 481.75 104.04 585.79 20,187.61 4,359.66 29.14
5 Loader, Wheel 2-2.5 M3 10.00 591.65 496.23 1,087.88 5,916.51 4,962.32 8.54
6 Crawler Dozer 280-330 HP 13.99 1,334.09 746.61 2,080.71 18,669.53 10,448.24 26.95

Equipment Sub-total          6,686.56             69,269.99         37,626.69                                89.45 


Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            77,443.88         37,626.69 

Average daily production (ADP) = 1,200.00 m3


Activity operational cost per crew day / ADP = 64.54 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 87.12 Birr/m3
Activity replacement cost per crew day / ADP = 31.36 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 42.33 Birr/m3
Total Activity Unit Rate =                      129.45 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 60 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Borrow to fill Scope: Earth Work                    1,200.00   m3   Result:              164.44   Birr/m3 
* upto 2 Km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 5.82
2 Equ.op.IV 4 29.99 102.31 3,068.81 30.23
3 Equ.op.II 2 10.00 28.42 284.20 2.80
4 Equ.op.III 15 117.62 39.79 4,679.90 46.10
5 Helper I 2 16.00 18.76 300.12 2.96
6 Labour I 10 80.00 12.62 1,009.49 9.94
7 Labour II 2 16.00 13.64 218.27 2.15
Labour Sub-total            10,151.95                                  9.82 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 13.88
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 7.26
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 5.14
4 Dump truck,6*4 (12m3) 12M3 91.62 481.75 104.04 585.79 44,137.46 9,531.80 47.35
5 Loader, Wheel 2-2.5 M3 10.00 591.65 496.23 1,087.88 5,916.51 4,962.32 6.35
6 Crawler Dozer 280-330 HP 13.99 1,334.09 746.61 2,080.71 18,669.53 10,448.24 20.03

Equipment Sub-total          6,686.56             93,219.84         42,798.83                                90.18 


Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day          103,371.79         42,798.83 

Average daily production (ADP) = 1,200.00 m3


Activity operational cost per crew day / ADP = 86.14 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 116.29 Birr/m3
Activity replacement cost per crew day / ADP = 35.67 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 48.15 Birr/m3
Total Activity Unit Rate =                      164.44 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 61 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.01(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Rock fill  Scope: Earth Work                       685.00   m3   Result:              294.17   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 4.00 73.89 295.57 6.00
2 Equ.op.IV 1 8.00 102.31 818.51 16.63
3 Equ.op.II 1 8.00 28.42 227.36 4.62
4 Equ.op.III 8 57.10 39.79 2,271.81 46.15
5 Helper I 2 16.00 18.76 300.12 6.10
6 Labour I 10 80.00 12.62 1,009.49 20.51
Labour Sub-total              4,922.87                                  4.36 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 25.09
2 Water truck,6*4 20000Lits - 422.98 145.63 568.61 - -
3 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 9.01
4 Dump truck,6*4 (12m3) 12M3 52.24 481.75 104.04 585.79 25,168.94 5,435.41 59.16
5 Loader, Wheel 2-2.5 M3 4.85 591.65 496.23 1,087.88 2,870.74 2,407.76 6.75
Equipment Sub-total          5,083.34             42,543.96         16,067.41                                37.71 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Rock Excavation M3 106.02 33.03 616.50 65,364.40 20,364.34 100.00
2
3
Material Sub-total            65,364.40         20,364.34                                57.93 
Total Cost per crew day          112,831.22         36,431.75 

Average daily production (ADP) = 685.00 m3


Activity operational cost per crew day / ADP = 164.72 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 222.37 Birr/m3
Activity replacement cost per crew day / ADP = 53.19 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 71.80 Birr/m3
Total Activity Unit Rate =                      294.17 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 62 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.01(d) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Improved subgrade  Scope: Earth Work                       980.00   m3   Result:              176.32   Birr/m3 
* upto 2 Km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 6.46
2 Equ.op.IV 4 27.43 102.31 2,806.32 30.68
3 Equ.op.II 2 10.00 28.42 284.20 3.11
4 Equ.op.III 13 98.99 39.79 3,938.63 43.05
5 Helper I 2 16.00 18.76 300.12 3.28
6 Labour I 10 80.00 12.62 1,009.49 11.03
7 Labour II 2 16.00 13.64 218.27 2.39
Labour Sub-total              9,148.18                                10.19 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 16.05
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 8.39
3 Roller,Vibrator,2Drums 8 ton 10.00 478.94 281.42 760.36 4,789.41 2,814.17 5.94
4 Dump truck,6*4 (12m3) 12M3 74.82 481.75 104.04 585.79 36,045.59 7,784.30 44.71
5 Loader, Wheel 2-2.5 M3 8.17 591.65 496.23 1,087.88 4,831.82 4,052.56 5.99
6 Crawler Dozer 280-330 HP 11.43 1,334.09 746.61 2,080.71 15,246.78 8,532.73 18.91

Equipment Sub-total          6,686.56             80,620.53         38,226.06                                89.81 


Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            89,768.72         38,226.06 

Average daily production (ADP) = 980.00 m3


Activity operational cost per crew day / ADP = 91.60 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 123.66 Birr/m3
Activity replacement cost per crew day / ADP = 39.01 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 52.66 Birr/m3
Total Activity Unit Rate =                      176.32 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 63 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.03(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Common (normal) excavation Scope: Earth Work                    1,120.00   m3   Result:                80.87   Birr/m3 
* upto 0.5 Km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 14.47
2 Equ.op.IV 2 16.00 102.31 1,637.02 40.07
3 Equ.op.III 6 43.93 39.79 1,748.05 42.79
4 Labour II 1 8.00 13.64 109.13 2.67
Labour Sub-total              4,085.35                                  8.61 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 16.00 1,334.09 746.61 2,080.71 21,345.50 11,945.82 49.20
2 Dump truck,6*4 (12m3) 12M3 36.00 481.75 104.04 585.79 17,342.99 3,745.34 39.98
3 Loader, Wheel 2-2.5 M3 7.93 591.65 496.23 1,087.88 4,693.76 3,936.77 10.82
4
5
Equipment Sub-total          3,754.38             43,382.25         19,627.93                                91.39 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            47,467.60         19,627.93 

Average daily production (ADP) = 1,120.00 m3 Weighted Rate for Cut to Spoil in any Material


Activity operational cost per crew day / ADP = 42.38 Birr/m3 Soft Excavation Quantity 128,947.12
Total Oper. unit cost including 35% overhead & profit = 57.22 Birr/m3 Hard Excavation Quantity 1,667,554.71
Activity replacement cost per crew day / ADP = 17.52 Birr/m3 Total Excavation Quantity                  1,796,501.83
Total Repl. unit cost including 35% overhead & profit = 23.66 Birr/m3 Weighted Rate                            201.78
Total Activity Unit Rate =                        80.87 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 64 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  42.03(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Rock excavation Scope: Earth Work                       400.00   m3   Result:              211.13   Birr/m3 
* including 0.5 Km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Quarry Foreman 1 8.00 56.84 454.73 9.86
2 Equ.op.IV 1 8.00 102.31 818.51 17.75
3 Equ.op.III 4 25.91 39.79 1,031.03 22.36
5 St.eq.opI 1 8.00 22.74 181.89 3.94
6 Powder Man I 1 8.00 30.69 245.55 5.32
7 Helper I 3 24.00 18.76 450.18 9.76
8 Labour II 2 16.00 13.64 218.27 4.73
9 Labour I 12 96.00 12.62 1,211.39 26.27
Labour Sub-total              4,611.55                                  9.50 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 37.42
2 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 10.60
3 Jack Hammer - 24.00 2.50 5.20 7.70 60.00 124.80 0.21
4 Drill, Self Prop, Crawler Type 4500 Kg 8.00 727.88 599.01 1,326.89 5,823.07 4,792.06 20.42
5 Loader, Wheel 2-2.5 M3 2.83 591.65 496.23 1,087.88 1,676.34 1,405.99 5.88
6 Dump truck,6*4 (12m3) 12M3 15.08 481.75 104.04 585.79 7,264.48 1,568.82 25.47
7 Hand Tools
Equipment Sub-total          5,485.40             28,518.87         14,013.78                                58.75 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Ammonium Nitrate Kg 60.00 150.00 9,000.00 58.39
2 Power Jell Kg 90.00 1.88 168.75 1.09
3 Electrical Detonator No 65.00 13.00 845.00 5.48
4 Cord m 16.00 150.00 2,400.00 15.57
5 Connecting wire m 12.00 250.00 3,000.00 19.46
6 Bits & Drills
Material Sub-total            15,413.75                      -                                  31.75 
Total Cost per crew day            48,544.17         14,013.78 

Average daily production (ADP) = 400.00 m3


Activity operational cost per crew day / ADP = 121.36 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 163.84 Birr/m3
Activity replacement cost per crew day / ADP = 35.03 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 47.30 Birr/m3
Total Activity Unit Rate =                      211.13 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 65 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  43.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Reinstatement of rock (hard) material borrow  Scope: Earth Work                         0.350      Result:         69,004.36   Birr/ha 
areas

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 1.00 73.89 73.89 5.94
2 Equ.op.IV 1 8.00 102.31 818.51 65.78
3 Helper I 1 8.00 18.76 150.06 12.06
4 Labour I 2 16.00 12.62 201.90 16.23
5 -
6 -
Labour Sub-total              1,244.36                                10.44 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2 - -
3 - -
4 - -
5 - -
Equipment Sub-total          2,080.71             10,672.75           5,972.91                                89.56 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 - -
2
3
Material Sub-total                        -                        -      
Total Cost per crew day            11,917.11           5,972.91 

Average daily production (ADP) = 0.35


Activity operational cost per crew day / ADP = 34,048.89 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 45,965.99 Birr/ha
Activity replacement cost per crew day / ADP = 17,065.45 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 23,038.36 Birr/ha
Total Activity Unit Rate =                 69,004.36 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 66 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  43.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Reinstatement of common (normal or soft)  Scope: Earth Work                         0.500      Result:         47,757.92   Birr/ha 
material borrow areas

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 1.00 73.89 73.89 7.09
2 Equ.op.IV 1 8.00 102.31 818.51 78.52
3 Helper I 1 8.00 18.76 150.06 14.39
4 -
5 -
6 -
Labour Sub-total              1,042.46                                  8.90 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 100.00
2 - -
3 - -
4 - -
5 - -
Equipment Sub-total          2,080.71             10,672.75           5,972.91                                91.10 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 - -
2
3
Material Sub-total                        -                        -      
Total Cost per crew day            11,715.21           5,972.91 

Average daily production (ADP) = 0.50


Activity operational cost per crew day / ADP = 23,430.42 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 31,631.07 Birr/ha
Activity replacement cost per crew day / ADP = 11,945.82 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 16,126.85 Birr/ha
Total Activity Unit Rate =                 47,757.92 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 67 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  44.04 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Side fills or Fill-flattening Scope: Earth Work                    1,200.00      Result:                61.32   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 15.32
2 Equ.op.IV 3 24.00 102.31 2,455.53 63.63
3 Equ.op.II 1 5.00 28.42 142.10 3.68
4 Equ.op.III 1 8.00 39.79 318.31 8.25
5 Helper I 1 8.00 18.76 150.06 3.89
6 Labour I 2 16.00 12.62 201.90 5.23
7 -
Labour Sub-total              3,859.04                                11.61 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 44.03
2 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 11.51
3 Roller,Vibrator,2Drums 8 ton 5.00 478.94 281.42 760.36 2,394.70 1,407.09 8.15
4 Crawler Dozer 280-330 HP 8.00 1,334.09 746.61 2,080.71 10,672.75 5,972.91 36.31
5 - -
6 - -

Equipment Sub-total          5,012.89             29,390.55         21,257.27                                88.39 


Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            33,249.60         21,257.27 

Average daily production (ADP) = 1,200.00


Activity operational cost per crew day / ADP = 27.71 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 37.41 Birr/m3
Activity replacement cost per crew day / ADP = 17.71 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 23.91 Birr/m3
Total Activity Unit Rate =                        61.32 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 68 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  51.01(a)(i) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Gravel Sub-base Scope: Pavement                       480.00   m3   Result:              262.35   Birr/m3 
* 8 km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 9.54
2 Equ.op.IV 2 16.00 102.31 1,637.02 26.43
3 Equ.op.III 7 55.31 39.79 2,200.88 35.54
4 Equ.op.II 2 16.00 28.42 454.73 7.34
5 Helper I 2 16.00 18.76 300.12 4.85
6 Labour I 10 80.00 12.62 1,009.49 16.30
Labour Sub-total              6,193.39                      -                                    9.84 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 35.31 481.75 104.04 585.79 17,012.65 3,674.00 36.39
2 Water truck,6*4 20000Lits 16.00 422.98 145.63 568.61 6,767.66 2,330.06 14.48
3 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 27.68
4 Loader, Wheel 2-2.5 M3 4.00 591.65 496.23 1,087.88 2,366.60 1,984.93 5.06
5 Roller,Vibrator,2Drums 8 ton 16.00 478.94 281.42 760.36 7,663.05 4,502.67 16.39
6
Equipment Sub-total          4,605.85             46,749.24         25,203.91                                74.26 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Select Material m3 20.86 10.67 480.00 10,013.35 5,119.64 100.00
Material Sub-total            10,013.35           5,119.64                                15.91 
Total Cost per crew day            62,955.98         30,323.54 

Average daily production (ADP) = 480.00 m3


Activity operational cost per crew day / ADP = 131.16 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 177.06 Birr/m3
Activity replacement cost per crew day / ADP = 63.17 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 85.28 Birr/m3
Total Activity Unit Rate =                      262.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *considering 100% Natural gravel

Stadia Engineering Works Consultant Plc Page 69 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  52.01(c)(ii) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Crushed -stone base  Scope: Pavement                       800.00   m3   Result:              653.02   Birr/m3 
* freehaul-18km
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 6.78
2 Equ.op.IV 2 16.00 102.31 1,637.02 18.79
3 Equ.op.III 17 129.29 39.79 5,144.10 59.03
4 Equ.op.II 2 16.00 28.42 454.73 5.22
5 Helper II 2 16.00 23.87 381.97 4.38
6 Labour I 5 40.00 12.62 504.75 5.79
Labour Sub-total              8,713.71                      -                                    3.05 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 107.62 481.75 104.04 585.79 51,845.46 11,196.40 61.78
2 Motor Grader 145-165 HP 16.00 808.70 794.52 1,603.22 12,939.27 12,712.25 15.42
3 Loader, Wheel 2-2.5 M3 13.67 591.65 496.23 1,087.88 8,085.90 6,781.83 9.64
4 Roller,Vibrator,2Drums 8 ton 16.00 478.94 281.42 760.36 7,663.05 4,502.67 9.13
5 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 4.03
Equipment Sub-total          4,605.85             83,917.51         36,358.18                                29.40 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Crushed Aggregate (Base Course) m3 241.00 81.48 800.00 192,796.47 65,187.34 100.00
Material Sub-total          192,796.47         65,187.34                                67.55 
Total Cost per crew day          285,427.69       101,545.52 

Average daily production (ADP) = 800.00 m3


Activity operational cost per crew day / ADP = 356.78 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 481.66 Birr/m3
Activity replacement cost per crew day / ADP = 126.93 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 171.36 Birr/m3
Total Activity Unit Rate =                      653.02 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Loader hours include 8 hours for base coarse material mixing

Stadia Engineering Works Consultant Plc Page 70 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  61.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Prime Coat (MC-30 cutback bitumen ) Scope: Pavement                    8,570.00  l  Result:                40.04   Birr/l 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 233.64 14.14
2 Driver III 2 16.00 36.38 272.58 16.49
3 St.eq.opI 2 16.00 22.74 203.36 12.30
4 Helper II 3 24.00 23.87 337.49 20.42
5 Labour I 6 48.00 12.62 605.70 36.65
6
7
Labour Sub-total              1,652.77                      -                                    0.66 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Water truck,6*4 20000Lits 4.00 422.98 145.63 568.61 980.90 581.42 13.51
2 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 4,699.69 783.04 64.73
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 8.00 499.25 114.83 614.07 332.11 306.40 4.57
4 Street Sweeper, Self Prop 1-2m 6.00 425.74 118.67 544.41 1,247.57 304.96 17.18
5
Equipment Sub-total          2,898.47               7,260.27           1,975.81                                  2.88 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Bitumen - MC-30 Kg 28.39 8,570.00 243,302.30 - 100.00
2
Material Sub-total          243,302.30                      -                                  96.47 
Total Cost per crew day          252,215.34           1,975.81 

Average daily production (ADP) = 8,570.00 l


Activity operational cost per crew day / ADP = 29.43 Birr/l
Total Oper. unit cost including 35% overhead & profit = 39.73 Birr/l
Activity replacement cost per crew day / ADP = 0.23 Birr/l
Total Repl. unit cost including 35% overhead & profit = 0.31 Birr/l
Total Activity Unit Rate =                        40.04 Birr/l

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Average Specific gravity of MC-30 is 0.95

Stadia Engineering Works Consultant Plc Page 71 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  62.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Tack Coat (Stable-grade bitumen emulsion  Scope: Pavement                    4,000.00   Result:                45.96   Birr/l 
(30%))

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 10.82
2 Labour I 6 48.00 12.62 605.70 48.05
3 Driver III 1 8.00 36.38 291.03 23.09
4 St.eq.opII 1 8.00 28.42 227.36 18.04
5 -
Labour Sub-total              1,260.50                                  0.96 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Street Sweeper, Self Prop 1-2m 8.00 425.74 118.67 544.41 3,405.95 949.37 25.38
2 Asphalt Kettle, Trailer Mounted 1500-2000Lit 8.00 499.25 114.83 614.07 3,993.96 918.62 29.76
3 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 44.86
4
Equipment Sub-total            13,419.86           5,219.06                                10.25 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Bitumen - AC RC-70 Kg 29.07 4,000.00 116,280.00 100.00
2
3
Material Sub-total          116,280.00                      -                                  88.79 
Total Cost per crew day          130,960.36           5,219.06 

Average daily production (ADP) = 4,000.00


Activity operational cost per crew day / ADP = 32.74 Birr/l
Total Oper. unit cost including 35% overhead & profit = 44.20 Birr/l
Activity replacement cost per crew day / ADP = 1.30 Birr/l
Total Repl. unit cost including 35% overhead & profit = 1.76 Birr/l
Total Activity Unit Rate = 45.96 Birr/l

Stadia Engineering Works Consultant Plc Page 72 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  63.02(b)* Category:  ADP=  March 21, 2017
Activity Name:  Double Surface Seal (150/200 penetration grade  Scope: Pavement                    4,000.00   m2   Result:                75.02    Br / m2 
bitumen) 1st layer

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 4.51
2 Labour I 10 80.00 12.62 1,009.49 33.38
3 Driver III 5 36.00 36.38 1,309.61 43.31
4 St.eq.opII 1 4.00 28.42 113.68 3.76
5 Equ.op.II 2 16.00 28.42 454.73 15.04
6
Labour Sub-total              3,023.94                                  1.47 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 24.00 426.76 88.12 514.88 10,242.18 2,114.94 30.62
2 Roller,Pneumatic 10 ton 12.00 553.82 236.35 790.18 6,645.90 2,836.26 19.87
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 4.00 499.25 114.83 614.07 1,996.98 459.31 5.97
4 Spreader, Aggregate 5-7m 8.00 1,067.62 405.33 1,472.95 8,540.95 3,242.63 25.54
5 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 18.00
6 Hand Tools 8.00
Equipment Sub-total            33,445.95         12,004.22                                16.25 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Chip Aggregate M 262.13 91.80 49.14 12,881.64 4,511.07 7.61
2 Bitumen - MC-3000 Kg 26.60 5,880.00 156,408.00 - 92.39
3
Material Sub-total          169,289.64           4,511.07                                82.28 
Total Cost per crew day          205,759.53         16,515.29 

Average daily production (ADP) = 4,000.00 m2


Activity operational cost per crew day / ADP = 51.44 Br / m2
Total Oper. unit cost including 35% overhead & profit = 69.44 Br / m2
Activity replacement cost per crew day / ADP = 4.13 Br / m2
Total Repl. unit cost including 35% overhead & profit = 5.57 Br / m2
Total Activity Unit Rate =                        75.02 Br / m2

Stadia Engineering Works Consultant Plc Page 73 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  63.02(b) Category:  ADP=  March 21, 2017
Activity Name:  Double Surface Seal (150/200 penetration grade  Scope: Pavement                    4,000.00      Result:              135.58    Br / m2 
bitumen)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 4.51
2 Labour I 10 80.00 12.62 1,009.49 33.38
3 Driver III 5 36.00 36.38 1,309.61 43.31
4 St.eq.opII 1 4.00 28.42 113.68 3.76
5 Equ.op.II 2 16.00 28.42 454.73 15.04
6
Labour Sub-total              3,023.94                                  1.83 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 24.00 426.76 88.12 514.88 10,242.18 2,114.94 30.62
2 Roller,Pneumatic 10 ton 12.00 553.82 236.35 790.18 6,645.90 2,836.26 19.87
3 Asphalt Kettle, Trailer Mounted 1500-2000Lit 4.00 499.25 114.83 614.07 1,996.98 459.31 5.97
4 Spreader, Aggregate 5-7m 8.00 1,067.62 405.33 1,472.95 8,540.95 3,242.63 25.54
5 Asphalt Distributor 6000 Lit 8.00 752.49 418.89 1,171.38 6,019.95 3,351.08 18.00
6 Hand Tools 8.00
Equipment Sub-total            33,445.95         12,004.22                                20.23 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Chip Aggregate M 262.13 91.80 22.86 5,991.46 2,098.17 4.65
2 Bitumen - MC-3000 Kg 26.60 4,620.00 122,892.00 - 95.35
3
Material Sub-total          128,883.46           2,098.17                                77.94 
Total Cost per crew day          165,353.35         14,102.39 

Average daily production (ADP) = 4,000.00  1st layer                75.02    Br / m2 


Activity operational cost per crew day / ADP = 41.34 Br / m2  2nd layer                60.57    Br / m2 
Total Oper. unit cost including 35% overhead & profit = 55.81 Br / m2
Activity replacement cost per crew day / ADP = 3.53 Br / m2
Total Repl. unit cost including 35% overhead & profit = 4.76 Br / m2
Total Activity Unit Rate =                      135.58 Br / m2

Stadia Engineering Works Consultant Plc Page 74 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  64.02(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Asphaltic Concrete (50 mm thick, 80/100  Scope: Pavement                    3,500.00   m2   Result:              349.56   Birr/m2 
bitumen)
* 18 Freehaul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 7.59
2 Equ.op.III 15 118.00 39.79 4,695.06 60.27
3 Equ.op.II 4 26.00 28.42 738.93 9.49
4 St.eq.opI 1 8.00 22.74 181.89 2.34
5 Helper II 3 24.00 23.87 572.96 7.36
6 Labour I 10 80.00 12.62 1,009.49 12.96
Labour Sub-total              7,789.48                      -                                    0.91 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 106.00 481.75 104.04 585.79 51,065.48 11,027.96 69.20
2 Roller,Vibrator,2Drums 8 ton 18.00 478.94 281.42 760.36 8,620.93 5,065.51 11.68
3 Roller,Pneumatic 10 ton 8.00 553.82 236.35 790.18 4,430.60 1,890.84 6.00
4 Asphalt Paver, Crawler 2.5-8m 8.00 779.21 789.34 1,568.55 6,233.71 6,314.68 8.45
5 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 2.31
6 Water truck,6*4 20000Lits 4.00 422.98 145.63 568.61 1,691.92 582.51 2.29
7 Asphalt Cutter - 4.00 10.80 14.04 24.84 43.20 56.15 0.06
Equipment Sub-total          4,842.73             73,788.81         25,412.33                                  8.63 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Asphalt Hot Mix M3 4,015.47 136.66 192.50 772,978.69 26,306.48 100.00
Material Sub-total          772,978.69         26,306.48                                90.45 
Total Cost per crew day          854,556.98         51,718.81 

Average daily production (ADP) = 3,500.00 m2 Asphalt Thickness: 50.00 mm


Activity operational cost per crew day / ADP = 244.16 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 329.61 Birr/m2
Activity replacement cost per crew day / ADP = 14.78 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 19.95 Birr/m2
Total Activity Unit Rate =                      349.56 Birr/m2
Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 75 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.02(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Major Structures Excavation (in Soft) Scope: Structure                       185.00   m3   Result:              110.11   Birr/m3 
*0.5Km free-haul to waste
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 16.78
2 Equ.op.III 2 13.95 39.79 554.91 21.33
3 Helper I 4 32.00 18.76 600.24 23.08
4 Labour I 10 80.00 12.62 1,009.49 38.81
5
Labour Sub-total              2,601.18                      -                                  22.54 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 52.54
2 Dump truck,6*4 (12m3) 12M3 5.95 481.75 104.04 585.79 2,864.69 618.65 32.04
3 Water Pump 230 Lit/min 24.00 57.43 3.80 61.23 1,378.28 91.12 15.42
4 Hand Tools
5
6
Equipment Sub-total              8,941.04           3,546.72                                77.46 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day            11,542.22           3,546.72 

Average daily production (ADP) = 185.00 m3


Activity operational cost per crew day / ADP = 62.39 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 84.23 Birr/m3
Activity replacement cost per crew day / ADP = 19.17 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 25.88 Birr/m3
Total Activity Unit Rate =                      110.11 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material


*Unit rate for hard excavation in structure can be taken directly from rock excavation

Stadia Engineering Works Consultant Plc Page 76 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.02(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Major Structures Excavation (in Hard) Scope: Structure                         80.00   m3   Result:              240.74   Birr/m3 
*0.5Km free-haul to waste
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 20.14
2 Equ.op.III 2 10.57 39.79 420.62 23.28
3 St.eq.opI 1 8.00 22.74 181.89 10.07
4 Labour I 4 32.00 12.62 403.80 22.35
5 Labour II 4 32.00 13.64 436.54 24.16
Labour Sub-total              1,806.63                      -                                  16.66 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Excavator, Wheel Type 1.09M3 8.00 587.26 354.62 941.88 4,698.07 2,836.94 51.98
2 Dump truck,6*4 (12m3) 12M3 2.57 481.75 104.04 585.79 1,238.79 267.52 13.70
3 Air Compressor 600CFM 8.00 377.78 18.65 396.43 3,022.22 149.20 33.44
4 Jack Hammer - 32.00 2.50 5.20 7.70 80.00 166.40 0.89
5 Hand Tools
Equipment Sub-total              9,039.08           3,420.07                                83.34 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day            10,845.71           3,420.07 

Average daily production (ADP) = 80.00 m3


Activity operational cost per crew day / ADP = 135.57 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 183.02 Birr/m3
Activity replacement cost per crew day / ADP = 42.75 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 57.71 Birr/m3
Total Activity Unit Rate =                      240.74 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering 40% Loose factor for excavated material

Stadia Engineering Works Consultant Plc Page 77 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.05(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Backfill using excavated material Scope: Structure                       200.00      Result:              140.56   Birr/m3 
*using the excavated material
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 24.43
2 Equ.op.II 2 16.00 28.42 454.73 30.54
3 Equ.op.III 1 8.00 39.79 318.31 21.38
4 Helper I 1 8.00 18.76 150.06 10.08
5 Labour I 2 16.00 12.62 201.90 13.56
6
Labour Sub-total              1,488.78                      -                                  11.08 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 28.32
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 32.07
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 39.61
4
Equipment Sub-total          2,416.85             11,948.57           7,386.22                                88.92 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
Material Sub-total                        -                        -      
Total Cost per crew day            13,437.34           7,386.22 

Average daily production (ADP) = 200.00


Activity operational cost per crew day / ADP = 67.19 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 90.70 Birr/m3
Activity replacement cost per crew day / ADP = 36.93 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 49.86 Birr/m3
Total Activity Unit Rate =                      140.56 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 78 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.05(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Backfill using imported material Scope: Structure                       200.00   m3   Result:              245.87   Birr/m3 
*using imported material of 10 km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 16.80
2 Equ.op.II 1 8.00 28.42 227.36 10.50
3 Equ.op.III 4 30.71 39.79 1,222.08 56.44
4 Helper I 1 8.00 18.76 150.06 6.93
5 Labour I 2 16.00 12.62 201.90 9.32
6
Labour Sub-total              2,165.18                      -                                    8.53 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 17.77
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 20.13
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 24.86
4 Dump truck,6*4 (12m3) 12M3 14.71 481.75 104.04 585.79 7,088.60 1,530.83 37.24
5
Equipment Sub-total          3,002.63             19,037.17           8,917.05                                75.02 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Select Material m3 20.86 10.67 200.00 4,172.23 2,133.18 100.00
2
Material Sub-total              4,172.23           2,133.18                                16.44 
Total Cost per crew day            25,374.58         11,050.23 

Average daily production (ADP) = 200.00 m3


Activity operational cost per crew day / ADP = 126.87 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 171.28 Birr/m3
Activity replacement cost per crew day / ADP = 55.25 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 74.59 Birr/m3
Total Activity Unit Rate =                      245.87 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Using rental loader


*30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 79 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.05(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Hand laid rock embankment Scope: Structure                         40.00      Result:              391.01   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 5.87
2 Equ.op.III 1 4.27 39.79 169.89 7.31
3 Labour I 20 160.00 12.62 2,018.99 86.83
4
5
Labour Sub-total              2,325.30                      -                                  25.49 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 3.27 481.75 104.04 585.79 1,575.25 340.19 61.66
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 38.34
3 -
Equipment Sub-total          2,368.20               2,554.84           1,143.00                                28.01 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Stone M3 106.02 33.03 40.00 4,241.00 1,321.29 100.00
2 -
3 -
Material Sub-total              4,241.00           1,321.29                                46.50 
Total Cost per crew day              9,121.14           2,464.29 

Average daily production (ADP) = 40.00


Activity operational cost per crew day / ADP = 228.03 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 307.84 Birr/m3
Activity replacement cost per crew day / ADP = 61.61 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 83.17 Birr/m3
Total Activity Unit Rate =                      391.01 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 80 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.08(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Rock foundation fill Scope: Structure                         30.00      Result:              435.76   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 5.95
2 Equ.op.III 1 3.45 39.79 137.37 5.99
3 Labour I 20 160.00 12.62 2,018.99 88.06
4
5
Labour Sub-total              2,292.77                      -                                  30.03 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 2.45 481.75 104.04 585.79 1,181.43 255.14 54.67
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 45.33
3 -
Equipment Sub-total          2,368.20               2,161.03           1,057.96                                28.31 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Stone M3 106.02 33.03 30.00 3,180.75 990.97 100.00
2 -
3 -
Material Sub-total              3,180.75              990.97                                41.66 
Total Cost per crew day              7,634.55           2,048.92 

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 254.49 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 343.55 Birr/m3
Activity replacement cost per crew day / ADP = 68.30 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 92.20 Birr/m3
Total Activity Unit Rate =                      435.76 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 81 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  81.08(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Compacted granular foundation fill Scope: Structure                       180.00      Result:              261.55   Birr/m3 
*using imported material of 10 km free haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For I 1 8.00 45.47 363.78 17.27
2 Equ.op.II 1 8.00 28.42 227.36 10.79
3 Equ.op.III 4 29.24 39.79 1,163.53 55.23
4 Helper I 1 8.00 18.76 150.06 7.12
5 Labour I 2 16.00 12.62 201.90 9.58
6
Labour Sub-total              2,106.64                      -                                    8.71 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 18.46
2 Roller,Vibrator,2Drums 8 ton 8.00 478.94 281.42 760.36 3,831.53 2,251.34 20.90
3 Loader, Wheel 2-2.5 M3 8.00 591.65 496.23 1,087.88 4,733.21 3,969.85 25.82
4 Dump truck,6*4 (12m3) 12M3 13.24 481.75 104.04 585.79 6,379.74 1,377.75 34.81
5
Equipment Sub-total          3,002.63             18,328.31           8,763.97                                75.77 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Select Material m3 20.86 10.67 180.00 3,755.01 1,919.86 100.00
2
Material Sub-total              3,755.01           1,919.86                                15.52 
Total Cost per crew day            24,189.95         10,683.83 

Average daily production (ADP) = 180.00


Activity operational cost per crew day / ADP = 134.39 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 181.42 Birr/m3
Activity replacement cost per crew day / ADP = 59.35 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 80.13 Birr/m3
Total Activity Unit Rate =                      261.55 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Using rental loader


*30% compaction factor for select material

Stadia Engineering Works Consultant Plc Page 82 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  82.01(a ) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Formwork for Class F1 surface finish Scope: Structure                         32.00      Result:              973.49   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carp. Foreman 1 8.00 64.80 518.39 4.80
2 Driver III 1 2.00 36.38 72.76 0.67
3 Carpenter II 16 128.00 54.57 6,984.61 64.64
4 Labour I 32 256.00 12.62 3,230.38 29.89
5
6
Labour Sub-total            10,806.14                      -                                  47.19 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total             514.88                  853.51              176.24                                  3.73 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 70.00 7,000.00 - 62.28
2 Lumber m3 10,000.00 0.32 3,200.00 - 28.47
3 Ply wood No 60.00 16.00 960.00 - 8.54
4 Nails kg 26.50 3.00 79.50 - 0.71
Material Sub-total            11,239.50                      -                                  49.08 
Total Cost per crew day            22,899.15              176.24 

Average daily production (ADP) = 32.00


Activity operational cost per crew day / ADP = 715.60 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 966.06 Birr/m2
Activity replacement cost per crew day / ADP = 5.51 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/m2
Total Activity Unit Rate =                      973.49 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole 1.5 & lumber 1 time

Stadia Engineering Works Consultant Plc Page 83 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  82.01(b ) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Formwork for Class F2 surface finish Scope: Structure                         36.00   m2   Result:              851.08   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carp. Foreman 1 8.00 64.80 518.39 4.80
2 Driver III 1 2.00 36.38 72.76 0.67
3 Carpenter II 16 128.00 54.57 6,984.61 64.64
4 Labour I 32 256.00 12.62 3,230.38 29.89
5
6
Labour Sub-total            10,806.14                      -                                  47.99 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Hand Tools
3
4
Equipment Sub-total             514.88                  853.51              176.24                                  3.79 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 70.00 7,000.00 - 64.46
2 Lumber m3 10,000.00 0.36 3,600.00 - 33.15
3 Ply wood No 60.00 3.00 180.00 - 1.66
4 Nails kg 26.50 3.00 79.50 - 0.73
Material Sub-total            10,859.50                      -                                  48.22 
Total Cost per crew day            22,519.15              176.24 

Average daily production (ADP) = 36.00 m2


Activity operational cost per crew day / ADP = 625.53 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 844.47 Birr/m2
Activity replacement cost per crew day / ADP = 4.90 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 6.61 Birr/m2
Total Activity Unit Rate =                      851.08 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *Considering to re-use Each Equaliptus pole 1.5 & lumber 1 time

Stadia Engineering Works Consultant Plc Page 84 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  83.01(a)(i) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Grade 60 Reinforcement Steel Scope: Structure                           0.51   t    Result:         34,757.89   Birr/t 
*(Grade-60)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Bar Sett.II 1 8.00 40.93 327.40 13.09
2 Bar Sett.I 4 32.00 30.69 982.21 39.27
3 St.eq.opI 1 8.00 22.74 181.89 7.27
4 Labour I 10 80.00 12.62 1,009.49 40.36
5
6
Labour Sub-total              2,501.00                      -                                  18.95 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Steel-cutter 8.00 - -
2 Barbending Jig 8.00 - -
3
4
Equipment Sub-total                        -                        -      
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Binding wire Kg 32.00 15.00 480.00 - 4.49
2 Reinforcement Bar (Mild, Grade-60) t 19,930.00 0.51 10,214.13 - 95.51
3
4
Material Sub-total            10,694.13                      -                                  81.05 
Total Cost per crew day            13,195.13                      -   

Average daily production (ADP) = 0.51 t


Activity operational cost per crew day / ADP = 25,746.59 Birr/t
Total Oper. unit cost including 35% overhead & profit = 34,757.89 Birr/t
Activity replacement cost per crew day / ADP = - Birr/t
Total Repl. unit cost including 35% overhead & profit = - Birr/t
Total Activity Unit Rate =                 34,757.89 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 85 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  83.01(a)(ii) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Grade 40 Reinforcement Steel Scope: Structure                           0.51   t    Result:         33,583.39   Birr/t 
*(Grade-40)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Bar Sett.II 1 8.00 40.93 327.40 13.09
2 Bar Sett.I 4 32.00 30.69 982.21 39.27
3 St.eq.opI 1 8.00 22.74 181.89 7.27
4 Labour I 10 80.00 12.62 1,009.49 40.36
5
6
Labour Sub-total              2,501.00                      -                                  19.62 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Steel-cutter 8.00 - -
2 Barbending Jig 8.00 - -
3
4
Equipment Sub-total                        -                        -      
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Binding wire Kg 32.00 15.00 480.00 - 4.68
2 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.51 9,768.25 - 95.32
3
4
Material Sub-total            10,248.25                      -                                  80.38 
Total Cost per crew day            12,749.25                      -   

Average daily production (ADP) = 0.51 t


Activity operational cost per crew day / ADP = 24,876.59 Birr/t
Total Oper. unit cost including 35% overhead & profit = 33,583.39 Birr/t
Activity replacement cost per crew day / ADP = - Birr/t
Total Repl. unit cost including 35% overhead & profit = - Birr/t
Total Activity Unit Rate =                 33,583.39 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 86 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  84.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Class 30/20 concrete in RC Structure Scope: Structure                         32.00   m3   Result:           3,266.49   Birr/m3 
*(Grade 30)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 3.85
2 Driver III 3 17.00 36.38 618.43 5.45
3 St.eq.opI 2 16.00 22.74 363.78 3.21
4 Mason I 8 64.00 22.17 1,418.75 12.50
5 Carpenter I 8 64.00 40.93 2,619.23 23.08
6 Carp. Foreman 1 8.00 64.80 518.39 4.57
7 Bar Sett.II 1 8.00 40.93 327.40 2.88
8 Labour I 50 400.00 12.62 5,047.47 44.47
Labour Sub-total            11,349.99                      -                                  15.76 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total          2,247.20               9,120.90           3,392.78                                12.67 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 144.00 36,832.32 - 71.46
2 Sand m3 461.54 19.20 8,861.54 - 17.19
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 11.35
Material Sub-total            51,543.44           2,020.89                                71.57 
Total Cost per crew day            72,014.34           5,413.67 

Average daily production (ADP) = 32.00 m3


Activity operational cost per crew day / ADP = 2,250.45 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 3,038.10 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate =                   3,266.49 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 87 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  84.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Class 25/20 concrete in RC Structure Scope: Structure                         32.00      Result:           3,093.84   Birr/m3 
*(Grade 25)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 3.85
2 Driver III 3 17.00 36.38 618.43 5.45
3 St.eq.opI 2 16.00 22.74 363.78 3.21
4 Mason I 8 64.00 22.17 1,418.75 12.50
5 Carpenter I 8 64.00 40.93 2,619.23 23.08
6 Carp. Foreman 1 8.00 64.80 518.39 4.57
7 Bar Sett.II 1 8.00 40.93 327.40 2.88
8 Labour I 50 400.00 12.62 5,047.47 44.47
Labour Sub-total            11,349.99                      -                                  16.71 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total          2,247.20               9,120.90           3,392.78                                13.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 128.00 32,739.84 - 69.00
2 Sand m3 461.54 19.20 8,861.54 - 18.68
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 12.33
Material Sub-total            47,450.96           2,020.89                                69.86 
Total Cost per crew day            67,921.86           5,413.67 

Average daily production (ADP) = 32.00


Activity operational cost per crew day / ADP = 2,122.56 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,865.45 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate =                   3,093.84 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 88 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  84.01(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Class 15/20 concrete in lean concrete Scope: Structure                         32.00   m3   Result:           2,570.71   Birr/m3 
*(Grade 15)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 6.12
2 Driver III 3 17.00 36.38 618.43 8.67
3 St.eq.opI 2 16.00 22.74 363.78 5.10
4 Mason I 3 24.00 22.17 532.03 7.46
5 Carpenter I 5 40.00 40.93 1,637.02 22.94
6 Carp. Foreman 1 8.00 64.80 518.39 7.27
7 Labour I 30 240.00 12.62 3,028.48 42.45
Labour Sub-total              7,134.67                      -                                  12.85 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 6.00 426.76 88.12 514.88 2,560.54 528.73 28.07
2 Loader, Wheel 2-2.5 M3 3.00 591.65 496.23 1,087.88 1,774.95 1,488.69 19.46
3 Water truck,6*4 20000Lits 8.00 422.98 145.63 568.61 3,383.83 1,165.03 37.10
4 Concrete Vibrator 5 HP 32.00 22.48 2.43 24.91 719.32 77.90 7.89
5 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 7.48
6 Hand Tools
Equipment Sub-total          2,247.20               9,120.90           3,392.78                                16.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 96.00 24,554.88 - 62.53
2 Sand m3 461.54 19.20 8,861.54 - 22.57
3 Crushed Aggregate M3 243.73 84.20 24.00 5,849.58 2,020.89 14.90
Material Sub-total            39,266.00           2,020.89                                70.72 
Total Cost per crew day            55,521.58           5,413.67 

Average daily production (ADP) = 32.00 m3


Activity operational cost per crew day / ADP = 1,735.05 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,342.32 Birr/m3
Activity replacement cost per crew day / ADP = 169.18 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 228.39 Birr/m3
Total Activity Unit Rate =                   2,570.71 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 89 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.03 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Elastomeric Bearing Scope: Structure                           2.00   No.   Result:         11,470.53   Birr/each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Welder II 1 8.00 45.47 363.78 100.00
2
Labour Sub-total                 363.78                      -                                    2.16 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 AC Welder, Diesel 300-400AMP 8.00 189.56 16.19 205.75 1,516.49 129.51 100.00
2
Equipment Sub-total             205.75               1,516.49              129.51                                  8.99 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 

1 Elastomeric Bearing (400mm*300mm*69mm) No 7,452.00 2.00 14,904.00 - 99.47


2 Electrode, #4 Kg 79.60 1.00 79.60 - 0.53
Material Sub-total            14,983.60                      -                                  88.85 
Total Cost per crew day            16,863.87              129.51 

Average daily production (ADP) = 2.00 No.


Activity operational cost per crew day / ADP = 8,431.93 Birr/each
Total Oper. unit cost including 35% overhead & profit = 11,383.11 Birr/each
Activity replacement cost per crew day / ADP = 64.76 Birr/each
Total Repl. unit cost including 35% overhead & profit = 87.42 Birr/each
Total Activity Unit Rate =                 11,470.53 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * Cost includes cutting, grinding, drilling & boltting of steel plate

Stadia Engineering Works Consultant Plc Page 90 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.07 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Concrete parapet  Scope: Structure                         66.00   m   Result:              685.12   Birr/m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 10.46
2 Driver III 1 2.50 36.38 90.95 2.18
3 St.eq.opI 1 8.00 22.74 181.89 4.36
4 Mason I 2 16.00 22.17 354.69 8.50
5 Carpenter I 2 16.00 40.93 654.81 15.69
6 Carpenter II 1 8.00 54.57 436.54 10.46
7 Labour I 20 160.00 12.62 2,018.99 48.37
8
Labour Sub-total              4,174.40                      -                                  12.95 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.50 426.76 88.12 514.88 1,066.89 220.31 55.31
2 Concrete Mixer,Trailer Mounted 250 Lit 16.00 42.64 8.28 50.92 682.26 132.41 35.37
3 Concrete Vibrator 5 HP 8.00 22.48 2.43 24.91 179.83 19.48 9.32
4 Hand Tools
5
Equipment Sub-total              1,928.98              372.20                                  5.98 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 3.09 1,425.60 5.46
2 Cement Quintal 255.78 30.89 7,900.53 30.24
3 Crushed Aggregate M3 243.73 84.20 4.63 1,129.26 390.13 4.32
4 Formwork m2 172.07 5.51 91.08 15,672.08 501.64 59.98
5
6
Material Sub-total            26,127.48              891.77                                81.06 
Total Cost per crew day            32,230.86           1,263.97 

Average daily production (ADP) = 66.00 m


Activity operational cost per crew day / ADP = 488.35 Birr/m
Total Oper. unit cost including 35% overhead & profit = 659.27 Birr/m
Activity replacement cost per crew day / ADP = 19.15 Birr/m
Total Repl. unit cost including 35% overhead & profit = 25.85 Birr/m
Total Activity Unit Rate =                      685.12 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 91 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.13(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Expansion joint with 20mm filler Scope: Structure                           8.10   m   Result:              365.89   Birr/m 
*including 20mm compressible joint filler board
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.III 1 1.00 39.79 39.79 5.11
2 Carpenter II 1 8.00 54.57 436.54 56.03
3 Labour I 3 24.00 12.62 302.85 38.87
4
Labour Sub-total                 779.18                      -                                  36.98 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
4
Equipment Sub-total             514.88                  426.76                88.12                                20.25 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Chipwood No 420.00 2.00 840.00 - 93.20
2 Bitumen - AC-60/70 Kg 19.10 - 3.21 61.26 - 6.80
3
Material Sub-total                 901.26                      -                                  42.77 
Total Cost per crew day              2,107.19                88.12 

Average daily production (ADP) = 8.10 m


Activity operational cost per crew day / ADP = 260.15 Birr/m
Total Oper. unit cost including 35% overhead & profit = 351.20 Birr/m
Activity replacement cost per crew day / ADP = 10.88 Birr/m
Total Repl. unit cost including 35% overhead & profit = 14.69 Birr/m
Total Activity Unit Rate =                      365.89 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 92 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.19(a)(i) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Dia. 100mm PVC drainage pipes Scope: Structure                         16.00      Result:                96.07   Birr/Each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 81.68
2 Equ.op.III 1 1.00 39.79 39.79 18.32
3
Labour Sub-total                 217.13                      -                                  20.67 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total             514.88                  426.76                88.12                                40.63 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 PVC Pipe, 110mm No 184.80 2.20 406.56 - 100.00
2
Material Sub-total                 406.56                      -                                  38.70 
Total Cost per crew day              1,050.45                88.12 

Average daily production (ADP) = 16.00


Activity operational cost per crew day / ADP = 65.65 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 88.63 Birr/Each
Activity replacement cost per crew day / ADP = 5.51 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 7.44 Birr/Each
Total Activity Unit Rate =                        96.07 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 93 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.19(b)(i) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Dia. 200mm PVC pipe weep holes Scope: Structure                         48.00   m   Result:                82.96   Birr/m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 81.68
2 Equ.op.III 1 1.00 39.79 39.79 18.32
3
Labour Sub-total                 217.13                      -                                    7.59 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total             514.88                  426.76                88.12                                14.91 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 PVC Pipe, 110mm No 184.80 12.00 2,217.60 - 100.00
2
Material Sub-total              2,217.60                      -                                  77.50 
Total Cost per crew day              2,861.49                88.12 

Average daily production (ADP) = 48.00 m


Activity operational cost per crew day / ADP = 59.61 Birr/m
Total Oper. unit cost including 35% overhead & profit = 80.48 Birr/m
Activity replacement cost per crew day / ADP = 1.84 Birr/m
Total Repl. unit cost including 35% overhead & profit = 2.48 Birr/m
Total Activity Unit Rate =                        82.96 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 94 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  87.23 Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Crushed Stone in drainage Strips Scope: Structure                           8.00   m3   Result:              575.16   Birr/m3 
*(sheeting material)
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labour I 4 32.00 12.62 403.80 91.03
2 Equ.op.III 1 1.00 39.79 39.79 8.97
3
Labour Sub-total                 443.59                      -                                  16.43 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
Equipment Sub-total             514.88                  426.76                88.12                                15.80 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Crushed Aggregate m 228.77 77.46 8.00 1,830.18 619.70 100.00
2
Material Sub-total              1,830.18              619.70                                67.77 
Total Cost per crew day              2,700.52              707.82 

Average daily production (ADP) = 8.00 m3


Activity operational cost per crew day / ADP = 337.56 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 455.71 Birr/m3
Activity replacement cost per crew day / ADP = 88.48 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 119.45 Birr/m3
Total Activity Unit Rate =                      575.16 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 20 km free haul

Stadia Engineering Works Consultant Plc Page 95 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  89.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Class "B" Stone Masonry Scope: Structure                         25.00   m3   Result:           1,660.28   Birr/m3 
*with 10km free-haul
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 8.00 54.57 436.54 3.77
2 Equ.op.III 1 5.00 39.79 198.94 1.72
3 St.eq.opI 1 8.00 22.74 181.89 1.57
4 Mason I 20 160.00 22.17 3,546.87 30.59
5 Carpenter II 1 8.00 54.57 436.54 3.77
6 Helper I 2 16.00 18.76 300.12 2.59
7 Labour I 40 320.00 12.62 4,037.98 34.83
8 Labour III 20 160.00 15.35 2,455.53 21.18
Labour Sub-total            11,594.41                      -                                  41.09 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 4.00 481.75 104.04 585.79 1,927.00 416.15 47.07
2 Loader, Crawler 2-2.5 M3 1.00 979.60 802.82 1,782.42 979.60 802.82 23.93
3 Water truck,6*4 20000Lits 2.00 422.98 145.63 568.61 845.96 291.26 20.66
4 Concrete Mixer,Trailer Mounted 250 Lit 8.00 42.64 8.28 50.92 341.13 66.21 8.33
5 Hand Tools
Equipment Sub-total          2,987.73               4,093.69           1,576.43                                14.51 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 26.25 6,714.23 - 53.58
2 Sand m3 461.54 6.00 2,769.23 - 22.10
3 Stone M3 106.02 33.03 28.75 3,048.22 949.68 24.32
Material Sub-total            12,531.67              949.68                                44.41 
Total Cost per crew day            28,219.77           2,526.11 

Average daily production (ADP) = 25.00 m3


Activity operational cost per crew day / ADP = 1,128.79 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 1,523.87 Birr/m3
Activity replacement cost per crew day / ADP = 101.04 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 136.41 Birr/m3
Total Activity Unit Rate =                   1,660.28 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 96 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  810.01(a) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  MSE Gabion wall facing Scope: Structure                           6.00      Result:           2,432.81   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
Labour Sub-total              1,161.15                      -                                  11.03 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
Equipment Sub-total                 426.76                88.12                                  4.05 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 PVC-coated Gabion boxes,3*3*1*1m No 3,881.76 2.00 7,763.52 86.86
2 Binding wire Kg 32.00 1.50 48.00 0.54
3 Geotextile M2 81.77 - 6.00 490.60 - 5.49
4 Stone M3 106.02 33.03 6.00 636.15 198.19 7.12
Material Sub-total              8,938.27              198.19                                84.91 
Total Cost per crew day            10,526.18              286.32 

Average daily production (ADP) = 6.00


Activity operational cost per crew day / ADP = 1,754.36 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 2,368.39 Birr/m2
Activity replacement cost per crew day / ADP = 47.72 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 64.42 Birr/m2
Total Activity Unit Rate =                   2,432.81 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 97 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  810.01(b) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Polymeric (Geogrid) Reinforcements Scope: Structure                       200.00      Result:              284.41   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 13.87
2 Labour I 8 64.00 12.62 807.60 82.09
3 Equ.op.III 1 1.00 39.79 39.79 4.04
Labour Sub-total                 983.80                      -                                    2.34 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total                 426.76                88.12                                  1.01 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Geogrid M2 203.18 200.00 40,635.54 100.00
2
Material Sub-total            40,635.54                      -                                  96.65 
Total Cost per crew day            42,046.10                88.12 

Average daily production (ADP) = 200.00


Activity operational cost per crew day / ADP = 210.23 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 283.81 Birr/m2
Activity replacement cost per crew day / ADP = 0.44 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 0.59 Birr/m2
Total Activity Unit Rate =                      284.41 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 98 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  810.01(c) Category: Mechanized  ADP=  March 21, 2017
Activity Name:  Scope: Structure                       110.00      Result:              447.51   Birr/m2 
Drainage at interface of backfill and in-situ soil

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.61
2 Equ.op.III 1 5.32 39.79 211.80 18.03
3 Helper I 1 1.00 18.76 18.76 1.60
4 Labour I 8 64.00 12.62 807.60 68.76
5
6
Labour Sub-total              1,174.57                      -                                    3.86 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Loader, Wheel 2-2.5 M3 0.47 591.65 496.23 1,087.88 276.60 231.99 9.35
2 Dump truck,6*4 (12m3) 12M3 4.86 481.75 104.04 585.79 2,339.24 505.18 79.09
3 Plate Compactor - 32.00 10.68 5.09 15.77 341.76 162.83 11.56
4 Hand Tools
5
Equipment Sub-total          1,689.44               2,957.60              899.99                                  9.71 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
3
1 Sub-base aggregate m 228.77 77.46 66.00 15,098.95 5,112.54 57.37
2 PVC Pipe, 110mm No 184.80 9.17 1,694.00 6.44
3 Perforated PVC Pipe, 150mm No 369.60 18.33 6,776.00 25.75
4 Impermeable Membrane M2 25.00 110.00 2,750.00 10.45
Material Sub-total            26,318.95           5,112.54                                86.43 
Total Cost per crew day            30,451.12           6,012.53 

Average daily production (ADP) = 110.00


Activity operational cost per crew day / ADP = 276.83 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 373.72 Birr/m2
Activity replacement cost per crew day / ADP = 54.66 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 73.79 Birr/m2
Total Activity Unit Rate =                      447.51 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 99 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  91.03(a)(i) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Gabion boxes (2x1x1)  Scope: Ancillary Works                           8.00      Result:              944.80   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
Labour Sub-total              1,161.15                      -                                  22.13 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
Equipment Sub-total                 426.76                88.12                                  8.13 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Gabion boxes, 2m*1m*1m No 686.58 4.00 2,746.33 75.07
2 Binding wire Kg 32.00 2.00 64.00 1.75
3 Stone M3 106.02 33.03 8.00 848.20 264.26 23.18
Material Sub-total              3,658.53              264.26                                69.73 
Total Cost per crew day              5,246.44              352.38 

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 655.80 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 885.34 Birr/m3
Activity replacement cost per crew day / ADP = 44.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 59.46 Birr/m3
Total Activity Unit Rate =                      944.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 100 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  91.03(a)(ii) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Gabion boxes (1.5x1x1)  Scope: Ancillary Works                           8.00      Result:              986.93   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.75
2 Equ.op.III 1 1.00 39.79 39.79 3.43
3 Mason I 1 8.00 22.17 177.34 15.27
4 Labour I 8 64.00 12.62 807.60 69.55
5
Labour Sub-total              1,161.15                      -                                  21.13 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand Tools
3
4
Equipment Sub-total                 426.76                88.12                                  7.76 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Gabion boxes, 1.5m*1m*1m No 561.75 5.33 2,996.00 76.66
2 Binding wire Kg 32.00 2.00 64.00 1.64
3 Stone M3 106.02 33.03 8.00 848.20 264.26 21.70
4
Material Sub-total              3,908.20              264.26                                71.11 
Total Cost per crew day              5,496.10              352.38 

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 687.01 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 927.47 Birr/m3
Activity replacement cost per crew day / ADP = 44.05 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 59.46 Birr/m3
Total Activity Unit Rate =                      986.93 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 101 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  91.04 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         50.00      Result:              110.38   Birr/m2 
Filter Fabric (Terram 1000 or equivalent)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 40.32
2 Labour I 2 16.00 12.62 201.90 59.68
3
Labour Sub-total                 338.32                      -                                    8.28 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1
Equipment Sub-total                        -                        -      
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Geo-Textile filter fabric M2 75.00 50.00 3,750.00 100.00
2
Material Sub-total              3,750.00                      -                                  91.72 
Total Cost per crew day              4,088.32                      -   

Average daily production (ADP) = 50.00


Activity operational cost per crew day / ADP = 81.77 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 110.38 Birr/m2
Activity replacement cost per crew day / ADP = - Birr/m2
Total Repl. unit cost including 35% overhead & profit = - Birr/m2
Total Activity Unit Rate =                      110.38 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 102 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  92.01(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         50.00      Result:              811.09   Birr/each 
Guide Posts (reinforced concrete C- 20)
*including class C-concrete footing
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 5.60
2 Labour I 15 120.00 12.62 1,514.24 62.13
3 Mason I 2 16.00 22.17 354.69 14.55
4 Driver II 1 8.00 34.10 272.84 11.19
5 Equ.op.III 1 4.00 39.79 159.15 6.53
6
Labour Sub-total              2,437.34                      -                                    8.38 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total              1,707.03              352.49                                  5.87 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 3.29 1,517.91 6.09
2 Cement Quintal 255.78 23.02 5,888.49 23.62
3
3 Crushed Aggregate M 243.73 84.20 4.54 1,105.73 382.00 4.43
4 Guide Posts No 288.44 4.55 50.00 14,421.76 227.69 57.84
5 Reflector No 20.00 100.00 2,000.00 - 8.02
Material Sub-total            24,933.89              609.69                                85.75 
Total Cost per crew day            29,078.26              962.18 

Average daily production (ADP) = 50.00


Activity operational cost per crew day / ADP = 581.57 Birr/each
Total Oper. unit cost including 35% overhead & profit = 785.11 Birr/each
Activity replacement cost per crew day / ADP = 19.24 Birr/each
Total Repl. unit cost including 35% overhead & profit = 25.98 Birr/each
Total Activity Unit Rate =                      811.09 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 103 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  92.01(c) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         20.00   No.   Result:              803.77   Birr/each 
Kilometer posts (reinforced concrete C- 20)
*including class c-concrete footing
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 6.71
2 Labour I 11 88.00 12.62 1,110.44 54.61
3 Mason I 2 16.00 22.17 354.69 17.44
4 Driver II 1 8.00 34.10 272.84 13.42
5 Equ.op.III 1 4.00 39.79 159.15 7.83
6
Labour Sub-total              2,033.54                      -                                  17.74 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 4.00 426.76 88.12 514.88 1,707.03 352.49 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total              1,707.03              352.49                                14.89 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.76 350.11 4.53
2 Cement Quintal 255.78 5.31 1,358.19 17.59
3
3 Crushed Aggregate M 243.73 84.20 1.01 246.52 3.19
4 Km Post No 288.44 4.55 20.00 5,768.70 91.07 74.69
Material Sub-total              7,723.52                91.07                                67.37 
Total Cost per crew day            11,464.09              443.56 

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 573.20 Birr/each
Total Oper. unit cost including 35% overhead & profit = 773.83 Birr/each
Activity replacement cost per crew day / ADP = 22.18 Birr/each
Total Repl. unit cost including 35% overhead & profit = 29.94 Birr/each
Total Activity Unit Rate =                      803.77 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 104 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  93.01 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Galvanized guard rails on steel post Scope: Ancillary Works                         20.00   m   Result:              494.17   Birr/m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total                 405.39                      -                                    5.60 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total                 426.76                88.12                                  5.90 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Guardrail m 320.04 20.00 6,400.73 - 100.00
2
Material Sub-total              6,400.73                      -                                  88.49 
Total Cost per crew day              7,232.88                88.12 

Average daily production (ADP) = 20.00 m


Activity operational cost per crew day / ADP = 361.64 Birr/m
Total Oper. unit cost including 35% overhead & profit = 488.22 Birr/m
Activity replacement cost per crew day / ADP = 4.41 Birr/m
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/m
Total Activity Unit Rate =                      494.17 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 105 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  94.01(a)(i) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         10.00   m2   Result:           1,572.79   Birr/m2 
Traffic signs (Area not exceeding 2 m²)
*thickness 2mm and Area not exceeding 2sq m.
Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total                 405.39                      -                                    3.51 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total                 426.76                88.12                                  3.69 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sign faces made by Alluminium alloy M2 1,073.00 10.00 10,730.00 - 100.00
2
Material Sub-total            10,730.00                      -                                  92.80 
Total Cost per crew day            11,562.15                88.12 

Average daily production (ADP) = 10.00 m2


Activity operational cost per crew day / ADP = 1,156.21 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 1,560.89 Birr/m2
Activity replacement cost per crew day / ADP = 8.81 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 11.90 Birr/m2
Total Activity Unit Rate =                   1,572.79 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: *1 m2 aluminium plate used for three signs

Stadia Engineering Works Consultant Plc Page 106 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  94.01(a)(ii) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Traffic signs (Area exceeding 2 m²) Scope: Ancillary Works                           8.00      Result:           1,603.85   Birr/m2 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Welder I 1 8.00 20.46 163.70 40.38
2 Labour I 2 16.00 12.62 201.90 49.80
3 Equ.op.III 1 1.00 39.79 39.79 9.81
Labour Sub-total                 405.39                      -                                    4.31 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
Equipment Sub-total                 426.76                88.12                                  4.53 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sign faces made by Alluminium alloy M2 1,073.00 8.00 8,584.00 - 100.00
2
Material Sub-total              8,584.00                      -                                  91.16 
Total Cost per crew day              9,416.15                88.12 

Average daily production (ADP) = 8.00


Activity operational cost per crew day / ADP = 1,177.02 Birr/m2
Total Oper. unit cost including 35% overhead & profit = 1,588.97 Birr/m2
Activity replacement cost per crew day / ADP = 11.02 Birr/m2
Total Repl. unit cost including 35% overhead & profit = 14.87 Birr/m2
Total Activity Unit Rate =                   1,603.85 Birr/m2

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 107 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  94.02(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         20.00      Result:              730.71   Birr/each 
Sign Supports (Concrete Class C 20/20)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 29.30
2 Bar Sett.I 1 8.00 30.69 245.55 21.97
3 Labour I 5 40.00 12.62 504.75 45.17
4 Equ.op.III 1 1.00 39.79 39.79 3.56
Labour Sub-total              1,117.49                      -                                  10.46 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 1.00 42.64 8.28 50.92 42.64 8.28 8.67
2 Concrete Vibrator 5 HP 1.00 22.48 2.43 24.91 22.48 2.43 4.57
3 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 86.76
Equipment Sub-total                 491.88                98.83                                  4.60 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 0.32 147.69 1.63
2 Cement Quintal 255.78 2.88 736.65 8.12
3
3 Crushed Aggregate M 243.73 84.20 0.48 116.99 40.42 1.29
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.21 4,075.33 44.90
5 Lumber m3 10,000.00 0.40 4,000.00 44.07
Material Sub-total              9,076.66                40.42                                84.94 
Total Cost per crew day            10,686.03              139.25 

Average daily production (ADP) = 20.00


Activity operational cost per crew day / ADP = 534.30 Birr/each
Total Oper. unit cost including 35% overhead & profit = 721.31 Birr/each
Activity replacement cost per crew day / ADP = 6.96 Birr/each
Total Repl. unit cost including 35% overhead & profit = 9.40 Birr/each
Total Activity Unit Rate =                      730.71 Birr/each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: Re-using the lumber 10 times

Stadia Engineering Works Consultant Plc Page 108 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  94.02(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Sign Supports (Steel) Scope: Ancillary Works                         20.00   No.   Result:              555.79   Birr/Each 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason I 1 8.00 22.17 177.34 42.32
2 Equ.op.III 1 1.00 39.79 39.79 9.50
3 Labour I 2 16.00 12.62 201.90 48.18
Labour Sub-total                 419.03                      -                                    5.14 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2
3
Equipment Sub-total             514.88                  426.76                88.12                                  5.24 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Steel Pipes (Dia. 75mm) No 600.00 12.17 7,300.00 - 100.00
2
Material Sub-total              7,300.00                      -                                  89.62 
Total Cost per crew day              8,145.79                88.12 

Average daily production (ADP) = 20.00 No.


Activity operational cost per crew day / ADP = 407.29 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 549.84 Birr/Each
Activity replacement cost per crew day / ADP = 4.41 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 5.95 Birr/Each
Total Activity Unit Rate =                      555.79 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 109 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  94.03 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                           4.80   m3   Result:           2,662.35   Birr/m3 
Concrete in road sign footings including exc. and 
backfilling (Class 15/20)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 6.24
2 Labour I 16 128.00 12.62 1,615.19 73.89
3 Mason I 2 16.00 22.17 354.69 16.23
4 Driver II 0 - 34.10 -
5 Equ.op.III 1 2.00 39.79 79.58 3.64
6
Labour Sub-total              2,185.87                      -                                  24.16 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 100.00
2 Pick Up,Double cab,4*4,Diesel - - 191.31 178.96 370.27 - -
3 Hand Tools
4
Equipment Sub-total                 853.51              176.24                                  9.43 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 1.92 886.15 14.75
2 Cement Quintal 255.78 17.28 4,419.88 73.57
3
3 Crushed Aggregate M 243.73 84.20 2.88 701.95 242.51 11.68
4
Material Sub-total              6,007.98              242.51                                66.41 
Total Cost per crew day              9,047.37              418.75 

Average daily production (ADP) = 4.80 m3


Activity operational cost per crew day / ADP = 1,884.87 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 2,544.57 Birr/m3
Activity replacement cost per crew day / ADP = 87.24 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 117.77 Birr/m3
Total Activity Unit Rate =                   2,662.35 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

NB: * 30km free haul distance for sand & aggregate hauling

Stadia Engineering Works Consultant Plc Page 110 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  95.01(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  White lines (broken or unbroken) (width of  Scope: Ancillary Works                           5.00   km   Result:         12,506.72   Birr/Km 
100mm)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.II 1 8.00 28.42 227.36 31.06
2 Labour I 5 40.00 12.62 504.75 68.94
3
Labour Sub-total                 732.11                      -                                    1.64 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Road Marking Machine - 8.00 501.46 223.15 724.61 4,011.70 1,785.22 100.00
2 Hand Tools
3
4
Equipment Sub-total              4,011.70           1,785.22                                  9.01 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Thermoplastic paint l 37.44 1,000.00 37,439.14 94.09
2 Glass beads Kg 26.00 90.50 2,353.00 5.91
3
Material Sub-total            39,792.14                      -                                  89.35 
Total Cost per crew day            44,535.95           1,785.22 

Average daily production (ADP) = 5.00 km


Activity operational cost per crew day / ADP = 8,907.19 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 12,024.71 Birr/Km
Activity replacement cost per crew day / ADP = 357.04 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 482.01 Birr/Km
Total Activity Unit Rate =                 12,506.72 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 111 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  95.01(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Yellow lines (broken or unbroken) (width of  Scope: Ancillary Works                           5.00   km   Result:         12,506.72   Birr/Km 
100mm)

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Equ.op.II 1 8.00 28.42 227.36 31.06
2 Labour I 5 40.00 12.62 504.75 68.94
3
Labour Sub-total                 732.11                      -                                    1.64 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Road Marking Machine - 8.00 501.46 223.15 724.61 4,011.70 1,785.22 100.00
2 Hand Tools
3
4
Equipment Sub-total              4,011.70           1,785.22                                  9.01 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Thermoplastic paint l 37.44 1,000.00 37,439.14 94.09
2 Glass beads Kg 26.00 90.50 2,353.00 5.91
3
Material Sub-total            39,792.14                      -                                  89.35 
Total Cost per crew day            44,535.95           1,785.22 

Average daily production (ADP) = 5.00 km


Activity operational cost per crew day / ADP = 8,907.19 Birr/Km
Total Oper. unit cost including 35% overhead & profit = 12,024.71 Birr/Km
Activity replacement cost per crew day / ADP = 357.04 Birr/Km
Total Repl. unit cost including 35% overhead & profit = 482.01 Birr/Km
Total Activity Unit Rate =                 12,506.72 Birr/Km

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 112 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  95.04(a) Category:  ADP=  March 21, 2017
Activity Name:  In situ asphalt Speed Bumps  Scope: Ancillary Works                         40.00      Result:           3,829.40    Br / m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 10.37
2 Labour I 5 40.00 12.62 504.75 38.38
3 Equ.op.III 1 3.00 39.79 119.37 9.08
4 St.eq.opII 1 4.00 28.42 113.68 8.64
5 Equ.op.II 1 4.00 28.42 113.68 8.64
6 Carpenter I 1 8.00 40.93 327.40 24.89
Labour Sub-total              1,315.30                                  1.23 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 3.00 426.76 88.12 514.88 1,280.27 264.37 26.13
2 Roller,Vibrator,2Drums 8 ton 4.00 478.94 281.42 760.36 1,915.76 1,125.67 39.11
3 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 34.76
4 Hand Tools
5
6 8.00
Equipment Sub-total              4,899.01           1,864.72                                  4.59 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Asphalt Hot Mix M3 3,135.65 152.50 32.00 100,340.72 4,880.07 99.84
2 Lumber m3 10,000.00 0.006 64.00 - 0.06
3 Equaliptus Pole (Dia. 100mm, 8m long) No 100.00 1.000 100.00 - 0.10
Material Sub-total          100,504.72           4,880.07                                94.18 
Total Cost per crew day          106,719.03           6,744.79 

Average daily production (ADP) = 40.00


Activity operational cost per crew day / ADP = 2,667.98 Br / m
Total Oper. unit cost including 35% overhead & profit = 3,601.77 Br / m
Activity replacement cost per crew day / ADP = 168.62 Br / m
Total Repl. unit cost including 35% overhead & profit = 227.64 Br / m
Total Activity Unit Rate =                   3,829.40 Br / m

Stadia Engineering Works Consultant Plc Page 113 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  95.04(b) Category:  ADP=  March 21, 2017
Activity Name:  In situ asphalt Rumble Strips  Scope: Ancillary Works                         12.00      Result:              907.86    Br / m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 10.70
2 Labour I 5 40.00 12.62 504.75 39.57
3 Equ.op.III 1 2.00 39.79 79.58 6.24
4 St.eq.opII 1 4.00 28.42 113.68 8.91
5 Equ.op.II 1 4.00 28.42 113.68 8.91
6 Carpenter I 1 8.00 40.93 327.40 25.67
Labour Sub-total              1,275.51                                20.34 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 2.00 426.76 88.12 514.88 853.51 176.24 19.08
2 Roller,Vibrator,2Drums 8 ton 4.00 478.94 281.42 760.36 1,915.76 1,125.67 42.84
3 Street Sweeper, Self Prop 1-2m 4.00 425.74 118.67 544.41 1,702.98 474.68 38.08
4 Hand Tools
5
6 8.00
Equipment Sub-total              4,472.25           1,776.60                                71.31 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Asphalt Hot Mix M3 3,135.65 152.50 0.14 451.53 21.96 86.25
2 Lumber m3 10,000.00 0.007 72.00 - 13.75
3
Material Sub-total                 523.53                21.96                                  8.35 
Total Cost per crew day              6,271.30           1,798.56 

Average daily production (ADP) = 12.00


Activity operational cost per crew day / ADP = 522.61 Br / m
Total Oper. unit cost including 35% overhead & profit = 705.52 Br / m
Activity replacement cost per crew day / ADP = 149.88 Br / m
Total Repl. unit cost including 35% overhead & profit = 202.34 Br / m
Total Activity Unit Rate =                      907.86 Br / m

Stadia Engineering Works Consultant Plc Page 114 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.01 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Stockpiling of Topsoil Scope: Ancillary Works                    1,120.00      Result:                66.80   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Const.For II 1 8.00 73.89 591.15 17.69
2 Equ.op.IV 2 16.00 102.31 1,637.02 48.97
3 Equ.op.III 4 25.27 39.79 1,005.33 30.08
4 Labour II 1 8.00 13.64 109.13 3.26
Labour Sub-total              3,342.62                                  8.86 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Crawler Dozer 280-330 HP 16.00 1,334.09 746.61 2,080.71 21,345.50 11,945.82 62.07
2 Dump truck,6*4 (12m3) 12M3 17.33 481.75 104.04 585.79 8,350.33 1,803.31 24.28
3 Loader, Wheel 2-2.5 M3 7.93 591.65 496.23 1,087.88 4,693.76 3,936.77 13.65
4
5
Equipment Sub-total          3,754.38             34,389.59         17,685.90                                91.14 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day            37,732.22         17,685.90 

Average daily production (ADP) = 1,120.00


Activity operational cost per crew day / ADP = 33.69 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 45.48 Birr/m3
Activity replacement cost per crew day / ADP = 15.79 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 21.32 Birr/m3
Total Activity Unit Rate =                        66.80 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 115 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.02(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Top-soiling  Scope: Ancillary Works                         60.00      Result:                49.64   Birr/m3 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.37
2 Equ.op.III 1 1.35 39.79 53.86 4.49
3 Labour I 10 80.00 12.62 1,009.49 84.14
4
Labour Sub-total              1,199.77                                63.19 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 0.93 481.75 104.04 585.79 447.34 96.61 64.02
2 Loader, Wheel 2-2.5 M3 0.43 591.65 496.23 1,087.88 251.45 210.90 35.98
3
4
5
Equipment Sub-total          1,673.67                  698.79              307.50                                36.81 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1
2
Material Sub-total                        -                        -      
Total Cost per crew day              1,898.56              307.50 

Average daily production (ADP) = 60.00


Activity operational cost per crew day / ADP = 31.64 Birr/m3
Total Oper. unit cost including 35% overhead & profit = 42.72 Birr/m3
Activity replacement cost per crew day / ADP = 5.13 Birr/m3
Total Repl. unit cost including 35% overhead & profit = 6.92 Birr/m3
Total Activity Unit Rate =                        49.64 Birr/m3

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 116 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.02(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Provide and apply chemical fertilizers Scope: Ancillary Works                           1.88      Result:         17,154.42   Birr/t 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total              1,185.70                                  5.00 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total             514.88                  426.76                88.12                                  1.80 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Urea t 11,800.00 1.875 22,125.00 - 100.00
2
Material Sub-total            22,125.00                      -                                  93.21 
Total Cost per crew day            23,737.46                88.12 

Average daily production (ADP) = 1.88


Activity operational cost per crew day / ADP = 12,659.98 Birr/t
Total Oper. unit cost including 35% overhead & profit = 17,090.97 Birr/t
Activity replacement cost per crew day / ADP = 47.00 Birr/t
Total Repl. unit cost including 35% overhead & profit = 63.45 Birr/t
Total Activity Unit Rate =                 17,154.42 Birr/t

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 117 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.03(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Planting of grass cuttings  Scope: Ancillary Works                           0.05      Result:       113,415.69   Birr/ha 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total              1,185.70                                28.83 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total             514.88                  426.76                88.12                                10.38 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Grass Cuttings ha 50,000.00 0.050 2,500.00 - 100.00
2
Material Sub-total              2,500.00                      -                                  60.79 
Total Cost per crew day              4,112.46                88.12 

Average daily production (ADP) = 0.05


Activity operational cost per crew day / ADP = 82,249.17 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 111,036.39 Birr/ha
Activity replacement cost per crew day / ADP = 1,762.45 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 2,379.31 Birr/ha
Total Activity Unit Rate =               113,415.69 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 118 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.03(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Seeding  Scope: Ancillary Works                           0.10      Result:         56,707.85   Birr/ha 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total              1,185.70                                28.83 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total             514.88                  426.76                88.12                                10.38 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Grass Seeds ha 25,000.00 0.100 2,500.00 - 100.00
2
Material Sub-total              2,500.00                      -                                  60.79 
Total Cost per crew day              4,112.46                88.12 

Average daily production (ADP) = 0.10


Activity operational cost per crew day / ADP = 41,124.59 Birr/ha
Total Oper. unit cost including 35% overhead & profit = 55,518.19 Birr/ha
Activity replacement cost per crew day / ADP = 881.22 Birr/ha
Total Repl. unit cost including 35% overhead & profit = 1,189.65 Birr/ha
Total Activity Unit Rate =                 56,707.85 Birr/ha

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 119 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  96.04 Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Replacement or replanting of trees and growth  Scope: Ancillary Works                       500.00      Result:              139.59   Birr/Each 
management

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Labor Foreman 1 8.00 17.05 136.42 11.51
2 Equ.op.III 1 1.00 39.79 39.79 3.36
3 Labour I 10 80.00 12.62 1,009.49 85.14
4
Labour Sub-total              1,185.70                                  2.30 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 100.00
2 Hand tools
3
4
5
Equipment Sub-total             514.88                  426.76                88.12                                  0.83 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Tree No 100.00 500.000 50,000.00 - 100.00
2
Material Sub-total            50,000.00                      -                                  96.88 
Total Cost per crew day            51,612.46                88.12 

Average daily production (ADP) = 500.00


Activity operational cost per crew day / ADP = 103.22 Birr/Each
Total Oper. unit cost including 35% overhead & profit = 139.35 Birr/Each
Activity replacement cost per crew day / ADP = 0.18 Birr/Each
Total Repl. unit cost including 35% overhead & profit = 0.24 Birr/Each
Total Activity Unit Rate =                      139.59 Birr/Each

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 120 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  99.02(a) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Masonry Safety Barrier Scope: Ancillary Works                         14.00      Result:           1,007.61   Birr/m 

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Mason Foreman 1 4.00 54.57 218.27 7.95
2 Equ.op.III 1 3.00 39.79 119.37 4.35
3 Mason I 5 40.00 22.17 886.72 32.30
4 Carpenter II 1 4.00 54.57 218.27 7.95
5 Labour II 5 40.00 13.64 545.67 19.88
6 Labour I 8 60.00 12.62 757.12 27.58
Labour Sub-total              2,745.42                      -                                  29.83 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Dump truck,6*4 (12m3) 12M3 2.00 481.75 104.04 585.79 963.50 208.07 61.96
2 Loader, Wheel 2-2.5 M3 1.00 591.65 496.23 1,087.88 591.65 496.23 38.04
3 Hand Tools
Equipment Sub-total          1,673.67               1,555.15              704.31                                16.90 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Cement Quintal 255.78 8.40 2,148.55 - 43.82
2 Sand m3 461.54 2.02 930.46 - 18.98
3 Stone M3 106.02 33.03 16.10 1,707.00 531.82 34.82
4 Lean Concrete M3 1,735.05 169.18 0.05 91.09 8.88 1.86
5 Formwork m2 172.07 5.51 0.15 25.81 0.83 0.53
Material Sub-total              4,902.92              541.53                                53.27 
Total Cost per crew day              9,203.48           1,245.83 

Average daily production (ADP) = 14.00


Activity operational cost per crew day / ADP = 657.39 Birr/m
Total Oper. unit cost including 35% overhead & profit = 887.48 Birr/m
Activity replacement cost per crew day / ADP = 88.99 Birr/m
Total Repl. unit cost including 35% overhead & profit = 120.13 Birr/m
Total Activity Unit Rate =                   1,007.61 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 121 of 122


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2
Activity No :  99.02(b) Category: Labour intensive  ADP=  March 21, 2017
Activity Name:  Scope: Ancillary Works                         30.00      Result:              845.03   Birr/m 
Safety Barrier Precast Concrete as per drawing

Labour
 Hours per  Hourly cost
Item No Type  Daily cost   % for operation  
crew day  (Indexed) 
1 Carpenter I 1 8.00 40.93 327.40 29.30
2 Bar Sett.I 1 8.00 30.69 245.55 21.97
3 Labour I 5 40.00 12.62 504.75 45.17
4 Equ.op.III 1 1.00 39.79 39.79 3.56
Labour Sub-total              1,117.49                      -                                    6.16 
Equipment
 Hours per
Item No Type Capacity  Hourly cost   Daily cost   % for Operaton 
crew day 
Oper. C.  Repl.C.   Total. C.   Oper. C.   Repl.C. 
1 Concrete Mixer,Trailer Mounted 250 Lit 1.00 42.64 8.28 50.92 42.64 8.28 8.67
2 Concrete Vibrator 5 HP 1.00 22.48 2.43 24.91 22.48 2.43 4.57
3 Dump truck,6*4 (8m3) 8M3 1.00 426.76 88.12 514.88 426.76 88.12 86.76
Equipment Sub-total                 491.88                98.83                                  2.71 
Material
Item No Type Unit  Unit price   Quantity   Daily cost   % for Operaton 
 Oper. C.  Repl. C.  Oper. C.   Repl. C. 
1 Sand m3 461.54 4.36 2,010.46 12.17
2 Cement Quintal 255.78 39.20 10,027.60 60.70
3
3 Crushed Aggregate M 243.73 84.20 6.53 1,592.55 550.19 9.64
4 Reinforcement Bar (Mild, Grade-40) t 19,060.00 0.05 1,015.52 6.15
2
5 Formwork m 172.07 5.51 10.89 1,873.84 59.98 11.34
Material Sub-total            16,519.96              550.19                                91.12 
Total Cost per crew day            18,129.33              649.02 

Average daily production (ADP) = 30.00


Activity operational cost per crew day / ADP = 604.31 Birr/m
Total Oper. unit cost including 35% overhead & profit = 815.82 Birr/m
Activity replacement cost per crew day / ADP = 21.63 Birr/m
Total Repl. unit cost including 35% overhead & profit = 29.21 Birr/m
Total Activity Unit Rate =                      845.03 Birr/m

Operation Cost: Fuel+Oil & Lub+ Maintenance +Tyre & Tube Cost
Total Cost : Operational + Financial + Depreciation Cost

Stadia Engineering Works Consultant Plc Page 122 of 122


JINKA TOWN ROAD PROJECT

SUMMARIZED INPUTS FOR


BREAKDOWNS
JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Overhead and Profit Factor


Overhead & Profit Factor 1.35

Date March 21, 2017

Project Duration
Total Construction Period (Months) 12
Mobilization Period (Months) 0

Stadia Engineering Works Consultant PLC Page 1 of 1


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


I.Labor Classification
Item No. I SUPERVISOR CLASS
1 Labourer Foreman
2 Quarry Foreman
3 Quarry Supervisor
4 Mason Foreman
5 Carpenter Foreman
6 Construction Foreman
7 Superintendant I
8 Superintendant II
Item No. II TECHNICAL CLASS
1 Electrician II
2 Mechanic II
3 Welder II
4 Electrician III
5 Mechanic III
6 Welder I
Item No. III OPERATORS CLASS
1 Equipment Operator I
2 Equipment Operator II
3 Equipment Operator III
4 Equipment Operator IV
5 Equipment Operator V
6 Sta.Equipment Operator I
7 Sta.Equipment Operator II
8 Sta.Equipment Operator III
9 Stat.Equip. Oper. IV
Item No. IV TRADEMEN CLASS
1 Powder man I
2 Powder man II
3 Barsetter I
4 Barsetter II
5 Carpenter I
6 Carpenter II
7 Carpenter III
8 Mason I
9 Mason II
10 Mason III
Item No. V SKILLED CLASS
1 Labourer II
2 Helper II
3 Helper III
4 Labourer III
Item No. VI UNSKILLED CLASS
1 Labourer I
2 Helper I

Stadia Engineering Works Consultant PLC Page 1 of 4


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour

II. Working Days per Month


a) No. of Working days per week (Monday - Saturday)= 6 day/week
b) No. of Working hours for one working day= 8 hour/day
c) Working hours/week (a*b)= 48 hour/week
d) Distributed Working hours/day in a week (c/a)= 8 hour/day
e) Working weeks/year (365.25days/7days)= 52.18 week/year
f) Working hours/month (e*c/12 months)= 208.71 hour/month
g) Working days/month (f/d)= 26.09 day/month

III.PAID NON-PRODUCTION DAYS

1.Annual leave per month,taking 19 days annual leave (19 days/12month)


= 1.58 day/month

2.Public holidays per month,12 holidays per year excluding Easter(12 days/12 month)
= 1.00 day/month

3.Leave for family event per month ,mourning,wedding..assuming 1.5 days per year(1.5 days /12 month)
= 0.13 day/month
4.Leave for special purpose per month,court case 6 days leave(6 days/12month)

= 0.50 day/month

5.Sick leave per month: (Treshhold is one month per year. Then assuming 15 days in a year(15 days/12
month)
= 1.25 day/month
6.Bad weather per month,assuming 60 rainy days in a year(60 days/12month)
= 5.00 day/month
7.Clothing and shoes supplies(assumed to be 1 day per month)
= 1.00 day/month
8.Pension/severance contribution to workers per month 11.00% (11.00%*g)
= 2.87 day/month
9.Maternal leave of 90 days - Considering a single mother's pregnancy once in 3 years
- Considering an average of 800 employees per month with Gender proportion
(y)=40 (females)/1485 (Total no. of employee)=0.027; out of which 50.0% of them
can give birth
- Hence, the Maternal leave per month is = (90 days/ 36 month)*y*50.0%
= 0.03 day/month

Stadia Engineering Works Consultant PLC Page 2 of 4


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


10.Perdiem for field workers ,by considering regular employees, 70.0% of the monthly salary (70.0%*g)
= 18.26 day/month
11.Insurance,by assuming 1.0% of monthly salary (1.0%*g)
= 0.26 day/month
12.Desert Allowance, 15.0% of basic salary (15.0%*g)
= 3.91 day/month

IV.LABOR INDEX FACTOR

1.Regular salary(g/g)= 1.000


2.Annual leave(1/g)= 0.061
3.Public holydays(2/g)= 0.038
4.Leave for family events(3/g)= 0.005
5.Leave for special purposes(4/g)= 0.019
6.Sick leave(5/g)= 0.048
7.Bad weather(6/g)= 0.192
8.Clothing & shoe(7/g)= 0.038
9.Pension/severance(8/g)= 0.110
10.Maternal leave(9/g)= 0.001
11.Perdiem for field workers(10/g)= 0.700
12.Insurance(11/g)= 0.010
13.Desert Allowance(12/g)= 0.150

Index factor = 2.372

Stadia Engineering Works Consultant PLC Page 3 of 4


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Calculation Of Hourly Indexed Salary of Direct Labour


Table 1 Indexed Hourly Salary List March 21, 2017
Title Name

Grade A

Grade D

Monthly
Average

Indexed
Annual

Hourly
Salary

Salary

Salary

Salary
Daily
a b c=(a+b)/2 d=c*12 e=d/313 f=e/8*2.372
Driver I 2,800.00 2,800.00 2,800.00 33,600.00 107.35 31.83
Driver II 3,000.00 3,000.00 3,000.00 36,000.00 115.02 34.10
Driver III 3,200.00 3,200.00 3,200.00 38,400.00 122.68 36.38
Driver IV 3,400.00 3,400.00 3,400.00 40,800.00 130.35 38.65
Driver V 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Equ.op.I 2,000.00 2,000.00 2,000.00 24,000.00 76.68 22.74
Equ.op.II 2,500.00 2,500.00 2,500.00 30,000.00 95.85 28.42
Equ.op.III 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Equ.op.IV 9,000.00 9,000.00 9,000.00 108,000.00 345.05 102.31
Equ.op.V 10,000.00 10,000.00 10,000.00 120,000.00 383.39 113.68
St.eq.opI 2,000.00 2,000.00 2,000.00 24,000.00 76.68 22.74
St.eq.opII 2,500.00 2,500.00 2,500.00 30,000.00 95.85 28.42
St.eq.opIII 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
St.eq.opIV 9,000.00 9,000.00 9,000.00 108,000.00 345.05 102.31
St.eq.opV 12,000.00 12,000.00 12,000.00 144,000.00 460.06 136.42
Labour I 1,110.00 1,110.00 1,110.00 13,320.00 42.56 12.62
Labour II 1,200.00 1,200.00 1,200.00 14,400.00 46.01 13.64
Labour III 1,350.00 1,350.00 1,350.00 16,200.00 51.76 15.35
Helper I 1,650.00 1,650.00 1,650.00 19,800.00 63.26 18.76
Helper II 2,100.00 2,100.00 2,100.00 25,200.00 80.51 23.87
Carpenter I 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Carpenter II 4,800.00 4,800.00 4,800.00 57,600.00 184.03 54.57
Bar Sett.I 2,700.00 2,700.00 2,700.00 32,400.00 103.51 30.69
Bar Sett.II 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Powder Man I 2,700.00 2,700.00 2,700.00 32,400.00 103.51 30.69
Powder Man II 3,600.00 3,600.00 3,600.00 43,200.00 138.02 40.93
Mason I 1,950.00 1,950.00 1,950.00 23,400.00 74.76 22.17
Mason II 2,850.00 2,850.00 2,850.00 34,200.00 109.27 32.40
Mason III 4,200.00 4,200.00 4,200.00 50,400.00 161.02 47.75
Elec. I 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Elec. II 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Elec. III 6,300.00 6,300.00 6,300.00 75,600.00 241.53 71.62
Welder I 1,800.00 1,800.00 1,800.00 21,600.00 69.01 20.46
Welder II 4,000.00 4,000.00 4,000.00 48,000.00 153.35 45.47
Welder III 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Mechanic I 3,500.00 3,500.00 3,500.00 42,000.00 134.19 39.79
Mechanic II 4,500.00 4,500.00 4,500.00 54,000.00 172.52 51.16
Mechanic III 6,300.00 6,300.00 6,300.00 75,600.00 241.53 71.62
Mat. Prod. Sup. 8,000.00 8,000.00 8,000.00 96,000.00 306.71 90.95
Batch plant Sup. 7,600.00 7,600.00 7,600.00 91,200.00 291.37 86.40
Mason Foreman 4,800.00 4,800.00 4,800.00 57,600.00 184.03 54.57
Carp. Foreman 5,700.00 5,700.00 5,700.00 68,400.00 218.53 64.80
Labor Foreman 1,500.00 1,500.00 1,500.00 18,000.00 57.51 17.05
Quarry Foreman 5,000.00 5,000.00 5,000.00 60,000.00 191.69 56.84
Safetyman I 3,000.00 3,000.00 3,000.00 36,000.00 115.02 34.10
Const.For I 4,000.00 4,000.00 4,000.00 48,000.00 153.35 45.47
Const.For II 6,500.00 6,500.00 6,500.00 78,000.00 249.20 73.89
Surveyor 8,000.00 8,000.00 8,000.00 96,000.00 306.71 90.95

Stadia Engineering Works Consultant PLC Page 4 of 4


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 2: Basic Material Price List March 21, 2017


Price at
Source Transportation Price at Site
Description Unit (Birr) cost (Birr) (Birr)
Diesel Litre - - 16.02
Petrol Litre - - 17.88
Cement Quintal 235.78 20.00 255.78
Binding wire Kg - - 32.00
Reinforcement Bar (Mild, Grade-40) t 18,260.00 800.00 19,060.00
Reinforcement Bar (Mild, Grade-60) t 19,130.00 800.00 19,930.00
Bitumen:
Bitumen - MC-30 Kg 27.39 1.00 28.39
Bitumen - AC-60/70 Kg 18.10 1.00 19.10
Bitumen - AC-80/100 Kg 25.00 1.00 26.00
Bitumen - AC RC-70 Kg 28.07 1.00 29.07
Bitumen - MC-3000 Kg 25.60 1.00 26.60
Explosive Material
Ammonium Nitrate Kg - - 60.00
Power Jell Kg - - 90.00
Electrical Detonator No - - 65.00
Cord m - - 16.00
Connecting wire m - - 12.00
Lumber m3 - - 10,000.00

Equaliptus Pole (Dia. 100mm, 8m long) No - - 100.00


Sand m3 - - 461.54
Nails kg - - 26.50
Chipwood No - - 420.00
Elastomeric Bearing
(400mm*300mm*69mm) No - - 7,452.00
Elastomeric Bearing
(400mm*250mm*45mm) No - - 4,050.00
Electrode, #4 Kg - - 79.60
Bituminous Paper, (2mm thick) M2 - - 35.00
PVC Pipe, 110mm No - - 184.80
Perforated PVC Pipe, 150mm No - - 369.60
Gabion boxes, 1m*1m*1m No 364.50 10.00 374.50
Gabion boxes, 2m*1m*1m No - - 686.58
Gabion boxes, 1.5m*1m*1m No - - 561.75

PVC-coated Gabion boxes,3*3*1*1m No 3,841.76 40.00 3,881.76


Geo-Textile filter fabric M2 - - 75.00
2
Impermeable Membrane M - - 25.00
Geogrid M2 195.18 8.00 203.18
Thermoplastic paint l - - 37.44
Glass beads Kg - - 26.00
Sign faces made by Alluminium alloy M2 - - 1,073.00
Tree No - - 100.00
Ply wood No - - 60.00
Guardrail m - - 320.04
Thermoplastic paint l - - 37.44
Steel Pipes (Dia. 75mm) No - - 600.00
Steel Pipes (Dia. 150mm) No - - 1,000.00
Split Pipes (Dia. 150mm) No - - 1,800.00
Grass Cuttings ha - - 50,000.00
Grass Seeds ha - - 25,000.00
Grass Seeds ha - - 25,000.00
Urea t 11,000.00 800.00 11,800.00
Reflector No - - 20.00

Stadia Engineering Works Consultant PLC Page 1 of 1


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 3: Equipment Cost March 21, 2017


Equipment Salvage Tyre
Equipment Life Time Depreciation Interest
Initial Cost Value
Cost
Item Equipment Type Rated HP
Capacity (about) (F/8hrs/ Unit Price Tyre (E((1.03)G-1)
((E-L-H)/F)
(Birr) (Hours) 250 days) 10% of E Size Qty Price (Set) Life /F)
(Birr/Hr)
(Yrs) (Birr) (Birr) (Hour) (Birr/Hr)
A B C D E F G H I J K L M N O
1 Dump truck,6*4 (8m3) 8M3 270 950,000 12,000 6.0 95,000 12-20,12R20 10 10,500.00 105,000.00 1,500 62.50 15.36
2 Dump truck,6*4 (12m3) 12M3 336 1,114,653 12,000 6.0 111,465 1200R20 11 10,500.00 115,500.00 1,500 73.97 18.03
3 Water truck,6*4 20000Lits 240 1,600,000 14,000 7.0 160,000 12R22.5 10 10,500.00 105,000.00 1,800 95.36 26.27
4 Asphalt Distributor 6000 Lit 200 4,800,000 14,000 7.0 480,000 11*20,12*20 6 10,500.00 63,000.00 2,200 304.07 78.81
5 Drill, Self Prop, Crawler Type 4500 Kg 200 5,400,000 10,000 5.0 540,000 - - 486.00 86.01
6 Excavator, Wheel Type 1.09M3 166 3,854,783 12,000 6.0 385,478 15.5*25 4 16,500.00 66,000.00 2,500 283.61 62.34
7 Excavator, Crawler Type 1.76M3 203 6,494,348 12,000 6.0 649,435 - - 487.08 105.02
8 Motor Grader 145-165 HP 165 7,399,565 10,000 5.0 739,957 13*24,14*24 6 13,000.00 78,000.00 1,300 658.16 117.86
9 Loader, Crawler 2-2.5 M3 189 7,421,304 10,000 5.0 742,130 - - 667.92 118.20
10 Loader, Wheel 2-2.5 M3 154 4,661,154 10,000 5.0 466,115 23.5*25 4 20,000.00 80,000.00 2,200 411.50 74.24
11 Roller,Vibrator,2Drums 8 ton 111.1 3,020,435 12,000 6.0 302,043 - - 226.53 48.84
12 Roller,Vibrator,2Drums 12 ton 130 3,258,261 12,000 6.0 325,826 - - 244.37 52.69
13 Roller,Pneumatic 10 ton 131 3,062,609 15,000 7.5 306,261 11*20 7 9,000.00 63,000.00 2,500 179.56 50.67
14 Crawler Dozer 280-330 HP 303 9,899,000 16,000 8.0 989,900 - - 556.82 165.05
15 Crusher Plant 51-100 TPH 370 15,000,000 17,000 8.5 1,500,000 10*20 16 9,000.00 144,000.00 4,000 785.65 252.03
16 Asphalt Paver, Crawler 2.5-8m 205 9,391,739 15,000 7.5 939,174 - - 563.50 155.39
17 Asphalt Plant 130-150TPH 1100 6,050,000 18,000 9.0 605,000 10*20 30 9,000.00 270,000.00 4,000 287.50 102.44
18 Asphalt Kettle, Trailer Mounted 1500-2000Lit 10 1,202,652 12,000 6.0 120,265 7.5*18 2 5,000.00 10,000.00 2,500 89.37 19.45
19 Spreader, Aggregate 5-7m 300 5,000,000 15,000 7.5 500,000 10*20 4 9,000.00 36,000.00 2,200 297.60 82.73
20 Concrete Vibrator 5 HP 5 18,700 8,000 4.0 1,870 - - 2.10 0.29
21 Concrete Mixer,Trailer Mounted 250 Lit 15 118,800.0 16,000 8.0 11,880 6.5*16 2 5,000.00 10,000.00 2,500 6.06 1.98
22 Concrete Mixer,Trailer Mounted 500 Lit 25 196,735.6 16,000 8.0 19,674 6.5*16 2 5,000.00 10,000.00 2,500 10.44 3.28
23 Air Compressor 600CFM 155 249,330 15,000 7.5 24,933 7.5*16 2 7,000.00 14,000.00 2,500 14.03 4.13
24 Water Pump 230 Lit/min 8 29,333 8,000 4.0 2,933 - - 3.30 0.46
25 Street Sweeper, Self Prop 1-2m 70 1,231,985 11,000 5.5 123,199 11.2*20 4 12,000.00 48,000.00 2,200 96.44 19.77
26 AC Welder, Diesel 300-400AMP 55 150,000 10,000 5.0 15,000 - - 13.50 2.39
27 Pick Up,Double cab,4*4,Diesel - 102 1,732,174 11,000 5.5 173,217 205R 16c,6J 4 5,000.00 20,000.00 2,100 139.91 27.80
28 Plate Compactor 5 37,500 8,000 4.0 3,750 - 4.22 0.59
29 Road Marking Machine 85 2,600,000 15,000 7.5 260,000 4 7,000.00 28,000.00 1,500 154.13 43.02
30 Asphalt Cutter 80,000 6,000 3.0 8,000 - 12.00 1.24

Stadia Engineering Works Consultant PLC Page 1 of 2


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 3: Equipment Cost March 21, 2017

Tyre Operating
Insurance Repair Cost Fuel Consumption Service Cost Owning Cost O&O Cost
Cost Cost
Item Equipment Type Rated HP
Capacity (about) Cost Factor (Cost=U*
Rate % of (N*R) (D*T) % of (V*W) (L/M) (S+V+X+Y) (N+O+Q) (Z+AA)
(E*P*G/F) (Lit/Hr/Hp Fuel Rate)
% N (Birr/Hr) (Lit/Hr) V (Birr/Hr) (Birr/Hr) (Birr/Hr) (Birr/Hr) (Birr/Hr)
(Birr/Hr) ) (Birr/Hr)
A B C D P Q R S T U V W X Y Z AA AB
1 Dump truck,6*4 (8m3) 8M3 270 2.16% 10.26 80% 50.00 0.0591 16.0 255.63 20% 51.13 70.00 426.76 88.12 514.88
2 Dump truck,6*4 (12m3) 12M3 336 2.16% 12.04 80% 59.18 0.0535 18.0 287.98 20% 57.60 77.00 481.75 104.04 585.79
3 Water truck,6*4 20000Lits 240 3.00% 24.00 80% 76.29 0.0625 15.0 240.30 20% 48.06 58.33 422.98 145.63 568.61
4 Asphalt Distributor 6000 Lit 200 1.50% 36.00 80% 243.26 0.1200 24.0 384.48 25% 96.12 28.64 752.49 418.89 1,171.38
5 Drill, Self Prop, Crawler Type 4500 Kg 200 1.00% 27.00 70% 340.20 0.1100 22.0 352.44 10% 35.24 - 727.88 599.01 1,326.89
6 Excavator, Wheel Type 1.09M3 166 0.45% 8.67 70% 198.53 0.1090 18.1 289.87 25% 72.47 26.40 587.26 354.62 941.88
7 Excavator, Crawler Type 1.76M3 203 0.45% 14.61 70% 340.95 0.1090 22.1 354.47 25% 88.62 - 784.05 606.71 1,390.76
8 Motor Grader 145-165 HP 165 0.50% 18.50 50% 329.08 0.1270 21.0 335.70 25% 83.92 60.00 808.70 794.52 1,603.22
9 Loader, Crawler 2-2.5 M3 189 0.45% 16.70 90% 601.13 0.1000 18.9 302.78 25% 75.69 - 979.60 802.82 1,782.42
10 Loader, Wheel 2-2.5 M3 154 0.45% 10.49 60% 246.90 0.1000 15.4 246.71 25% 61.68 36.36 591.65 496.23 1,087.88
11 Roller,Vibrator,2Drums 8 ton 111.1 0.40% 6.04 70% 158.57 0.1500 16.7 266.97 20% 53.39 - 478.94 281.42 760.36
12 Roller,Vibrator,2Drums 12 ton 130 0.40% 6.52 70% 171.06 0.1600 20.8 333.22 20% 66.64 - 570.92 303.58 874.49
13 Roller,Pneumatic 10 ton 131 0.40% 6.13 70% 125.69 0.1600 21.0 335.78 20% 67.16 25.20 553.82 236.35 790.18
14 Crawler Dozer 280-330 HP 303 0.50% 24.75 90% 501.14 0.1320 40.0 640.74 30% 192.22 - 1,334.09 746.61 2,080.71
15 Crusher Plant 51-100 TPH 370 1.00% 75.00 90% 707.08 0.2000 74.0 1,185.48 33% 391.21 36.00 2,319.77 1,112.67 3,432.45
16 Asphalt Paver, Crawler 2.5-8m 205 1.50% 70.44 80% 450.80 0.0800 16.4 262.73 25% 65.68 - 779.21 789.34 1,568.55
17 Asphalt Plant 130-150TPH 1100 1.50% 45.38 90% 258.75 0.1000 110.0 1,762.20 33% 581.53 67.50 2,669.98 435.31 3,105.29
18 Asphalt Kettle, Trailer Mounted 1500-2000Lit 10 1.00% 6.01 50% 44.68 2.5000 25.0 400.50 13% 50.06 4.00 499.25 114.83 614.07
19 Spreader, Aggregate 5-7m 300 1.00% 25.00 80% 238.08 0.1410 42.3 677.65 20% 135.53 16.36 1,067.62 405.33 1,472.95
20 Concrete Vibrator 5 HP 5 0.40% 0.04 50% 1.05 0.2500 1.3 20.03 7% 1.40 - 22.48 2.43 24.91
21 Concrete Mixer,Trailer Mounted 250 Lit 15 0.40% 0.24 50% 3.03 0.1300 2.0 31.24 14% 4.37 4.00 42.64 8.28 50.92
22 Concrete Mixer,Trailer Mounted 500 Lit 25 0.40% 0.39 50% 5.22 0.1000 2.5 40.05 14% 5.61 4.00 54.88 14.12 68.99
23 Air Compressor 600CFM 155 0.40% 0.50 50% 7.01 0.1290 20.0 320.32 14% 44.84 5.60 377.78 18.65 396.43
24 Water Pump 230 Lit/min 8 0.25% 0.04 80% 2.64 0.3750 3.0 48.06 14% 6.73 - 57.43 3.80 61.23
25 Street Sweeper, Self Prop 1-2m 70 0.40% 2.46 50% 48.22 0.2600 18.2 291.56 22% 64.14 21.82 425.74 118.67 544.41
26 AC Welder, Diesel 300-400AMP 55 0.40% 0.30 50% 6.75 0.1820 10.0 160.36 14% 22.45 - 189.56 16.19 205.75
27 Pick Up,Double cab,4*4,Diesel - 102 1.30% 11.26 50% 69.95 0.0590 6.0 96.41 16% 15.43 9.52 191.31 178.96 370.27
28 Plate Compactor 5 1.50% 0.28 50% 2.11 0.1000 0.5 8.01 7% 0.56 - 10.68 5.09 15.77
29 Road Marking Machine 85 2.00% 26.00 80% 123.31 0.2200 18.7 299.57 20% 59.91 18.67 501.46 223.15 724.61
30 Asphalt Cutter 2.00% 0.80 90% 10.80 - - - 0% - - 10.80 14.04 24.84

Stadia Engineering Works Consultant PLC Page 2 of 2


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
No Type & Capacity
Materials Production
a  Borrow Material production M3 1 Crawler Dozer                         686.00 
3
b Select Material production M 1 Crawler Dozer                         560.00 
c Quarry Rock Production M3 1 Crawler Dozer                         480.00 
Rock Crushing -Surface & concrete   3
d M 1 Crusher Plant                         240.00 
Aggregate
3
e Rock Crushing -Base Aggregate M 1 Crusher Plant                         260.00 
f Rock Crushing -Sub Base Aggregate M3 1 Crusher Plant                         280.00 
3
g Hot Mix Production (AC - 60/70) M 1 Asphalt Plant                        200.00 
h Hot Mix Production (AC - 80/100) M3 1 Asphalt Plant                        200.00 
i Pipe Production(Dia.36) Each 15 Pipe Molds                          15.00 
j Pipe Production(Dia.42) Each 15 Pipe Molds                          15.00 
k Pipe Production(Dia.48) Each 15 Pipe Molds                          15.00 
l Guide Post Production Each 1 Concrete Mixer                          30.00 
m KM Post Production Each 1 Concrete Mixer                          30.00 
n HCB Production Each 1 HCB Machine                        160.00 
o Sand Production M3 1 Excavator, Wheel Type                          28.00 
3 3
p Sand Hauling M 1 Front End Loader (2.5 M )                      1,129.41 
q Formwork - Minor Drainage M2 1 Carp. Foreman                          32.00 
r Duct Marker Blocks Production Each 1 Concrete Mixer                          30.00 
3 3
s Class A bedding (Class 20/20 concrete) M 1 Concrete Mixer 1/4 M                          12.00 
t Rock Crushing -Chip Aggregate M3 1 Crusher Plant                         200.00 

Construction Activities
15.01(a) 1 Crawler Dozer                             0.77 
15.01(b) Maintenance of Diversion km 1 Crawler Dozer                             0.70 
15.01(c) 1 Crawler Dozer                             0.77 
15.01(d) 1 Safety Man                            1.00 
15.01(e) 1 Safety Man                            1.00 
21.01 Clearing and Grubbing ha 1 Crawler Dozer                             1.10 
22.06(a) Demolishing Plain concrete 1 Excavator, Wheel Type                          30.00 
22.06(b) Demolishing Reinforced concrete 1 Excavator, Wheel Type                          18.00 
22.06(c) Demolishing Masonry Structures - mortared 1 Excavator, Crawler Type                          20.00 
22.06(d) Demolishing Masonry Structures - dry 1 Excavator, Crawler Type                          30.00 

31.01(a) Open Drain Excavation (in soft) m3 1 Wheel Excavator(2.5m3)                        120.00 


31.01(b) Open Drain Exc. (in Hard) (Extra-over) m3 1 Wheel Excavator(2.5m3)                        100.00 
31.05 2 Motor Grader (120-150 FWHP)                     1,200.00 
32.01(a) Minor Structures Excavation (in Soft) m3 1 Wheel Excavator(2.5m3)                        150.00 
Minor Structures Exc. (in Hard) (Extra-
32.01(b) m3 1 Wheel Excavator(2.5m3)                          90.00 
over)
3
32.02(a) Backfilling using the excavated material m3 1 Dump Truck 7m                          70.00 
Backfilling using  Imported selected  3
32.02(b) m3 1 Dump Truck 7m                          70.00 
material
36'' diameter R.C pipe installation on class 
32.03(a)(i) 1 Front End Loader (2.0-2.5 M3)                          11.00 
A Bedding
42'' diameter R.C pipe installation on class  3
32.03(a)(ii) 1 Front End Loader (2.0-2.5 M )                          11.00 
A Bedding
48'' diameter R.C pipe installation on class  3
32.03(a)(iii) 1 Front End Loader (2.0-2.5 M )                          11.00 
A Bedding
36'' diameter R.C pipe installation on class 
32.03(b)(i) 1 Front End Loader (2.0-2.5 M3)                          11.00 
B Bedding
42'' diameter R.C pipe installation on class  3
32.03(b)(ii) 1 Front End Loader (2.0-2.5 M )                          11.00 
B Bedding
48'' diameter R.C pipe installation on class 
32.03(b)(iii) m 1 Front End Loader (2.0-2.5 M3)                          11.00 
B Bedding
Service Duct using ordinary pipes (150mm 
32.16(a) m 1 Mason I                           20.00 
diameter steel pipes) 
Service Duct using split pipes (150mm 
32.16(b) 1 Mason I                           20.00 
diameter steel pipes)
32.17 Duct marker blocks No. 1 Labor Forman                          20.00 
32.18 Chambers for ducts 1 Concrete Mixer 1/4 M3                            7.00 
Class 25/20 Concrete Curbing (size .45m X  3
33.01(a)(i) m 1 Concrete Mixer 1/4 M                        155.00 
.17m)
Class 25/20 Concrete Curbing (size .20m X  3
33.01(a)(ii) m 1 Concrete Mixer 1/4 M                        240.00 
.25m)

Stadia Engineering Works Consultant PLC Page 1 of 3


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
Concrete Chute (Class 20/20) including  3
33.03(a) 1 Concrete Mixer 1/4 M                        100.00 
Formwork
Concrete lining (Class 20/20) including  3
33.09(a) 1 Concrete Mixer 1/4 M                          12.00 
Formwork
Pedestrian drain covers (Class 25/20 - 
33.17(b)(i) No. 1 Concrete Mixer                          30.00 
1.4mX1.2mX0.15m)
Pedestrian drain covers (Class 25/20 - 
33.17(b)(ii) 1 Concrete Mixer                          30.00 
1.6mX1.2mX0.15m)
Vehicle drain covers (Class 25/20 -
33.17(b)(iii) No. 1 Concrete Mixer                          30.00 
1.6mX1.2mX0.20m)
34.01(b)(i) Stone Pitching for outlet & inlet of culverts  m2 1 Mason II                          50.00 
34.03(b) Cement-mortared stone walls m3 1 Mason Forman                            8.00 
Pre-cast concrete blocks for side walk 
34.04(c) m2 1 Labor Forman                          96.00 
pavement 

Removal of unsuitable material and 
41.01(b) m3 1 Crawler Dozer                         585.67 
replacement with suitable material
41.02 Road bed preparation and compaction m3 1 Motor Grader (120-150 FWHP)                        586.00 
42.01(a) Cut to fill m3 2 Motor Grader (120-150 FWHP)                     1,200.00 
42.01(b) Borrow to fill m3 2 Motor Grader (120-150 FWHP)                     1,200.00 
42.01(c) Rock fill  m3 1 Crawler Dozer                         685.00 
42.01(d) Improved subgrade  m3 2 Motor Grader (120-150 FWHP)                        980.00 
42.03(a) Common (normal) excavation m3 2 Crawler Dozer                      1,120.00 
42.03(b) Rock excavation m3 1 Crawler Dozer                         400.00 
Reinstatement of rock (hard) material 
43.01(a) 1 Crawler Dozer                           0.350 
borrow areas
Reinstatement of common (normal or soft) 
43.01(b) 1 Crawler Dozer                           0.500 
material borrow areas
44.04 Side fills or Fill-flattening 2 Motor Grader (120-150 FWHP)                     1,200.00 

51.01(a)(i) Gravel Sub-base m3 1 Motor Grader (120-150 FWHP)                        480.00 


52.01(c)(ii) Crushed -stone base  m3 2 Motor Grader (120-150 FWHP)                        800.00 

61.01(a) Prime Coat (MC-30 cutback bitumen ) l 1 Asphalt Distributor 6000 Ltrs                     8,570.00 


Tack Coat (Stable-grade bitumen emulsion 
62.01(a) 1 Asphalt Distributor 6000 Ltrs                     4,000.00 
(30%))
Double Surface Seal (150/200 penetration 
63.02(b)* m2 1 Spreader, Aggregate                     4,000.00 
grade bitumen) 1st layer
Double Surface Seal (150/200 penetration 
63.02(b) 1 Spreader, Aggregate                     4,000.00 
grade bitumen)
Asphaltic Concrete (50 mm thick, 80/100 
64.02(a) m2 1 Asphalt Paver, Crawler                     3,500.00 
bitumen)

81.02(a) Major Structures Excavation (in Soft) m3 1 Wheel Excavator(2.5m3)                        185.00 


81.02(b) Major Structures Excavation (in Hard) m3 1 Wheel Excavator(2.5m3)                          80.00 
81.05(a) Backfill using excavated material 1 Front End Loader (2.0-2.5 M3)                        200.00 
3
81.05(b) Backfill using imported material m3 1 Front End Loader (2.0-2.5 M )                        200.00 
81.05(c) Hand laid rock embankment 1 Labor Forman                          40.00 
81.08(a) Rock foundation fill 1 Labor Forman                          30.00 
81.08(c) Compacted granular foundation fill 1 Front End Loader (2.0-2.5 M3)                        180.00 
82.01(a ) Formwork for Class F1 surface finish 1 Carp. Foreman                          32.00 
82.01(b ) Formwork for Class F2 surface finish m2 1 Carp. Foreman                          36.00 
83.01(a)(i) Grade 60 Reinforcement Steel t  1 Steel - cutter                          0.513 
83.01(a)(ii) Grade 40 Reinforcement Steel t  1 Steel - cutter                          0.513 
3
84.01(a) Class 30/20 concrete in RC Structure m3 2 Concrete Mixer 1/2 M                          32.00 
3
84.01(b) Class 25/20 concrete in RC Structure 2 Concrete Mixer 1/2 M                          32.00 
3
84.01(c) Class 15/20 concrete in lean concrete m3 2 Concrete Mixer 1/2 M                          32.00 
87.03 Elastomeric Bearing No. 1 AC Welder, Diesel                            2.00 
3
87.07 Concrete parapet  m 1 Concrete Mixer 1/4 M                          66.00 
87.13(a) Expansion joint with 20mm filler m 1 Carpenter II                            8.10 
87.19(a)(i) Dia. 100mm PVC drainage pipes 1 Mason I                          16.00 
87.19(b)(i) Dia. 200mm PVC pipe weep holes m 1 Mason I                          48.00 
87.23 Crushed Stone in drainage Strips m3 4 Labour I                            8.00 
89.01(b) Class "B" Stone Masonry m3 20 Mason I                          25.00 
810.01(a) MSE Gabion wall facing 1 Labor Forman                            6.00 
810.01(b) Polymeric (Geogrid) Reinforcements 1 Labor Forman                        200.00 
Drainage at interface of backfill and in-situ 
810.01(c) 1 Dump Truck 7m3                        110.00 
soil

Stadia Engineering Works Consultant PLC Page 2 of 3


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Table 4: Production rate of Construction Activities


March 21, 2017
Activity No. Activity Name Unit Main Resource to be Allocated Production Rate
91.03(a)(i) Gabion boxes (2x1x1)  1 Labor Forman                            8.00 
91.03(a)(ii) Gabion boxes (1.5x1x1)  1 Labor Forman                            8.00 
91.04 Filter Fabric (Terram 1000 or equivalent) 1 Labor Forman                          50.00 
92.01(b) Guide Posts (reinforced concrete C- 20) 1 Labor Forman                          50.00 
92.01(c) Kilometer posts (reinforced concrete C- 20) No. 1 Labor Forman                          20.00 
93.01 Galvanized guard rails on steel post m 1 Welder I                          20.00 
94.01(a)(i) Traffic signs (Area not exceeding 2 m²) m2 1 Welder I                          10.00 
94.01(a)(ii) Traffic signs (Area exceeding 2 m²) 1 Welder I                            8.00 
94.02(a) Sign Supports (Concrete Class C 20/20) 1 Concrete Mixer(250 litre)                          20.00 
94.02(b) Sign Supports (Steel) No. 1 Mason I                           20.00 
Concrete in road sign footings including 
94.03 m3 1 Dump Truck                            4.80 
exc. and backfilling (Class 15/20)
White lines (broken or unbroken) (width of 
95.01(a) km 1 Road Marker                            5.00 
100mm)
Yellow lines (broken or unbroken) (width of 
95.01(b) km 1 Road Marker                            5.00 
100mm)
95.04(a) In situ asphalt Speed Bumps  1 Labor Forman                          40.00 
95.04(b) In situ asphalt Rumble Strips  1 Labor Forman                          12.00 
96.01 Stockpiling of Topsoil 2 Crawler Dozer                      1,120.00 
96.02(a) Top-soiling  1 Labor Forman                          60.00 
96.02(b) Provide and apply chemical fertilizers 1 Labor Forman                          1.875 
96.03(a) Planting of grass cuttings  1 Labor Forman                            0.05 
96.03(b) Seeding  1 Labor Forman                            0.10 
Replacement or replanting of trees and 
96.04 1 Labor Forman                        500.00 
growth management
99.02(a) Masonry Safety Barrier 1 Mason Forman                          14.00 
Safety Barrier Precast Concrete as per 
99.02(b) 1 Concrete Mixer(250 litre)                          30.00 
drawing

Stadia Engineering Works Consultant PLC Page 3 of 3


JINKA TOWN ROAD PROJECT Ethiopian Roads Authority
Alternative 2

Productivity calculation sheet for Dump Trucks and Loaders


Table 5: Dump Trucks (Production Depend on hualing Distance) March 21, 2017
Tested
D/Truck
Hauling Tested Load- Daily Daily
Cycle Time No of Trip Capacity Material Type To
Distance Speed Unload 3 Production Production
(Hr) (No) (m ) be Haul
(Km) (Km/Hr) Time (m3) (km-m3)
(Compacted)
(Minute)
a b c d=c/60+a*2/b e=8/d f g=e*f h=a*g
Backfill material for
13.70 35 6 0.88 9.06 12 109 1,490
diversion
1.00 35 6 0.16 50.91 12 611 611 Clearing wasting
5.00 35 6 0.39 20.74 12 249 1,244 Cut Wasting
1.50 35 6 0.19 43.08 12 517 775 Top soil stockpiling
14.25 35 10 0.98 8.16 12 98 1,395 Crusher stone hauling
5.00 35 8 0.42 19.09 12 229 1,145 Cut to fill hauling
13.70 35 8 0.92 8.73 12 105 1,436 Borrow hauling
13.70 35 6 0.88 9.06 12 109 1,490 Natural subbase
26.50 35 40 2.18 3.67 12 44 1,166 Asphalt mix
Stone hauling (hand-
13.10 35 10 0.92 8.74 8 70 916
laid)
13.10 35 10 0.92 8.74 12 105 1,374 Stone hauling (fill)
5.00 35 10 0.45 17.68 12 212 1,061 Stone hauling (waste)
10.50 35 8 0.73 10.91 12 131 1,375 Sand hauling
26.50 35 6 1.61 4.96 12 59 1,576 Aggregate (Chipping)
26.50 35 6 1.61 4.96 12 59 1,576 Crushed Base course

Table 6: Loaders

Bucket
Cycle Time Efficiency Productivity
Loader Type Capacity Remark
(Minute) (%) (m3/day)
(m3)
a b c d=(480/b)*a*c
It works only for borrow & natural subbase loading b/c
Own 2.5 1.00 80% 960
a lot of time needed to separate boulders
It works for waste & crushed material loading b/c no
Own 2.5 0.85 80% 1,129
need of separation of boulders

NB: Efficiency of loader decreases due to many factors, but the mostly happened problem is shortage of working space due to quarry location.

Stadia Engineering Works Consultant PLC Page 1 of 1

You might also like