Progress Report

Project Details
Project name CCTV installation At Bureau of Public Enterprises (BPE)

Location Maitama, FCT Abuja

Reporting period 12th September 2020 – 22nd October 2020

Report compiled by DABTOS NIGERIA ENTERPRISE

Date submitted 22nd October 2020


Summary
The installation and configuration of CCTV camera are in process, this process
helps in achieving great success. Below are the activities involve and the progress
achieved
Activities & Outputs
Activity 1 – Cameras Map Out

Status Achieved

Objective Mapping out point of the locating of exiting cameras and the
new ones to be installed.

Activity dates 12th September 2020

Progress This activity was carried out with the help of some of the
stakeholder on the project which was done very well.

Outputs We were able to locate all the exciting cameras and map out
created the location for the new one

Activity 2 – Drilling & Running of Cables

Status In progress

Objective Drilling and running of cables for the cameras in the premises

Activity dates 14th September 2020 to 3rd October 2020

Progress We have been able to drill and run 36 cables successful, we are
just having little challenges in running the remain two (2) cables
due to no access to the offices we need to run the cable
through

Outputs The cables are run accord to the specification required by the
created organisation (stakeholders) and all cable are neatly run
Activity 3 – Termination of Cables

Status In progress

Objective Termination of cables

Activity dates 24th September 2020 – 6th October 2020

Progress About 10(ten) cables have being terminated and 28 cables to go

Outputs We will be termination the cables for proper connection of the


created CCTV

Activity 4 – Mounting of Cameras

Status Achieved

Objective Mounting of camera

Activity dates 12th October 2020 to 15th October 2020

Progress Completed

Outputs The camera will be mounted of the mapped out point and
created positioned well
Activity 5 – Configuration & Testing

Status 1n Progress

Objective Configuration and testing

Activity dates 16th October 2020 – 29th of October 2020

Progress In Progress

Outputs For good connection within the system


created
Results
Activities Result as of 21th Status
October 2020

(%)

Locating and mapping out new and existing 100% achieved


point

Drilling and running of cables 100% achieved

Terminating of cable 100% achieved

Mounting of cameras 100% achieved

Configuration and testing 70% 1n progress

Summary
As of 21st of October, 2020, 90% of the project has reached. We are looking
forward to completing the project.