The document outlines the work schedule for a Pertamina Plaju - AUX project in July and August 2021. It involves rewiring and testing the functions of 22 drawers in the MCC (Motor Control Center). Key activities include preparing for the work, rewiring each drawer number sequentially, testing the functions, and making revisions if needed as issues are discovered such as drawers with incorrect motor capacities. The schedule is detailed by date and assigns tasks to team members Aziz and Yudi to complete the work by the end of August.
The document outlines the work schedule for a Pertamina Plaju - AUX project in July and August 2021. It involves rewiring and testing the functions of 22 drawers in the MCC (Motor Control Center). Key activities include preparing for the work, rewiring each drawer number sequentially, testing the functions, and making revisions if needed as issues are discovered such as drawers with incorrect motor capacities. The schedule is detailed by date and assigns tasks to team members Aziz and Yudi to complete the work by the end of August.
The document outlines the work schedule for a Pertamina Plaju - AUX project in July and August 2021. It involves rewiring and testing the functions of 22 drawers in the MCC (Motor Control Center). Key activities include preparing for the work, rewiring each drawer number sequentially, testing the functions, and making revisions if needed as issues are discovered such as drawers with incorrect motor capacities. The schedule is detailed by date and assigns tasks to team members Aziz and Yudi to complete the work by the end of August.
The document outlines the work schedule for a Pertamina Plaju - AUX project in July and August 2021. It involves rewiring and testing the functions of 22 drawers in the MCC (Motor Control Center). Key activities include preparing for the work, rewiring each drawer number sequentially, testing the functions, and making revisions if needed as issues are discovered such as drawers with incorrect motor capacities. The schedule is detailed by date and assigns tasks to team members Aziz and Yudi to complete the work by the end of August.
MATRIK TIME SCHEDULE PEKERJAAN PERTAMINA PLAJU - AUX PROJECT
Bulan JuLY 2021 Agust 2021
NO DESCRIPTION PERSON KETERANGAN Tanggal 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 PERJALANAN BUS, JKT-PALEMBANG meeting & persiapan JSI Final for energize Energize 12kv MV TR dan MCC monitoring after energize 3 days Prepare Panel MCC test A PERSIAPAN PEKERJAAN MCC 1 Pengetesan Function sesuai dgn drawing lama Aziz & Yudi temuan fungsi tidak sesuai 2 perbaikan temuan & Drawing revisi Aziz & Yudi revisi drawing sesuai diskusi 3 Analisa system Drawer MCC di hotel dengan team PTM B URAIAN PEKERJAAN ACTIVITAS DI SITE 1 Persiapan Pekerjaan Aziz & Yudi 2 Rewiring & test function drawer mcc no 1 Aziz & Yudi 3 Rewiring & test function drawer mcc no 2 Aziz & Yudi Temuan KW drawer tidak sesuai, dgn 4 Rewiring & test function drawer mcc no 3 Aziz & Yudi actual Motor di site. Drawer TK1-2 kapasitas motor lebih besar, 5 Rewiring & test function drawer mcc no 4 Aziz & Yudi harus upgrade kapasitas modul C445 dan Kontaktor 6 Rewiring & test function drawer mcc no 5 Aziz & Yudi 7 Rewiring & test function drawer mcc no 6 Aziz & Yudi 8 Rewiring & test function drawer mcc no 7 Aziz & Yudi 9 Rewiring & test function drawer mcc no 8 Aziz & Yudi pengajuan ke manajemen BCP 10 Rewiring & test function drawer mcc no 9 Aziz & Yudi pengajuan ke manajemen BCP 11 Rewiring & test function drawer mcc no 10 Aziz & Yudi 12 Rewiring & test function drawer mcc no 11 Aziz & Yudi 13 Rewiring & test function drawer mcc no 12 Aziz & Yudi 14 Rewiring & test function drawer mcc no 13 Aziz & Yudi 15 Rewiring & test function drawer mcc no 14 Aziz & Yudi 16 Rewiring & test function drawer mcc no 15 Aziz & Yudi 17 Rewiring & test function drawer mcc no 16 Aziz & Yudi 18 Rewiring & test function drawer mcc no 17 Aziz & Yudi 19 Rewiring & test function drawer mcc no 18 Aziz & Yudi 20 Rewiring & test function drawer mcc no 19 Aziz & Yudi 21 Rewiring & test function drawer mcc no 20 Aziz & Yudi 22 Rewiring & test function drawer mcc no 21 Aziz & Yudi 23 Rewiring & test function drawer mcc no 22 Aziz & Yudi