Professional Documents
Culture Documents
TSPP 9
TSPP 9
THIS
Printing Specification
Document Details
Title SPECIFICATION FOR THE WELDING OF
FITTINGS TO PIPELINES OPERATING
UNDER PRESSURE
THIS
continued
Special Instructions
SPECIFICATION FOR
July 2011
© National Grid plc 2011- All Rights Reserved
T/SP/P/9
CONTENTS
Page
FOREWORD v
BRIEF HISTORY v
1. SCOPE 1
2. REFERENCES 1
3. DEFINITIONS 1
6. PIPE MATERIAL 3
15. PREHEATING 11
18. INSPECTION 16
21. RECORDS 18
TABLES
2 FITTING SCHEDULE 20
FIGURES
APPENDICES
A LIST OF REFERENCES 38
B DEFINITIONS 40
G CONSUMABLE HANDLING 63
N EXCAVATION DETAILS 80
FOREWORD
th
This Specification was approved by the Gas Engineering Policy Manager, on 17 July 2011 for use by
managers, engineers and supervisors throughout National Grid Gas.
National Grid Gas documents are revised, when necessary, by the issue of new editions. Users should
ensure that they are in possession of the latest edition by referring to the Gas Documents Library
available on infonetUK (company intranet.)
Compliance with this Document does not confer immunity from prosecution for breach of statutory or
other legal obligations.
BRIEF HISTORY
KEY CHANGES (Identify the changes from the previous version of this document)
Section Amendments
2 2
General- Clause 9.1 Yield Strength amended from ≥ 458 N/mm to ≥ 485 N/mm
Table 1B Addition of Longitudinal Seam Welds - All Passes into the table
DISCLAIMER
This safety and engineering document is provided for use by National Grid Gas and such of its
contractors as are obliged by the terms and conditions of their contracts to comply with this document.
Where this document is used by any other party it is the responsibility of that party to ensure that this
document is correctly applied.
In this document:
Should: indicates best practice and is the preferred option. If an alternative method is used then a
suitable and sufficient risk assessment shall be completed to show that the alternative method delivers
the same, or better, level of protection.
SPECIFICATION FOR
THE WELDING OF FITTINGS TO STEEL PIPES OPERATING AT PRESSURES OF 2 bar AND ABOVE
(Supplementary to BS 6990)
1. SCOPE
This specification is for the welding and inspection of fittings and attachment welds, to in-service natural
gas pipelines or pipe work, of a minimum nominal wall thickness of 4 mm and above.
This specification shall apply to carbon steel pipelines or pipe work operating at pressures of 2 bar and
above.
All welding and inspection shall be carried out in accordance with this specification, which is
supplementary to, and shall be read in conjunction with the latest version of BS 6990. In case of conflict
between the requirements of this specification and BS 6990, the requirements of this specification shall
apply.
This specification does not include any attachments made to pipe work downstream of any domestic,
commercial or industrial meter connection.
National Grid is fully committed to achieving high standards of performance in safeguarding the health
and safety of employees and minimising both the risk to the public and the impact on the environment
through our activities. The National Grid Gas Requirements Manual sets the performance standards by
which National Grid, its suppliers and contractors will operate.
Only fully approved low hydrogen welding processes, shall be used to make welded attachments to
pressurised gas pipelines or pipe work. This specification does not include attachments made by pin
brazing, conventional brazing, soldering or withdrawn arc stud welding.
The preferred fitting types and their applications are given in Table 2 and Figure 1.
2. REFERENCES
This specification makes reference to the documents listed in Appendix A. The latest edition of the
document, including all addenda and revisions shall apply unless specified otherwise.
3. DEFINITIONS
For the purpose of this specification the terms and definitions listed in Appendix B shall apply.
this specification, shall be satisfied before any claim of compliance with this specification can be made or
verified (see Appendix E).
All personnel shall fully understand what to do in the event of an incident occurring.
5.3 Excavations
Excavations shall meet the current statutory and National Grid requirements. Experience has shown that
the working space provided adjacent to the pipe when carrying out an activity of this type, has a direct
bearing on the safety of the operation. Recommended minimum dimensions are given in Appendix N and
shall only be reduced with the consultation and agreement of the welding and drilling teams and in each
case as a result of a specific risk assessment being carried out by the Engineer responsible for the
excavation.
Background lighting should be to Table 2 of T/PM/EL/1, for exterior illumination levels for working areas.
Attention is drawn to the additional lighting requirements for inspection purposes prescribed in BS EN ISO
17638.
Weather protection canopies shall be of flame retardant material, and shall be of adequate size to provide
unhindered access for the heating, welding and inspection operations. A minimum height of 2 metres
above the pipe is recommended.
Operator tiredness or lapses in concentration could put the operation and other personnel at risk.
Where welding operations are likely to exceed the normal working day, the minimum number of relief
personnel required shall be one welder, one welder’s assistant and one inspector. They shall replace
individual team members (of the same discipline) on a rotational basis. In some circumstances a relief
crew, working on a shift basis may be required. It is recommended that continuous working periods in
excess of 3 hours for individuals be avoided (see Table 3)
5.5 Pipelines containing defective girth welds or girth welds of unknown quality
Attention is drawn to the requirements of National Grid T/PR/P/18 procedure, to reduce the risk of
pipeline girth weld failure, whilst working on pipelines designed to operate at pressures greater than 7 bar
(or such pipelines which have been down rated), which may contain defective girth welds, or girth welds
of unknown quality.
Pipelines or pipe work which have been designed to operate at pressures below 7 bar and have been
constructed in accordance with National Grid T/SP/P/1 or P13 specifications, will contain girth welds
which may have been inspected on a percentage basis only. Therefore, caution is advised where work on
pipelines or pipe work may impose additional loading conditions, and where such girth welds are in
proximity to the proposed T/SP/P/9 welded attachment.
6. PIPE MATERIAL
National Grid has carried out extensive experimental testing on a wide range of carbon steel linepipe
materials in order to qualify welding procedures. The materials tested include pipe representing “high
chemistry pipe” occasionally found on older pipelines with carbon equivalent values (IIW formula – see
below) of up to 0.49%. Line pipe materials supplied from the early1970’s onwards will normally have
carbon equivalents much lower than this and may be safely welded using the typical procedures given in
Appendix F of this specification. Recent testing has extended the range of pipe materials to include
welding to L555 and X80 material pipe.
Material chemistry shall be confirmed prior to any welding taking place. When pipe material sampling is
required to establish the material chemistry, this shall be done in accordance with T/PM/Q/10. If any
doubt exists about the suitability of a particular pipe material for live welding then expert advice shall be
sought.
Following drilling operations and where the pipe coupons are not being re-used, retention of pipe coupons
may be required for analysis and testing in accordance with T/PM/Q/10. The results shall be recorded for
future reference (see Appendix L).
Note: Welding and cutting equipment, cables, instruments and accessories shall comply with the
appropriate British and European standards where they exist (e.g. BS 638 and EN 169).
Adequate means of measuring current and voltage shall be available and calibrated for use in
accordance with BS 7570. Checks of welding current and polarity shall be made on scrap material prior to
commencement and following any substantial break in welding. The return current connecting clamp shall
at all times be connected to the work at a point as close as possible to the actual weld. Return paths via
pipe hangers, steelworks or structures shall not be used.
When welding to pipelines or pipe work with wall thickness between 4.0 mm and 4.9 mm, consideration
should be given to the use of an in-line current limiting or anti-surge device between the welding
generator and the welding tongs. It should be recognised that remote amperage / voltage controls have
the potential for an accidental increase in welding current to occur.
See clause 16.2.2 for guidance on the frequency of current monitoring.
Basic coated low hydrogen electrodes exhibiting diffusible hydrogen levels equal to or less than 5 ml/100g
of deposited weld metal and suitable for vertical down welding shall be used (with the exception of 9.1.1).
When required by the Employer batch testing of flux coated electrodes shall be carried out in accordance
with BS EN ISO 3690 to confirm that the levels of diffusible hydrogen per 100g/ml of deposited weld metal
meets the requirements of BS EN 1011: Part 2; scale D.
2
Where pipe materials with a yield strength ≥ 485 N/mm are to be welded, consumable batch testing shall
be carried out by the manufacturer. A BS EN 10204 Type 3 .1 certificate based on specific inspection is
required for each production lot/heat. The consumable certificate shall report the chemical composition,
yield strength, tensile strength, elongation and impact test values (defined by the product specification).
When fittings are manufactured from L460 NL1 / NL2 or Hyplus-29 materials, a temper bead, welded in
the vertical up direction, shall be applied to the final pass of the fillet weld in accordance with the
approved procedure (see Appendix F and Appendix M). For longitudinal seam welds in fittings made from
these materials, the temper bead shall be applied using the original welding parameters and the
consumables specified on the approved procedure.
It should be recognised that welding to pipelines or pipe work with a nominal wall thickness in the
range of 4.0 mm to 4.9 mm carries an increased potential risk of pipe wall penetration, therefore
lower risk options and techniques shall be given due consideration at the planning stage.
National Grid have established standard welding procedures for welding to carbon steel
natural gas pipelines under typical pressure and flow rate conditions. Extensive welding
trials, procedure qualification and operational experience (where applicable) have
validated the use of the welding procedure parameters given in Appendix F). These
procedures shall be used subject to positive confirmation of the pipe material chemistry
being available and suitable (see clause 6) and that the temperature decay time is
confirmed in accordance with 15.2.2 prior to welding.
Group 1) For pipes of wall thickness equal to or greater than 4.00 mm up to and including
4.9 mm, the top plate shall be 10 mm thick and the bottom plate shall be 4.00
mm thick (see Figure 2a).
Group 2) For pipes of wall thickness equal to or greater than 5.00 mm up to and including
12.7 mm, the top plate shall be 10mm thick and the bottom plate shall be 5.00
mm thick (see Figure 2b).
Group 3) For pipes of wall thickness greater than 12.7 mm the top and bottom plates shall
both be 25.4 mm thick (see Figure 2c).
a) Approval for welding in thickness Group 1 of clause 11.3.1 shall also qualify for welding
materials in thickness Group 2.
b) Group 2 and Group 3 thickness ranges require separate qualification by the welder (apart
from qualification of Group 2 being covered by Group 1 approval).
c) A welder who has satisfactorily completed a welding procedure test shall be considered
qualified to use that procedure.
The familiarisation / demonstration fillet weld shall fully meet the requirements of clause 11.4. Where the
familiarisation / demonstration fillet weld produced is unsatisfactory, the welder shall be given the
opportunity of further practice, before being required to produce another familiarisation / demonstration
fillet weld. If the second demonstration weld is unsatisfactory, the welder shall not be permitted to weld on
pipe within this wall thickness range, without further training and satisfactory welder approval testing.
11.3.6 Preheating
The test joint shall be pre-heated by propane torch to a temperature of 150 ºC (a minimum temperature of
50 ºC may be used for test plates with a wall thickness less than 10 mm). Care shall be taken to ensure
that the inter-pass temperature does not exceed 250 ºC. Touch pyrometers, thermocouples or
temperature indicating crayons, which melt at the indicated temperature, shall be used. Crayons, which
indicate temperature by colour change, shall not be used (see clause 15.1.3).
11.3.7 Consumables
The consumables used shall be as specified in the approved welding procedure and shall comply with
clause 9.1.
11.3.8 Technique
The circumferential fillet welding procedure shall be used for the fillet weld test plates (The vertical down
welding technique being employed to produce the vertical position test plate fillet weld). In all cases the
base plate shall be buttered before the throat of the fillet weld is filled. The pass deposition sequences
shall follow those shown in Figure 2a, 2b or 2c, in accordance with the approved welding procedure.
The first pass in the throat of the fillet (pass A or its equivalent, in Figures 2a, 2b or 2c), shall not extend
beyond one electrode run out length before being reinforced by the deposition of the next pass. In order to
comply with clause 11.4.2.1, starts and stops shall be staggered in the central portion of the fillet weld
length.
11.4 Testing
11.4.1 Visual
The completed fillet shall be free from overspill and undercut and display a good regular profile. Weld leg
lengths shall be equal. The weld profile shall not be concave, i.e. the fillet throat thickness shall not be
less than the leg length times 0.707 (see Figure 8a).
The test plate external surface, representing the pipe inside surface below the fillet weld, shall show no
evidence of re-melt or burn through.
11.4.2.2 Requirements
On visual examination, at a magnification of x5, the weld shall show no cracks or lack of fusion into the
parent plate / pipe. Other flaws such as porosity, slag entrapment, lack of inter run fusion etc., shall not
exceed the proportions shown in Figure 10. Planar flaws shall not be permitted and excessive amounts of
non-planar defects may also be the cause for rejection in the weld regions indicated by shaded areas in
Figure 10.
The penetration of the buttering layer shall be even throughout. For welding to pipelines or pipe work with
a thickness of the range 4.0 mm to 4.9 mm, the test plate weld bead penetration shall be recorded on the
mechanical test certificate. Weld bead penetration exceeding 50% of the wall thickness of the plate/pipe
shall be cause for rejection and shall require re-qualification of the welder.
* Provided that evidence of regular and satisfactory application of the approved welding procedure in the
appropriate wall thickness range listed above is available, the qualification period may be extended for a
similar period without further testing.
11.5.1 Records
Full records of all welder qualification tests shall be kept (see Appendix K). Documentary evidence of
previous qualification approval shall only be deemed acceptable if authenticated by either a National Grid
Engineer, or by the BGAS/CSWIP Welding Inspector, who witnessed/inspected the welder’s most recent
P/9 production weld. This evidence shall in all cases, be verified (as far as is reasonably practicable) by
the Responsible Engineer. It is recommended that the welder maintain his welder qualification records in
a T/SP/P/9 log book or file (see Appendix K).
* Coal tar enamels, mastic and polyethylene coatings, 600mm either side of the proposed
fitting attachment location.
* Fusion bonded epoxy and paint coatings, 250mm either side of the proposed fitting
attachment location.
NOTE: Certain coatings will melt and emit toxic/carcinogenic fumes when heated by a flame. Pipe
coatings shall only be removed and disposed of using safe methods which are approved by National Grid.
If any doubt exists then expert advice shall be sought.
It may sometimes be advantageous to locate a fitting over a localised area of defective seam weld in
order to remove the defect when drilling and removing the pipe coupon. In a similar way it may be
appropriate to capture a defective girth weld, pipe lamination or corroded area within a full encirclement
repair sleeve or fitting. For guidance see National Grid procedure T/PM/P/11 or T/PM/P/20 as applicable.
12.3 Inspection
12.3.1 Pipe material
12.3.1.1 Material examination (proposed area of pipe covered by the attachment)
The area of the pipe beneath the fitting location shall be examined ultrasonically to ensure freedom from
lamination, which might interfere with welding and drilling operations. The area shall be scanned on a 75
mm square grid (see Figure M.1), and ultrasonic testing practice shall be in accordance with BS EN
²
10160 (amended to cover wall thicknesses above 4.0 mm). Laminations greater than 500 mm shall be
considered unacceptable unless they can be fully encapsulated by the fitting, avoiding the area to be
drilled or welded. Should an unacceptable lamination be confirmed, the fitting shall be relocated to a
suitable attachment area.
Particular attention shall be given to the area where the circumferential fillet welds will cross the
pipe seam weld and attach the fitting to the pipe. No weld defects shall be permitted in a zone
100 mm either side of this junction.
b) The record of the results of all seam weld inspection and examination shall be submitted to the
Responsible Engineer. This will allow the final location of the fittings to be agreed and shall be
done prior to any seam weld dressing.
Where weld defects are found consideration shall be given to the relocation of the attachment
fitting. The Responsible Engineer shall decide whether encapsulation by the split-tee fitting is
possible (see clause 12.2.3). Defective seam welds shall not be dressed. For guidance see
National Grid procedure T/PM/P/11 or T/PM/P/20 as applicable.
All submerged arc welded seams shall be dressed flush with the pipe surface to allow the split tee to fit
snugly and to minimise any gap between the fitting and the pipe. Dressing shall not proceed until all
inspection has been carried out and the final position of the fitting has been confirmed.
The dressing of pipe seam welds shall only be carried out by suitably trained operators competent in the
safe use of grinders. Great care shall be taken to avoid damage to the pipe wall and appropriate
precautions shall be taken to ensure that the operators work from a stable base e.g. the use of platforms
rather than ladders when working on large diameter pipe work. The operation shall be carefully carried
out under the constant supervision of the Welding Inspector and in accordance with an approved method
statement.
Once the seam weld has been dressed flush, a final visual and MPI examination shall be carried out. Any
damage found as a result of the weld dressing shall be reported to the Responsible Engineer and shall be
assessed in accordance with National Grid procedure T/PM/P/11 or T/PM/P/20 as applicable.
Bevel defects shall be removed by grinding and repaired where necessary, to an approved welding
procedure. Any repaired areas shall be re-examined by magnetic particle examination and shall be free of
defects.
Where the thickness of an encirclement fitting is greater than twice the thickness of the pipe that it is
being attached to, then the top edge of the circumferential fitting end shall be tapered at an angle of 45
degrees, to present a face to the fillet weld of 2t (see Figure 8c).
Should excessive pipe ovality result in an excessive longitudinal seam root gap, the fitting shall be
relocated to an acceptable area of pipe. If this is not possible, then subject to the size of gap between the
inside of the fitting and the pipe being equal to or less than 6.0 mm, the fitting bevel face may be built up
using an approved welding procedure. Following re-bevelling to the correct dimensions, the fitting face
shall be inspected visually and by magnetic particle inspection confirm the absence of defects.
The backing bars shall conform to BSI PD 970, type 080 A 15 or equivalent, and be of a sufficient length
to provide a 150 mm projection at each end of the fitting. This projection shall provide the base for the
attachment of carbon steel run-on and run-off plates attached to the ends of the fitting longitudinal seam
weld preparations (attention is drawn to BS 6990 clause 18.2 and 18.3).
The backing bar shall be in the machined recess and in close contact with the fitting. Where ovality of the
pipe could cause distortion of the backing bar during heating, the bar shall be wedged to ensure contact
with the tee. All wedges shall be removed following deposition of the root bead.
For fittings ≤ 300 mm nominal diameter supplied in accordance with T/SP/F/4 the backing strip will be 2
mm thick x 25 mm wide. For fittings > 300 mm nominal diameter supplied in accordance with T/SP/F/4
the backing strip will be 4 mm thick x 25 mm wide. For below 7 bar fittings supplied to an ‘appropriate
specification’ (see 7.2) backing bars with equivalent dimensions shall be used.
Where a small diameter fitting is supplied without the appropriate recess to accommodate the
recommended backing bar size, the thinner backing bar should be used.
13.3.3 Run-on, run-off plates
Suitably profiled run-on and run-off plates shall be tack welded to the backing bar (see Figure 5). The
location of individual tack welds shall be suitable to secure the plates firmly to the backing bar and fitting.
Only qualified T/SP/P/9 welders shall be used to tack weld the run-on, run-off plates using electrodes and
parameters in accordance with the approved welding procedure for pass one.
The ends of the fitting shall be pre-heated to a minimum temperature of 150 ºC and shall be checked
according to clause 15.1.3. The run-on and run-off plates shall be clean and heated to a temperature of
between 50 ºC to 100 ºC. Care should be taken when pre-heating the tee to avoid distortion of the
backing bar prior to welding the longitudinal seam.
14 STRAY ARCS
Stray arcs shall be avoided (see Appendix I).
15 PRE-HEATING
15.1 General
Preheating operations shall have adequate immediate working space, which should be determined by an
assessment of the type of activity, equipment and method of heating employed (see clause 5.3). Only
propane or oxy-propane torches and/or an approved electrical method shall be used.
In circumstances of high gas flow rates that result in rapid pipe temperature decay, oxy-propane heating
torches may be used. However, such torches, if used incorrectly, may cause injury to the person and
damage to the pipe. Only properly trained personnel shall operate oxy-propane torches, they shall be
briefed and made fully aware of the potential risks and hazards associated with this sort of equipment
prior to the operation.
Only competent personnel shall undertake the heating of under pressure pipelines or pipe work.
Heating of a pressurised pipe may only be done under the direct supervision of the Welding
Inspector.
Induction heating is the preferred electrical heating method for pre-heating and maintaining weld inter-
pass temperatures on large diameter, thick wall split-tees (see the guidance notes in Appendix M).
Induction heating methods are approved only for the heating of split-tee longitudinal seam welds and to
heat the fitting when welding circumferential fillet welds. The Responsible Engineer should seek expert
advice when considering the use of Induction heating for applications other than those stated above.
All electrical resistance and induction heating equipment shall be installed and operated by a trained and
competent technician. A detailed procedure for the deployment, monitoring and removal of the heating
equipment and thermocouples shall be submitted to the Employer for approval prior to work commencing.
Other methods of temperature measurement shall not be used without the prior approval of National Grid
and will only be considered following a detailed and documented evaluation.
For temperature measurement methods see clause 15.1.3. This will give an indication of the available
welding period between reheating cycles. Heat input from the welding arcs may extend this period and
regular temperature measurement shall be made throughout the welding period to derive the maximum
benefit from this effect.
Note:
** When assessing the temperature decay rate on pipelines or pipe work with a wall thickness less
than 5 mm, the temperatures to be recorded shall be in accordance with the appropriate preheat
and inter-pass temperatures given in the approved welding procedure for that pipe thickness.
Care should be taken, particularly when heating pipelines or pipe work with a thinner wall
thickness and low gas flow rate, to prevent localised overheating.
shall not exceed 300 ºC. Welding shall cease when the temperature falls to 150 ºC (or to the preheat and
weld inter-pass temperature stated in the approved welding procedure for that pipe thickness).
The fittings / attachments shall be preheated to a minimum temperature of 150 ºC. Strain gauge pads
shall be clean and dry prior to welding, if preheating is required to dry the pads, they shall not exceed a
temperature of 100 ºC.
Where the length of the fittings is > 750 mm, a minimum of two welders shall work on each seam. This
may be reduced to one welder on each seam where the length of the fitting is [ 750 mm. The seams shall
be welded simultaneously. For nominal pipe outside diameters of 150 mm and below, one welder may be
used to weld the fitting. The welding technique used shall provide a balanced deposition sequence
between both longitudinal seam welds. The number of welders and inspectors required for different pipe
sizes is given in Table 3.
Welding shall commence in the centre of the fitting and progress to the ends as shown in Figure 6. Starts
and stops shall be staggered by not less than 25 mm. This method of work shall continue until at least
two complete layers of weld metal have been deposited over the entire seam weld length (see Figure 4).
At this point the yoke clamps may be removed and welding may progress in the direction of preference
until the joint is completed.
With horizontal taps using full encirclement tees, to avoid flange misalignment the fitting shall be fully
supported prior to the removal of the yoke clamps. The fitting should remain supported until at least the
completion of the first circumferential fillet weld. The supports shall be positioned so not to interfere with
safe access to or from the workplace and/or excavation.
When fittings are manufactured from BS EN 10208-3 P460 NL1 / NL2 grade or Hyplus-29 materials a
temper bead shall be applied to the final weld run of the longitudinal seam welds in accordance with the
approved welding procedure (see Appendix F and Appendix M).
The welding of longitudinal seam welds shall normally be carried out in one cycle. However, when
planning a hot-tap operation, the Employer and the National Grid Welding Engineer may approve and
allow the interruption of large diameter, thick wall, longitudinal seam welds subject to a satisfactory written
risk assessment being carried out (see Appendix M.2). In such cases the following conditions apply:
• The nominal diameter of the pipeline and split tee is ≥ 750 mm and the thickness of the fitting is
≥ 50 mm.
• The seam weld shall be filled out to a minimum of half the wall thickness of the fitting along the
entire length of the seam weld before interruption. The fitting may then be allowed to cool
naturally to ambient temperature.
• Prior to welding recommencing each longitudinal seam weld shall be examined by MPI to confirm
the absence of injurious defects.
• Preheating shall be carried out as specified in 15.0.
16.1.2 Removal of the run-on, run-off plates
Upon completion of the longitudinal welds, the end plates shall be removed using a disc grinder. This
operation shall be supervised at all times by the Welding Inspector. Care shall be taken to prevent the
grinding disc touching or reducing the pipe wall thickness and the ends shall be left in a suitable condition
for subsequent inspection.
Should the pipe wall thickness accidentally be reduced by grinding in the area immediately adjacent to
edge of the fitting the Responsible Engineer shall be informed. Providing that the damage is within the leg
length of the subsequent circumferential buttering passes, the depth of the grinding score shall be
measured and the remaining pipe ligament established. Subject to the remaining ligament thickness
being equal to 85% of the nominal pipe wall thickness or 5.0 mm whichever is the greater, the pipe wall
thickness may be restored by deposition of the subsequent buttering passes. For remaining ligaments
less than 5.0 mm the Responsible Engineer shall take expert advice. Any other type of damage found, or
metal loss due to grinding outside the buttering layer zone, shall be assessed in accordance with National
Grid procedure T/PM/P/11 or T/PM/P/20 as applicable.
The completed longitudinal seam welds shall be thoroughly cleaned and inspected in accordance with
clause 18.0. Any weld defects found shall be assessed in accordance with clause 19.2.
For nominal pipe outside diameters of 150mm and below, one welder may be used to weld the fitting. The
welding technique used shall provide a balanced deposition sequence between both sides of the
circumferential fillet weld.
The buttering layers shall be deposited with an appropriate electrode diameter (see Table 1). The first
bead shall be deposited as close as possible to the fitting without impinging or making any attachment to
it. The fillet leg length and gap between the pipe and fitting shall determine the number of buttering runs
required. Starts and stops of adjacent weld runs shall be staggered by not less than 25 mm (see Figure
9).
Pass 6 as shown in Figure 7a, or pass 9 as shown in Figure 7b, or their equivalent, shall be deposited as
close as possible to the extremity of pass 5 or its equivalent, as shown in Figure 7 without impinging on to
the pipe wall.
The number of weld runs deposited in the buttering layers is determined by the required fillet weld leg
length & throat thickness. For pipelines designed to operate at stress levels below 30% the minimum leg
length shall be at least equal to the pipeline design thickness. For pipelines designed to operate at stress
levels above 30% SMYS, the minimum leg length shall be at least twice the pipeline design thickness.
(see Figure 8).
When fittings are manufactured from BS EN 10208-3 P460 NL1 / NL2 grade or Hyplus-29 materials a
temper bead shall be applied to the final weld run of the circumferential fillet weld in accordance with the
approved welding procedure (see Appendix F and Appendix M).
In some circumstances to make maximum use of available welding time, buttering the pipe at each end of
the fitting prior to sealing the throat of the first fillet weld may be considered. The buttering passes shall
not be deposited at both ends simultaneously. The Responsible Engineer shall agree this option in each
case. However, the effects of weld shrinkage from the first completed fillet weld shall be taken into
account.
The completed circumferential fillet welds shall be thoroughly cleaned and inspected in accordance with
clause 18.0. Any weld defects found shall be assessed in accordance with clause 19.2.
All welding shall be stringer bead regardless of position. The weld shall be completed in one cycle.
The completed attachment weld shall be thoroughly cleaned and inspected in accordance with clause
18.0. Any weld defects found shall be assessed in accordance with clause 19.2.
16.3.2.1 Set-on-fittings and flanged attachments to pipe with a wall thickness below 5.0mm
To minimise weld bead penetration on pipe with a wall thickness less than 5mm, the deposition of a
circular band of buttering layers at the location may be considered before placing the fitting on the pipe. In
such cases, the buttering layer shall be inspected by Magnetic Particle examination prior to fitting the
attachment.
Visible flaws such as cavities and other deposition faults shall be removed and particular attention paid to
the cleanliness of the junctions between the weld metal and the fusion faces, before deposition of further
weld metal. Clusters of surface porosity or individual pores and high points shall be removed by grinding.
All stops and starts may be ground smooth if necessary to ensure fusion of the subsequent weld run pick
up.
Welding shall cease immediately should visible cracking be discovered. The Authorising engineer
shall be informed and the cause of any cracking into the pipe wall investigated and treated in
accordance with National Grid procedure T/PR/P/11 or T/PM/P/20 as applicable.
18. INSPECTION
18.1 General
18.1.1 Non-destructive examination procedures
Inspection procedures in accordance with T/SP/NDT/2 shall be submitted to National Grid for approval
prior to the commencement of work. Adequate lighting and weather protection for inspection purposes
shall be made available (see clause 5.3).
inter-run cleaning is being done and that an acceptable defect free weld with good profile is being
achieved. The weld shall be visually examined upon completion and shall have a good profile with a
positive reinforcement. Undercut and overspill shall not be permitted and shall be removed by grinding /
blending without detriment to the minimum wall thickness design requirements for pipe or fitting.
Small attachment fittings (90 mm nominal diameter and below) shall be welded in one cycle omitting the
intermediate magnetic particle examination, except when buttering is applied prior to fitting set-up (see
clause 16.3.2.1).
i) Welding Inspector
ii) MPI Inspector
The Inspector shall be required to demonstrate a period of 3 years experience in the implementation of
the T/SP/P/9 Inspection procedures. In order to achieve this level of experience, with the approval of the
Employer, the inspector will be permitted to work on a T/SP/P/9 operation provided that they are
supervised by either a qualified inspector or a designated mentor who meets the requirements outlined
above.
All non-destructive examination (NDT) personnel shall be qualified to the appropriate grade in the
BGAS/CSWIP inspector approval scheme.
As a variation to this requirement, the Employer may consider the use of NDT personnel qualified to an
equivalent level in another certification scheme to undertake the NDT operations.
Existing girth and seam welds that do not meet the requirements specified above shall be dealt with as
follows:
a) Girth welds operating at pressures greater than 7 bar shall be assessed in accordance with
T/PR/P/18 procedures (see 5.5).
b) Girth welds operating at pressures equal to or less than 7 bar shall be subject to a risk
assessment by the Responsible Engineer and may require encapsulation in accordance
with T/PM/P/11 or T/PM/P20 as appropriate.
c) Unacceptable defects found on pipe seam welds shall either be fully encapsulated by the
hot-tap fitting or the fitting shall be moved to a location free from unacceptable defects
(see12.3.2).
All surface breaking or visual defects other than cracking shall be completely removed and rectified by
dressing, or grinding and re-welding (see clause 17). No weld shall be repaired without the approval and
supervision of the Welding Inspector.
Repair excavations shall be sufficiently deep and long to remove the defect. The ends and sides of the
excavation shall be gradually tapered from the base to the external weld surface. The width and profile
shall give adequate access for re-welding. The removal of the defect shall be confirmed by magnetic
particle examination prior to re-welding.
All welded repairs shall be carried out in accordance with the approved original welding procedure and
this specification. Providing that there is no deviation from the approved original welding procedure,
specific repair welding procedure sheets are not required. Any deviation from the original welding
procedure shall require qualification in accordance with BS 6990 and this specification.
Imperfections, defects or damage found on the original pipe surface, which may extend below the original
pipe surface shall be treated in accordance with National Grid procedure T/PR/P/11 or T/PM/P/20 as
applicable.
21. RECORDS
The Employer shall approve all documentation relating to the planning, risk assessment, preparation,
welding and inspection operations at the appropriate stage of the operation. Upon completion of the
activity the documentation required under the contract shall be retained for the asset life.
NOTES:
Pipe wall thickness range
Electrode
Note 4.0 to 4.9 mm 5.0 to 5.9mm > 6 mm
diameter
Maximum allowable welding current (amperage)
1 2.5 mm 90A 100A 100A
4
2 3.25 mm 110A 140A 150A
Buttering passes DC – negative
Recommended
1&2 Remainder of passes DC + positive DC + positive
polarity
DC - /+ negative or positive
3.25 mm diameter electrodes may be used in place of 4.0 mm diameter electrodes for
3
the subsequent passes on pipe less than 8 mm thickness.
4 For pipe wall thickness ≥ 20 mm the maximum amperage may be increased to 170A.
TABLE 3 - MINIMUM WELDER / INSPECTOR STAFFING LEVELS FOR SPLIT TEE CONNECTIONS
(2)
Number of welders
Nominal Pipe Number of
(2)
Diameter Inspectors
Long. Weld Circ. Weld
50 – 150 mm 1 1 1
200 – 350 mm 2 2 1
400 – 450 mm 2 2 2
(1)
> 450mm 2 or 4 2 2
Notes: 1 A minimum of four welders are required for fittings of > 750 mm in length (see clause 16.1).
2 Where extended periods of welding are anticipated then relief welders and inspectors shall be
made available (see clause 5.4). In some circumstances a relief crew, working on a shift basis
may be required. The number of operatives to be used shall be stated on the project method
statement.
ENCAPSULATION
DOME END
"O" LET
(B) DIRECT BRANCHES
CODS MOUTH
BRANCH
NOT TO SCALE
FLAT
(2F/PB)
Actual pipe
OVERHEAD thickness
(4F/PE) 10
0
15
1.4 t
1.5 GAP
300
Actual thickness, t
Buttering runs
VERTICAL
(3F/PG)
FLAT
(2F/PB)
OVERHEAD
(4F/PE) 5 10
0
15
10
1.5 GAP
300
5
Buttering runs
VERTICAL
(3F/PG)
FLAT
(2F/PB)
OVERHEAD 25
(4F/PE) 25
0
15
25
1.5 GAP
300
25
Buttering runs
VERTICAL
(3F/PG)
TOP HALF
OF FITTING
BOTTOM HALF
OF FITTING
Figure 3a. Joint preparation for longitudinal seam welds. Vertical off-
take, fitting wall thickness less than 25 mm.
TOP HALF
OF FITTING
30° (+5, -0)
(up to 1/2 T)
BOTTOM HALF
OF FITTING
Figure 3b. Joint preparation for longitudinal seam welds. Vertical off-
take, fitting wall thickness equal to or greater than 25 mm.
FITTING FITTING
FITTING FITTING
TOP HALF
OF FITTING
A MINIMUM OF TWO
COMPLETE WELD LAYERS
SHALL BE DEPOSITED
PRIOR TO RELEASE OF THE
YOKE-TYPE CLAMP.
BOTTOM HALF N.B. EACH LAYER SHALL
OF FITTING CONSIST OF ONE OR MORE
WELD RUNS.
50 - 150
BACKING BAR
~75
FITTING RUN ON/OFF TAB
PIPE
Dimensions in mm
150 X 75
CARBON STEEL
BAR (8-12 THK),
ANGLED TO SUIT
LONG. SEAM WELD
PREPARATION.
25 X 4
CARBON STEEL
BACKING BAR.
Remaining Passes
FITTING
FITTING
11
10
8
6 7 9 6
1 2 3 4 5 1 2 3 4 5
PIPE PIPE
a.) Buttering run sequence. d.) Fill run sequence, 1st layer.
FITTING
16
FITTING
15
11 14
10 13
8
6 7 8 9 7 9 12 6
1 2 3 4 5 1 2 3 4 5
PIPE PIPE
b.) Buttering run sequence, excess gap. e.) Fill run sequence, 2nd layer.
etc.
16
FITTING
15
FITTING
11 14
10 13
8 8
7 6 7 9 12 6
1 2 3 4 5 1 2 3 4 5
PIPE PIPE
c.) Throat closure weld runs. f.) Fill run sequence, cap layer.
LEG LENGTH
=1.4t + GAP
<2t FITTING < 2t
t PIPE
A) FITTING < 2t
2t + GAP
2t FITTING = 2t
t PIPE
B) FITTING = 2t
2t + GAP
2t
t PIPE
C) FITTING > 2t
FIGURE 8. CIRCUMFERENTIAL FILLET WELD DIMENSIONS.
B) & C) FOR PIPELINES DESIGNED TO OPERATE AT STRESS LEVELS ABOVE 30% SMYS
(i.e. a 'mitre' fillet) and the profile shall not show any concavity.)
(Note: The completed fillet weld shall be of equal leg length
FIRST SEGMENT
SECOND SEGMENT
WELDING DIRECTION
SEGMENT
SEGMENT
NOT TO SCALE
mm
PIPE
FIGURE 11 - WELD BUTTERING AND FILL SEQUENCE FOR SET-ON FITTING ATTACHMENT.
2 PLATE 2
1 1
PIPE
APPENDIX A
LIST OF REFERENCES
This Specification makes reference to the documents listed below (see clause 2).
BS EN 10208-3 Flat products made of steels for pressure puposes – Part 3: Weldable fine grain
steels, normalised
BS EN 10160 Ultrasonic testing of steel flat product of thickness equal or greater than 6 mm
(reflection method).
BS EN ISO 3690 Welding and allied processes. Determination of hydrogen content in ferritic steel
weld metal.
British Standards
BS 638 Specification for arc welding power sources, equipment and accessories
Part 4 - Welding cables
Part 5 - Accessories
Part 7 - Safety requirements for installation and use
Part 8 - Electrode Holders and hand held torches and guns for MIG,MAG and
TIG welding
Part 9 - Power sources for manual arc welding with limited duty
Part 10 - Safety requirements for arc welding equipment: welding power sources
BSI PD 970 Wrought steels for mechanical and allied engineering purposes – Requirements for
carbon, carbon manganese and alloy hot worked or cold worked finished steels.
BS 6990 Code of practice for Welding on steel pipes containing process fluids or their
residuals
T/SP/F/1 Technical specification for carbon and carbon manganese steel forgings and
forged components for operating pressures greater than 7 bar.
T/SP/F/4 Technical specification for hot tap and stopping-off connections (for operating
pressures 2 bar to 100 bar inclusive).
T/SP/P/1 Technical specification for welding of steel pipe operating at pressures not greater
than 7bar.
T/SP/P/2 Technical specification for welding of land pipelines and installations designed to
operate at pressures greater than 7 bar (incorporating BS 4515).
T/SP/P/8 Specification for welding of steel onshore natural gas installations designed to
operate at pressures greater than 7 bar.
T/SP/NDT/2 Specification for non-destructive testing of welded joints in steel pipelines and pipe
work.
T/PM/P/11 Management procedure for inspection, assessment and repair of damaged (non-
leaking) steel pipelines above 150 mm nominal diameter and designed to operate
at pressures greater than 2 bar.
T/PM/P/20 Management procedure for inspection, assessment and repair of damaged (non-
leaking) steel pipelines and pipework up to 150 mm nominal diameter and
designed to operate at pressures greater than 2 bar.
T/PR/P/18 Work Procedures for working on pipelines containing defective girth welds or girth
welds of unknown quality.
T/SP/PW/11 Part 1 Specification for pipework systems operating exceeding 7 bar – Design and
materials.
T/PL/RE/1 Policy for the capture, update and retention of engineering asset records.
T/PM/G/17 Management Procedure for The Management Of New Works, Modifications and
Repairs.
APPENDIX B DEFINITIONS
Approved Welder:
A welder who has demonstrated their skill and ability by producing a satisfactory test weld or welds in
accordance with the requirements of this specification.
Responsible Engineer:
National Grid Engineer (or nominated representative), responsible for ensuring that this specification is
complied with.
Employer:
Shall mean National Grid plc.or its nominated representative.
HAZ
Heat affected zone.
Inspector:
The body, association or employee, that ensures that the construction and materials used are in
accordance with this specification.
Joint:
The completed weld joining two sections of pipe, a section of pipe to a fitting or two fittings.
Leg length:
The distance between the inter-section of the fusion faces and the toe of a fillet weld, measured along the
fusion face (see Figure 8).
Mechanized welding:
Welding where the welding parameters are controlled mechanically or electronically and may be manually
varied during welding to maintain the required welding conditions.
Pipe coupon:
The part of the pipe removed during a drilling operation.
Positional Welding:
Welding where the pipe or assembly is held stationary.
Root run:
The deposited first weld run in the base of a multi-run weld.
Note: Also known as a ‘root stringer bead’ in vertical down welding.
Semi-automatic welding:
Welding in which some of the welding variables are automatically controlled, but manual guidance is
necessary.
Throat thickness:
The minimum cross sectional length of weld metal measured from the root face of the fillet weld,
excluding any buttering runs necessary to reduce a gap between the fitting and the pipe (see Figure 8).
Welding procedure:
A specific course of action followed in welding, including lists of materials and where necessary, tools to
be used.
Weld Layer:
A number of weld runs placed side by side to produce a weld deposit of the required width at that location,
for the given joint preparation. (see Figure 4).
Weld Run:
A weld deposit produced by a single pass or traverse of the welding electrode.
APPENDIX C
APPENDIX D
APPENDIX E
APPENDIX F
Procedure No: 01
Longitudinal Seam Weld
(3 & 9 o’clock Position)
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material T/SP/F/4-BS EN 10028-3 – Product
Pipe Fluid
1.0562 Grade P335N Natural Gas
CEV 0.42%
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) 2G (PB)
Fitting Position Horizontal/Vertical Branch
A 3 + 3, -0 mm
B 30 + 5, -0 deg A B
2 4 6
C 10 + 5, -0 deg 1 3 5
C
D 1.5 + 1, -0 mm
D
Clamping Method Yoke Clamp Pre-Heat Temp ( 0C ) Min 250, Max 300
Pre-Heat
Run Off/ Run On Tabs PD 970 – 080 A15 or equivalent Application *Oxy Propane Torch
Pre-Heat Temp ( 0C ) See P/9 Appendix H and 13.3.3. Measurement Tempilstik® and/or
thermocouple
Technique
Baking Temp ( 0C ) N/A ** Use VacPak Clamp Removal See Instruction No. 3
Holding Temp ( 0C ) N/A ** Use VacPak 1. Number of welders per seam weld; see instruction No.1.
Notes
* Oxy Propane or electrical preheating or a combination of both may be used (see clause 15.0 of T/SP/P/9).
** Filarc 27P or an equivalent National Grid approved electrode. Vacuum packed and treated as per electrode control procedure.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 02
Longitudinal Seam Weld
(6 & 12 o’clock Position)
Pipe Fluid
1.0562 Grade P335N Natural Gas
CEV 0.42%
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) 1G & 4G (PA & PE)
Fitting Position Horizontal/Horizontal Branch
A 3 + 3, -0 mm B C
B 30 + 5, -0 deg
D 3 4
C 30 + 5, -0 deg 2
D 1.5 + 1, -0 mm 1
A
Clamping Method Yoke Clamp Pre-Heat Temp ( 0C ) Min 250, Max 300
Pre-Heat
Run Off/ Run On Tabs PD 970 – 080 A15 or equivalent Application *Oxy Propane Torch
Pre-Heat Temp ( 0C ) See P/9 Appendix H and 13.3.3 Measurement Tempilstik® and/or
thermocouple
Technique
Baking Temp ( 0C ) N/A ** Use VacPak Clamp Removal See Instruction No. 2
Holding Temp ( 0C ) N/A ** Use VacPak 1. Number of welders per seam weld; see instruction No.1.
Notes
* Oxy Propane or electrical preheating or a combination of both may be used (see clause 15.0 of T/SP/P/9).
** Filarc 27P or an equivalent National Grid approved electrode. Vacuum packed and treated as per electrode control procedure.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 03
Circumferential Fillet
Buttering
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material T/SP/F/4-BS EN 10028-3 – Product
Pipe Fluid
1.0562 Grade P335N Natural Gas
CEV 0.42%
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) PG (5F)
Fitting Position Horizontal/Vertical Branch
Interpass Temp ( 0C )
Fitting
Set Up
Quiver Temp ( 0C ) N/A ** Use VacPak shall be deposited as close to the toe of the final buttering
pass as possible, without impinging onto the parent plate.
Shielding Gas N/A ** Use VacPak
Side Gas Wire AV.
Flux Welding
Weld Weld No. Of Dia. AC/DC+ Heat
Pass Process Direction Welders
Electrode
(mm) /DC-
Type/Gas Flow Amps Volts Speed Feed Input
No. Shield Rate (mm/sec) Speed (KJ/mm)
Vertical 1 per
1 SMAW **27P 3.25 DC+ Basic N/A 110-150 20-26 3.0 N/A 0.99
Down side
Name: Name:
Title: Title:
Date: Date:
Procedure No: 04
Completion of
circumferential fillet weld
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material T/SP/F/4-BS EN 10028-3 – Product
Pipe Fluid
1.0562 Grade P335N Natural Gas
CEV 0.42%
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) PG (5F)
Fitting Position Horizontal/Vertical Branch
C
Fitting Fitting C Fitting B
Fitti ng B
A
5 6
4 4 5 6 A 4 4
1 2 3 1 2 3 1 2 3
1 2 3
Pipe Pipe Pipe Pipe
2t 2t 2t 2t
Name: Name:
Title: Title:
Date: Date:
Procedure No: 05
Circumferential Fillet -
Completion
Temper Bead for P460/Hyplus 29
Typical Weld Procedure Specification material fittings
Revision No. 0
Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material T/SP/F/4-BS EN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) 5F (PF)
Fitting Position Horizontal/Vertical Branch
Joint Details Pass Locations
Groove prepared by
grinding (see note 2).
Interpass Temp ( 0C )
Fitting
Set Up
E50 6 Mn 1Ni B 12 H5 /
Consumable -
Instructions:
1. Oxy Propane (see P/9 - Appendix H) or electrical preheating methods (or a combination of both may be used).
2. Prior to deposition of the temper bead ( pass 1) the previous final pass of the fillet weld shall be prepared by grinding using a 4mm disc
Care shall be taken to maintain the edge of the final pass to provide a clear guideline for deposition of the temper bead..
3. The temper bead pass may be applied at the blocking or segment stage.
4. Care shall be taken to prevent impingement of the temper bead onto the fitting.
5. Stop starts shall be offset by a minimum distance of 25mm.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 06
Weldolets and Flanged
Attachments
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material T/SP/F/1 – F60 Grade Product Natural Gas
Fluid
Pipe
Pipe Material/CEV% API 5L X52 Pressure (Range)
Base Materials
19 to 32 bar
confirmed 0.46%
Wall Thickness / Dia. 9.5mm / 610mm – 60.3mm Flow (Range) 0.1 to 0.3 m/s
Range Covered Dia / WT >6.0mm – 12.7mm (w.t.) Welding Process SMAW
>114.3mm (dia.)
Process
Pipe Position Fixed Horizontal Weld Position(s) PB (2G)
Fitting Position 60.3mm vertical Branch
(12 o’clock pipe position)
Joint Details Pass Locations
SET-ON
FITTING S E T -O N
F IT T IN G
S e e n o te b e lo w
8
Gap 3.0 mm
6
(+1, -0) 3 7
1 2 4 5
PIPE P IP E
Name: Name:
Title: Title:
Date: Date:
Procedure No: 07
Cathodic Protection Plate
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material BS EN 10025 – S275JR Product Natural Gas
Fluid
Pipe
Base Materials
Process
>114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) PB (2F)
Fitting Position 12 o’clock pipe position
Joint Details Pass Locations
CP Plate
2
1
Pipe
Clamping Method N/A Pre-Heat Temp ( 0C ) Min 250, Max 300
Pre-Heat
Quiver Temp ( 0C ) N/A ** Use VacPak maximum gap to be 1.5 mm between plate and pipe.
2. CP Plate to be fully welded around the periphery
Shielding Gas N/A
Side Gas Wire AV.
Flux Welding
Weld Weld No. Of Dia. AC/DC+ Heat
Pass Process Direction Welders
Electrode
(mm) /DC-
Type/Gas Flow Amps Volts Speed Feed Input
No. Shield Rate (mm/sec) Speed (KJ/mm)
1 SMAW Flat 1 **27P 3.25 DC+ Basic N/A 110-130 20-26 3.0 N/A 0.99
2 SMAW Flat 1 **27P 3.25 DC+ Basic N/A 110-130 20-26 3.0 N/A 0.99
Instructions:
1. Temperature decay to be carried out prior to commencement of welding (seeT/SP/P/9 clause 15.2.2).
2. For preheating strain gauge pads see clause 15.3.
3. A minimum of two passes shall be applied. The second pass is to be deposited as close as possible to the extremity of the first pass without impinging onto the
pipe surface (see Figure 12 of T/SP/P/9).
4. Weld to be completed in one cycle.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 08
Circumferential Fillet Buttering -
4.0mm to 4.9mm wall thickness
pipe
Typical Weld Procedure Specification Revision No. 0
Date: 1st January 2010
Project: Wye to Sedd pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material BS EN 1501 – 151 Grade Product Natural Gas
Pipe Fluid
430A
Pipe Material/CEV% BS 3602 / Pressure (Range) 4 to 6 bar
Base Materials
Confirmed 0.35%
Wall Thickness / Dia. 4.0mm / 114mm dia. Flow (Range) 0.1 to 0.3 m/s
Range Covered Dia / WT 4.0mm – 6.0mm (w.t.) Welding Process SMAW
114.3mm (dia.)
Process
Pipe Position Fixed Horizontal Weld Position(s) PG (5F)
Fitting Position Horizontal/Vertical
Branch
Joint Details Pass Locations
Quiver Temp ( 0C ) N/A ** Use VacPak 2. The ‘tempering pass’ shall be deposited as close to the
toe of the final buttering pass as possible, without
Shielding Gas N/A impinging onto the parent plate.
Side Gas Wire AV.
Flux Welding
Weld Weld No. Of Dia. AC/DC+ Heat
Pass Process Direction Welders
Electrode
(mm) /DC-
Type/Gas Flow Amps Volts Speed Feed Input
No. Shield Rate (mm/sec) Speed (KJ/mm)
Vertical 1 per
1 SMAW **27P 2.5 DC- Basic N/A 70 - 90 20 - 26 3.0 N/A 0.6
Down side
The remainder of the buttering passes as per pass one.
Instructions:
1. Temperature decay to be carried out prior to commencement of welding (see T/SP/P/9 clause 15.2.2).
2. Additional layers of buttering may be required depending on the gap between pipe and fitting. The maximum gap shall be 6mm.
3. Passes 1 to 3 or passes 1 to 4 (where an extra layer is required) or equivalent shall be deposited in layers or segments around the pipe.
4. The Temper bead may be omitted if access to the root is likely to be hindered.
5. Stop/starts to be staggered by a minimum of 25mm.
6. The completed buttering passes shall be examined by Magnetic Particle Inspection, before continuing the fillet weld. If any evidence of cracking is found,
welding shall cease immediately and National Grid shall be informed.
* Propane or Oxy Propane heating may be used (see clause 15.0 of T/SP/P/9 and Appendix H).
** Filarc 27P or an equivalent National Grid approved electrode. Vacuum packed and treated as per electrode control procedure.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 09
Circumferential Fillet
Completion - 4.0mm to 4.9mm
wall thickness pipe
Typical Weld Procedure Specification Revision No. 0
Date: 1st January 2010
Project: Wye to Sedd pipeline Client: National Grid
Specification/Procedure National Grid T/SP/P/9
Fitting Material BS EN 1501 – 151 Grade 430A Product Natural Gas
Fluid
Pipe
Pipe Material/CEV% BS 3602 Pressure (Range)
Base Materials
4 to 6 bar
0.35%
Wall Thickness / Dia. 4.0mm / 114mm dia. Flow (Range) 0.1 to 0.3 m/s
Range Covered Dia / WT 4.0mm – 6.0mm (w.t.) Welding Process SMAW
Process
114.3mm (dia.)
Pipe Position Fixed Horizontal Weld Position(s) PG (5F)
Fitting Position Horizontal/Vertical Branch
PIPE
PIPE
Interpass Temp ( 0C )
Fitting
Set Up
Instructions:
1. Temperature decay to be carried out prior to commencement of welding (seeT/SP/P/9 clause 15.2.2).
2. Pass A is not to extend beyond one electrode run out length before deposition of pass B,
3. Stop/starts to be staggered by a minimum of 25mm.
4. Once pass B has been completed around the entire circumference of the pipe, the fillet weld can be completed in balanced layers or segments to take maximum
benefit of localised weld inter- pass temperatures.
5. The minimum inter-pass temperature of 150 0C is to be maintained on the fitting but can be relaxed to 100 0C on the pipe after completion of pass C.
* Propane or Oxy Propane heating may be used (see clause 15.0 of T/SP/P/9 and Appendix H).
** Filarc 27P or an equivalent National Grid approved electrode. Vacuum packed and treated as per electrode control procedure.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 10
Longitudinal Seam Weld
(3 & 9 o’clock Position)
Revision No. 0
Typical Weld Procedure Specification
Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material T/SP/F/4-BSEN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
14.3mm – 22.9mm (W.T)
Pipe Position Fixed Horizontal Weld Position(s) 2G (PB)
Fitting Position Horizontal/Vertical Branch
E 1.5mm (+ 1, - 0 mm)
F 50% t >25mm
Clamping Method Yoke Clamp or Clamp brackets Pre-Heat Temp ( 0C ) Min 250, Max 300
Pre-Heat
Fitting
Set Up
Baking Temp ( 0C ) N/A Use VacPak Clamp Removal See Instruction No. 2
Holding Temp ( 0C ) N/A Use VacPak
Notes
Instructions:
1. Oxy Propane (see P/9 - Appendix H) or electrical preheating methods (or a combination of both may be used).
2. When the length of the fitting exceeds 750mm two welders shall be used on each longitudinal seam. One welder per side can be used for seams less than
750mm in length.
3. Welding will commence in the middle of the fitting and progress to the ends for the first two weld layers. At this point in the procedure, welding can
progress in the direction of preference.
4. A minimum of two complete weld layers shall be deposited (see P/9 – Figure 4) prior to the removal of clamp. The fitting shall be fully supported before
the clamp is released.
5. A temper bead cap deposition sequence shall be used (see P/9-16.1).
Name: Name:
Title: Title:
Date: Date:
Procedure No: 11
Longitudinal Seam Weld
(6 & 12 o’clock Position)
Revision No. 0
Typical Weld Procedure Specification
Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material T/SP/F/4-BSEN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
Pipe Position Fixed Horizontal Weld Position(s) 1G and 4G (PA/PE)
Fitting Position Horizontal/Horizontal Branch
E 1.5mm (+ 1, - 0 mm)
F 50% t >25mm
Clamping Method Yoke Clamp or Clamp brackets Pre-Heat Temp ( 0C ) Min 250, Max 300
Pre-Heat
Interpass Temp ( 0C )
Fitting
Set Up
Backing Strip PD 970 – 080 A15 or equivalent Min 150, Max 250
Weld
Baking Temp ( 0C ) N/A Use VacPak Clamp Removal See Instruction No. 2
Holding Temp ( 0C ) N/A Use VacPak
Notes
Instructions:
1. Oxy Propane (see P/9 - Appendix H) or electrical preheating methods (or a combination of both may be used).
2. When the length of the fitting exceeds 750mm two welders shall be used on each longitudinal seam. One welder per side can be used for seams less than
750mm in length.
3. Welding will commence in the middle of the fitting and progress to the ends for the first two weld layers. At this point in the procedure welding can
progress in the direction of preference.
4. A minimum of two complete weld layers shall be deposited (see P/9 – Figure 4) prior to the removal of clamp. The fitting shall be fully supported before
the clam is released.
5. Care shall be taken to balance the welding of the flat and overhead weld seams.
6. A temper bead cap deposition sequence shall be used (see P/9-16.1).
Name: Name:
Title: Title:
Date: Date:
Procedure No: 12
Circumferential Fillet Buttering
Revision No. 0
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
Pipe Position Fixed Horizontal Weld Position(s) 5F (PF)
Fitting Position Horizontal / Horizontal Branch
Pipe
t
Vertical ESAB
All SMAW 1 per side 90 DH
3.2 DC+ Basic N/A 140-170 20-24 5.5 N/A 0.5
Down
Instructions:
1. Temperature decay to be carried out prior to the commencement of welding (see T/SP/9 clause 15.2.2).
2. The buttering passes may be deposited using either of the two options provided above. However, the two different consumables shall not be mixed.
3. Additional layers of buttering may be required depending on the gap between Pipe and Fitting. The maximum gap shall be 6mm.
4. Passes 1-5 or passes 1 to 8 (or equivalent) if an extra layer is required shall be positioned in segments around the pipe circumference. The tempering
pass shall be deposited as close to the toe of the final buttering pass a possible, without impinging on parent plate.
5. Stop-starts to be off set by a minimum distance of 25 mm.
6. The completed buttering passes shall be examined by Magnetic Particle Inspection prior to continuing with the fillet weld.
7. Pre-heat and interpass temperatures shall be measured on the pipe surface.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 13
Circumferential Fillet -
Completion
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material T/SP/F/4-BSEN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
Pipe Position Fixed Horizontal Weld Position(s) 5F (PF)
Fitting Position Horizontal / Branch
Interpass Temp ( 0C )
Fitting
Set Up
Name: Name:
Title: Title:
Date: Date:
Procedure No: 14
Circumferential Fillet -
Completion
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material T/SP/F/4-BSEN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Process
14.3mm – 22.9mm (W.T)
Pipe Position Fixed Horizontal Weld Position(s) 5F (PF)
Fitting Position Horizontal/Vertical Branch
Interpass Temp ( 0C )
Fitting
Set Up
Classifications E55 6 Mn1Ni B 41H5 / E9018-G Cleaning Method Hand and/or Power Tools
Controls
Name: Name:
Title: Title:
Date: Date:
Procedure No: 15
Circumferential Fillet -
Completion (Temper Bead
for P460/Hyplus 29 Materials)
Typical Weld Procedure Specification Revision No. 0
Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material T/SP/F/4-BSEN 10028-3 – Product
Pipe Fluid
Grade P460 NL2 No. 1.8918 Natural Gas
CEV 0.47%
Base Materials
Pipe Material/Ce L555 MB No. 1.8978 / 0.44% Pressure (Range) TBA (e.g. 64 to 70 bar)
Wall Thickness / Dia. 15.9 mm / 1219 mm OD Flow (Range) TBA (e.g. 1 to 2 m/s)
Range Covered Dia / WT > 609.5mm to < 1219mm (dia) Welding Process SMAW
Process
14.3mm – 22.9mm (W.T)
Pipe Position Fixed Horizontal Weld Position(s) 5F (PG)
Fitting Position Horizontal/Vertical Branch
Interpass Temp ( 0C )
Fitting
Set Up
E50 6 Mn 1Ni B 12 H5 /
Consumable -
Instructions:
1. Oxy Propane (see P/9 - Appendix H) or electrical preheating methods (or a combination of both may be used).
2. Prior to deposition of the temper bead ( pass 1) the previous final pass of the fillet weld shall be prepared by grinding using a 4mm disc
Care shall be taken to maintain the edge of the final pass to provide a clear guideline for deposition of the temper bead..
3. The temper bead may be applied at the blocking or segment stage.
4. Care shall be taken to prevent impingement of the temper bead onto the fitting.
5. Stop starts shall be offset by a minimum distance of 25mm.
Name: Name:
Title: Title:
Date: Date:
Procedure No: 16
Set-on fitting attachments
Revision No. 0
Typical Weld Procedure Specification Date: 1st January 2010
Project: Exe to Wye pipeline Client: National Grid
Specification/Procedure T/SP/P/9: 2009
Fitting Material X65 (60.3 mm branch) / 0.38% Product Natural Gas
CEV 0.43%
Fluid
Pipe
Base Materials
Process
14.3mm – 22.9mm (W.T)
Pipe Position Fixed Horizontal Weld Position(s) 2G (PB)
Fitting Position 12 O’Clock Position
PIPE
Classifications E55 6 Mn1Ni B 41H5 / E9018-G Cleaning Method Hand and/or Power Tools
Controls
Instructions:
1. Temperature decay to be carried out, see T/SP/P/9 clause 15.2.2 prior to commencement of welding.
2. Fitting to be pre-heated to 150 0C.
3. The weld shall be completed in one cycle (care being taken to prevent overheating above the maximum inter-pass temperature).
4. Pass No. 8 or its equivalent (see Figure 11 of T/SP/P/9,) to be placed as close as possible to the extremity of pass 4 or its equivalent, without impinging
onto the pipe.
5. Stop/starts to be staggered by a minimum of 25mm.
* Oxy Propane or electrical preheating or a combination of both may be used (see clause 15.0 of T/SP/P/9).
Name: Name:
Title: Title:
Date: Date:
Procedure No:
Revision No. 0
Typical Weld Procedure Specification Date:
Project: Client:
Specification/Procedure
Fitting Material Product
Fluid
Base Materials
Pipe
Pipe Material/Ce Pressure (Range)
Wall Thickness / Dia. Flow (Range)
Range Covered Dia / WT Welding Process
Process
Pipe Position Weld Position(s)
Fitting Position
Joint Details Pass Locations
Quiver Temp ( 0C )
Shielding Gas
Side Gas Wire AV.
Flux Welding
Weld Weld No. Of Dia. AC/DC+ Heat
Pass Process Direction Welders
Electrode
(mm) /DC-
Type/Gas Flow Amps Volts Speed Feed Input
No. Shield Rate (mm/sec) Speed (KJ/mm)
Instructions:
Name: Name:
Title: Title:
Date: Date:
APPENDIX G
In addition to the manufacturers recommendations for the storage and use of low- hydrogen electrodes,
the following conditions shall apply (also see consumable handling flow chart):
1. When used in accordance with the manufacturer’s recommendations, the packaging shall be
capable of guaranteeing equal to or less than 5 ml/100 g of diffusible hydrogen in the deposited
weld metal.
2. Only electrode packs which are undamaged and where the vacuum is intact (if appropriate) or the
seal is unbroken shall be issued to site.
3. Only one pack shall be opened at a time and the seal shall be checked to make sure it is intact
before opening. Where visual indication of the moisture level in the pack is provided, this shall be
checked after opening of the pack. Electrodes from faulty packs shall not be used.
4. Once a vacuum pack is opened, electrodes shall only be removed from the pack one at a time.
Where means of re-sealing the pack is provided, this shall be carried out each time the welding
operation is interrupted (see item 6).
5. Electrode packs shall be shielded from damp conditions. Electrodes showing signs of moisture.
Damage or contamination shall not be used.
6. Any electrodes left in a vacuum pack that has been opened and exceeds the manufacturers
recommended maximum exposure period, shall not be used and shall be removed from the
workplace. Un-used electrodes shall not be re-baked for use on T/SP/P/9 operations (see 9.1).
NOTE: There is no benefit to be gained from baking electrodes taken directly from an undamaged
vacuum pack. However, in certain circumstances it may be beneficial to use the electrodes
from a heated quiver (minimum of 75 °C).
Consumable Handling
Consumables
received
from supplier.
No Do consumables
have required
Certification.
Yes
Check condition
of vacuum packaging
No Is packaging sound,
seal unbroken and
Vacuum contained.
Yes
Store consumables in
accordance with the
manufacturers instructions.
Check condition
of vacuum packaging
prior to use.
No Is packaging sound,
seal unbroken and
vacuum contained.
Yes
Following completion
Are consumables of working shift or in
Discard or
No being used in accordance with
Yes accordance with the manufacturers
return to supplier. manufacturer’s instructions. Instructions, unused
(humidity levels etc.). consumables from open packs
shall be removed from the workplace.
APPENDIX H
N1. The use of oxy-propane heating torches to raise the pipe surface temperature to the level
required by this specification (clause 15.2) may be necessary. It is recognised that a method of rapid shut
off of the torch gases is desirable for safety reasons.
N2. The following supplier has developed heating equipment (identified as the ‘National Grid
superheating lamp kit’), which in tests, have satisfied National Grid safety requirements for controlled
rapid shut off:
Note: For consistently safe operation, it is imperative that the correct type of flash-back arrestors and
flame traps are used in conjunction with this safety shut off valve. For this reason the equipment is sold
as a kit complete with the correct torch, gas regulators and hoses as shown above. Training in the safe
use of this equipment, in accordance with the manufacturers recommended procedure, shall be
considered mandatory.
APPENDIX I
H.2 If arc strikes are made in parent plate during any repair, or are discovered when a pipeline has
been excavated for any reason, they shall be removed by dressing. After all traces of the arc strike have
been removed, between 0.5 mm and 0.7 mm thickness of metal shall be removed from the valley of the
crater formed by dressing (This is to remove potential hardened areas below the arc-strike).
H.3 The repair area shall be checked by magnetic particle examination and the remaining wall
thickness of the pipe or fitting measured to confirm that they are within the permitted tolerance.
H.4 Stray arcs shall only be repaired by an approved National Grid P/11(P/20) technician. All
relevant details shall be recorded and reported.
H.5 Should the removal of an arc strike result in the remaining pipe wall thickness being below the
minimum pipe manufacturing under thickness tolerance, the area shall be assessed in accordance with
T/PM/P/11 or T/PM/P/20 as applicable.
APPENDIX J
Comments:
APPENDIX K
Project /
contract:
Notes:
A copy of this test record should be given to the welder for his retention.
APPENDIX L
L.1 Prior to making a welded attachment to a pressurised gas pipeline, positive confirmation of the
existing pipeline material type, carbon equivalent value (CEV) and approximate grade shall be
made.
L.2 As a minimum, the following items shall be determined either by review of existing records, or
where these do not exist, pipe material sampling:
a) Chemical analysis and CEV
b) Tensile strength / yield strength (applicable where a material coupon is available)
c) Hardness of the material
L.3 The results from records / material analysis that include details of the pipeline location,
diameter, wall thickness, material chemistry, grade and CEV shall be collated and recorded on
the T/SP/P/9 material sampling record sheet provided overleaf.
No.:
T/SP/P/9 MATERIAL SAMPLING RECORD SHEET
Date:
Pipe material sampling to determine the material properties shall be carried out in accordance with
T/PM/Q/10.
Project:
T/PM/Q/10 Report
Report date(s):
number(s):
*Welding
Sample No. & test Pipe Measured Estimated IIW issues?
Area sampled
date diameter thickness pipe grade CEV% Indicate Yes
or No
Location 1
Location 2
Location 3
Location 4
Location 5
Location 6
* If analysis of the pipe material properties or pipe chemistry raises any concerns with regard to the material
weldability, state the reason why. No welding shall be carried out in this location until it is established that this
can be done safely and without the risk of weld or HAZ cracking (see 6.0).
Notes:
1. Copies of all relevant reports and records pertaining to this material sampling and analysis shall be attached to this
sheet.
2. For UKT pipelines a copy of this report shall be sent to the GNI Integrity Manager, Asset Management, National
Grid House, Warwick Technology Park, Gallows Hill, Warwick CV34 6DA
3. For UKD pipelines a copy of this report shall be sent to the Engineering Manager, Network Strategy,
National Grid Gas Distribution, Brick Kiln Street, Hinckley, Leicestershire, LE10 ONA.
Project:
Date:
Location:
T/SP/P/9 checklist: Issue 2 Sheet 2 of 3
Findings
No. QUESTION Comments
or x
20 Have test and material certificates been obtained for all
materials and welding consumables?
21 Is it necessary to modify the fitting weld bevel? If so has
it been done correctly? (13.0 of T/SP/P/9)
22 What lifting equipment has been provided? Has it a valid
safety tag, is suitable and in good condition?
23 Have the condition of existing pipeline welds been
considered prior to pipeline excavation? (5.5 and 12.2 of
T/SP/P/9)
24 Is reinforcement and support of the pipeline necessary?
if so, has it been properly provided in the excavation
(5.5 of T/SP/P/9)
25 Is the excavation of suitable size to permit a safe
T/SP/P/9 operation? (5.3, 15.1 and Appendix N of
T/SP/P/9)
26 Have proper safety barriers been erected and warning
signs displayed?
27 Have all personnel been supplied with the PPE,
appropriate for the operation? (see site specific Risk
Assessment)
28 What gas monitoring will be carried out? Are the gas
monitors approved and calibrated?
29 Has safe and unobstructed access and egress to the
work site and excavation been provided?
30 Has provision been made for adequate weather
protection and lighting in and around the work area?
(5.3)
31 Has the ovality of the pipeline been checked?
32 Have the correct pipe NDT examinations been carried
out (both initially and following any 48 hour delay)?
33 Has any damage to the pipeline been found or occurred
during excavation and coating removal? (T/PM/P/11 or
T/PM/P/20)
32 Have pipe lamination/flaws been found that require the
relocation of the fitting? (12.1.3, 12.2.3 and 12.3.1 of
T/SP/P/9)
33 Has the minimum pipeline wall thickness been confirmed
by measurement and recorded?
34 Has the split-tee been fitted to the pipeline in accordance
with T/SP/P/9 using appropriate clamps? (13.3)
35 Have backing bars been fitted? (13.3 of T/SP/P/9)
36 Are weldolets, long weld neck flanges, CP plates or
other similar attachments to be welded to the pipeline?
Have the necessary inspection operations for these
attachments been carried out (12.0 of T/SP/P/9)?
FINDINGS: - ITEM CHECKED - SATISFACTORY x - ITEM CHECKED - UNSATISFACTORY
Project:
Date:
Location:
T/SP/P/9 checklist: Issue 2 Sheet 3 of 3
Findings
No. QUESTION Comments
or x
37 Has the welding process been approved and qualified
in accordance with T/SP/P/9? (10 of T/SP/P/9)
38 Has an approved welding procedure(s) been issued
for construction? (10.2 of T/SP/P/9)
39 Are copies of the welding procedures available at the
work location?
40 Are Welders, Inspectors and pipe heating operators
fully familiar with the welding procedures?
41 Is a T/SP/P/9 weld repair procedure required and
been issued for construction? (20 of T/SP/P/9)
42 What method(s) of pre-heating and intermediate
heating is to be used? (15 of T/SP/P/9), are they
approved?
43 Is the temperature monitoring equipment and method
of measurement approved?
44 Can the heating source be isolated or switched off
quickly in an emergency?
45 Is the longitudinal welding sequence as defined in16.0
of T/SP/P/9?
46 Has the pipe temperature decay rate been measured
and recorded? (15.2.2.1of T/SP/P/9)
47 Is the circumferential fillet welding sequence as
defined in 16.2 of T/SP/P/9?
48 Is a temper bead required for the final pass of the
seam or fitting fillet weld and has it been deposited?
(see 16.1, 16.2.6 and the guidance notes below).
49 Has it been necessary to adjust the gas flow rate or
pressure?
50 Have all necessary intermediate and final weld
inspections been carried out (16.0, 17.0 18.0, 19.0
and 20.0 of T/SP/P/9)
51 Have proper welding and inspection records been
compiled and retained?
52 Has the permit been closed and Network Control
advised upon completion of the work?
53 Have any necessary T/PM/G/17 issues been raised,
appraised and signed off?
FINDINGS: - ITEM CHECKED - SATISFACTORY x - ITEM CHECKED - UNSATISFACTORY
BS 6990: Section two, highlights relevant important safety considerations for this operation.
The reference numbers and headings given below are those of the relevant clauses etc, in this
Specification.
The prevention of an unsafe incident occurring during a hot-tap or under-pressure welding operation
relies on the positive participation of every person directly or indirectly involved with the operation.
Therefore, each stage of the operation must be planned, prepared and executed in a safe and competent
manner. All personnel shall be fully aware of the hazards and risks associated with this type of operation,
remain vigilant at all times (both to their own actions and to the actions of other team members around
them) and shall not deviate from the approved or recommended procedures.
Should any concern exist regarding the safe continuation of an under-pressure operation then work
should cease immediately and the Employer shall be informed.
The use of Vacuum packed basic, low hydrogen electrodes are mandatory for manual welding (see
clause 9.1, Appendix F). The reason for this stipulation is to guarantee levels diffusible hydrogen less
than 5 ml/100g in the deposited weld metal and to reduce the potential for weldment cracking to occur.
However, this can only be achieved if the electrodes are handled carefully and used in accordance with
the manufacturer’s recommendations. Basic, low hydrogen electrodes are more liable to porosity at weld
starts than other types of electrodes. They are also prone to producing general porosity if long arcs are
employed. This is particularly important in relation to clauses 16.1.3 and 16.2.5, all stop starts shall be
staggered to minimise any accumulation of undetected porosity in a localised area, which has the
potential to provide a gas leakage path (see clause 17.1.2).
In Table 1, the maximum allowable welding currents stated, are dependent upon the thickness of the pipe
wall. It is essential that these limits are not exceeded, as the welding current directly affects penetration
into the pipe wall. If too great a current is used, there is a possibility of the welding arc penetrating right
through the pipe wall, thus causing a 'blow-out'. Under normal circumstances, the maximum current
levels quoted incorporate a safety margin that is quite adequate, this margin shall not be reduced by the
use of excessive current.
The additional fillet weld qualification tests are necessary to ensure that the welder has the ability to use
the specified basic low hydrogen type of electrode in all the required welding positions and directions and
can produce sound welds applying the T/SP/P/9 techniques.
The reason for the familiarisation/demonstration weldment (required prior to T/SP/P/9 welding on pipes
with a wall thickness between 4.0mm and 4.9 mm), is to demonstrate to the welder and to confirm to
National Grid, that the electrode size, welding current and technique employed, can be used safely
without the risk of pipe wall penetration.
National Grid have carried out extensive preheating trials using Induction heating methods under live gas
conditions on pipe of different thickness and at various gas flow rates. To date, the use of Induction
heating methods to preheat the carrier pipe under live gas flow conditions have proved
ineffective. Therefore, the application of Induction heating methods is limited to preheating and
temperature maintenance of the hot-tap fitting only.
Trials have been carried out using a 27kW and 35kW power source. It should not be assumed that using
a power source with a greater output will resolve the problem. High temperatures can *reduce the
mechanical strength of the pipe wall, so careful application of preheat is required to prevent overheating,
under the coils. A maximum temperature of 300°C is stipulated.
* The welding procedures and preheating levels in T/SP/P/9 are designed to produce sound welds without
affecting the integrity of the existing pipe material or pipeline. The most common method of heating the
pipeline for hot-tap welding is to use gas heating methods, usually applied in discrete local areas around
the pipe. The preheating operation is closely monitored by the Welding Inspector and apart from some
published cases, is safely carried out without damage to the pipeline.
If electrical heating methods are proposed for heating the carrier pipe the Responsible Engineer and
Welding Engineer should confirm whether pressure de-rating is necessary.
A hard zone in a pipeline is not desirable. There is also the possibility that hydrogen may be released by
cathodic protection methods, which may lead to embrittlement of the HAZ. Therefore, various means of
controlling hardness shall be employed (see clauses 15.2.2.1, 15.2.2.3, 16.2.4 and 16.2.6).
* To prevent localised overheating, the minimum preheat and inter pass temperature envelope may be
different for welding directly to pipes with a wall thickness less than 5 mm. The temperatures applied shall
be subject to the results of heat/sink tests and will be stated on the approved welding procedure.
** The upper limit of 300 °C was chosen because above 350 °C the yield stress of the pipe material
begins to decrease markedly and the pipe could deform under the action of the internal gas pressure; a
50 °C safety margin is applied thus limiting the maximum temperature to 300 °C.
The time for the temperature to drop from **250 °C to *150 °C needs to be checked before welding (see
clause 15.2.2.1), so that the welder and inspector will know what time is available before reheating is
needed. Some T/SP/P/9 welding operations may continue for several hours or even several days, Gas
flow rates can vary during this time, therefore, the heat sink decay time shall be regularly checked during
the welding operation.
Careful removal of the run-on / run-off plates is necessary so that a smooth face is produced and damage
to the carrier pipe is avoided. A disc grinder shall be used for the removal; thermal cutting shall not be
used.
In order to control and minimise the effects of weld toe and HAZ hardness a temper bead technique is
applied during welding. This is illustrated by the deposition sequence shown for pass 6 or pass 9 or their
equivalent (Figure 7a and Figure 7b respectively), which is deposited as close as possible to the toe of
pass 5. This uses the heat from pass 6 or 9, or their equivalent, to anneal the toe of pass 5 and its
associated HAZ, thereby reducing the hardness levels. Care is required in positioning the ‘temper bead’
weld run adjacent to the weld toe to maximise the annealing effect.
High chemistry hot-tap tee fitting materials typically made from P460 NL1 or NL2 grade material can have
a maximum carbon equivalent value (CEV) of 0.53% and in certain circumstances, can exhibit high
hardness levels in the HAZ of the final weld run. This could affect both the longitudinal and circumferential
welds.
2
To ensure acceptable levels of hardness, a procedure has been developed to temper the final weld run
of circumferential fillet welds (see Appendix F). To produce the desired effect, it is important that the
temper bead is deposited as close as possible to the toe of the fillet weld without impinging on to the
surface of the fitting. It is also important that the original final weld pass, when deposited does not
excessively overlap the fitting surface.
Careful grinding of the final weld run will produce a partial excavation that provides a clear guideline to
enable the welder to accurately deposit the temper bead, give a smoother weld profile and ensure that
maximum benefit is obtained from the heat input of the temper bead (see Appendix F).
For longitudinal seam welds the preparation and application of the temper bead pass can be applied
using the same welding parameters and consumables as the original welding procedure.
Notes:
This Appendix and checklist is provided for the guidance of the Engineer responsible for planning and
executing a safe under-pressure welding operation. The list is not comprehensive and should be added
to, where appropriate, depending on the specific site conditions and requirements.
The welding of large diameter fittings to pipelines can result in extended working hours for all personnel
involved. National Grid has a duty of care to ensure that all personnel are not put at unnecessary risk
during an under-pressure welding operation due to the effects of fatigue (see clause 5.4).
IF ANY DOUBT EXISTS AS TO THE CORRECT PRACTICES TO BE USED, EXPERT ADVICE SHALL
ALWAYS BE TAKEN BEFORE WELDING TO A PRESSURISED GAS PIPELINE OR PIPE WORK.
REFERENCES.
1. Neil Millwood and James Gilliver - Advantica report number 8045: November 2008 - X80 Hot-tap
weld procedure development.
2. James Gilliver – X80 Hot Tap welding development – Temper bead welding trials.
Confirm minimum pipe wall thickness, freedom from lamination and SCC in a 150 mm
band with its centre on the proposed edge of the fitting in the area to be welded
Fill
Buttering layer
2t + gap Pipeline
t
Not to scale
APPENDIX N
EXCAVATION DETAILS
Plan view
Trench Fitting
Pipe
2.0m 2.0m
Sectional View
Minimum of 2.0m
for rain cover
cover
2.0m 2.0m
*0.6 to 1.0 m
* Sufficient clearance shall be provided under the pipe to accommodate any necessary boarding and
support needed to raise the working level above standing water, while maintaining sufficient distance
from the base to the pipe for cleaning, heating, welding and inspection activities. It is recommended
that the Engineer responsible for the excavation agrees the requirements for the excavation with the
welding team during or prior to the preparation of the excavation.
ENDNOTE
Comments
Comments and queries regarding the technical content of this document should be directed to:
UK Transmission: UK Distribution:
Buying documents
Contractors and other users external to National Grid should direct their requests for further copies of
National Grid safety and engineering documents to the department or group responsible for the initial
issue of their contract documentation. Alternatively enquires may be made to the Asset Specifications
Manager, GNI Transmission Asset Management at the above address.