RUWANPURA EXPRESSWAY PROJECT

Highway Section from Kahathuduwa to Ingiriya – Phase I

CONTRACT No. RDA/GOSL/REP/LCB/P-01, 02, 03, 04

METHOD STATEMENT FOR

THE DEMOLITION OF EXISTING STRUCTURES,


TREE CUTTING AND CLEARING & GRUBBING

Document Ref : RDA/GOSL/REP/LCB/MS/001

Revision: 00

Date: 30/11/2020

APPROVED
REV DATE DESCRIPTION
RE DATE

The Demolition of Existing Structures,


00 30/11/2020
Tree Cutting and Clearing & Grubbing,
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

CONTENTS
1.0 SCOPE OF WORK ..........................................................................................................................................................................4

2.0 RESOURCE ALLOCATION ............................................................................................................................................................4

2.1 MAN POWER .............................................................................................................................................................................4

2.2 SITE ORGANIZATION STRUCTURE ........................................................................................................................................5

2.3 MACHINES AND EQUIPMENTS ...............................................................................................................................................6

3.0 METHODOLOGY ............................................................................................................................................................................6

3.1 CONSTRUCTION FLOW CHART ..............................................................................................................................................6

3.2 DETAILED METHOD OF CARRYING OUT THE WORK SCOPE .............................................................................................6


3.2.1 DEMOLITION OF EXISTING STRUCTURES ....................................................................................................................6
3.2.2 TREE CUTTING .................................................................................................................................................................6
3.2.3 CLEARING AND GRUBBING ............................................................................................................................................7

4.0 SAFETY MANAGEMENT AND CONTROL ....................................................................................................................................7

4.1 SITE TRAFFIC CONTROL .........................................................................................................................................................7

4.2 SAFETY MANAGEMENT ...........................................................................................................................................................8

5.0 MEASUREMENT CONTROL ..........................................................................................................................................................8

APPENDIX A – CONSTRUCTION FLOW CHART ...............................................................................................................................9

APPENDIX B – PAYMENT ITEMS EXTRACTED FROM BOQ ..........................................................................................................10

SECTION - 1...................................................................................................................................................................................10

SECTION - 2...................................................................................................................................................................................11

SECTION - 3...................................................................................................................................................................................12

SECTION - 4...................................................................................................................................................................................13

P a g e 2 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

TABLE OF FIGURES
Figure 1: Site Organization Structure ....................................................................................................... 5

ABBREVIATION

1) BOQ - Bills of Quantities


2) RDA - Road Development Authority
3) ROW - Right of Way
4) SK - Skilled Labor
5) USK - Unskilled Labor

P a g e 3 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

1.0 SCOPE OF WORK

The following method statement refers to the steps and procedures involved in the demolition of existing
structures, tree cutting and clearing & grubbing, as described in Section 200.

Details of the flow of work, measurement control, man power and equipment involved during these activities
have been discussed below. Safety precautions and environmental management plan would be also
assessed based on the main contractors Safety Plan and Environmental Management Plan to carry out the
stated earthwork activities.

2.0 RESOURCE ALLOCATION

2.1 MAN POWER

1) Project Manager
2) Site Engineer
3) Technical Officer
4) Surveyor
5) Supervisor
6) Flagmen (If necessary)
7) SK/USK labour
8) Operators & Drivers
9) Safety and Environmental officer (If Needed)

P a g e 4 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

2.2 SITE ORGANIZATION STRUCTURE

Project Manager

Site Engineer

Material Technician
(Materials Testing Safety & Environmental
Laboratory) Officer

Technical Officer

Lab Technicians
Supervisor

Operators

Skilled
Labor

Lab helpers Flagmen

Unskilled
Labor

Figure 1: Site Organization Structure

P a g e 5 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

2.3 MACHINES AND EQUIPMENTS

Following items of machine illustrates the major machinery that can be expected on site. However, it is
important to note that the works involved may not be limited to machinery listed below. Each one’s quantity
and capacity requirement may be varies depending on the criticality of work, risks being performed.

1) Bulldozer
2) Excavator
3) Excavator Breaker
4) Grader
5) Vibration Roller
6) Dump Truck
7) Rammer
8) Backhoe Loader JCB

3.0 METHODOLOGY

3.1 CONSTRUCTION FLOW CHART

Appendix A – Construction Flowchart illustrates the construction workflow that is to take place in order to
effectively carryout the removal of structures & trees and the clearing & grubbing.

3.2 DETAILED METHOD OF CARRYING OUT THE WORK SCOPE

Once the Right of Way (ROW) has been confirmed, and the final site survey and disposal plan has been
approved, the contractor is to move forward with the clearing and grubbing process.

3.2.1 DEMOLITION OF EXISTING STRUCTURES

 Any form of structure requested by the Client and/or the Engineer is to be removed with care.

 Such material is to be transported to an Engineer designated location.

 All the structures that lie within the design confinement of the road being constructed should be
removed.

3.2.2 TREE CUTTING

 A joint tree survey alongside the resident engineer is to be carried out and the trees are to be marked
depending on their girth 1m above the ground.

 Any tree with girth less than 300mm is to be classed as clearing and grubbing material.

 The marked trees are to be cut down and the useful cuts are to be transported and stockpiled.

P a g e 6 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

3.2.3 CLEARING AND GRUBBING

 Once the marked trees have been cut and existing structures removed, the clearing and grubbing
activities will take place.

 All remaining/unmarked trees, stumps and roots are to be cleared.

 Any stump or solid object that is 75mm or less from the ground level can be left undisturbed as long
as it lies outside the excavation and embankment areas.

 All stumps more than 1m below the subgrade and embankment slopes are to be disregarded as well.

 The rest should be cut flush or below the final slope line.

 All topsoil is expected to be removed to an average depth of 200mm over any embankment fill
section.

 All removed material is to be transported to the approved disposal site.

 All disposal material and debris is to be buried at the designated location, with 300mm of cover
material in order to mitigate the risk of fires.

The entire process will be regarded as complete once the final inspection has been done and the Engineer
gives the approval to move forward with the project.

4.0 SAFETY MANAGEMENT AND CONTROL

4.1 SITE TRAFFIC CONTROL

The following management plan is taken in accordance with the ‘Manual on Traffic Control Devices’ issued by
the RDA.

 The utilization of proper traffic signs, barricade tapes and boards and traffic cones are to be placed in
locations where the road width is reduced to the work in progress.

 The speed limits should be reduced on roads close to cleaning and grubbing works.

 The deployment of flagmen in key areas (such as junctions) where larger volumes or traffic (greater
activity) is expected.

 The flagmen and workers are to be provided with reflective jackets, light battens and walkie-talkies in
order ensure a safer working environment.

 Diversion routs are to be clearly illustrated in areas where the movement of vehicles seems
impractical.

P a g e 7 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

4.2 SAFETY MANAGEMENT

Safety management is to be implemented as per Main contractor’s requirement and Method Statement
approved by the main contractor. All necessary precautions are to be taken in order to avoid any form of
accidents and/or damage with regard to site workers and/or adjoining properties.

Everyone on site is expected to wear their safety helmets and steel toe cap shoes, and depending on the task
at hand, gloved and/or safety glasses are to be worn.

An on-site first aid kit as well as a standby vehicle is to be parked in the vicinity in case an accident needs to
be tended to.

5.0 MEASUREMENT CONTROL

Appendix B- Payment Items extracted from BOQ aids in illustrating the breakdown of some of the major
costs/payments incurred during the three stages discussed above. However, it is important to recognize that
the rates are subject to change as the project progresses. As stated before, trees with a girth less than
300mm would be removed during cleaning and grubbing process and only the requested structures would be
carefully extracted.

All timber cuts would be returned to the property owner or the relevant government authority, as directed by
the Engineer. The Contractor will not be permitted to claim any of the materials.

P a g e 8 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

APPENDIX A – CONSTRUCTION FLOW CHART

Confirmation or Approval of Right of Way

Did the
Engineer
Approve?

Yes

Submission of Disposal Plan Joint tree Survey with


Engineer (Tree Marking)

Did the Did the


No No
Engineer Engineer
Approve? Approve?

Yes Yes

Clearing and Grubbing Works

Stockpile Useful Tree Cuts Transport Disposal Material/


and Salvaged Structures Debris to approved Site

Work Complete, Final Inspection


Required

P a g e 9 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

APPENDIX B – PAYMENT ITEMS EXTRACTED FROM BOQ

SECTION - 1

Item
Pay Item Item Description Unit Quantity
Nr
201 Clearing

1 201.001 General clearing ha.


7.04
2 201.002 Clearing & grubbing ha.
64.04
3 201.003a Remove trees dia 600mm to 1000 mm nr
985.00
4 201.003b Remove trees dia 1000 to 2000mm nr
4,505.00
5 201.003c Remove trees over dia 2000mm nr
2,685.00

6 Remove of stumps and roots previously felled trees girth dia


201.003d nr
600-1000 mm ( provisionally ) 4,190.00

7 Remove of stumps and roots previously felled trees girth dia


201.003e nr
1000-2000mm ( provisionally ) 1,580.00

8 Remove of stumps and roots previously felled trees girth over


201.003f nr
dia 2000mm ( provisionally ) 1,460.00

202 Demolish and Remove Buildings, Waterways sq.m


11,850.00
9 202.001 remove existing Building, (floor area ) nr
80.00
10 202.002 Water well depth up to 3.00m ( provisionally ) nr
60.00
11 202.003 Water well depth 3.00 - 6.00m ( provisionally ) nr
45.00
12 202.004 Water well depth 6.00 - 10.00m ( provisionally ) nr
180.00
13 202.005 Septic tank ( provisionally ) sq.m
11,850.00
203 Dismantling Structures

14 203.001 Masonry cu.m


160.00
15 203.002 Concrete cu.m
120.00
16 203.003 Rubble masonry cu.m
65.00

P a g e 10 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

SECTION - 2

Item
Pay Item Item Description Unit Quantity
Nr
201 Clearing

1 201.001 General clearing ha. 5.10

2 201.002 Clearing & grubbing ha. 50.97

3 201.003a Remove trees dia 600mm to 1000 mm nr 8,090.00

4 201.003b Remove trees dia 1000 to 2000mm nr 4,000.00

5 201.003c Remove trees over dia 2000mm nr 2,390.00

6 Remove of stumps and roots previously felled trees girth dia


201.003d nr
600-1000 mm ( provisionally ) 3,736.00

7 Remove of stumps and roots previously felled trees girth dia


201.003e nr
1000-2000mm ( provisionally ) 1,400.00

8 Remove of stumps and roots previously felled trees girth over


201.003f nr
dia 2000mm ( provisionally ) 1,300.00

202 Demolish and Remove Buildings, Waterways sq.m

9 202.001 remove existing Building, (floor area ) nr 10,555.00

10 202.002 Water well depth up to 3.00m ( provisionally ) nr 80.00

11 202.003 Water well depth 3.00 - 6.00m ( provisionally ) nr 60.00

12 202.004 Water well depth 6.00 - 10.00m ( provisionally ) nr 45.00

13 202.005 Septic tank ( provisionally ) sq.m 180.00

203 Dismantling Structures

14 203.001 Masonry cu.m 105.00

15 203.002 Concrete cu.m 140.00

16 203.003 Rubble masonry cu.m 65.00

P a g e 11 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

SECTION - 3

Item
Pay Item Item Description Unit Quantity
Nr
201 Clearing

1 201.001 General clearing ha. 5.97

2 201.002 Clearing & grubbing ha. 59.65

3 201.003a Remove trees dia 600mm to 1000 mm nr 7,500.00

4 201.003b Remove trees dia 1000 to 2000mm nr 3,200.00

5 201.003c Remove trees over dia 2000mm nr 2,400.00

6 Remove of stumps and roots previously felled trees girth dia


201.003d nr
600-1000 mm ( provisionally ) 3,800.00

7 Remove of stumps and roots previously felled trees girth dia


201.003e nr
1000-2000mm ( provisionally ) 1,200.00

8 Remove of stumps and roots previously felled trees girth over


201.003f nr
dia 2000mm ( provisionally ) 1,100.00

202 Demolish and Remove Buildings, Waterways sq.m

9 202.001 remove existing Building, (floor area ) nr 10,800.00

10 202.002 Water well depth up to 3.00m ( provisionally ) nr 65.00

11 202.003 Water well depth 3.00 - 6.00m ( provisionally ) nr 55.00

12 202.004 Water well depth 6.00 - 10.00m ( provisionally ) nr 45.00

13 202.005 Septic tank ( provisionally ) sq.m 175.00

203 Dismantling Structures

14 203.001 Masonry cu.m 140.00

15 203.002 Concrete cu.m 120.00

16 203.003 Rubble masonry cu.m 60.00

P a g e 12 | 13
Ruwanpura Expressway Project
Highway Section from Kahathuduwa to Ingiriya – Phase I
Demolition of Existing Structures, Tree Cutting and Clearing & Grubbing Method Statement No. 001

SECTION - 4

Item
Pay Item Item Description Unit Quantity
Nr
201 Clearing

1 201.001 General clearing ha. 1.23

2 201.002 Clearing & grubbing ha. 19.96

3 201.003a Remove trees dia 600mm to 1000 mm nr 4,800.00

4 201.003b Remove trees dia 1000 to 2000mm nr 3,500.00

5 201.003c Remove trees over dia 2000mm nr 2,400.00

6 Remove of stumps and roots previously felled trees girth dia


201.003d nr
600-1000 mm ( provisionally ) 4,000.00

7 Remove of stumps and roots previously felled trees girth dia


201.003e nr
1000-2000mm ( provisionally ) 2,100.00

8 Remove of stumps and roots previously felled trees girth over


201.003f nr
dia 2000mm ( provisionally ) 1,100.00

202 Demolish and Remove Buildings, Waterways sq.m

9 202.001 remove existing Building, (floor area ) nr 8,500.00

10 202.002 Water well depth up to 3.00m ( provisionally ) nr 45.00

11 202.003 Water well depth 3.00 - 6.00m ( provisionally ) nr 65.00

12 202.004 Water well depth 6.00 - 10.00m ( provisionally ) nr 40.00

13 202.005 Septic tank ( provisionally ) sq.m 155.00

203 Dismantling Structures

14 203.001 Masonry cu.m 120.00

15 203.002 Concrete cu.m 130.00

16 203.003 Rubble masonry cu.m 50.00

P a g e 13 | 13