MAJOR MATERIAL RECONCILIATION - SOIL - TYPE I

PROJECT NAME 214- THIMBIRIYAWA ROAD UPDATED UP TO 4-Oct


PROJECT CODE MORH/RDA/LBRRP/NWP/KRG/2020/214

* Soil 100% compaction factor = 1.42


Design Qty - A BOQ qty - B IPA QTY - C
USED QTY IN Diference Diference
BOQ NO DESCRIPTION UNIT IN IN IN IN IN LOOSE with design with BOQ (B2
IN LOOSE (Cube)- D (A2 - D) - D)
COMPACTED LOOSE(Cube) - COMPACTED LOOSE(Cube) - COMPACTED( (Cube) - C2
A1 (Cu.m) A2 (Cu.m)- B1 B2 Cu.m) - C1

For BOQ Items


Embankment construction Cu.m 1,004.07 503.81 562.00 281.99 562.00 281.99 34.00 469.81 247.99

Sub Base constructon Cu.m 1,181.27 592.72 1,575.00 790.28 1,575.00 790.28 1,006.00 (413.28) (215.72)

Shoulder construction Cu.m 552.79 277.37 495.00 248.37 495.00 248.37 153.00 124.37 95.37

For PS
Back filling - culvert Cu.m 22.20 11.14 15.00 (15.00) (15.00)

By road preparation Cu.m 44.84 22.50 15.50 (15.50) (15.50)

1+000-1+300 SHOULDER 31.50

2,738.13 1,373.90 2,632.00 1,320.64 2,699.04 1,354.28 1,255.00 150.40 97.14

TOTAL UAGE OF SITE - D 1,255.00


TOTAL RECEIVED QTY TO SITE - STOCK BOOK 1,277.50
TOTAL ISSUED TO SITE - D 1,255.00
MATERIAL AT SITE 22.50
WAISTAGE/ SAVING (AS PER DESIGN) _ A2-D 118.90
WAISTAGE/ SAVING (AS PER BOQ) _ B2-D 65.64
MAJOR MATERIAL RECONCILIATION - ABC
PROJECT NAME 214- THIMBIRIYAWA ROAD UPDATED UP TO 6-Oct
PROJECT CODE MORH/RDA/LBRRP/NWP/KRG/2020/214

* ABC 100% compaction factor = 1.42


Design Qty - A BOQ qty - B IPA QTY - C
USED QTY IN Diference Diference
BOQ NO DESCRIPTION UNIT IN IN IN IN IN LOOSE (Cube)- with design with BOQ (B2
IN LOOSE D (A2 - D) - D)
COMPACTED LOOSE(Cube) - COMPACTED LOOSE(Cube) - COMPACTED( (Cube) - C2
A1 (Cu.m) A2 (Cu.m)- B1 B2 Cu.m) - C1

ABC Laying
ABC Laying Cu.m 1,181.49 592.83 1,358.44 624.02 1,358.44 624.02 593.00 (0.17) 31.02

For PS

Back filling - culvert Cu.m - - -

By road preparation Cu.m - -

1,181.49 592.83 1,358.44 624.02 1,358.44 624.02 593.00 (0.17) 31.02

TOTAL UAGE OF SITE - D 593.00

TOTAL RECEIVED QTY TO SITE - STOCK BOOK 636.00

TOTAL ISSUED TO SITE - D 593.00

MATERIAL AT SITE 43.00

WAISTAGE/ SAVING (AS PER DESIGN) _ A2-D (0.17)

WAISTAGE/ SAVING (AS PER BOQ) _ B2-D 31.02


MAJOR MATERIAL RECONCILIATION - CONCRETE
PROJECT NAME 214- THIMBIRIYAWA ROAD UPDATED UP TO 4-Oct
PROJECT CODE MORH/RDA/LBRRP/NWP/KRG/2020/214
IPA CLAIMED TOTAL QTY
BOQ NO DESCRIPTION UNIT Design Qty -A QTY -B USED QTY -C UNBILLED QTY B-C
Grade 15
00+456 (1/1)
Concrete G15 (40) for Screed Cu.m 0.66 0.66 0.66
Collur joint Base Concrete G15 (40) Cu.m 0.36 (0.36)
Concrete G15 (40) for wall Cu.m 7.08 6.23 0.85
00+990 (1/2)
HW base screed G15 Cu.m 0.38 0.38 0.38
Encase bed screed G 15 Cu.m 0.28 0.26 0.26
Concrete G15 (40) for wall Cu.m 2.34 2.05 0.29
01+103 (2/1)
Concrete G15 (40) for Screed Cu.m 0.38
0.64 0.64
Encase bed screed G 15 Cu.m 0.28
Concrete G15 (40) for wall Cu.m 2.37 2.36 0.01
Grade 20
00+456 (1/1)
Collar joint Concrete G20 (40) 0.38 0.20 0.20
00+990 (1/2)
Head wall Concrete G20 (40) Cu.m 2.47 -
01+103 (2/1)
Head wall Concrete G20 (40) Cu.m 2.67 -
Grade 25
00+456 (1/1)
Concrete G25 (40) for Screed Cu.m 0.79 (0.79)
Base Concrete G25 (40) Cu.m 2.64 4.40 3.68 0.72
Head wall Concrete G25 (40) Cu.m 9.10 -
Collur joint Base Concrete G25 (40) Cu.m 0.19 (0.19)
Concrete G25 (40) Cu.m 0.58 0.58
00+990 (1/2)
Concrete G25 (40) for Screed Cu.m 0.48 (0.48)
Base Concrete G25 (40) Cu.m 1.53 1.53 1.63 (0.10)
Encase bed Concrete G25 (40) Cu.m 0.66 1.26 (0.60)
3.49
EncasementConcrete G25 (40) Cu.m 3.24 3.10 0.14
01+103 (2/1)
Concrete G25 (40) for Screed Cu.m 0.48 (0.48)
Base Concrete G25 (40) Cu.m 1.53 1.53 1.63 (0.10)
EncasementConcrete G25 (40) Cu.m 3.49 3.36 4.26 (0.90)
29.28 29.23 28.50 - 0.73
TOTAL ISSUED TO SITE - C 28.50
TOTAL RECEIVED TO SITE - C 28.50
TOTAL REQUAREMENT AS PER DESIGN - A 29.23
MATERIAL AT SITE -
WAISTAGE/ SAVING (B - C) 0.73

G 15 - 1.98 13.73 11.00


G 20 - 5.52 0.20 -
G 25 - 21.78 15.30 17.50
29.28 29.23 28.50