Professional Documents
Culture Documents
Operations Tower 1: See Attached Attendance Sheet
Operations Tower 1: See Attached Attendance Sheet
DISCUSSION:
ITEM PERSON
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN TARGET DATE
RESPONSIBLE
OPERATIONS TOWER 1
Ongoing piling of CHB ( Note : Client Inspection for the First 3 layer) End of this
For update.
February 2021
Ongoing Rectification - Madval @ Area 1
MINUTES OF MEETING i
SUBJECT: INTERNAL MEETING NO. 03 DATE: 22-Feb-21 n
c
PROJECT/LOCATION: VENUE: l
MANDANI BAY QUAY
MCC-MBQ u
ARCHITECTURAL OFFICE d
ATTENDEES: see attached Attendance Sheet e
MEETING AGENDA: Weekly Internal Meeting (Every Friday from 8:00am – 10:00am) o
n
DISCUSSION:
n
ITEM PERSON e
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN TARGET DATE
RESPONSIBLE x
t
COMMERCIAL a
1 SRF UPDATES Pleasee see attached summary For update P. Imson Progressive Update g
e
2 Gondola Finalization of Gondola to coordinate with structural n
Confirmation in plans if there's a garbage shoot to check plans d
3 Garbage Shoot AJ Reyes a
Rectification of Precast Slab (Epoxy Injection) for SRF ?
4 Precast Slab Operations
Withdrawal of Lanko 731 will also be signed by the OE of Structural for proper monitoring to coordinate with OE structural (
5 Lanko 731 Operations Y
/
OPERATIONS TOWER 1 N
Ongoing piling of CHB ( Note : Client Inspection for the First 3 layer) End of this February )
For update.
2021
Ongoing Rectification - Madval @ Area 1 ( 55% )
For update. 18-Mar-21
Ongoing Rectification - RIC For update. 18-Mar-21
6 BASEMENT A. Banzon
Ongoing Rectification - IRINCO (20%) For update. 18-Mar-21
Waiting for approved wall setting out plans To update Technical 18-Mar-21
#REF! OPERATIONS TOWER 2
7 BASEMENT -PODIUM Ongoing Rectification @ Area 2 - Madval with 10 Manpower (50%) For update. J.Masong 27-Mar-21
8 BASEMENT - TOWER Ongoing rectification - Cadcor - (30%) For update. J.Masong 27-Mar-21
#REF! OPERATIONS TOWER 4
9 BASEMENT Ongoing Rectification - Admin Workers - ( 85% ) For update. J.Masong 25-Feb-21
SUBMITTALS
10 Plumbing Fixtures- ongoing for SRF AJ Reyes /M. Pogoy R
F
Item for SRF A
11 Ceiling , Painting , Kitchen Cabinet for SRF AJ Reyes /M. Pogoy
u
p
d
a
t
e
e
o
n
n
ITEM
SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON TARGET DATE e
NO RESPONSIBLE x
** NOTHING FOLLOWS ** t
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final
& executory a
Prepares By: Noted by: g
e
Mary Joy Vequizo Albert Saavedra n
d
Project Manager - Architectural
a
?
(
Y
/
N
)
o
i
n
MINUTES OF MEETING c
l
SUBJECT: INTERNAL MEETING NO. 04 DATE: 1-Mar-21 u
PROJECT/LOCATION: VENUE: d
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
e
ATTENDEES: see attached Attendance Sheet
o
MEETING AGENDA: Weekly Internal Meeting (Every Friday from 7:30am – 10:00am) n
DISCUSSION:
n
ITEM PERSON e
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN TARGET DATE
RESPONSIBLE x
t
HUMAN RESOURCE a
1 Finishing Foreman To hire Finishing Foreman To send PRF K. Simpson g
Transfer of Coreteam from LVG to Mandani e
2 Coreteam For update K. Simpson n
COMMERCIAL d
Pleasee see attached summary a
1 SRF UPDATES For update P. Imson Progressive Update ?
2 Gondola Finalization of Gondola to coordinate with structural
(
Rectification of Precast Slab (Epoxy Injection) for SRF Y
4 Precast Slab Operations
/
OPERATIONS TOWER 1 N
Madval - Need additional manpower For update. )
Ongoing Rectification - Madval @ Area 1 ( 62% ) For update. 18-Mar-21
5 BASEMENT Ongoing Rectification - RIC For update. A. Banzon 18-Mar-21
Ongoing Rectification - IRINCO (20%) For update. 18-Mar-21
Waiting for approved wall setting out plans To update Technical 18-Mar-21
#REF! OPERATIONS TOWER 2
6 BASEMENT -PODIUM Ongoing Rectification @ Area 2 - Madval with 10 Manpower (50%) For update. J.Masong 27-Mar-21
7 BASEMENT - TOWER Ongoing rectification - Cadcor - (30%) For update. J.Masong 27-Mar-21
#REF! OPERATIONS TOWER 4
Ongoing Rectification - Admin Workers - ( 90% ) can not proceed in the Opening area due to For update.
8 BASEMENT the ongoing structural works at GF. J.Masong 25-Feb-21
SUBMITTALS
Plumbing Fixtures- waiting for brochures R
9 for SRF AJ Reyes /M. Pogoy F
10 Ceiling - ongoing for SRF AJ Reyes /M. Pogoy A
Items for SRF
11 Painting - ongoing - Basement is done for SRF AJ Reyes /M. Pogoy u
p
12 Kitchen Cabinet - ongoing for SRF AJ Reyes /M. Pogoy d
** NOTHING FOLLOWS ** a
t
e
-
o
n
n
ITEM
SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON TARGET DATE e
NO RESPONSIBLE x
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final & executory t
Prepares By: Noted by: a
Mary Joy Vequizo Albert Saavedra g
e
Project Manager - Architectural n
d
a
?
(
Y
/
N
)
o
i
n
MINUTES OF MEETING c
l
SUBJECT: INTERNAL MEETING NO. 06 DATE: 15-Mar-21 u
PROJECT/LOCATION: VENUE: d
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
e
ATTENDEES: see attached Attendance Sheet
o
MEETING AGENDA: Weekly Internal Meeting (Every Friday from 7:30am – 09:00am) n
DISCUSSION:
n
ITEM PERSON e
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN TARGET DATE
RESPONSIBLE x
t
COMMERCIAL a
1 SRF UPDATES Pleasee see attached summary For update P. Imson Progressive Update g
Finalization of Gondola e
2 Gondola to coordinate with structural
n
3 Precast Slab Rectification of Precast Slab (Epoxy Injection) for SRF Operations d
OPERATIONS TOWER 1 a
RIC needs additional manpower for CHB piling Added 9 manpower ?
Ongoing Rectification - Madval @ Zone 1 PODIUM ( 100%) For inspection For update. 18-Mar-21 (
4 BASEMENT A. Banzon Y
Ongoing Rectification - RIC @ Zone 1 Tower 1 (100%) For inspection For update. 18-Mar-21
/
Waiting for approved wall setting out plans To update Technical 18-Mar-21 N
#REF! OPERATIONS TOWER 2 )
5 BASEMENT -PODIUM Ongoing Rectification - Madval @ Zone 2 PODIUM with 20 Manpower (63%) For update. J.Masong 27-Mar-21
6 BASEMENT - TOWER Ongoing rectification - Cadcor - @ Zone 2 TOWER 2 (75.6%) For update. J.Masong 27-Mar-21
#REF! OPERATIONS TOWER 3
7 BASEMENT Ongoing Rectification - IRINCO / CORETEAM @ZONE 3 TOWER 3 (53%) For update. J.Masong 25-Feb-21
8 BASEMENT Ongoing Rectification -Madval @ ZONE 3 PODIUM (45%) For update. J.Masong 25-Feb-21
#REF! OPERATIONS TOWER 4
Ongoing Rectification - Admin Workers - ( 90% ) can not proceed in the Opening area due to For update.
9 BASEMENT the ongoing structural works at GF. J.Masong 25-Feb-21
SUBMITTALS
Plumbing Fixtures- waiting for brochures R
10 for SRF AJ Reyes /M. Pogoy F
11 Ceiling - ongoing for SRF AJ Reyes /M. Pogoy 18-Mar-21 A
Items for SRF
12 Painting - ongoing - Basement is done for SRF AJ Reyes /M. Pogoy 15-Mar-21 u
p
13 Kitchen Cabinet - ongoing for SRF M. Sta Maria 17-Mar-21 d
** NOTHING FOLLOWS ** a
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final & executory
t
e
Prepares By: Noted by: -
c
/
o
o
n
n
ITEM
SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON TARGET DATE e
NO RESPONSIBLE x
Albert Saavedra t
Mary Joy Vequizo
Project Manager - Architectural a
g
e
n
d
a
?
(
Y
/
N
)
TR
F
o
A
R
iF
n
A
MINUTES OF MEETING c
lf
SUBJECT: INTERNAL MEETING NO. 07 DATE: 24-May-21 u
o
PROJECT/LOCATION: VENUE: rd
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE c
e
ATTENDEES: see attached Attendance Sheet o
o
u
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
p
DISCUSSION: l
en
ITEM re
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
b
t
COMMERCIAL e
a
Need payment for NC hardrock to proceed the delivery a
m
1 CHB Delivery For update J. Bongcasan g
ce
2 SRF Updates For follow up For update J. Bongcasan o
n
n
d
TECHNICAL UPDATES n
ae
Almost Interior Design needs revision to submit on Thursday ?
3 Drawings For update M. Valencia c
(5.27.21) t
CHB - Not approved due to structural requirements i(
4 Value Engineering For update M. Valencia Y
n
For resubmit g/
5 Wheel Stop For update M. Valencia
N
6 Dropwall Drywall HTLI required a Mock up Contact Loreno for the quotation M. Valencia / Operation t)
o
7 Dropwall Drywall HTLI required a Mock up Contact Loreno for the quotation M. Valencia / Operation
T
OPERATIONS o
8 Materials on site Monitor the quantity of materials on site For update everyday C. Guanzing / P. Osmil Progressive update w
e
9 Rectification @ Zone 2 To finish the rectification on committed date Catch up with the schedule P.Osmil 29-May-21 r
C. Guanzing
Rectification @ Tower 1 To finish the rectification on committed date 2
10 BSMT
Ongoing plastering -
11 Zone 3
SUBMITTALS f
o
11 OVS - plumbing fixtures To send Company Profile Forward company profile to client r
f
o
r
I
5
-
p
r
e
s
s
u
r
e
s
F
A
i
n
f
MINUTES OF MEETING co
lr
SUBJECT: INTERNAL MEETING NO. 08 DATE: 14-Jun-21 u
PROJECT/LOCATION: VENUE: cd
MANDANI BAY QUAY MCC-MBQ o
ARCHITECTURAL OFFICE u
e
ATTENDEES: see attached Attendance Sheet p
o
l
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
e
DISCUSSION: r
n
ITEM e
b
NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE xe
at
COMMERCIAL m
1 CHB Delivery Estimated 700 pcs / day ( 650 psi) For update J. Bongcasan ac
g
o
2 Cement GDSM - supplier for cement e
n
For follow up n
3 SRF Updates For update J. Bongcasan ed
ca
TECHNICAL UPDATES t
BSMT - 100% ?i
GROUND FLOOR : ZONE 1 - 80 % , to submit today n
For update R. Brazil 19-Jun-21 g(
Y
4 Wall setting out status GROUND FLOOR : ZONE 2 - Complete with comments For update 26-Jun-21
/t
GROUND FLOOR : ZONE 3 - 30 % ongoing For update 3-Jul-21 o
N
GROUND FLOOR : ZONE 4 - Zero % )
Change to macrowall T
o
5 As built plans Archi Ops to coordinate with Surveyor - Regie for the As built plans w
e
OPERATIONS r
To completely finish masonry and rectificaton works of Zone 1 - 4
6 Masonry and Rectification C. Guanzing / P. Osmil 26-Jun-21
works 2
n
ITEM e
SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
NO x
Albert Saavedra t
Mary Joy Vequizo
Office Engineer Project Manager - Architectural a
g
e
n
d
a
?
(
Y
/
N
)
T
o
i
n
MINUTES OF MEETING c
l
SUBJECT: INTERNAL MEETING NO. 09 DATE: June 21, 2021 u
PROJECT/LOCATION: VENUE: d
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
e
ATTENDEES: see attached Attendance Sheet
o
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
DISCUSSION:
n
ITEM
SUBJECT KEY POINTS DISCUSSED UPDATE ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE e
NO x
t
COMMERCIAL
Estimated 700 pcs / day ( 650 psi) Test = Passed for 650 psi - 6 inches 1400 pcs qty ( in demand ) 1200 psi stock- 6 inches a
No delivery last Saturday (June 19, 2021). For testing remaining CHB placed at Batching g
Plant. e
1 CHB Delivery progressive update of delivery J. Bongcasan
n
d
a
GDSM - supplier for cement Available Cement on Site - QTY ? ?
2 Cement progressive update of delivery J. Bongcasan
(
Rectification JO to proceed JO for rectifiction / Painitng JO is still floating progressive update
Y
/
3 Job Order J. Bongcasan N
)
TECHNICAL UPDATES
BSMT - 100%
GROUND FLOOR : ZONE 1 - 80 % , to submit today Zone 1 & 2 to receive today ( June 21, 2021) from client
For update R. Brazil / M. Valencia 19-Jun-21
4 Wall setting out status GROUND FLOOR : ZONE 2 - Complete with comments Third flr Equipment Room - not yet started
For update R. Brazil / M. Valencia 26-Jun-21
GROUND FLOOR : ZONE 3 - 30 % ongoing Zone 3 submitted last Saturday to ff up after 2 days For update R. Brazil / M. Valencia 3-Jul-21
GROUND FLOOR : ZONE 4 - Zero % Zone 4 - ongoing to submit to client June 23, 2021 For update R. Brazil / M. Valencia
Archi Ops to coordinate with Surveyor - Regie for the As built plans GF = ok today to convert to PDF - Tower 3 only Basement
5 As built plans Field Engineeer/ Architect of per Archi Dept
Zone to coordinate with Regie
CONCERN OF TECHNICAL TO OPERATION
Thinckness of Marcowall Macrowall to return the plan to Megawide on June 24, 2021
6 Macrowall to ff up Macrowall / to submit Plan C. Guanzing 6/24/21
of 5th floor to technical
OPERATIONS
To completely finish masonry and rectificaton works of Zone 1 - 4
Masonry and Rectification
8 works progressive update C. Guanzing / P. Osmil 26-Jun-21
I
5
-
p
r
e
s
s
u
r
e
s
l
a
b
d
e
t
a
i
l
t
o
b
e
r
e
l
e
a
s
e
d
o
i
n
c
MINUTES OF MEETING l
DATE: u
SUBJECT: INTERNAL MEETING NO. 11 July 05, 2021
d
PROJECT/LOCATION: VENUE: e
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
ATTENDEES: see attached Attendance Sheet o
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
DISCUSSION:
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED UPDATE ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
HUMAN RESOURCE
a
g
Pending Medicard Card for Dependent of Marianett coordinate with H.O with the list of dependent , for e
1 Medicard Medicard Dependent Sta. Maria checking of erroneous spelling of names For update E.Ducay
n
d
a
COMMERCIAL ?
(
3 CHB Delivery Estimated 700 pcs / day ( 650 psi) Testing of CHB ongoing progressive update of deliverJ. Bongcasan Y
/
N
)
4 Cement GDSM - supplier for cement Delivery of 740 bags Cement every other day Good for 2 weeks remaining cement progressive update of deliverJ. Bongcasan
Status of Job Order for EDCL - Zone 3 for follow up H.O done progressive update J. Bongcasan
Rectification at Podium BSMT
Status of Job Order for Manhole Cover-
5 Job Order waiting for Loreno , Ladder Rung and Trench for follow up H.O progressive update J. Bongcasan
Grating
Status of Job Order for JVVC - Rectification @ for follow up H.O done progressive update J. Bongcasan
Tower 4 GF (SRF # 068)
TECHNICAL UPDATES
GROUND FLOOR : ZONE 1 Already 100% - not included ID's
For update R. Brazil / M. Valencia 19-Jun-21
Wall setting out GROUND FLOOR : ZONE 2 Already 100% - not included ID's Zone 2 and 4 GF - ok
6 For update R. Brazil / M. Valencia 26-Jun-21
plan status
GROUND FLOOR : ZONE 3 to receive from client today 6.28.21 Zone 1& 3 GF - to mobilize @ GF (edcl) For update R. Brazil / M. Valencia 3-Jul-21
GROUND FLOOR : ZONE 4 to receive from client today 6.28.21 V.E - to resubmit tomorrow For update R. Brazil / M. Valencia
Archi Ops to coordinate with Surveyor - Regie Cancelled - OPS will not do the As built Zone to 4 - 2nd flr - one week to receive , waiting for
7 As built plans for the As built plans section Noted Noted Noted
Transmitted plans of MEPF to Archi Dept MEPF and Archi dept agreed that Archi dept will follow
8 MEPF Plans approved plans from Technical only Noted Noted Noted
CONCERN OF TECHNICAL TO OPERATION
to ff up Macrowall / to
9 Macrowall Thickness of Marcowall Macrowall to return the plan to Megawide on June 24, submit Plan of 5th floor to C. Guanzing 6/24/21
2020 technical
to ff up Macrowall / to
9 Work Start Notice Work Start Notice process flow Macrowall to return the plan to Megawide on June 24, submit Plan of 5th floor to C. Guanzing 6/24/21
2020 technical
OPERATIONS
r
o
cn
o
u
n
p
e
ITEM NO SUBJECT KEY POINTS DISCUSSED UPDATE ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE lx
et
Rectification at Tower 1 Complete - except of the Masonry GF - ongoing / Rectification - End of July Tower progressive update r
C. Guanzing / P. Osmil 26-Jun-21
storage rooms for floor topping 1 a
10 Zone 1 Masonry and Rectification works Update b
g
ee
Rectification @ Basement - Complete 100% Masonry - fire exit 01 - lacking from MEPF / Apuro progressive update C. Guanzing / P. Osmil 26-Jun-21 a
n
m
d
Podium Basement - Balance Plastering for Masonry a
progressive update 30-Jun-21 c
?
Works
o
Podium Basement - Done Rectification Apuro - July 17, 2021 (ric) / Jheb Zone 4 - July 17 , 2021 Noted Noted Noted n
(
11 Zone 2 Masonry and Rectification works Update n
Y
Coordinate with Limitless / e/
Tower 2 GF Rectification of Build US JO No. 300159101 ongoing - end of July / masonry - End of August NJEB for the take over of P. Osmil / J. Shillingford 3-Jul-21 cN
for Take Over t)
works
i
n
12 Zone 3 Masonry and Rectification works Update Rectification at Podium BSMT - still waiting for Job Masonry BSMT- July 10, 2021/ Rectification of EDCL start ff up Commercial for the J.O C. Guanzing / J. Masong 10-Jul-21 g
Order of EDCL to release from H.O today - End of July
t
Masonry BSMT - lacking piling of CHB / rectification of C. Guanzing / J. Masong / 30-Jun-21 o
13 Zone 4 Masonry and Rectification works Update Rectification of Madval at Podium - still ongoing Madval for take over of United Colourtech For update A. Banzon
T
Rectify Laitance of Conrcrete at Zone 1 & 3 For update C. Guanzing / J. Masong / 12-Jul-21 o
A. Banzon w
14 Rectification on Slab Rectification of Laitance Concrete e
P. Osmil / J. Shillingford /
Rectify Laitance of Conrcrete at Zone 2 & 4 For update M. Sta.maria 19-Jul-21 r
15 Ready to receive for painting works from the masonry Masonry works - BASE ON SCHEDULE Noted Noted Noted
works 2
SUBMITTALS f
OVS - plumbing Need actual sample waiting for the arrival of actual sample o
15 forwarded last Saturday to ff up the sample first week of July r
fixtures
Need actual sample Document need from KENT - for rfa this week Real u
16 Laminated Floors For update R.Cases 30-Jun-21 p
d
17 Swimming Pool to check finishes ( Architectural) Landscape - Soil how many cubic meters ? done - submitted to QS (lacking playground equipment ) for update R. Almario a
Modified waterproofing tank lining - to submit today / Holz - Downpayment - to t
18 Waterproofing submit schedule on Wednesday / target within the week for update R.Cases e
waterproofing- amenity deck , landscape, pool tank lining - to submit today / Holz - Downpayment - to w
18 Roofdeck - membraine submit schedule on Wednesday / target within the week for update R.Cases
i
** NOTHING FOLLOWS ** t
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final & executory h
f
o
r
I
5
-
p
r
e
s
i
n
c
MINUTES OF MEETING l
DATE: u
SUBJECT: INTERNAL MEETING NO. 11 July 05, 2021
d
PROJECT/LOCATION: VENUE: e
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
ATTENDEES: see attached Attendance Sheet o
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
DISCUSSION:
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED UPDATE ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
HUMAN RESOURCE
a
Coordinate with H.O with the list of g
1 Medicard Medicard Dependent dependent , for checking of erroneous For update E.Ducay e
spelling of names n
d
a
COMMERCIAL ?
(
2 CHB Delivery Estimated 700 pcs / day ( 650 psi) Testing of CHB ongoing progressive update of delivery J. Bongcasan Y
/
N
)
3 Cement GDSM - supplier for cement Remaining cement good for 2 weeks progressive update of delivery J. Bongcasan
TECHNICAL UPDATES
GROUND FLOOR : ZONE 1 Already 100% - not included ID's
For update R. Brazil / M. Valencia 19-Jun-21
Wall setting out GROUND FLOOR : ZONE 2 Already 100% - not included ID's
5 For update R. Brazil / M. Valencia 26-Jun-21
plan status
GROUND FLOOR : ZONE 3 Done For update R. Brazil / M. Valencia 3-Jul-21
GROUND FLOOR : ZONE 4 V.E - to resubmit tomorrow For update R. Brazil / M. Valencia
CONCERN OF TECHNICAL TO OPERATION
Pending
6 Macrowall Thickness of Marcowall Sealant for macrowall - penguin & k2GP - For update C. Guanzing 6/24/21
for discussion commercial
o
n
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED UPDATE ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
Architectural and Technical department
agreed that WSN needs to be sign first by a
7 Work Start Notice Work Start Notice process flow Architectural before it will be process in Noted Noted Noted g
NOVADE. e
n
d
OPERATIONS a
?
11 Zone 4 Masonry and Rectification works Update Rectification of Madval for take over of For update P. Osmil / J. Shillingford / M. 30-Jun-21
United Colourtech- for SRF Sta.maria
APURO - Jheb July 17 , 2021
18 Waterproofing Modified waterproofing Holz - to submit schedule on Wednesday for update R.Cases w
i
t
** NOTHING FOLLOWS ** h
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final & executory
J
Prepares By: Noted by: .
Mary Joy Vequizo Albert Saavedra T
Office Engineer Project Manager - Architectural a
p
a
l
e
s
R
F
A
f
o
r
I
5
-
p
r
e
s
s
u
r
e
i
n
c
MINUTES OF MEETING l
DATE: u
SUBJECT: INTERNAL MEETING NO. 12 July 12, 2021
d
PROJECT/LOCATION: VENUE: e
MANDANI BAY QUAY MCC-MBQ
ARCHITECTURAL OFFICE
ATTENDEES: see attached Attendance Sheet o
MEETING AGENDA: Weekly Internal Meeting (Every Monday from 7:30am – 09:00am) n
DISCUSSION:
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
HUMAN RESOURCE
a
g
For follow up status in Head office e
1 Medicard Medicard Dependent For update E.Ducay n
Marianett Dependent d
a
?
(
Cecil cant access- need screenshot Y
2 Human Edge Disable of Peoplecore this mont forward to HR today For update / For follow up E.Ducay / M.J Vequizo
/
N
)
SAFETY
Project ID Need to provide Project ID/ Pass for For process For update R. Lugo July 17,2021
employees
BERDE Prepare used Phenolic / Plywood for donation For update R. Lugo
to the community for BERDE points
MEPF
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
COMMERCIAL
a
g
2 CHB Delivery Estimated 700 pcs / day ( 650 psi) progressive update of delivery J. Bongcasan e
n
d
a
3 Cement GDSM - supplier for cement progressive update of delivery J. Bongcasan ?
(
To check available 10mm and 12mm Y
3 Rebars Need 16 mm on site rebars on site before proceeding with progressive update of delivery J. Bongcasan /
the delivery N
)
4 Conrete Epoxy To be use for bonding agent as per structural to discuss on Thursday what PO to cancel For Update J. Bongcasan
Doron A & B
Job order SRF 071 - Masonry Works from EDCL to RIC for follow up H.O progressive update J. Bongcasan
TECHNICAL UPDATES
GROUND FLOOR : ZONE 1
Site implementation concern - as per wall
setting out
For update R. Brazil / M. Valencia 19-Jun-21
ask nalang ko adrian lol
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
GROUND FLOOR : ZONE 3 t
Received already - done review - for sign For update R. Brazil / M. Valencia 3-Jul-21
ni MEPF a
GROUND FLOOR : ZONE 4 g
Received For update e
Zone 1 - next week July 19, 2021 forward n
Wall setting out to client (some delays due to vaccination d
5 plan status on July 15,21) Before enf of July a
SECOND FLOOR : ZONE 1 For update R. Brazil / M. Valencia Client will return ?
the WSOP
(
Y
/
Before enfd of July mabalik na ni Client Before enf of July N
SECOND FLOOR : ZONE 2 Zone 2- July 21,2021 forward to client For update R. Brazil / M. Valencia Client will return )
the WSOP
OPERATIONS
Masonry Basement - balance FE 01 due to
MEPF
8 MASONRY WORKS Masonry GF - ongoing progressive update C. Guanzing / P. Osmil 26-Jun-21
Zone 1
Rectification at Tower 1 to finish on end
of July
8 RECTIFICATION WORKS progressive update C. Guanzing / P. Osmil 26-Jun-21
Floor topping - initial start today 7.05.21
@ Tower 1 ( Admin)
o
n
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
MASONRY WORKS Masonry to finish on End of August progressive update P. Osmil / J. Shillingford 8/31/21 a
g
e
n
9 Zone 2 d
Rectification ongoing to finish on end of a
RECTIFICATION WORKS July For update P. Osmil / J. Shillingford 7/30/21 ?
(
Y
/
Masonry BSMT- July 17, 2021 include mid N
10 MASONRY WORKS stair ff up Commercial for the J.O C. Guanzing / J. Masong 7/17/21 )
Zone 3
10 RECTIFICATION WORKS Rectification of EDCL start today BSMT ff up Commercial for the J.O C. Guanzing / J. Masong 7/30/21
and to finish on end of July 2021
Done except MEPF issues
P. Osmil / J. Shillingford / M.
11 MASONRY WORKS For update Sta.maria 30-Jun-21
Zone 4
Rectification of Madval for take over of
11 RECTIFICATION WORKS United Colourtech- for SRF For update P. Osmil / J. Shillingford / M. 30-Jun-21
Sta.maria
APURO - Jheb July 17 , 2022
For update - per floor / zone For update C. Guanzing / J. Masong / A. 12-Jul-21
Banzon
12 Rectification on Slab Rectification of Laitance Concrete
P. Osmil / J. Shillingford / M.
For update - per floor / zone For update Sta.maria 19-Jul-21
14 Leak Test Leak Test of Tank Zone 1 - 80% For update C. Guanzing / A. Banzon
o
n
n
e
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
t
a
g
e
15 Schedule n
d
a
?
(
Y
/
N
)
ow
en
r
n
e2
ITEM NO SUBJECT KEY POINTS DISCUSSED ACTIONS TO BE TAKEN PERSON RESPONSIBLE TARGET DATE
x
SUBMITTALS t-
af
go
OVS - plumbing Document s forwarded to client last er
15 fixtures Need actual sample Saturday 07.03.22 to ff up the sample first week of July
n
d
u
ap
For RFA ?d
16 Laminated Floors Need actual sample For update R.Cases 30-Jun-21 a
(t
eY
/
18 Waterproofing Modified waterproofing for update for update R.Cases N
w
)i
** NOTHING FOLLOWS ** t
These minutes are honest recollection of all the discussion transpired during the meeting. Should any party will have correction & comments , you have 1 day from receipt hereof for update and revision. Otherwise, all items above will be deemed true, correct , final & executory h