Construction of 2 Nos of Rolling stock Depots at Rangehill & Vanaz including Civil and E&M Works for our

Pune Metro Rail Project


Daily Progress Report-Range hill Depot
PARTLY
Engineer: General Consultant WEATHER: CLEAR FOG RAINY
RAINY
Contractor: URC Construction (P) LTD PROGRESS DATE: 02-Apr-21

Day Progress This month


Cum. Progress Cum.Progress till This Month
S.NO Activity Scope Unit Plan/Progress Delay / Ahead Achieved till Remarks
till last day Date plan
02-04-21 date

Planned 100713 170 100883


1 Excavation works- for all kinds of soil 101206 Cum 0 4709 350
Achieved 100713 170 100883
Excavation works- Ordinary/Weathered Planned 52740 52740
2 63309 Cum 150 200
rock/Hard rock Achieved 52890 52890
Planned 58000 58000
3 Filling works- for all kinds of soil 58000 Cum 0
Achieved 58000 58000
Planned 94728 212 94940
4 Garbage Soil Filling/Rock/Garbage/ Screened Soil 97000 Cum 0 1944 212
Achieved 94728 212 94940
Planned 51850 51850
5 Rock disposal outside the Depot 63309 Cum 0
Achieved 51850 51850

ETU BUILDING

Planned 4352 4352


1 Wall Putty-1st Coat 4650 Sqm 0
Achieved 4352 4352
Planned 24 24 Fire Door Balance-4
2 Door Fixing 28 Nos 0
Achieved 24 24 Nos

Planned 2442 252 2694


3 Wall Primer 4250 Sqm 0 1200 502.0
Achieved 2442 252 2694
Planned 99 99
4 Tiles-Floor 119 Sqm 0
Achieved 99 99

INTEGRATED WORKSHOP BUILDING

Planned 22 22
1 Footing PCC 24 Nos 0
Achieved 22 22
Planned 22 22
2 Footing RCC 24 Nos 0
Achieved 22 22
Planned 91 91
3 Column & shear wall RCC Up to Plinth Beam 93 Nos 0
Achieved 91 91
Planned 35 35
4 Corbel Beam RCC 38 Nos 0
Achieved 35 35
Column & shear wall RCC Above Corbel Beam Planned 22 22
5 38 Nos 0
Upto Transit Level Slab Beam Bottom Achieved 22 22
Planned 660 660
6 Floor PCC 700.000 Sqm 0
Achieved 660 660
Planned 80 80
7 Tie Beam-559.3 @ Grid E 90.000 Rmt 0 10
Achieved 80 80
Planned 30 30
8 Tie Beam @ Grid B" 90.000 Rmt 0
Achieved 30 30
Planned 8 8
9 Above Tie Beam-559.3 @ Grid E 10.000 Nos 0 2
Achieved 8 8
Planned 4 4
10 Jack Pit PCC 7.000 Nos 0 3
Achieved 4 4
Planned 4 4
11 Jack Pit Raft RCC 7.000 Nos 0 3
Achieved 4 4
Planned 4 4
12 Jack Pit Wall RCC 7.000 Nos 0 3 1st ift in Progress
Achieved 4 4
Planned 52 52
13 Inspection Bay Track-1 D-E Raft RCC 86.800 Rmt 0 34.00
Achieved 52 52
Planned 80 80
14 Inspection Bay Track-1 D-E Wall RCC 173.600 Rmt 0 97.00 1st Lift in Progress
Achieved 80 80
Planned 20 20
15 Inspection Bay Track-2 D-E Raft RCC 86.800 Rmt 0 50.00
Achieved 20 20
Planned 80 80
16 Inspection Bay Track-2 D-E Wall RCC 173.600 Rmt 0 90.00 1st Lift in Progress
Achieved 80 80
Planned 50 50
17 Inspection Bay Track-2 D-E PCC 86.800 Rmt 0 30.00
Achieved 50 50
Planned 50 50
18 Inspection Bay Track-2 D-E Raft RCC 86.800 Rmt 0 36.80
Achieved 50 50
Planned 30 30
19 Inspection Bay Track-2 D-E Wall RCC 173.600 Rmt 0 150
Achieved 30 30
Planned 155 155
20 Repair Bay PCC 2728.000 Sqm 0 1250
Achieved 155 155
Planned 450 450
21 Grade Slab RCC @ Annexure Building 1120.000 Sqm 0 600
Achieved 450 450
Planned 240 240
22 Repair Bay PCC(B-B") 788.000 Sqm 0 600
Achieved 240 240
Planned 63 63
23 Block Work-Annexure Building 172.000 Cum 0 120
Achieved 63 63
Planned 15 15
24 Column Above SF Slab to Transit Slab 22.000 Nos 0 7
Achieved 15 15
BOUNDARY WALL
Planned 957 957
1 Raft PCC 1255 Rmt 0 17
Achieved 957 957
Planned 970 970
2 Raft RCC 1255 Rmt 0 17
Achieved 970 970
Planned 952 18.00 970
3 Wall RCC 1255 Rmt 0 17 18
Achieved 952 18.00 970
Planned 976 976
4 Plastering 1050 Sqm 0
Achieved 976 976
Planned 185 185
5 Pre-Cast Panel Eretion(East Side) 417 Nos 0
Achieved 185 185
Planned 40 40
6 Tie Beam RCC 1258 Rmt 0
Achieved 40 40
CSD
Planned 40 40
1 Pull PIT PCC 410 Nos 0 30
Achieved 40 40
Planned 34 34
1 Pull PIT RCC 410 Nos 0 30
Achieved 34 34
Planned 633 633
2 Trench PCC 2184 Rmt 0 150
Achieved 633 633
Planned 322 322
3 Trench Raft RCC 2184 Rmt 0 150
Achieved 322 322
Planned 484 484
3 Trench Wall RCC 4368 Rmt 0 300 20
Achieved 484 484
Planned 13 13
4 High Mast PCC 15 Nos 0 2
Achieved 13 13
Planned 13 13
5 High Mast RCC 15 Nos 0 2
Achieved 13 13
Planned 18 18
6 910mm Dia Chamber 52 Nos 0 2
Achieved 18 18
Planned 4 4
7 1220mm Dia Chamber 21 Nos 0 5
Achieved 4 4
Planned 5 5
8 1520mm Dia Chamber 7 Nos 0 1
Achieved 5 5

Hume Pipe Details:

Planned 301 301


9 Hume Pipe-450 NP2 418 Rmt 0
Achieved 301 301
Planned 43 43
10 Hume Pipe-450 NP3 172 Rmt 0
Achieved 43 43
Planned 2329 80.00 2409
11 Hume Pipe-250 NP2 13050 Rmt 0 1500 262
Achieved 2329 80.00 2409
Planned 44 44
12 Hume Pipe-250 NP4 548 Rmt 0
Achieved 44 44
Planned 26 25.6
13 Hume Pipe-150 NP2 5084 Rmt 0 152
Achieved 26 25.6
Planned 44 44
14 Hume Pipe-250 NP3 298.91 Rmt 0
Achieved 44 44
Planned 49 49
15 GI Pipe 150mm Dia 1650 Rmt 0 250
Achieved 49 49
Planned 60 60
16 HDPE Pipe-160mm 3000 Rmt 0 1100 60
Achieved 60 60

Track Well Crossing

Planned 1.00 1.00


1 Wall RCC 2.0 Nos 0 1 Lift in Progress
Achieved 1.00 1.00

Loading & Unloading Platform

Planned 66.83 66.83


1 GSB 210.0 Cum 0 145.00
Achieved 66.83 66.83
Planned 63.00 63.00
2 PCC 70.0 Rmt 0 7.00
Achieved 63.00 63.00
Planned 63.00 63.00
3 Raft RCC 70.0 Rmt 0 7.00 1st Lift Completed
Achieved 63.00 63.00
Planned 828.00 828.00
4 Pavement PCC 1620.0 Sqm 0 800.00
Achieved 828.00 828.00
ADMIN BUILDING

Planned 743 743


1 FF Slab RCC 850 Cum 0 107
Achieved 743 743
Planned 30 30 1st & 2nd Lift In
2 Column Above FF Slab 42 Nos 0 15 3
Achieved 30 30 Progress
Construction of 2 Nos of Rolling stock Depots at Rangehill & Vanaz including Civil and E&M Works for our Pune Metro Rail Project
Daily Progress Report-Range hill Depot
PARTLY
Engineer: General Consultant WEATHER: CLEAR FOG RAINY
RAINY
Contractor: URC Construction (P) LTD PROGRESS DATE: 02-Apr-21

Day Progress This month


Cum. Progress Cum.Progress till This Month
S.NO Activity Scope Unit Plan/Progress Delay / Ahead Achieved till Remarks
till last day Date plan
02-04-21 date

Material status

Equipment deployment Deployed Unit Today Received Cumulative Approved


Category Nos Material Name Unit
details (Nos) Qty quantity till date Make/Source

02-Apr-21
Mason & stone mason 36 Excavator 2 Steel MT 6202 JSW

MC / Unskilled 43 Tipper 8 10 mm aggregate MT 9787

Plastering mason + Helper 18 JCB 1 20mm aggregate MT 21016.3

Brick Mason + Helper 0 Bob Cat 1 M-Sand MT 27381.73

Carpenter + Carpenter Helper 138 Water tanker 1 River/Plastering Sand MT 543.87

Barbender + Barbender Helper - Night Work 106 Hydra Crane 2 Cement-OPC MT 9140.92 Ultra-Tech

Scaffolder 52 Transit mixer 3 Cement-PSC MT 5001.6 JSW

Tile Mason 3 vehicles for pickup (bolero , camber) 2 GSB MT 3830.93

Windoor-Client office fabrication works 0 JCB Mini Roller 1 AAC Blocks Nos 27248 Ultra-Tech

Aluminium Fabricator 0 Earth rammer 1

Manpower status on
Welder & Welder helper 21 Tractor with trailer 1

Tree transplantation 0 Tractor bull 1

Plumbers 1 Bar bending machine 4

Electrician/High Mast Installation 11 Bar cutting machine 4

Painter 15 Batching Plant 30 Cum/Hr 2

Drivers + others 40 Mixture machine (Single phase) 1

Kota Stone 0 Dynamic Mini Roller 1

PEB Work 6 Weigh Bridge - Weigh Tech 1

Water proofing works 10 Generator - 62.5 KVA 1

Generator - 30 KVA 1

Generator - 125 KVA 1

Total 500 Dewatering Pumps / curing pumps 28

Vibrator- petrol/electric 14

Other minor tools / tackles/


1
equipments - as per requirement

Notes Name: Shankar Swaminathan Designation: Planning Manager