Professional Documents
Culture Documents
ETU BUILDING
Planned 22 22
1 Footing PCC 24 Nos 0
Achieved 22 22
Planned 22 22
2 Footing RCC 24 Nos 0
Achieved 22 22
Planned 91 91
3 Column & shear wall RCC Up to Plinth Beam 93 Nos 0
Achieved 91 91
Planned 35 35
4 Corbel Beam RCC 38 Nos 0
Achieved 35 35
Column & shear wall RCC Above Corbel Beam Planned 22 22
5 38 Nos 0
Upto Transit Level Slab Beam Bottom Achieved 22 22
Planned 660 660
6 Floor PCC 700.000 Sqm 0
Achieved 660 660
Planned 80 80
7 Tie Beam-559.3 @ Grid E 90.000 Rmt 0 10
Achieved 80 80
Planned 30 30
8 Tie Beam @ Grid B" 90.000 Rmt 0
Achieved 30 30
Planned 8 8
9 Above Tie Beam-559.3 @ Grid E 10.000 Nos 0 2
Achieved 8 8
Planned 4 4
10 Jack Pit PCC 7.000 Nos 0 3
Achieved 4 4
Planned 4 4
11 Jack Pit Raft RCC 7.000 Nos 0 3
Achieved 4 4
Planned 4 4
12 Jack Pit Wall RCC 7.000 Nos 0 3 1st ift in Progress
Achieved 4 4
Planned 52 52
13 Inspection Bay Track-1 D-E Raft RCC 86.800 Rmt 0 34.00
Achieved 52 52
Planned 80 80
14 Inspection Bay Track-1 D-E Wall RCC 173.600 Rmt 0 97.00 1st Lift in Progress
Achieved 80 80
Planned 20 20
15 Inspection Bay Track-2 D-E Raft RCC 86.800 Rmt 0 50.00
Achieved 20 20
Planned 80 80
16 Inspection Bay Track-2 D-E Wall RCC 173.600 Rmt 0 90.00 1st Lift in Progress
Achieved 80 80
Planned 50 50
17 Inspection Bay Track-2 D-E PCC 86.800 Rmt 0 30.00
Achieved 50 50
Planned 50 50
18 Inspection Bay Track-2 D-E Raft RCC 86.800 Rmt 0 36.80
Achieved 50 50
Planned 30 30
19 Inspection Bay Track-2 D-E Wall RCC 173.600 Rmt 0 150
Achieved 30 30
Planned 155 155
20 Repair Bay PCC 2728.000 Sqm 0 1250
Achieved 155 155
Planned 450 450
21 Grade Slab RCC @ Annexure Building 1120.000 Sqm 0 600
Achieved 450 450
Planned 240 240
22 Repair Bay PCC(B-B") 788.000 Sqm 0 600
Achieved 240 240
Planned 63 63
23 Block Work-Annexure Building 172.000 Cum 0 120
Achieved 63 63
Planned 15 15
24 Column Above SF Slab to Transit Slab 22.000 Nos 0 7
Achieved 15 15
BOUNDARY WALL
Planned 957 957
1 Raft PCC 1255 Rmt 0 17
Achieved 957 957
Planned 970 970
2 Raft RCC 1255 Rmt 0 17
Achieved 970 970
Planned 952 18.00 970
3 Wall RCC 1255 Rmt 0 17 18
Achieved 952 18.00 970
Planned 976 976
4 Plastering 1050 Sqm 0
Achieved 976 976
Planned 185 185
5 Pre-Cast Panel Eretion(East Side) 417 Nos 0
Achieved 185 185
Planned 40 40
6 Tie Beam RCC 1258 Rmt 0
Achieved 40 40
CSD
Planned 40 40
1 Pull PIT PCC 410 Nos 0 30
Achieved 40 40
Planned 34 34
1 Pull PIT RCC 410 Nos 0 30
Achieved 34 34
Planned 633 633
2 Trench PCC 2184 Rmt 0 150
Achieved 633 633
Planned 322 322
3 Trench Raft RCC 2184 Rmt 0 150
Achieved 322 322
Planned 484 484
3 Trench Wall RCC 4368 Rmt 0 300 20
Achieved 484 484
Planned 13 13
4 High Mast PCC 15 Nos 0 2
Achieved 13 13
Planned 13 13
5 High Mast RCC 15 Nos 0 2
Achieved 13 13
Planned 18 18
6 910mm Dia Chamber 52 Nos 0 2
Achieved 18 18
Planned 4 4
7 1220mm Dia Chamber 21 Nos 0 5
Achieved 4 4
Planned 5 5
8 1520mm Dia Chamber 7 Nos 0 1
Achieved 5 5
Material status
02-Apr-21
Mason & stone mason 36 Excavator 2 Steel MT 6202 JSW
Barbender + Barbender Helper - Night Work 106 Hydra Crane 2 Cement-OPC MT 9140.92 Ultra-Tech
Windoor-Client office fabrication works 0 JCB Mini Roller 1 AAC Blocks Nos 27248 Ultra-Tech
Manpower status on
Welder & Welder helper 21 Tractor with trailer 1
Generator - 30 KVA 1
Vibrator- petrol/electric 14