You are on page 1of 14

NAME: KUNA SATYA SRINIVASA RAJU

ROLL NO :200914006 (CEM)


PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Develop the schedule, apply the resources and estimate the cost of the project. The activities

and the resources are given below. The activities are listed according to the WBS levels. Apply

WBS and organize the activities. Create a Project calendar (6 days/week and 10 hr/day

working). Link this calendar with a Global base calendar. Create the OBS and EPS of your

choice and link with the Project.

OBS created
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

EPS Created

Global Calendar
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Project Created

Mentioned 6-day work week created.


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Time Period

Project Calendar Assigned to Project


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Project WBS Created.

Activities Entered against WBS


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

When entered In Weeks in duration primavera converts to days (say 4 weeks= to be entered as
4w)

Predecessor entering
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Relationship + Lead Entered.

Simultaneously relations + Lag Lead Entry Done.


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Scheduling

Gannt Chart (at Start)


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Gannt Chart (at End)

Resource Code created by adding, naming & Scouting.


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Resource Linked to Resource Code.

Unit Rate & Measuring Unit Created for Project Manager Since its 1 it is mentioned as Each.
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Completed listing all resources and classified it to coding.

Resource added to activity A and budgeted Qty given as 1


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Final Output after assigning All the resources.

Report Of Budgeted Cost


NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Batched Report
NAME: KUNA SATYA SRINIVASA RAJU
ROLL NO :200914006 (CEM)
PROJECT MANAGEMENT LAB-2 ASSIGNMENT NO -6

Batched Report