You are on page 1of 83

Republic of the Philippines

Department of Public Works and Highways


QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Dalahican Road, Lucena City

Construction of Two (2) Storey Ten (10)


Classroom Academic School Building at
Tiaong East Elementary School,
Tiaong, Quezon

CY 2020 BEFF
CY 2020 BEFF
Republic of the Philippines
Department of Public Works and Highways
Quezon II District Engineering Office
Lucena City

Date: ______________

EXECUTIVE SUMMARY

For : THE DISTRICT ENGINEER

Project ID :
Project Name : Construction of Two (2) Storey Ten (10) Classroom
Academic School Building at Tiaong East Elementary
School,
Location of Project : Tiaong, Quezon
2. Project Category : School Building
3. Source of Fund : CY 2020 BEFF
4. Action Recommended: For Aproval
5. Implementing Office
: DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : ₱ 30,202,762.50
8. ABC : ₱ 30,127,255.59
9. Project Duration : 300 C.D.
10. Mode Implementation
: By Contract

PREPARED BY:

CESAR ANTONIO P. JADER


Architect II

SUBMITTED BY:

FAUSTINO MARK ANTHONY S. DE LA CRUZ


Chief, Planning and Design Section
COMPUTATION OF ESTIMATED PROJECT DURATION

PROJECT: Construction of Two (2) Storey Ten (10) Classroom Academic


School Building at Tiaong East Elementary School,

LOCATION: Sariaya

AMOUNT: ₱ 30,202,762.500

PROJECT CATEGORY: Building

Computation of Duration:

Type of Building used as reference: 2 STY 10 CL

Area of Building used as reference: 1,045.00 m²

Building Duration based on the Modified Std. 205 c.d.


DPWH - DepEd School Buildings as of July
31, 2019 (as per memorandum dated August
6, 2019 from DPWH Central Office):

Type of Building: 2 STY 10 CL

Area of Building: 1,045.00 m²

Calendar Days by Ratio: 210 c.d.

Additional Calendar Days due to New Item of 90 c.d.


Works and increase in quantity of Item of
Works due to additional structures and actual
site condition:

PROJECT DURATION : say.. 300.00 c.d.


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : Construction of Two (2) Storey Ten (10) Classroom Academic School Building Appropriation : Php 30,202,762.50
at Tiaong East Elementary School, Source of Fund : CY 2020 BEFF
Project ID : Target Start Date :
Location : Tiaong, Quezon Total Project Duration : 300 C.D.
Project Description : Construction of 2-Storey 10-Classroom School Buidling (with stairwall 5m
width, steel casement windowat rear portion with security grilles for the front jalousie
windows, fire protection system, overhead tank and cistern)

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
Part I Facilities for the Engineer 0.38% 90,924.54 0.38% 90924.54
Part II Other General Requirements 6.75% 1,626,229.15 6.75% 1626229.15
Project Component ID PROJECT COMPONENT DESCRIPTION
PART III Civil, Mechanical, Electrical, and Sanitary/Plumbing Works
PART A EARTHWORKS 21.68% 5,225,530.57 21.68% 5,225,530.57
PART B PLAIN AND REINFORCED CONCRETE WORKS (PLS. SEE FORM POW-2015-01C-00) 31.39% 7,564,706.35 31.39% 7,564,706.35
PART C FINISHING WORKS & OTHER CIVIL WORKS 31.42% 7,573,715.99 31.42% 7,573,715.99
PART D ELECTRICAL WORKS 3.26% 785,226.87 3.26% 785,226.87
PART E MECHANICAL WORKS 5.13% 1,235,977.48 5.13% 1,235,977.48

Total 100% 24,102,310.95 100% 24,102,310.95

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 4,717,276.91 4,717,276.91 A. Total Direct Cost 24,102,310.95 24,102,310.95
2. Materials 17,271,737.44 17,271,737.44 B. OCM and Profit 4,590,313.42 4,590,313.42
3. Rental of Equipment 2,113,296.60 2,113,296.60 C. Value Added Tax (5%) 1,434,631.22 1,434,631.22
4. Provisional Sum / Daywork D. Total Construction Cost 30,127,255.59 30,127,255.59
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 4,590,313.42 4,590,313.42 E. Eng'g & Administrative Overhead, 0.25% 75,506.91 75,506.91
6. Value Added Tax (5%) 1,434,631.22 1,434,631.22 F. RROW Acquisition
7. EAO, 0.25% 75,506.91 75,506.91 G. Physical Reserved (Contingency)
8. RROW Acquisition
9. Physical Reserved (Contingency)
10.TOTAL ESTIMATED COST 30,202,762.50 30,202,762.50 H. TOTAL ESTIMATED COST 30,202,762.50 30,202,762.50

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Architect II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART I FACILITIES FOR THE ENGINEER
I.1.1 Offices and Laboratory for the Engineer
As Submitted 0.36% 1.00 L.s. 62,279.74 24,144.80 - 86,424.54 86,424.54 8% 6,913.96 4,666.93 98,005.43
A.1.1(3) Construction of Field Office for the Engineer
As Evaluated 0.36% 1.00 L.s. 62,279.74 24,144.80 - 86,424.54 86,424.54 8% 6,913.96 4,666.93 98,005.43
As Submitted 0.02% 300.00 ea. 4,500.00 - - 15.00 4,500.00 8% 360.00 243.00 5,103.00
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.02% 300.00 ea. 4,500.00 - - 15.00 4,500.00 8% 360.00 243.00 5,103.00
As Submitted 66,779.74 24,144.80 - 90,924.54 7,273.96 4,909.93 103,108.43
TOTAL OF PART I
As Evaluated 66,779.74 24,144.80 - 90,924.54 7,273.96 4,909.93 103,108.43
PART II OTHER GENERAL REQUIREMENTS
As Submitted 0.28% 1.00 L.s. 66,877.26 - - 66,877.26 66,877.26 0% - 3,343.86 70,221.12
B.3 Permits and Clearances
As Evaluated 0.28% 1.00 L.s. 66,877.26 - - 66,877.26 66,877.26 0% - 3,343.86 70,221.12
As Submitted 0.02% 1.00 Ea 2,815.00 924.80 92.48 3,832.28 3,832.28 20% 766.46 229.94 4,828.68
B.5 Project Billboard/ Sign Board
As Evaluated 0.02% 1.00 Ea 2,815.00 924.80 92.48 3,832.28 3,832.28 20% 766.46 229.94 4,828.68
As Submitted 5.43% 1.00 L.s. 977,304.41 318,000.00 20,215.20 1,315,519.61 1,315,519.61 8% 105,241.57 71,038.06 1,491,799.24
B.7(2) Occupational Safety and Health Program
As Evaluated 5.43% 1.00 L.s. 977,304.41 318,000.00 20,215.20 1,315,519.61 1,315,519.61 8% 105,241.57 71,038.06 1,491,799.24
As Submitted 0.99% 1.00 L.s. - - 240,000.00 240,000.00 240,000.00 0% - 12,000.00 252,000.00
B.9 Mobilization/Demobilization
As Evaluated 0.99% 1.00 L.s. - - 240,000.00 240,000.00 240,000.00 0% - 12,000.00 252,000.00
As Submitted 1,046,996.67 318,924.80 260,307.68 1,626,229.15 106,008.03 86,611.86 1,818,849.04
TOTAL OF PART II
As Evaluated 1,046,996.67 318,924.80 260,307.68 1,626,229.15 106,008.03 86,611.86 1,818,849.04

(Project ID)
(Project Component ID - Description)
CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING
PART III WORKS
PART A EARTHWORKS
As Submitted 1.39% 1.00 l.s. - 56,864.40 279,848.04 336,712.44 336,712.44 20% 67,342.49 20,202.75 424,257.68
800(2) Clearing and Grubbing
As Evaluated 1.39% 1.00 l.s. - 56,864.40 279,848.04 336,712.44 336,712.44 20% 67,342.49 20,202.75 424,257.68
As Submitted 0.90% 1.00 L.s. - 37,909.60 179,150.96 217,060.56 217,060.56 20% 43,412.11 13,023.63 273,496.30
801(1) Removal of Structure and Obstruction
As Evaluated 0.90% 1.00 L.s. - 37,909.60 179,150.96 217,060.56 217,060.56 20% 43,412.11 13,023.63 273,496.30
As Submitted 0.57% 591.65 m³ - 8,011.83 130,283.79 233.75 138,295.62 20% 27,659.12 8,297.74 174,252.48
803(1)a Structure Excavation (Common Soil)
As Evaluated 0.57% 591.65 m³ - 8,011.83 130,283.79 233.75 138,295.62 20% 27,659.12 8,297.74 174,252.48
As Submitted 0.29% 446.86 m³ - 12,299.09 57,768.60 156.80 70,067.69 20% 14,013.54 4,204.06 88,285.29
804(1)a Embankment from Structure Excavation
As Evaluated 0.29% 446.86 m³ - 12,299.09 57,768.60 156.80 70,067.69 20% 14,013.54 4,204.06 88,285.29
As Submitted 0.59% 88.50 m³ 128,057.29 2,435.82 11,440.99 1,603.78 141,934.10 20% 28,386.82 8,516.05 178,836.97
804(1)b Embankment from Borrow
As Evaluated 0.59% 88.50 m³ 128,057.29 2,435.82 11,440.99 1,603.78 141,934.10 20% 28,386.82 8,516.05 178,836.97
As Submitted 0.68% 83.79 m³ 139,674.49 18,910.70 6,185.31 1,966.47 164,770.50 20% 32,954.10 9,886.23 207,610.83
804(4) Gravel Fill
As Evaluated 0.68% 83.79 m³ 139,674.49 18,910.70 6,185.31 1,966.47 164,770.50 20% 32,954.10 9,886.23 207,610.83
As Submitted 17.15% 1.00 L.s. 3,143,763.90 920,841.60 92,084.16 4,156,689.66 4,156,689.66 20% 831,337.93 249,401.38 5,237,428.97
807(1) Site Development
As Evaluated 17.15% 1.00 L.s. 3,143,763.90 920,841.60 92,084.16 4,156,689.66 4,156,689.66 20% 831,337.93 249,401.38 5,237,428.97
As Submitted 3,411,495.68 1,057,273.04 756,761.85 5,225,530.57 1,045,106.11 313,531.84 6,584,168.52
TOTAL OF PART A
As Evaluated 3,411,495.68 1,057,273.04 756,761.85 5,225,530.57 1,045,106.11 313,531.84 6,584,168.52
PART B PLAIN AND REINFORCED CONCRETE WORKS
As Submitted 10.80% 409.05 m³ 2,465,344.35 64,523.24 88,154.56 6,400.25 2,618,022.15 20% 523,604.43 157,081.33 3,298,707.91
900(8) Structural Concrete (27.58 Mpa @ 28 days)
As Evaluated 10.80% 409.05 m³ 2,465,344.35 64,523.24 88,154.56 6,400.25 2,618,022.15 20% 523,604.43 157,081.33 3,298,707.91
As Submitted 4.72% 22,277.83 Kg 905,259.62 172,370.43 66,527.52 51.36 1,144,157.57 20% 228,831.51 68,649.45 1,441,638.53
902(1)a Reinforcing Steel (Deformed) Grade 40
As Evaluated 4.72% 22,277.83 Kg 905,259.62 172,370.43 66,527.52 51.36 1,144,157.57 20% 228,831.51 68,649.45 1,441,638.53
As Submitted 10.94% 50,570.57 Kg 2,109,627.18 391,280.06 151,017.16 52.44 2,651,924.40 20% 530,384.88 159,115.46 3,341,424.74
902(1)b Reinforcing Steel (Deformed), Grade 60
As Evaluated 10.94% 50,570.57 Kg 2,109,627.18 391,280.06 151,017.16 52.44 2,651,924.40 20% 530,384.88 159,115.46 3,341,424.74
As Submitted 4.75% 2,232.10 m² 457,420.90 486,046.02 207,135.31 515.48 1,150,602.23 20% 230,120.45 69,036.13 1,449,758.81
903(2) Formworks & Falseworks
As Evaluated 4.75% 2,232.10 m² 457,420.90 486,046.02 207,135.31 515.48 1,150,602.23 20% 230,120.45 69,036.13 1,449,758.81
As Submitted 5,937,652.05 1,114,219.75 512,834.55 7,564,706.35 1,512,941.27 453,882.37 9,531,529.99
TOTAL OF PART B
As Evaluated 5,937,652.05 1,114,219.75 512,834.55 7,564,706.35 1,512,941.27 453,882.37 9,531,529.99
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
PART C FACILITIES FOR THE ENGINEER
FINISHING
C.1 Termite Control Works
As Submitted 0.27% 205.29 L 52,348.95 10,935.87 1,093.59 313.60 64,378.41 20% 12,875.68 3,862.70 81,116.79
1000(1) Soil Poisoning
As Evaluated 0.27% 205.29 L 52,348.95 10,935.87 1,093.59 313.60 64,378.41 20% 12,875.68 3,862.70 81,116.79
As Submitted 52,348.95 10,935.87 1,093.59 64,378.41 12,875.68 3,862.70 81,116.79
Sub - Total C.1
As Evaluated
C.2. Masonry Works
As Submitted 0.88% 331.76 m² 159,760.09 36,203.91 18,538.75 646.56 214,502.75 20% 42,900.55 12,870.17 270,273.47
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel), 100mm
As Evaluated 0.88% 331.76 m² 159,760.09 36,203.91 18,538.75 646.56 214,502.75 20% 42,900.55 12,870.17 270,273.47
As Submitted 2.42% 609.72 m² 466,010.95 80,032.46 40,981.81 962.78 587,025.22 20% 117,405.04 35,221.51 739,651.77
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm
As Evaluated 2.42% 609.72 m² 466,010.95 80,032.46 40,981.81 962.78 587,025.22 20% 117,405.04 35,221.51 739,651.77
As Submitted 625,771.04 116,236.37 59,520.56 801,527.97 160,305.59 48,091.68 1,009,925.24
Sub - Total C.2
As Evaluated 625,771.04 116,236.37 59,520.56 801,527.97 160,305.59 48,091.68 1,009,925.24
C.3 Fabricated Materials
As Submitted 0.65% 1.00 L.s. 103,903.80 48,089.60 4,808.96 156,802.36 156,802.36 20% 31,360.47 9,408.14 197,570.97
1010(4) Wooden Doors & Windows
As Evaluated 0.65% 1.00 L.s. 103,903.80 48,089.60 4,808.96 156,802.36 156,802.36 20% 31,360.47 9,408.14 197,570.97
As Submitted 0.12% 19.35 m² 13,545.00 13,980.38 1,398.04 1,494.75 28,923.42 20% 5,784.68 1,735.41 36,443.51
1010(2)a Door (Flush)
As Evaluated 0.12% 19.35 m² 13,545.00 13,980.38 1,398.04 1,494.75 28,923.42 20% 5,784.68 1,735.41 36,443.51
As Submitted 1.14% 43.20 m² 237,600.00 34,519.20 3,451.92 6,378.96 275,571.12 20% 55,114.22 16,534.27 347,219.61
1010(2)b Door (Wooden Panel)
As Evaluated 1.14% 43.20 m² 237,600.00 34,519.20 3,451.92 6,378.96 275,571.12 20% 55,114.22 16,534.27 347,219.61
As Submitted 0.20% 1.00 L.s. 34,000.00 12,947.20 1,294.72 48,241.92 48,241.92 20% 9,648.38 2,894.52 60,784.82
1003(17) Carpentry and Joinery Works
As Evaluated 0.20% 1.00 L.s. 34,000.00 12,947.20 1,294.72 48,241.92 48,241.92 20% 9,648.38 2,894.52 60,784.82
As Submitted 0.26% 9.36 m² 51,480.00 8,323.20 4,351.32 6,854.12 64,154.52 20% 12,830.90 3,849.27 80,834.69
1006(4) Steel Louver Door
As Evaluated 0.26% 9.36 m² 51,480.00 8,323.20 4,351.32 6,854.12 64,154.52 20% 12,830.90 3,849.27 80,834.69
As Submitted 1.90% 116.64 m² 232,696.80 149,817.60 78,323.76 3,950.94 460,838.16 20% 92,167.63 27,650.29 580,656.08
1005(1) Residential Casement Steel Window
As Evaluated 1.90% 116.64 m² 232,696.80 149,817.60 78,323.76 3,950.94 460,838.16 20% 92,167.63 27,650.29 580,656.08
As Submitted 0.64% 48.00 m² 109,855.68 41,102.22 4,110.22 3,230.59 155,068.12 20% 31,013.62 9,304.09 195,385.83
1009(1)a Jalousie Window (Glass)
As Evaluated 0.64% 48.00 m² 109,855.68 41,102.22 4,110.22 3,230.59 155,068.12 20% 31,013.62 9,304.09 195,385.83
As Submitted 0.34% 1.00 L.s. 55,886.98 22,195.20 3,783.52 81,865.70 81,865.70 20% 16,373.14 4,911.94 103,150.78
1005(6) Window Accessory
As Evaluated 0.34% 1.00 L.s. 55,886.98 22,195.20 3,783.52 81,865.70 81,865.70 20% 16,373.14 4,911.94 103,150.78
As Submitted 0.11% 1.00 L.s. 26,070.00 - - 26,070.00 26,070.00 20% 5,214.00 1,564.20 32,848.20
1004(2) Finishing Hardware
As Evaluated 0.11% 1.00 L.s. 26,070.00 - - 26,070.00 26,070.00 20% 5,214.00 1,564.20 32,848.20
As Submitted 1.30% 1.00 L.s. 184,143.65 75,819.20 56,319.92 316,282.77 316,282.77 20% 63,256.55 18,976.97 398,516.29
1051(6) Railing
As Evaluated 1.30% 1.00 L.s. 184,143.65 75,819.20 56,319.92 316,282.77 316,282.77 20% 63,256.55 18,976.97 398,516.29
As Submitted 1,049,181.91 406,793.80 157,842.38 1,613,818.09 322,763.59 96,829.10 2,033,410.78
Sub-Total C.3
As Evaluated 1,049,181.91 406,793.80 157,842.38 1,613,818.09 322,763.59 96,829.10 2,033,410.78
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
C.4 Finishing Works FACILITIES FOR THE ENGINEER
As Submitted 2.02% 2,665.57 m² 294,024.79 177,281.92 17,728.19 183.46 489,034.90 20% 97,806.98 29,342.09 616,183.97
1027(1) Cement Plaster Finish
As Evaluated 2.02% 2,665.57 m² 294,024.79 177,281.92 17,728.19 183.46 489,034.90 20% 97,806.98 29,342.09 616,183.97
As Submitted 0.53% 1,113.78 m² - 64,415.79 64,470.45 115.72 128,886.24 20% 25,777.25 7,733.17 162,396.66
1021(1)a Cement Floor Finish (Plain)
As Evaluated 0.53% 1,113.78 m² - 64,415.79 64,470.45 115.72 128,886.24 20% 25,777.25 7,733.17 162,396.66
As Submitted 2.16% 597.46 m² 371,399.06 138,266.57 13,826.66 876.20 523,492.29 20% 104,698.46 31,409.54 659,600.29
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
As Evaluated 2.16% 597.46 m² 371,399.06 138,266.57 13,826.66 876.20 523,492.29 20% 104,698.46 31,409.54 659,600.29
As Submitted 0.02% 18.00 Lm 3,420.90 436.85 43.69 216.75 3,901.44 20% 780.29 234.09 4,915.82
1003(11)a1 Fascia Board (19mm, Fiber Cement Board)
As Evaluated 0.02% 18.00 Lm 3,420.90 436.85 43.69 216.75 3,901.44 20% 780.29 234.09 4,915.82
As Submitted 0.44% 534.21 m² 75,724.27 27,638.64 2,763.86 198.66 106,126.77 20% 21,225.35 6,367.61 133,719.73
1038(1) Reflective Insulation
As Evaluated 0.44% 534.21 m² 75,724.27 27,638.64 2,763.86 198.66 106,126.77 20% 21,225.35 6,367.61 133,719.73
As Submitted 1.30% 196.24 m² 196,012.26 107,852.93 10,785.29 1,603.40 314,650.48 20% 62,930.10 18,879.03 396,459.61
1018(1) Glazed Tiles and Trims
As Evaluated 1.30% 196.24 m² 196,012.26 107,852.93 10,785.29 1,603.40 314,650.48 20% 62,930.10 18,879.03 396,459.61
As Submitted 0.22% 56.07 m² 30,260.81 21,571.14 2,157.11 962.89 53,989.06 20% 10,797.81 3,239.34 68,026.21
1018(2) Unlglazed Tiles
As Evaluated 0.22% 56.07 m² 30,260.81 21,571.14 2,157.11 962.89 53,989.06 20% 10,797.81 3,239.34 68,026.21
As Submitted 0.35% 437.02 m² 25,237.91 53,887.48 5,388.75 193.39 84,514.14 20% 16,902.83 5,070.85 106,487.82
1016(1)a Water Proofing Cement Base
As Evaluated 0.35% 437.02 m² 25,237.91 53,887.48 5,388.75 193.39 84,514.14 20% 16,902.83 5,070.85 106,487.82
As Submitted 996,080.00 591,351.32 117,164.00 1,704,595.32 340,919.07 102,275.72 2,147,790.11
Sub-Total C.4
As Evaluated 996,080.00 591,351.32 117,164.00 1,704,595.32 340,919.07 102,275.72 2,147,790.11
C.5 Painting Works
As Submitted 3.55% 3,076.67 m² 369,763.43 446,102.50 44,610.25 279.68 860,476.18 20% 172,095.24 51,628.57 1,084,199.99
1032(1)a Painting Works (Masonry/Concrete)
As Evaluated 3.55% 3,076.67 m² 369,763.43 446,102.50 44,610.25 279.68 860,476.18 20% 172,095.24 51,628.57 1,084,199.99
As Submitted 0.63% 556.59 m² 54,432.83 89,669.89 8,966.99 275.01 153,069.71 20% 30,613.94 9,184.18 192,867.83
1032(1)b Painting Works (Wood Painting)
As Evaluated 0.63% 556.59 m² 54,432.83 89,669.89 8,966.99 275.01 153,069.71 20% 30,613.94 9,184.18 192,867.83
As Submitted 0.20% 183.35 m² 18,720.40 27,914.12 2,791.41 269.57 49,425.93 20% 9,885.19 2,965.56 62,276.68
1032(1)c Painting Works (Steel)
As Evaluated 0.20% 183.35 m² 18,720.40 27,914.12 2,791.41 269.57 49,425.93 20% 9,885.19 2,965.56 62,276.68
As Submitted 442,916.66 563,686.51 56,368.65 1,062,971.82 212,594.37 63,778.31 1,339,344.50
Sub-Total C.5
As Evaluated 442,916.66 563,686.51 56,368.65 1,062,971.82 212,594.37 63,778.31 1,339,344.50
C.6 Roof Framing and Roofing Works
As Submitted 1.41% 587.75 m² 253,049.89 81,441.31 8,144.13 582.96 342,635.33 20% 68,527.07 20,558.12 431,720.52
1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
As Evaluated 1.41% 587.75 m² 253,049.89 81,441.31 8,144.13 582.96 342,635.33 20% 68,527.07 20,558.12 431,720.52
As Submitted 2.46% 6,900.12 Kg 454,962.52 44,784.42 97,225.35 86.52 596,972.29 20% 119,394.46 35,818.34 752,185.09
1047(2)a Structural Steel (Trusses)
As Evaluated 2.46% 6,900.12 Kg 454,962.52 44,784.42 97,225.35 86.52 596,972.29 20% 119,394.46 35,818.34 752,185.09
As Submitted 1.96% 5,764.10 Kg 394,610.29 30,198.28 50,305.20 82.43 475,113.77 20% 95,022.75 28,506.83 598,643.35
1047(2)b Structural Steel (Purlins)
As Evaluated 1.96% 5,764.10 kg 394,610.29 30,198.28 50,305.20 82.43 475,113.77 20% 95,022.75 28,506.83 598,643.35
As Submitted 0.30% 862.40 Kg 55,961.14 15,343.35 1,534.34 84.46 72,838.83 20% 14,567.77 4,370.33 91,776.93
1047(6) Metal Structure Accessories (Steel Plates)
As Evaluated 0.30% 862.40 Kg 55,961.14 15,343.35 1,534.34 84.46 72,838.83 20% 14,567.77 4,370.33 91,776.93
As Submitted 0.05% 221.78 Kgs 8,821.08 3,945.79 394.58 59.34 13,161.45 20% 2,632.29 789.69 16,583.43
1047(7)b Metal Structure Accessories (Sagrods)
As Evaluated 0.05% 221.78 Kgs 8,821.08 3,945.79 394.58 59.34 13,161.45 20% 2,632.29 789.69 16,583.43
As Submitted 0.12% 484.95 Kgs 19,867.05 8,627.97 862.80 60.54 29,357.82 20% 5,871.56 1,761.47 36,990.85
1047(4) Metal Structure Accessories (Crossbracing)
As Evaluated 0.12% 484.95 Kgs 19,867.05 8,627.97 862.80 60.54 29,357.82 20% 5,871.56 1,761.47 36,990.85
As Submitted 0.04% 44.00 ea. 8,800.00 1,525.92 152.59 238.15 10,478.51 20% 2,095.70 628.71 13,202.92
1047(3)c Metal Structure Accessories (Turnbuckle)
As Evaluated 0.04% 44.00 ea. 8,800.00 1,525.92 152.59 238.15 10,478.51 20% 2,095.70 628.71 13,202.92
As Submitted 0.05% 55.00 L.m. 11,429.14 1,271.60 127.16 233.23 12,827.90 20% 2,565.58 769.67 16,163.15
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
As Evaluated 0.05% 55.00 L.m. 11,429.14 1,271.60 127.16 233.23 12,827.90 20% 2,565.58 769.67 16,163.15
As Submitted 0.02% 22.32 L.m. 4,710.57 516.04 51.60 236.48 5,278.21 20% 1,055.64 316.69 6,650.54
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
As Evaluated 0.02% 22.32 L.m. 4,710.57 516.04 51.60 236.48 5,278.21 20% 1,055.64 316.69 6,650.54
As Submitted 0.01% 10.00 L.m. 3,285.70 195.93 19.59 350.12 3,501.22 20% 700.24 210.07 4,411.53
1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)
As Evaluated 0.01% 10.00 L.m. 3,285.70 195.93 19.59 350.12 3,501.22 20% 700.24 210.07 4,411.53
As Submitted 1,215,497.38 187,850.61 158,817.34 1,562,165.33 312,433.06 93,729.92 1,968,328.31
Sub-Total C.6
As Evaluated 1,215,497.38 187,850.61 158,817.34 1,562,165.33 312,433.06 93,729.92 1,968,328.31
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT UNIT COST TOTAL % VALUE
FACILITIES FOR THE ENGINEER
C.7 Plumbing / Sanitary Works
As Submitted 0.28% 1.00 L.s. 47,937.75 18,410.24 1,841.02 68,189.01 68,189.01 20% 13,637.80 4,091.34 85,918.15
1001(8) Sewer Line Works
As Evaluated 0.28% 1.00 L.s. 47,937.75 18,410.24 1,841.02 68,189.01 68,189.01 20% 13,637.80 4,091.34 85,918.15
As Submitted 0.69% 1.00 L.s. 131,526.63 32,217.92 3,221.79 166,966.34 166,966.34 20% 33,393.27 10,017.98 210,377.59
1002(24) Cold Water lines
As Evaluated 0.69% 1.00 L.s. 131,526.63 32,217.92 3,221.79 166,966.34 166,966.34 20% 33,393.27 10,017.98 210,377.59
As Submitted 0.57% 1.00 L.s. 100,395.23 34,118.64 3,411.86 137,925.73 137,925.73 20% 27,585.15 8,275.54 173,786.42
1001(9) Storm Drainage and Downspout
As Evaluated 0.57% 1.00 L.s. 100,395.23 34,118.64 3,411.86 137,925.73 137,925.73 20% 27,585.15 8,275.54 173,786.42
As Submitted 0.97% 1.00 L.s. 194,454.21 36,992.00 3,699.20 235,145.41 235,145.41 20% 47,029.08 14,108.72 296,283.21
1002(4) Plumbing FIxtures
As Evaluated 0.97% 1.00 L.s. 194,454.21 36,992.00 3,699.20 235,145.41 235,145.41 20% 47,029.08 14,108.72 296,283.21
As Submitted 0.52% 1.00 L.s. 105,021.86 18,334.25 1,833.43 125,189.54 125,189.54 20% 25,037.91 7,511.37 157,738.82
1001(11) Septic Vault (Concrete / CHB)
As Evaluated 0.52% 1.00 L.s. 105,021.86 18,334.25 1,833.43 125,189.54 125,189.54 20% 25,037.91 7,511.37 157,738.82
As Submitted 0.13% 20.00 Ea 20,670.22 9,248.00 924.80 1,542.15 30,843.02 20% 6,168.60 1,850.58 38,862.20
1001(5)b Catch Basin (CHB)
As Evaluated 0.13% 20.00 Ea 20,670.22 9,248.00 924.80 1,542.15 30,843.02 20% 6,168.60 1,850.58 38,862.20
As Submitted 600,005.90 149,321.05 14,932.10 764,259.05 152,851.81 45,855.53 962,966.39
Sub-Total C.7
As Evaluated 600,005.90 149,321.05 14,932.10 764,259.05 152,851.81 45,855.53 962,966.39
As Submitted 4,981,801.84 2,026,175.53 565,738.62 7,573,715.99 1,514,743.17 454,422.96 9,542,882.12
TOTAL OF PART C
As Evaluated 4,981,801.84 2,026,175.53 565,738.62 7,573,715.99 1,514,743.17 454,422.96 9,542,882.12
PART D ELECTRICAL WORKS
As Submitted 0.55% 1.00 L.s. 113,801.34 17,234.59 1,723.46 132,759.39 132,759.39 20% 26,551.88 7,965.56 167,276.83
1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in)
As Evaluated 0.55% 1.00 L.s. 113,801.34 17,234.59 1,723.46 132,759.39 132,759.39 20% 26,551.88 7,965.56 167,276.83
As Submitted 0.80% 1.00 L.s. 170,229.40 22,141.44 2,214.14 194,584.98 194,584.98 20% 38,917.00 11,675.10 245,177.08
1101(33) Wires and Wiring Devices
As Evaluated 0.80% 1.00 L.s. 170,229.40 22,141.44 2,214.14 194,584.98 194,584.98 20% 38,917.00 11,675.10 245,177.08
As Submitted 1.04% 1.00 L.s. 244,155.30 6,890.40 689.04 251,734.74 251,734.74 20% 50,346.95 15,104.08 317,185.77
1102(1) Panel Board with Main Breaker
As Evaluated 1.04% 1.00 L.s. 244,155.30 6,890.40 689.04 251,734.74 251,734.74 20% 50,346.95 15,104.08 317,185.77
As Submitted 0.85% 1.00 L.s. 175,830.00 27,561.60 2,756.16 206,147.76 206,147.76 20% 41,229.55 12,368.87 259,746.18
1103(1) Lighting Fixtures & Lamps
As Evaluated 0.85% 1.00 L.s. 175,830.00 27,561.60 2,756.16 206,147.76 206,147.76 20% 41,229.55 12,368.87 259,746.18
As Submitted 704,016.04 73,828.03 7,382.80 785,226.87 157,045.38 47,113.61 989,385.86
TOTAL OF PART D
As Evaluated 704,016.04 73,828.03 7,382.80 785,226.87 157,045.38 47,113.61 989,385.86
PART E MECHANICAL WORKS
As Submitted 4.08% 1.00 Set 894,057.54 87,192.08 8,719.21 989,968.83 989,968.83 20% 197,993.77 59,398.13 1,247,360.73
1202(5) Fire Hose Cabinet Assembly
As Evaluated 4.08% 1.00 Set 894,057.54 87,192.08 8,719.21 989,968.83 989,968.83 20% 197,993.77 59,398.13 1,247,360.73
As Submitted 0.89% 1.00 L.s. 204,067.88 9,927.20 992.72 214,987.80 214,987.80 20% 42,997.56 12,899.27 270,884.63
1106(1) CCTV System
As Evaluated 0.89% 1.00 L.s. 204,067.88 9,927.20 992.72 214,987.80 214,987.80 20% 42,997.56 12,899.27 270,884.63
As Submitted 0.13% 1.00 L.s. 24,870.00 5,591.68 559.17 31,020.85 31,020.85 20% 6,204.17 1,861.25 39,086.27
1208(1) Fire Alarm System
As Evaluated 0.13% 1.00 L.s. 24,870.00 5,591.68 559.17 31,020.85 31,020.85 20% 6,204.17 1,861.25 39,086.27
As Submitted 1,122,995.42 102,710.96 10,271.10 1,235,977.48 247,195.50 74,158.65 1,557,331.63
TOTAL OF PART E
As Evaluated 1,122,995.42 102,710.96 10,271.10 1,235,977.48 247,195.50 74,158.65 1,557,331.63
As Submitted 16,157,961.03 4,374,207.31 1,852,988.92 22,385,157.26 4,477,031.43 1,343,109.43 28,205,298.12
TOTAL OF PART III
As Evaluated 16,157,961.03 4,374,207.31 1,852,988.92 22,385,157.26 4,477,031.43 1,343,109.43 28,205,298.12
As Submitted 16,157,961.03 4,374,207.31 1,852,988.92 22,385,157.26 4,477,031.43 1,343,109.43 28,205,298.12
TOTAL OF (Project ID)
As Evaluated 16,157,961.03 4,374,207.31 1,852,988.92 22,385,157.26 4,477,031.43 1,343,109.43 28,205,298.12
As Submitted 17,271,737.44 4,717,276.91 2,113,296.60 24,102,310.95 4,590,313.42 1,434,631.22 30,127,255.59
GRAND TOTAL
As Evaluated 17,271,737.44 4,717,276.91 2,113,296.60 24,102,310.95 4,590,313.42 1,434,631.22 30,127,255.59
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

PART I FACILITIES FOR THE ENGINEER

I.1.1 Offices and Laboratory for the Engineer

A.1.1(3) Construction of Field Office for the Engineer 1.00 1.00 L.s. 86,424.54 86,424.54 86,424.54 86,424.54 98,005.43 98,005.43 0.36% 0.36%

A.1.4(1) Provision of Progress Photographs 300.00 300.00 ea. 4,500.00 4,500.00 15.00 15.00 17.01 17.01 0.02% 0.02%

TOTAL OF PART I 90,924.54

PART II OTHER GENERAL REQUIREMENTS

B.3 Permits and Clearances 1.00 1.00 L.s. 66,877.26 66,877.26 66,877.26 66,877.26 70,221.12 70,221.12 0.28% 0.28%

B.5 Project Billboard/ Sign Board 1.00 1.00 Ea 3,832.28 3,832.28 3,832.28 3,832.28 4,828.68 4,828.68 0.02% 0.02%

B.7(2) Occupational Safety and Health Program 1.00 1.00 L.s. 1,315,519.61 1,315,519.61 1,315,519.61 1,315,519.61 1,491,799.24 1,491,799.24 5.43% 5.43%

B.9 Mobilization/Demobilization 1.00 1.00 L.s. 240,000.00 240,000.00 240,000.00 240,000.00 252,000.00 252,000.00 0.99% 0.99%

TOTAL OF PART II 1,626,229.15

Project ID

(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

PART A EARTHWORKS

800(2) Clearing and Grubbing 1.00 1.00 l.s. 336,712.44 336,712.44 336,712.44 336,712.44 424,257.68 424,257.68 1.39% 1.39%

801(1) Removal of Structure and Obstruction 1.00 1.00 L.s. 217,060.56 217,060.56 217,060.56 217,060.56 273,496.30 273,496.30 0.90% 0.90%

803(1)a Structure Excavation (Common Soil) 591.65 591.65 m³ 138,295.62 138,295.62 233.75 233.75 294.52 294.52 0.57% 0.57%

804(1)a Embankment from Structure Excavation 446.86 446.86 m³ 70,067.69 70,067.69 156.80 156.80 197.57 197.57 0.29% 0.29%

804(1)b Embankment from Borrow 88.50 88.50 m³ 141,934.10 141,934.10 1,603.78 1,603.78 2,020.76 2,020.76 0.59% 0.59%

804(4) Gravel Fill 83.79 83.79 m³ 164,770.50 164,770.50 1,966.47 1,966.47 2,477.75 2,477.75 0.68% 0.68%

807(1) Site Development 1.00 1.00 L.s. 4,156,689.66 4,156,689.66 4,156,689.66 4,156,689.66 5,237,428.97 5,237,428.97 17.15% 17.15%

TOTAL OF PART A 5,363,826.19

PART B PLAIN AND REINFORCED CONCRETE WORKS

900(8) Structural Concrete (27.58 Mpa @ 28 days) 409.05 409.05 m³ 2,618,022.15 2,618,022.15 6,400.25 6,400.25 8,064.31 8,064.31 10.80% 10.80%

902(1)a Reinforcing Steel (Deformed) Grade 40 22,277.83 22,277.83 Kg 1,144,157.57 1,144,157.57 51.36 51.36 64.71 64.71 4.72% 4.72%

902(1)b Reinforcing Steel (Deformed), Grade 60 50,570.57 50,570.57 Kg 2,651,924.40 2,651,924.40 52.44 52.44 66.07 66.07 10.94% 10.94%

903(2) Formworks & Falseworks 2,232.10 2,232.10 m² 1,150,602.23 1,150,602.23 515.48 515.48 649.50 649.50 4.75% 4.75%

TOTAL OF PART B 7,564,706.35

PART C FINISHING

C.1 Termite Control Works

1000(1) Soil Poisoning 205.29 205.29 L 64,378.41 64,378.41 313.60 313.60 81,116.79 81,116.79 0.27% 0.27%

Sub-Total C.1 64,378.41

C.2. Masonry Works


Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

1046(2)a1 FACILITIES
CHB Non Load Bearing (including FOR THE
Reinforcing ENGINEER
Steel), 100mm 331.76 331.76 m² 214,502.75 214,502.75 646.56 646.56 814.67 814.67 0.88% 0.88%

1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm 609.72 609.72 m² 587,025.22 587,025.22 962.78 962.78 1,213.10 1,213.10 2.42% 2.42%

Sub-Total C.2 801,527.97

C.3 Fabricated Materials

1010(4) Wooden Doors & Windows 1.00 1.00 L.s. 156,802.36 156,802.36 156,802.36 156,802.36 197,570.97 197,570.97 0.65% 0.65%

1010(2)a Door (Flush) 19.35 19.35 m² 28,923.42 28,923.42 1,494.75 1,494.75 1,883.39 1,883.39 0.12% 0.12%

1010(2)b Door (Wooden Panel) 43.20 43.20 m² 275,571.12 275,571.12 6,378.96 6,378.96 347,219.61 347,219.61 1.14% 1.14%

1003(17) Carpentry and Joinery Works 1.00 1.00 L.s. 48,241.92 48,241.92 48,241.92 48,241.92 60,784.82 60,784.82 0.20% 0.20%

1006(4) Steel Louver Door 9.36 9.36 m² 64,154.52 64,154.52 6,854.12 6,854.12 8,636.18 8,636.18 0.26% 0.26%

1005(1) Residential Casement Steel Window 116.64 116.64 m² 460,838.16 460,838.16 3,950.94 3,950.94 580,656.08 580,656.08 1.90% 1.90%

1009(1)a Jalousie Window (Glass) 48.00 48.00 m² 155,068.12 155,068.12 3,230.59 3,230.59 195,385.83 195,385.83 0.64% 0.64%

1005(6) Window Accessory 1.00 1.00 L.s. 81,865.70 81,865.70 81,865.70 81,865.70 103,150.78 103,150.78 0.34% 0.34%

1004(2) Finishing Hardware 1.00 1.00 L.s. 26,070.00 26,070.00 26,070.00 26,070.00 32,848.20 32,848.20 0.11% 0.11%

1051(6) Railing 1.00 1.00 L.s. 316,282.77 316,282.77 316,282.77 316,282.77 398,516.29 398,516.29 1.30% 1.30%

Sub-Total C.3 1,613,818.09

C.4 Finishing Works

1027(1) Cement Plaster Finish 2,665.57 2,665.57 m² 489,034.90 489,034.90 183.46 183.46 231.16 231.16 2.02% 2.02%

1021(1)a Cement Floor Finish (Plain) 1,113.78 1,113.78 m² 128,886.24 128,886.24 115.72 115.72 145.81 145.81 0.53% 0.53%

1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board) 597.46 597.46 m² 523,492.29 523,492.29 876.20 876.20 1,104.01 1,104.01 2.16% 2.16%

1003(11)a1 Fascia Board (19mm, Fiber Cement Board) 18.00 18.00 Lm 3,901.44 3,901.44 216.75 216.75 273.10 273.10 0.02% 0.02%

1038(1) Reflective Insulation 534.21 534.21 m² 106,126.77 106,126.77 198.66 198.66 250.31 250.31 0.44% 0.44%

1018(1) Glazed Tiles and Trims 196.24 196.24 m² 314,650.48 314,650.48 1,603.40 1,603.40 2,020.28 2,020.28 1.30% 1.30%

1018(2) Unlglazed Tiles 56.07 56.07 m² 53,989.06 53,989.06 962.89 962.89 1,213.24 1,213.24 0.22% 0.22%

1016(1)a Water Proofing Cement Base 437.02 437.02 m² 84,514.14 84,514.14 193.39 193.39 243.67 243.67 0.35% 0.35%

Sub-Total C.4 1,704,595.32

C.5 Painting Works

1032(1)a Painting Works (Masonry/Concrete) 3,076.67 3,076.67 m² 860,476.18 860,476.18 279.68 279.68 352.39 352.39 3.55% 3.55%

1032(1)b Painting Works (Wood Painting) 556.59 556.59 m² 153,069.71 153,069.71 275.01 275.01 346.52 346.52 0.63% 0.63%

1032(1)c Painting Works (Steel) 183.35 183.35 m² 49,425.93 49,425.93 269.57 269.57 339.66 339.66 0.20% 0.20%

Sub-Total C.5 1,062,971.82

C.6 Roof Framing and Roofing Works

1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk 587.75 587.75 m² 342,635.33 342,635.33 582.96 582.96 734.53 734.53 1.41% 1.41%

1047(2)a Structural Steel (Trusses) 6,900.12 6,900.12 Kg 596,972.29 596,972.29 86.52 86.52 109.01 109.01 2.46% 2.46%
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALAUTED AS SUBMITTED AS EVALAUTED

1047(2)b Structural Steel (Purlins) FACILITIES FOR THE ENGINEER 5,764.10 5,764.10 Kg 475,113.77 475,113.77 82.43 82.43 103.86 103.86 1.96% 1.96%

1047(6) Metal Structure Accessories (Steel Plates) 862.40 862.40 Kg 72,838.83 72,838.83 84.46 84.46 106.42 106.42 0.30% 0.30%

1047(7)b Metal Structure Accessories (Sagrods) 221.78 221.78 Kgs 13,161.45 13,161.45 59.34 59.34 74.77 74.77 0.05% 0.05%

1047(4) Metal Structure Accessories (Crossbracing) 484.95 484.95 Kgs 29,357.82 29,357.82 60.54 60.54 76.28 76.28 0.12% 0.12%

1047(3)c Metal Structure Accessories (Turnbuckle) 44.00 44.00 ea. 10,478.51 10,478.51 238.15 238.15 13,202.92 13,202.92 0.04% 0.04%

1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26) 55.00 55.00 L.m. 12,827.90 12,827.90 233.23 233.23 16,163.15 16,163.15 0.05% 0.05%

1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26) 22.32 22.32 L.m. 5,278.21 5,278.21 236.48 236.48 6,650.54 6,650.54 0.02% 0.02%

1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter) 10.00 10.00 L.m. 3,501.22 3,501.22 350.12 350.12 4,411.53 4,411.53 0.01% 0.01%

Sub-Total C.6 1,562,165.33

TOTAL OF PART C

C.7 PLUMBING/SANITARY WORKS

1001(8) Sewer Line Works 1.00 1.00 L.s. 68,189.01 68,189.01 68,189.01 68,189.01 85,918.15 85,918.15 0.28% 0.28%

1002(24) Cold Water lines 1.00 1.00 L.s. 166,966.34 166,966.34 166,966.34 166,966.34 210,377.59 210,377.59 0.69% 0.69%

1001(9) Storm Drainage and Downspout 1.00 1.00 L.s. 137,925.73 137,925.73 137,925.73 137,925.73 173,786.42 173,786.42 0.57% 0.57%

1002(4) Plumbing FIxtures 1.00 1.00 L.s. 235,145.41 235,145.41 235,145.41 235,145.41 296,283.21 296,283.21 0.97% 0.97%

1001(11) Septic Vault (Concrete / CHB) 1.00 1.00 L.s. 125,189.54 125,189.54 125,189.54 125,189.54 157,738.82 157,738.82 0.52% 0.52%

1001(5)b Catch Basin (CHB) 20.00 20.00 Ea 30,843.02 30,843.02 1,542.15 1,542.15 1,943.11 1,943.11 0.13% 0.13%

Sub-Total C.7 764,259.05

TOTAL OF PART C 7,573,715.99

PART D ELECTRICAL WORKS

1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in) 1.00 1.00 L.s. 132,759.39 132,759.39 132,759.39 132,759.39 167,276.83 167,276.83 0.55% 0.55%

1101(33) Wires and Wiring Devices 1.00 1.00 L.s. 194,584.98 194,584.98 194,584.98 194,584.98 245,177.08 245,177.08 0.80% 0.80%

1102(1) Panel Board with Main Breaker 1.00 1.00 L.s. 251,734.74 251,734.74 251,734.74 251,734.74 317,185.77 317,185.77 1.04% 1.04%

1103(1) Lighting Fixtures & Lamps 1.00 1.00 L.s. 206,147.76 206,147.76 206,147.76 206,147.76 259,746.18 259,746.18 0.85% 0.85%

TOTAL OF PART D 785,226.87

PART E MECHANICAL WORKS

1202(5) Fire Hose Cabinet Assembly 1.00 1.00 Set 989,968.83 989,968.83 989,968.83 989,968.83 1,247,360.73 1,247,360.73 4.08% 4.08%

1106(1) CCTV System 1.00 1.00 L.s. 214,987.80 214,987.80 214,987.80 214,987.80 270,884.63 270,884.63 0.89% 0.89%

1208(1) Fire Alarm System 1.00 1.00 L.s. 31,020.85 31,020.85 31,020.85 31,020.85 39,086.27 39,086.27 0.13% 0.13%

TOTAL OF PART D 1,235,977.48

TOTAL OF PART III 22,523,452.88

TOTAL OF (Project ID) 22,523,452.88

GRAND TOTAL 24,240,606.57 100.00% 100.00%


Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02-00
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP
ITEM NO. DESCRIPTION VAT TOTAL INDIRECT COST TOTAL COST
COST % VALUE
AS SUBMITTED 90,924.54 8.00% 7,273.96 4,909.93 12,183.89 103,108.43
PART I FACILITIES FOR THE ENGINEER
AS EVALUATED 90,924.54 8.00% 7,273.96 4,909.93 12,183.89 103,108.43
AS SUBMITTED 1,626,229.15 0.00% 106,008.03 86,611.86 192,619.89 1,818,849.04
PART II OTHER GENERAL REQUIREMENTS
AS EVALUATED 1,626,229.15 0.00% 106,008.03 86,611.86 192,619.89 1,818,849.04

(Project ID)
(Project Component ID - Description)

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS

AS SUBMITTED 5,225,530.57 20.00% 1,045,106.11 313,531.84 1,358,637.95 6,584,168.52


PART A EARTHWORKS
AS EVALUATED 5,225,530.57 20.00% 1,045,106.11 313,531.84 1,358,637.95 6,584,168.52
AS SUBMITTED 7,564,706.35 20.00% 1,512,941.27 453,882.37 1,966,823.64 9,531,529.99
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS EVALUATED 7,564,706.35 20.00% 1,512,941.27 453,882.37 1,966,823.64 9,531,529.99
AS SUBMITTED 7,573,715.99 20.00% 1,514,743.17 454,422.96 1,969,166.13 9,542,882.12
PART C FINISHING
AS EVALUATED 7,573,715.99 20.00% 1,514,743.17 454,422.96 1,969,166.13 9,542,882.12
AS SUBMITTED 785,226.87 20.00% 157,045.38 47,113.61 204,158.99 989,385.86
PART D ELECTRICAL WORKS
AS EVALUATED 785,226.87 20.00% 157,045.38 47,113.61 204,158.99 989,385.86
AS SUBMITTED 1,235,977.48 20.00% 247,195.50 74,158.65 321,354.15 1,557,331.63
PART E MECHANICAL WORKS
AS EVALUATED 1,235,977.48 20.00% 247,195.50 74,158.65 321,354.15 1,557,331.63
AS SUBMITTED 22,385,157.26 20.00% 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
TOTAL OF PART III
AS EVALUATED 22,385,157.26 20.00% 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
AS SUBMITTED 22,385,157.26 20.00% 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
TOTAL OF (Project ID)
AS EVALUATED 22,385,157.26 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
AS SUBMITTED 24,102,310.95 4,590,313.42 1,434,631.22 6,024,944.64 30,127,255.59
TOTAL
AS EVALUATED 24,102,310.95 4,590,313.42 1,434,631.22 6,024,944.64 30,127,255.59

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Evaluated by: Approved:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN MA. CHYMBELIN D. IBAL ROGELIO S. CRESPO
Architect II Chief, Planning & Design Section Chief, Construction Section Assistant District Engineer District Engineer
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART I FACILITIES FOR THE ENGINEER
AS SUBMITTED 1.00 L.s. 86,424.54 8.00% 6,913.96 4,666.93 11,580.89 98,005.43 98,005.43
A.1.1(3) Construction of Field Office for the Engineer
AS EVALUATED 1.00 L.s. 86,424.54 8.00% 6,913.96 4,666.93 11,580.89 98,005.43 98,005.43
AS SUBMITTED 300.00 ea. 4,500.00 8.00% 360.00 243.00 603.00 5,103.00 17.01
A.1.4(1) Provision of Progress Photographs
AS EVALUATED 300.00 ea. 4,500.00 8.00% 360.00 243.00 603.00 5,103.00 17.01
AS SUBMITTED 90,924.54 7,273.96 4,909.93 12,183.89 103,108.43
TOTAL OF PART I
AS EVALUATED 90,924.54 7,273.96 4,909.93 12,183.89 103,108.43
PART II OTHER GENERAL REQUIREMENTS
AS SUBMITTED 1.00 L.s. 66,877.26 0.00% - 3,343.86 3,343.86 70,221.12 70,221.12
B.3 Permits and Clearances
AS EVALUATED 1.00 L.s. 66,877.26 0.00% - 3,343.86 3,343.86 70,221.12 70,221.12
AS SUBMITTED 1.00 Ea 3,832.28 20.00% 766.46 229.94 996.40 4,828.68 4,828.68
B.5 Project Billboard/ Sign Board
AS EVALUATED 1.00 Ea 3,832.28 20.00% 766.46 229.94 996.40 4,828.68 4,828.68
AS SUBMITTED 1.00 L.s. 1,315,519.61 8.00% 105,241.57 71,038.06 176,279.63 1,491,799.24 1,491,799.24
B.7(2) Occupational Safety and Health Program
AS EVALUATED 1.00 L.s. 1,315,519.61 8.00% 105,241.57 71,038.06 176,279.63 1,491,799.24 1,491,799.24
AS SUBMITTED 1.00 L.s. 240,000.00 0.00% - 12,000.00 12,000.00 252,000.00 252,000.00
B.9 Mobilization/Demobilization
AS EVALUATED 1.00 L.s. 240,000.00 0.00% - 12,000.00 12,000.00 252,000.00 252,000.00
AS SUBMITTED 1,626,229.15 106,008.03 86,611.86 192,619.89 1,818,849.04
TOTAL OF PART II
AS EVALUATED 1,626,229.15 106,008.03 86,611.86 192,619.89 1,818,849.04
Project ID
(Project Component ID - Description)
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
AS SUBMITTED 1.00 l.s. 336,712.44 20.00% 67,342.49 20,202.75 87,545.24 424,257.68 424,257.68
800(2) Clearing and Grubbing
AS EVALUATED 1.00 l.s. 336,712.44 20.00% 67,342.49 20,202.75 87,545.24 424,257.68 424,257.68
AS SUBMITTED 1.00 L.s. 217,060.56 20.00% 43,412.11 13,023.63 56,435.74 273,496.30 273,496.30
801(1) Removal of Structure and Obstruction
AS EVALUATED 1.00 L.s. 217,060.56 20.00% 43,412.11 13,023.63 56,435.74 273,496.30 273,496.30
AS SUBMITTED 591.65 m³ 138,295.62 20.00% 27,659.12 8,297.74 35,956.86 174,252.48 294.52
803(1)a Structure Excavation (Common Soil)
AS EVALUATED 591.65 m³ 138,295.62 20.00% 27,659.12 8,297.74 35,956.86 174,252.48 294.52
AS SUBMITTED 446.86 m³ 70,067.69 20.00% 14,013.54 4,204.06 18,217.60 88,285.29 197.57
804(1)a Embankment from Roadway/Structure Excavation
AS EVALUATED 446.86 m³ 70,067.69 20.00% 14,013.54 4,204.06 18,217.60 88,285.29 197.57
AS SUBMITTED 88.50 m³ 141,934.10 20.00% 28,386.82 8,516.05 36,902.87 178,836.97 2,020.76
804(1)b Embankment from Borrow
AS EVALUATED 88.50 m³ 141,934.10 20.00% 28,386.82 8,516.05 36,902.87 178,836.97 2,020.76
AS SUBMITTED 83.79 m³ 164,770.50 20.00% 32,954.10 9,886.23 42,840.33 207,610.83 2,477.75
804(4) Gravel Fill
AS EVALUATED 83.79 m³ 164,770.50 20.00% 32,954.10 9,886.23 42,840.33 207,610.83 2,477.75
AS SUBMITTED 1.00 l.s. 4,156,689.66 20.00% 831,337.93 249,401.38 1,080,739.31 5,237,428.97 5,237,428.97
807(1) Site Development
AS EVALUATED 1.00 l.s. 4,156,689.66 20.00% 831,337.93 249,401.38 1,080,739.31 5,237,428.97 5,237,428.97
AS SUBMITTED 5,225,530.57 1,045,106.11 313,531.84 1,358,637.95 6,584,168.52
TOTAL OF PART A
AS EVALUATED 5,225,530.57 1,045,106.11 313,531.84 1,358,637.95 6,584,168.52
PART B PLAIN AND REINFORCED CONCRETE WORKS
AS SUBMITTED 409.05 m³ 2,618,022.15 20.00% 523,604.43 157,081.33 680,685.76 3,298,707.91 8,064.31
900(8) Structural Concrete (27.58 Mpa @ 28 days)
AS EVALUATED 409.05 m³ 2,618,022.15 20.00% 523,604.43 157,081.33 680,685.76 3,298,707.91 8,064.31
AS SUBMITTED 22,277.83 Kg 1,144,157.57 20.00% 228,831.51 68,649.45 297,480.96 1,441,638.53 64.71
902(1)a Reinforcing Steel (Deformed) Grade 40
AS EVALUATED 22,277.83 Kg 1,144,157.57 20.00% 228,831.51 68,649.45 297,480.96 1,441,638.53 64.71
AS SUBMITTED 50,570.57 Kg 2,651,924.40 20.00% 530,384.88 159,115.46 689,500.34 3,341,424.74 66.07
902(1)b Reinforcing Steel (Deformed), Grade 60
AS EVALUATED 50,570.57 Kg 2,651,924.40 20.00% 530,384.88 159,115.46 689,500.34 3,341,424.74 66.07
AS SUBMITTED 2,232.10 m² 1,150,602.23 20.00% 230,120.45 69,036.13 299,156.58 1,449,758.81 649.50
903(2) Formworks & Falseworks
AS EVALUATED 2,232.10 m² 1,150,602.23 20.00% 230,120.45 69,036.13 299,156.58 1,449,758.81 649.50
AS SUBMITTED 7,564,706.35 1,512,941.27 453,882.37 1,966,823.64 9,531,529.99
TOTAL OF PART B
AS EVALUATED 7,564,706.35 1,512,941.27 453,882.37 1,966,823.64 9,531,529.99

Preparation and Submission: Evaluation:


Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART C FACILITIES FOR THE
FINISHING ENGINEER
WORKS
AS SUBMITTED 205.29 L 64,378.41 20.00% 12,875.68 3,862.70 16,738.38 81,116.79 395.13
1000(1) Soil Poisoning
AS EVALUATED 205.29 L 64,378.41 20.00% 12,875.68 3,862.70 16,738.38 81,116.79 395.13
AS SUBMITTED 331.76 m² 214,502.75 20.00% 42,900.55 12,870.17 55,770.72 270,273.47 814.67
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel), 100mm
AS EVALUATED 331.76 m² 214,502.75 20.00% 42,900.55 12,870.17 55,770.72 270,273.47 814.67
AS SUBMITTED 609.72 m² 587,025.22 20.00% 117,405.04 35,221.51 152,626.55 739,651.77 1,213.10
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel), 150mm
AS EVALUATED 609.72 m² 587,025.22 20.00% 117,405.04 35,221.51 152,626.55 739,651.77 1,213.10
AS SUBMITTED 1.00 L.s. 156,802.36 20.00% 31,360.47 9,408.14 40,768.61 197,570.97 197,570.97
1010(4) Wooden Doors & Windows
AS EVALUATED 1.00 L.s. 156,802.36 20.00% 31,360.47 9,408.14 40,768.61 197,570.97 197,570.97
AS SUBMITTED 19.35 m² 28,923.42 20.00% 5,784.68 1,735.41 7,520.09 36,443.51 1,883.39
1010(2)a Door (Flush)
AS EVALUATED 19.35 m² 28,923.42 20.00% 5,784.68 1,735.41 7,520.09 36,443.51 1,883.39
AS SUBMITTED 43.20 m² 275,571.12 20.00% 55,114.22 16,534.27 71,648.49 347,219.61 8,037.49
1010(2)b Door (Wooden Panel)
AS EVALUATED 43.20 m² 275,571.12 20.00% 55,114.22 16,534.27 71,648.49 347,219.61 8,037.49
AS SUBMITTED 1.00 L.s. 48,241.92 20.00% 9,648.38 2,894.52 12,542.90 60,784.82 60,784.82
1003(17) Carpentry and Joinery Works
AS EVALUATED 1.00 L.s. 48,241.92 20.00% 9,648.38 2,894.52 12,542.90 60,784.82 60,784.82
AS SUBMITTED 9.36 m² 64,154.52 20.00% 12,830.90 3,849.27 16,680.17 80,834.69 8,636.18
1006(4) Steel Louver Door
AS EVALUATED 9.36 m² 64,154.52 20.00% 12,830.90 3,849.27 16,680.17 80,834.69 8,636.18
AS SUBMITTED 116.64 m² 460,838.16 20.00% 92,167.63 27,650.29 119,817.92 580,656.08 4,978.19
1005(1) Residential Casement Steel Window
AS EVALUATED 116.64 m² 460,838.16 20.00% 92,167.63 27,650.29 119,817.92 580,656.08 4,978.19
AS SUBMITTED 1.00 L.s. 81,865.70 20.00% 16,373.14 4,911.94 21,285.08 103,150.78 103,150.78
1005(6) Window Accessory
AS EVALUATED 1.00 L.s. 81,865.70 20.00% 16,373.14 4,911.94 21,285.08 103,150.78 103,150.78
AS SUBMITTED 48.00 m² 155,068.12 20.00% 31,013.62 9,304.09 40,317.71 195,385.83 4,070.54
1009(1)a Jalousie Window (Glass)
AS EVALUATED 48.00 m² 155,068.12 20.00% 31,013.62 9,304.09 40,317.71 195,385.83 4,070.54
AS SUBMITTED 1.00 L.s. 26,070.00 20.00% 5,214.00 1,564.20 6,778.20 32,848.20 32,848.20
1004(2) Finishing Hardware
AS EVALUATED 1.00 L.s. 26,070.00 20.00% 5,214.00 1,564.20 6,778.20 32,848.20 32,848.20
AS SUBMITTED 1.00 L.s. 316,282.77 20.00% 63,256.55 18,976.97 82,233.52 398,516.29 398,516.29
1051(6) Railing
AS EVALUATED 1.00 L.s. 316,282.77 20.00% 63,256.55 18,976.97 82,233.52 398,516.29 398,516.29
AS SUBMITTED 2,665.57 m² 489,034.90 20.00% 97,806.98 29,342.09 127,149.07 616,183.97 231.16
1027(1) Cement Plaster Finish
AS EVALUATED 2,665.57 m² 489,034.90 20.00% 97,806.98 29,342.09 127,149.07 616,183.97 231.16
AS SUBMITTED 1,113.78 m² 128,886.24 20.00% 25,777.25 7,733.17 33,510.42 162,396.66 145.81
1021(1)a Cement Floor Finish (Plain)
AS EVALUATED 1,113.78 m² 128,886.24 20.00% 25,777.25 7,733.17 33,510.42 162,396.66 145.81
AS SUBMITTED 597.46 m² 523,492.29 20.00% 104,698.46 31,409.54 136,108.00 659,600.29 1,104.01
1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
AS EVALUATED 597.46 m² 523,492.29 20.00% 104,698.46 31,409.54 136,108.00 659,600.29 1,104.01
AS SUBMITTED 18.00 Lm 3,901.44 20.00% 780.29 234.09 1,014.38 4,915.82 273.10
1003(11)a1 Fascia Board (19mm, Fiber Cement Board)
AS EVALUATED 18.00 Lm 3,901.44 20.00% 780.29 234.09 1,014.38 4,915.82 273.10
AS SUBMITTED 534.21 m² 106,126.77 20.00% 21,225.35 6,367.61 27,592.96 133,719.73 250.31
1038(1) Reflective Insulation
AS EVALUATED 534.21 m² 106,126.77 20.00% 21,225.35 6,367.61 27,592.96 133,719.73 250.31
AS SUBMITTED 196.24 m² 314,650.48 20.00% 62,930.10 18,879.03 81,809.13 396,459.61 2,020.28
1018(1) Glazed Tiles and Trims
AS EVALUATED 196.24 m² 314,650.48 20.00% 62,930.10 18,879.03 81,809.13 396,459.61 2,020.28
AS SUBMITTED 56.07 m² 53,989.06 20.00% 10,797.81 3,239.34 14,037.15 68,026.21 1,213.24
1018(2) Unlglazed Tiles
AS EVALUATED 56.07 m² 53,989.06 20.00% 10,797.81 3,239.34 14,037.15 68,026.21 1,213.24
AS SUBMITTED 437.02 m² 84,514.14 20.00% 16,902.83 5,070.85 21,973.68 106,487.82 243.67
1016(1)a Water Proofing Cement Base
AS EVALUATED 437.02 m² 84,514.14 20.00% 16,902.83 5,070.85 21,973.68 106,487.82 243.67
AS SUBMITTED 3,076.67 m² 860,476.18 20.00% 172,095.24 51,628.57 223,723.81 1,084,199.99 352.39
1032(1)a Painting Works (Masonry/Concrete)
AS EVALUATED 3,076.67 m² 860,476.18 20.00% 172,095.24 51,628.57 223,723.81 1,084,199.99 352.39

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
FACILITIES FOR THE ENGINEER AS SUBMITTED 556.59 m² 153,069.71 20.00% 30,613.94 9,184.18 39,798.12 192,867.83 346.52
1032(1)b Painting Works (Wood Painting)
AS EVALUATED 556.59 m² 153,069.71 20.00% 30,613.94 9,184.18 39,798.12 192,867.83 346.52
AS SUBMITTED 183.35 m² 49,425.93 20.00% 9,885.19 2,965.56 12,850.75 62,276.68 339.66
1032(1)c Painting Works (Steel)
AS EVALUATED 183.35 m² 49,425.93 20.00% 9,885.19 2,965.56 12,850.75 62,276.68 339.66
AS SUBMITTED 587.75 m² 342,635.33 20.00% 68,527.07 20,558.12 89,085.19 431,720.52 734.53
1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
AS EVALUATED 587.75 m² 342,635.33 20.00% 68,527.07 20,558.12 89,085.19 431,720.52 734.53
AS SUBMITTED 6,900.12 Kg 596,972.29 20.00% 119,394.46 35,818.34 155,212.80 752,185.09 109.01
1047(2)a Structural Steel (Trusses)
AS EVALUATED 6,900.12 Kg 596,972.29 20.00% 119,394.46 35,818.34 155,212.80 752,185.09 109.01
AS SUBMITTED 5,764.10 Kg 475,113.77 20.00% 95,022.75 28,506.83 123,529.58 598,643.35 103.86
1047(2)b Structural Steel (Purlins)
AS EVALUATED 5,764.10 Kg 475,113.77 20.00% 95,022.75 28,506.83 123,529.58 598,643.35 103.86
AS SUBMITTED 862.40 Kg 72,838.83 20.00% 14,567.77 4,370.33 18,938.10 91,776.93 106.42
1047(6) Metal Structure Accessories (Steel Plates)
AS EVALUATED 862.40 Kg 72,838.83 20.00% 14,567.77 4,370.33 18,938.10 91,776.93 106.42
AS SUBMITTED 221.78 Kgs 13,161.45 20.00% 2,632.29 789.69 3,421.98 16,583.43 74.77
1047(7)b Metal Structure Accessories (Sagrods)
AS EVALUATED 221.78 Kgs 13,161.45 20.00% 2,632.29 789.69 3,421.98 16,583.43 74.77
AS SUBMITTED 484.95 Kgs 29,357.82 20.00% 5,871.56 1,761.47 7,633.03 36,990.85 76.28
1047(4) Metal Structure Accessories (Crossbracing)
AS EVALUATED 484.95 Kgs 29,357.82 20.00% 5,871.56 1,761.47 7,633.03 36,990.85 76.28
AS SUBMITTED 44.00 ea. 10,478.51 20.00% 2,095.70 628.71 2,724.41 13,202.92 300.07
1047(3)c Metal Structure Accessories (Turnbuckle)
AS EVALUATED 44.00 ea. 10,478.51 20.00% 2,095.70 628.71 2,724.41 13,202.92 300.07
AS SUBMITTED 55.00 L.m. 12,827.90 20.00% 2,565.58 769.67 3,335.25 16,163.15 293.88
1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
AS EVALUATED 55.00 L.m. 12,827.90 20.00% 2,565.58 769.67 3,335.25 16,163.15 293.88
AS SUBMITTED 22.32 L.m. 5,278.21 20.00% 1,055.64 316.69 1,372.33 6,650.54 297.96
1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
AS EVALUATED 22.32 L.m. 5,278.21 20.00% 1,055.64 316.69 1,372.33 6,650.54 297.96
AS SUBMITTED 10.00 L.m. 3,501.22 20.00% 700.24 210.07 910.31 4,411.53 441.15
1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)
AS EVALUATED 10.00 L.m. 3,501.22 20.00% 700.24 210.07 910.31 4,411.53 441.15
AS SUBMITTED 1.00 L.s. 68,189.01 20.00% 13,637.80 4,091.34 17,729.14 85,918.15 85,918.15
1001(8) Sewer Line Works
AS EVALUATED 1.00 L.s. 68,189.01 20.00% 13,637.80 4,091.34 17,729.14 85,918.15 85,918.15
AS SUBMITTED 1.00 L.s. 166,966.34 20.00% 33,393.27 10,017.98 43,411.25 210,377.59 210,377.59
1002(24) Cold Water lines
AS EVALUATED 1.00 L.s. 166,966.34 20.00% 33,393.27 10,017.98 43,411.25 210,377.59 210,377.59
AS SUBMITTED 1.00 L.s. 137,925.73 20.00% 27,585.15 8,275.54 35,860.69 173,786.42 173,786.42
1001(9) Storm Drainage and Downspout
AS EVALUATED 1.00 L.s. 137,925.73 20.00% 27,585.15 8,275.54 35,860.69 173,786.42 173,786.42
AS SUBMITTED 1.00 L.s. 235,145.41 20.00% 47,029.08 14,108.72 61,137.80 296,283.21 296,283.21
1002(4) Plumbing FIxtures
AS EVALUATED 1.00 L.s. 235,145.41 20.00% 47,029.08 14,108.72 61,137.80 296,283.21 296,283.21
AS SUBMITTED 1.00 L.s. 125,189.54 20.00% 25,037.91 7,511.37 32,549.28 157,738.82 157,738.82
1001(11) Septic Vault (Concrete / CHB)
AS EVALUATED 1.00 L.s. 125,189.54 20.00% 25,037.91 7,511.37 32,549.28 157,738.82 157,738.82
AS SUBMITTED 20.00 Ea 30,843.02 20.00% 6,168.60 1,850.58 8,019.18 38,862.20 1,943.11
1001(5)b Catch Basin (CHB)
AS EVALUATED 20.00 Ea 30,843.02 20.00% 6,168.60 1,850.58 8,019.18 38,862.20 1,943.11
AS SUBMITTED 7,573,715.99 1,514,743.17 454,422.96 1,969,166.13 9,542,882.12
TOTAL OF PART C
AS EVALUATED 7,573,715.99 1,514,743.17 454,422.96 1,969,166.13 9,542,882.12

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Republic of the Philippines
Department of Public Works and Highways
QUEZON II DISTRICT ENGINEERING OFFICE
REGION IV-A
Lucena City
FORM ABC-2015-02A-00
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 300 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART D FACILITIES FOR THE
ELECTRICAL ENGINEER
WORKS
AS SUBMITTED 1.00 L.s. 132,759.39 20.00% 26,551.88 7,965.56 34,517.44 167,276.83 167,276.83
1100(10) Conduit, Boxes, and Fittings (Conduit Works / Conduit Rough-in)
AS EVALUATED 1.00 L.s. 132,759.39 20.00% 26,551.88 7,965.56 34,517.44 167,276.83 167,276.83
AS SUBMITTED 1.00 L.s. 194,584.98 20.00% 38,917.00 11,675.10 50,592.10 245,177.08 245,177.08
1101(33) Wires and Wiring Devices AS EVALUATED 1.00 L.s. 194,584.98 20.00% 38,917.00 11,675.10 50,592.10 245,177.08 245,177.08
AS SUBMITTED 1.00 L.s. 251,734.74 20.00% 50,346.95 15,104.08 65,451.03 317,185.77 317,185.77
1102(1) Panel Board with Main Breaker
AS EVALUATED 1.00 L.s. 251,734.74 20.00% 50,346.95 15,104.08 65,451.03 317,185.77 317,185.77
AS SUBMITTED 1.00 L.s. 206,147.76 20.00% 41,229.55 12,368.87 53,598.42 259,746.18 259,746.18
1103(1) Lighting Fixtures & Lamps
AS EVALUATED 1.00 L.s. 206,147.76 20.00% 41,229.55 12,368.87 53,598.42 259,746.18 259,746.18
AS SUBMITTED 785,226.87 157,045.38 47,113.61 204,158.99 989,385.86
TOTAL OF PART D
AS EVALUATED 785,226.87 157,045.38 47,113.61 204,158.99 989,385.86
PART E MECHANICAL WORKS
AS SUBMITTED 1.00 Set 989,968.83 20.00% 197,993.77 59,398.13 257,391.90 1,247,360.73 1,247,360.73
1202(5) Fire Hose Cabinet Assembly
AS EVALUATED 1.00 Set 989,968.83 20.00% 197,993.77 59,398.13 257,391.90 1,247,360.73 1,247,360.73
AS SUBMITTED 1.00 L.s. 214,987.80 20.00% 42,997.56 12,899.27 55,896.83 270,884.63 270,884.63
1106(1) CCTV System
AS EVALUATED 1.00 L.s. 214,987.80 20.00% 42,997.56 12,899.27 55,896.83 270,884.63 270,884.63
AS SUBMITTED 1.00 L.s. 31,020.85 20.00% 6,204.17 1,861.25 8,065.42 39,086.27 39,086.27
1208(1) Fire Alarm System
AS EVALUATED 1.00 L.s. 31,020.85 20.00% 6,204.17 1,861.25 8,065.42 39,086.27 39,086.27
AS SUBMITTED 1,235,977.48 247,195.50 74,158.65 321,354.15 1,557,331.63
TOTAL OF PART E
AS EVALUATED 1,235,977.48 247,195.50 74,158.65 321,354.15 1,557,331.63
AS SUBMITTED 22,385,157.26 4,477,031.43 1,343,109.43 6,141,495.01 30,083,983.90
TOTAL OF PART III
AS EVALUATED 22,385,157.26 4,477,031.43 1,343,109.43 6,141,495.01 30,083,983.90
AS SUBMITTED 22,385,157.26 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
TOTAL OF (Project ID)
AS EVALUATED 22,385,157.26 4,477,031.43 1,343,109.43 5,820,140.86 28,205,298.12
AS SUBMITTED 24,102,310.95 4,590,313.42 1,434,631.22 6,024,944.64 30,127,255.59
GRAND TOTAL
AS EVALUATED 24,102,310.95 4,590,313.42 1,434,631.22 6,024,944.64 30,127,255.59

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

CESAR ANTONIO P. JADER FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Architect II Chief, Planning & Design Section Chief, Construction Section
Planning & Design Section
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon
FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Backhoe 0.80 m3 1 31
3
2 Dump Truck 12 yd 2 32
3 Plate Compactor 5 hp 1 33
4 Concrete Vibrator 5 amp 2 34
5 Pumpcrete - 1 35
6 One (1) Bagger Mixer - 1 36
7 Bar Cutter - 1 37
8 Bar Bender - 1 38
9 Welding Machine 500 amp 2 39
10 Cutting Outfit - 1 40
11 Truck Mounted Crane 20 - 25 mt 1 41
12 Drilling Machine - 1 42
13 Power Throwel - 1 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
25 55
26 56
27 57
30 60
SUB-TOTAL SUB-TOTAL
TOTAL
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.1(3) Construction of Field Office for the Engineer


Unit of Measurement : l.s.
Output per Hour - As Evaluated : 1.00
Output per Hour - As Submitted : 1.00

No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor
a. Construction Foreman 1 40.00 101.45 4,058.00
b. Skilled Laborer 3 40.00 73.29 8,794.80
c. Unskilled Laborer 5 40.00 56.46 11,292.00

Labor Sub - Total for A1 (As Submitted) 24,144.80


A2. Labor
a. Construction Foreman 1 40.00 101.45 4,058.00
b. Skilled Laborer 3 40.00 73.29 8,794.80
c. Unskilled Laborer 5 40.00 56.46 11,292.00

Labor Sub - Total for A2 (As Evaluated) 24,144.80


No of No. of
Name and Capacity Monthly Rate Amount (PhP)
B1. Unit/s Hr/s
Equipment

Equipment Sub - Total for B1 (As Submitted)


Equipment
B2.
Equipment Sub - Total for B2 (As Evaluated)
C1. Total (A1 + B1) 24,144.80
C2. Total (A2 + B2) 24,144.80
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 24,144.80
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 24,144.80
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1. Materials
a. Plywood Marine (0.00625m x pc. 15.00 500.00 7,500.00
b. Good Lumber bd.ft. 309.55 60.00 18,572.83
c. GI Sheet Plain Gauge 26 x 8' (0.551 mm thk) sq.m. 13.00 255.00 3,315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Door Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel G-1 cu.m. 3.00 1,587.58 4,762.74
h. Sand cu.m. 2.00 1,307.58 2,615.16
i. Reinforcing Steel Bar Grade 40 kg. 95.82 41.00 3,928.46
j. CHB Ordinary (101mm x 203mm x 406mm) pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 W Flourescent LF set 1.00 255.00 255.00
n. Duplex Conv. Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board Cabinet set 1.00 500.00 500.00
q. #16 GI Tie Wire kgs. 2.00 80.00 160.00
r. Misc. (Forms, CWN, Bolts, Electrical Wires, Chairs, Table etc.) lot 1.00 7,070.05 7,070.05

Equipment Sub - Total for F1 (As Submitted) 62,279.74


F2. Materials
a. Plywood Marine (0.00625m x pc. 15.00 500.00 7,500.00
b. Good Lumber bd.ft. 309.55 60.00 18,572.83
c. GI Sheet Plain Gauge 26 x 8' sq.m. 13.00 255.00 3,315.00
d. 2" x 4" Door Hinges pc. 3.00 70.00 210.00
e. 2" x 3" Door Hinges pc. 8.00 41.00 328.00
f. Portland Cement bag 37.00 250.00 9,250.00
g. Gravel G-1 cu.m. 3.00 1,587.58 4,762.74
h. Sand cu.m. 2.00 1,307.58 2,615.16
i. Reinforcing Steel Bar Grade kg. 95.82 41.00 3,928.46
j. CHB Ordinary (101mm x pcs. 150.00 15.00 2,250.00
k. Fascia Board (1/2 x 12" Marine l.m. 8.40 93.75 787.50
l. Ridge Roll l.m. 4.20 100.00 420.00
m. 20 W Flourescent LF set 1.00 255.00 255.00
n. Duplex Conv. Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board Cabinet set 1.00 500.00 500.00
q. #16 GI Tie Wire kgs. 2.00 80.00 160.00
r. Misc. (Forms, CWN, Bolts, Electrical Wires, Chairs, Table etc.) lot 1.00 7,070.05 7,070.05

Materials Sub - Total for F2 (As Evaluated) 62,279.74


G1. Direct Unit Cost (E1 + F1) - As Submitted 86,424.54
G2. Direct Unit Cost (E2 + F2) - As Evaluated 86,424.54
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6,913.96
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6,913.96
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4,666.93
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4,666.93
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 98,005.43
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 98,005.43

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : ea.
Output per Hour - As Evaluated : 1.00
Output per Hour - As Submitted : 1.00

No. of No. of
Designation Hourly Rate Amount (PhP)
A1. Person/s Hr/s
Labor

Labor Sub - Total for A1 (As Submitted) -


A2. Labor

Labor Sub - Total for A2 (As Evaluated) -


No of No. of
Name and Capacity Monthly Rate Amount (PhP)
B1. Unit/s Hr/s
Equipment

Equipment Sub - Total for B1 (As Submitted)


Equipment
B2.
Equipment Sub - Total for B2 (As Evaluated)
C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 ea.
D2. Output per our - As Evaluated = 1 ea.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1. Materials

a. Developing pc. 1.00 15.00 15.00

Equipment Sub - Total for F1 (As Submitted) 15.00


F2. Materials

a. Developing pc. 1.00 15.00 15.00

Materials Sub - Total for F2 (As Evaluated) 15.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 15.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 15.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 1.20
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 1.20
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 0.81
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 0.81
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 17.01
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 17.01

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.3 Permits and Clearances


Unit of Measurement : L.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Labor -
b. Skilled Laborer -
c. Unskilled Laborer -
-
Sub - Total for A1 (As Submitted) -
A2. Labor
a. Construction Foreman -
b. Skilled Laborer -
c. Unskilled Laborer -

Sub - Total for A2 (As Evaluated) -


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Sub - Total for B1 (As Submitted) -


B2
Equipment

Sub - Total for B2 (As Evaluated) -


C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1
Materials

a. Fire Safety Evaluation Clearance Fee L.s. 1.00 30,127.26 30,127.26


b. Brgy. Clearance For Construction Fee L.s. 1.00 500.00 500.00
c. Professional Fee L.s. 1.00 10,000.00 10,000.00
d. Blue Print 20" x 30 " Sheet 250.00 25.00 6,250.00
e. Business Tax L.s. 1.00 20,000.00 20,000.00

Sub - Total for F1 (As Submitted) 66,877.26


Materials
F2
a. Fire Safety Evaluation Clearance Fee L.s. 1.00 30,127.26 30,127.26
b. Brgy. Clearance For Construction Fee L.s. 1.00 500.00 500.00
c. Professional Fee L.s. 1.00 10,000.00 10,000.00
d. Blue Print 20" x 30 " Sheet 250.00 25.00 6,250.00
e. Business Tax L.s. 1.00 20,000.00 20,000.00

Sub - Total for F2 (As Evaluated) 66,877.26


G1. Direct Unit Cost (E1 + F1) - As Submitted 66,877.26
G2. Direct Unit Cost (E2 + F2) - As Evaluated 66,877.26
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 0% of G1 -
I2. Contractor's Profit (CP) - As Evaluated 0% of G2 -
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3,343.86
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3,343.86
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 70,221.12
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 70,221.12

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.5 Project Billboard/ Sign Board


Unit of Measurement : ea
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 4.00 101.45 405.80


b. Skilled Laborer 1 4.00 73.29 293.16
c. Unskilled Laborer 1 4.00 56.46 225.84
.
Sub - Total for A1 (As Submitted) 924.80
A2. Labor
a. Construction Foreman 1 4.00 101.45 405.80
b. Skilled Laborer 1 4.00 73.29 293.16
c. Unskilled Laborer 1 4.00 56.46 225.84

Sub - Total for A2 (As Evaluated) 924.80


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of labor cost) 92.48

Sub - Total for B1 (As Submitted) 92.48


B2
Equipment

Minor Tools (10% of labor cost) 92.48

Sub - Total for B2 (As Evaluated) 92.48


C1. Total (A1 + B1) 1,017.28
C2. Total (A2 + B2) 1,017.28
D1. Output per our - As Submitted = 1 ea
D2. Output per our - As Evaluated = 1 ea
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,017.28
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,017.28
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1
Materials

a. Plywood Marine (0.00625m x 1.2m x 2.44m) pc. 1.00 500.00 500.00


b. Coco Lumber bd.ft. 41.00 35.00 1,435.00
c. Project Sign ( tarpaulin) sq.ft. 32.00 25.00 800.00
d. CWN Assorted kl. 1.00 80.00 80.00

Sub - Total for F1 (As Submitted) 2,815.00


Materials
F2
a. Plywood Marine (0.00625m x 1.2m x 2.44m) pc. 1.00 500.00 500.00
b. Coco Lumber bd.ft. 41.00 35.00 1,435.00
c. Project Sign ( tarpaulin) sq.ft. 32.00 25.00 800.00
d. CWN Assorted kl. 1.00 80.00 80.00

Sub - Total for F2 (As Evaluated) 2,815.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,832.28
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,832.28
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 459.87
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 459.87
I1. Contractor's Profit (CP) - As Submitted 8% of G1 306.58
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 306.58
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 229.94
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 229.94
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,828.67
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,828.67

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s Man - Days Daily Rate Amount (PhP)


A1.
Labor
DURATION: 300
a. Safety Practitioner / Officer (Full Time) 1 300 500.00 150,000.00
b. Health Personnel - First Aider (Full Time) 1 300 280.00 84,000.00
c. Health Personnel - Sanitation Aide (Full Time) 1 300 280.00 84,000.00

Sub - Total for A1 (As Submitted) 318,000.00


A2. Labor
DURATION: 300
a. Safety Practitioner / Officer (Part Time) 1 300 500.00 150,000.00
b. Health Personnel (Full Time) 1 300 280.00 84,000.00
c. Health Personnel - Sanitation Aide (Full Time) 1 300 280.00 84,000.00

Sub - Total for A2 (As Evaluated) 318,000.00


Name and Capacity Unit Quantity Daily Rate Amount (PhP)
B1.
Equipment
a. G.I pipe barricades 4.5 m x 1.2 m 7 80 21.93 12,280.80
b. G.I pipe barricades 9.5 m x 1.2 m 2 80 49.59 7,934.40

Sub - Total for B1 (As Submitted) 20,215.20


B2. Equipment
a. G.I pipe barricades 4.5 m x 1.2 m 7 80 21.93 12,280.80
b. G.I pipe barricades 9.5 m x 1.2 m 2 80 49.59 7,934.40

Sub - Total for B2 (As Evaluated) 20,215.20


C1. Total (A1 + B1) 338,215.20
C2. Total (A2 + B2) 20,215.20
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 338,215.20
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 338,215.20
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Materials and Facilities for regular disinfection, l.s. 1.00 150,000.00 150,000.00
temperature check and COVID 19 Rapid Test
First Aid Kit
Testing Facilities (Movable Tent, Tables, Chairs)
Rapid Testing Kit for COVID19 x no. of personnel
Thermometer
Alchohol 70% Solutiion
Automatic Alchohol Sanitizer

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 21,562.83 0.27 5,907.62
b. Safety Shoes man-days 7,042.11 3.29 23,152.14
c. Working Gloves man-days 21,562.83 26.67 575,008.80
d. Safety Vest man-days 21,562.83 0.83 17,969.03
e. Rain Coats man-days 6,468.85 0.34 2,171.05
f. Dust Mask man-days 781.13 63.25 49,406.28
g. Facemask man-days 21,562.83 5.00 107,814.15
h. Face Shield man-days 21,562.83 1.67 35,938.05
i. Body Harness and Lanyard man-days 284.47 3.21 913.14
j. Rubber Boots man-days 793.00 1.39 1,102.27

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') set 23.00 123.68 2,844.64
d. Caution Tape, 100ft roll 1.00 800.00 800.00
e. Safety Net (1/8" x 2.7m x 90m.) roll 1.00 3,500.00 3,500.00

Sub - Total for F1 (As Submitted) 977,304.41


F2. Materials

a. Materials and Facilities for regular disinfection, l.s. 1.00 150,000.00 150,000.00
temperature check and COVID 19 Rapid Test
First Aid Kit
Testing Facilities (Movable Tent, Tables, Chairs)
Rapid Testing Kit for COVID19 x no. of personnel
Thermometer
Alchohol 70% Solutiion
Automatic Alchohol Sanitizer

Personal Protective Equipment(PPE)


a. Safety Helmet man-days 21,562.83 0.27 5,907.62
b. Safety Shoes man-days 7,042.11 3.29 23,152.14
c. Working Gloves man-days 21,562.83 26.67 575,008.80
d. Safety Vest man-days 21,562.83 0.83 17,969.03
e. Rain Coats man-days 6,468.85 0.34 2,171.05
f. Dust Mask man-days 781.13 63.25 49,406.28
g. Facemask man-days 21,562.83 5.00 107,814.15
h. Face Shield man-days 21,562.83 1.67 35,938.05
i. Body Harness and Lanyard man-days 284.47 3.21 913.14
j. Rubber Boots man-days 793.00 1.39 1,102.27

Signages and Barricades


a. PPE Signage (4' x 8') set 1.00 506.37 506.37
b. Safety First (4' x 4') set 1.00 270.87 270.87
c. Warning Signs (2' x 3') set 23.00 123.68 2,844.64
d. Caution Tape, 100ft roll 1.00 800.00 800.00
e. Safety Net (1/8" x 2.7m x 90m.) roll 1.00 3,500.00 3,500.00

Sub - Total for F2 (As Evaluated) 977,304.41


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,315,519.61
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,315,519.61
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 8% of G1 105,241.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 105,241.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 71,038.06
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 71,038.06
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,491,799.24
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,491,799.24

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : B.9 Mobilization/Demobilization


Unit of Measurement : l.s.
Output : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

Sub - Total for A1 (As Submitted) -


A2. Labor

Sub - Total for A2 (As Evaluated) -


Name and Capacity No of Unit/s NO. of Trips Rate Amount (PhP)
B1.
Equipment

a. (Not to Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 1 12.00 20,000.00 240,000.00
(Service Truck, Low Bed Trailer)

Sub - Total for B1 (As Submitted) 240,000.00


B2. Equipment

a. (Not to Exceed 1% of E.D.C. ) as per D.O. 197 Series of 2016 1 12.00 20,000.00 240,000.00
(Service Truck, Low Bed Trailer)

Sub - Total for B2 (As Evaluated) 240,000.00


C1. Total (A1 + B1) 240,000.00
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 240,000.00
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 240,000.00
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 240,000.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 240,000.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 0% of G1 -
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 0% of G2 -
I1. Contractor's Profit (CP) - As Submitted 0% of G1 -
I2. Contractor's Profit (CP) - As Evaluated 0% of G2 -
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 12,000.00
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 12,000.00
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 252,000.00
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 252,000.00

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(2) Clearing and Grubbing


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
Clearing of Site (Cutting of Trees and Cutting of Uneven Terrain
a. Construction Foreman 1 120.00 101.45 12,174.00
b. Skilled Laborer 2 120.00 73.29 17,589.60
c. Unskilled Laborer 4 120.00 56.46 27,100.80

Sub - Total for A1 (As Submitted) 56,864.40


A2. Labor
Clearing of Site (Cutting of Trees and Cutting of Uneven Terrain
a. Construction Foreman 1 120.00 101.45 12,174.00
b. Skilled Laborer 2 120.00 73.29 17,589.60
c. Unskilled Laborer 4 120.00 56.46 27,100.80

Sub - Total for A2 (As Evaluated) 56,864.40


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 120.00 1,537.00 184,440.00


b. Dump Truck (12yd³) 2 30.00 1,420.00 85,200.00
c. Chainsaw 2 30.00 75.36 4,521.60
Minor Tools (10% of Labor Cost) 5,686.44

Sub - Total for B1 (As Submitted) 279,848.04


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 120.00 1,537.00 184,440.00


b. Dump Truck (12yd³) 2 30.00 1,420.00 85,200.00
c. Chainsaw 2 30.00 75.36 4,521.60
Minor Tools (10% of Labor Cost) 5,686.44

Sub - Total for B2 (As Evaluated) 279,848.04


C1. Total (A1 + B1) 336,712.44
C2. Total (A2 + B2) 336,712.44
D1. Output per our - As Submitted = 1 l.s.
D2. Output per our - As Evaluated = 1 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 336,712.44
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 336,712.44
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 336,712.44
G2. Direct Unit Cost (E2 + F2) - As Evaluated 336,712.44
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 40,405.49
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 40,405.49
I1. Contractor's Profit (CP) - As Submitted 8% of G1 26,937.00
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 26,937.00
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 20,202.75
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 20,202.75
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 424,257.67
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 424,257.67

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 801(1) Removal of Structure and Obstruction


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
Demolition of 6CL Marcos Type Building and Covered Walkway
a. Construction Foreman 1 80.00 101.45 8,116.00
b. Skilled Laborer 2 80.00 73.29 11,726.40
c. Unskilled Laborer 4 80.00 56.46 18,067.20

Sub - Total for A1 (As Submitted) 37,909.60


A2. Labor
Demolition of 6CL Marcos Type Building and Covered Walkway
a. Construction Foreman 1 80.00 101.45 8,116.00
b. Skilled Laborer 2 80.00 73.29 11,726.40
c. Unskilled Laborer 4 80.00 56.46 18,067.20

Sub - Total for A2 (As Evaluated) 37,909.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 80.00 1,537.00 122,960.00


b. Dump Truck (12yd³) 1 20.00 1,420.00 28,400.00
c. Jackhammer 2 80.00 150.00 24,000.00
Minor Tools (10% of Labor Cost) 3,790.96

Sub - Total for B1 (As Submitted) 179,150.96


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 80.00 1,537.00 122,960.00


b. Dump Truck (12yd³) 1 20.00 1,420.00 28,400.00
c. Jackhammer 2 80.00 150.00 24,000.00
Minor Tools (10% of Labor Cost) 3,790.96

Sub - Total for B2 (As Evaluated) 179,150.96


C1. Total (A1 + B1) 217,060.56
C2. Total (A2 + B2) 217,060.56
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 217,060.56
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 217,060.56
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 217,060.56
G2. Direct Unit Cost (E2 + F2) - As Evaluated 217,060.56
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 26,047.27
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 26,047.27
I1. Contractor's Profit (CP) - As Submitted 8% of G1 17,364.84
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 17,364.84
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13,023.63
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13,023.63
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 273,496.31
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 273,496.31

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)a Structure Excavation (Common Soil)


Unit of Measurement : m³
Output per hour : 20.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 270.83


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 270.83


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12yd³) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B1 (As Submitted) 4,404.08


B2. Equipment

a. Backhoe (0.80 m³/1.04 yd³) 1 1.00 1,537.00 1,537.00


b. Dump Truck (12yd³) 2 1.00 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B2 (As Evaluated) 4,404.08


C1. Total (A1 + B1) 4,674.91
C2. Total (A2 + B2) 4,674.91
D1. Output per our - As Submitted = 20 m³
D2. Output per our - As Evaluated = 20 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 233.75
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 233.75
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 233.75
G2. Direct Unit Cost (E2 + F2) - As Evaluated 233.75
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 28.05
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 28.05
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.70
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.70
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14.02
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14.02
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 294.52
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 294.52

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)a Embankment from Structure Excavation


Unit of Measurement : m³
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 270.83


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 270.83


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B1 (As Submitted) 1,272.08


B2. Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Dump Truck (12yd³) 1 0.75 1,420.00 1,065.00
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B2 (As Evaluated) 1,184.33


C1. Total (A1 + B1) 1,542.91
C2. Total (A2 + B2) 1,455.16
D1. Output per our - As Submitted = 9.84 m³
D2. Output per our - As Evaluated = 9.84 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 156.80
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 147.88
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 156.80
G2. Direct Unit Cost (E2 + F2) - As Evaluated 147.88
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 18.82
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 17.75
I1. Contractor's Profit (CP) - As Submitted 8% of G1 12.54
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11.83
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 9.41
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 9.41
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 197.57
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 197.57

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)b Embankment from Borrow


Unit of Measurement : m³
Output per hour : 9.84

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 270.83


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 270.83


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B1 (As Submitted) 1,272.08


B2. Equipment

a. Plate Compactor (5hp) 1 0.75 123.00 92.25


b. Backhoe (0.80 m³/1.04 yd³) 1 0.75 1,537.00 1,152.75
Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B2 (As Evaluated) 1,272.08


C1. Total (A1 + B1) 1,542.91
C2. Total (A2 + B2) 1,542.91
D1. Output per our - As Submitted = 9.84 m³
D2. Output per our - As Evaluated = 9.84 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 156.80
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 156.80
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Common Borrow m³ 1.25 1,157.58 1,446.98


(w/ 25% Shrinkage Factor)

Sub - Total for F1 (As Submitted) 1,446.98


F2. Materials

a. Common Borrow m³ 1.25 1,157.58 1,446.98


(w/ 25% Shrinkage Factor)

Sub - Total for F2 (As Evaluated) 1,446.98


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,603.78
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,603.78
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 192.45
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 192.45
I1. Contractor's Profit (CP) - As Submitted 8% of G1 128.30
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 128.30
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 96.23
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 96.23
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 2,020.76
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 2,020.76

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(4) Gravel Fill


Unit of Measurement : m³
Output per hour : 1.200

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 270.83


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 270.83


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Plate Compactor (5hp) 1 0.50 123.00 61.50


b. Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B1 (As Submitted) 88.58


B2. Equipment

a. Plate Compactor (5hp) 1 0.50 123.00 61.50


b. Minor Tools (10% of Labor Cost) 27.08

Sub - Total for B2 (As Evaluated) 88.58


C1. Total (A1 + B1) 359.41
C2. Total (A2 + B2) 359.41
D1. Output per our - As Submitted = 1.20 m³
D2. Output per our - As Evaluated = 1.20 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 299.51
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 299.51
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Gravel G-1 m³ 1.05 1,587.58 1,666.96


(w/ 5% Srinkage Factor)

Sub - Total for F1 (As Submitted) 1,666.96


F2. Materials

a. Gravel G-1 m³ 1.05 1,587.58 1,666.96


(w/ 5% Srinkage Factor)

Sub - Total for F2 (As Evaluated) 1,666.96


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,966.47
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,966.47
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 235.98
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 235.98
I1. Contractor's Profit (CP) - As Submitted 8% of G1 157.32
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 157.32
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 117.99
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 117.99
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 2,477.75
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 2,477.75

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 807(1) Site Development


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor
a. Construction Foreman 1 960.00 101.45 97,392.00
b. Skilled Laborer 4 960.00 73.29 281,433.60
c. Unskilled Laborer 10 960.00 56.46 542,016.00

Sub - Total for A1 (As Submitted) 920,841.60


A2. Labor
a. Construction Foreman 1 960.00 101.45 97,392.00
b. Skilled Laborer 4 960.00 73.29 281,433.60
c. Unskilled Laborer 10 960.00 56.46 542,016.00

Sub - Total for A2 (As Evaluated) 920,841.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
a. Minor Tools (10% of Labor Cost) 92,084.16

Sub - Total for B1 (As Submitted) 92,084.16


B2. Equipment
a. Minor Tools (10% of Labor Cost) 92,084.16

Sub - Total for B2 (As Evaluated) 92,084.16


C1. Total (A1 + B1) 1,012,925.76
C2. Total (A2 + B2) 1,012,925.76
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,012,925.76
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,012,925.76
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials
a. Landscaping and Drainage Improvement l.s. 1.00 20,000.00 20,000.00
b. Electrical System Improvement
Meralco Service Utility Lines and Accessories l.s. 1.00 5,000.00 5,000.00
c. Concreting of School Entrance and Parking
450.00 m²
Cement bags 428.00 250.00 107,000.00
Gravel cu.m. 45.00 1,587.58 71,441.10
Sand cu.m. 22.50 1,307.58 29,420.55
10mm dia. RSB kgs. 1452.30 37.50 54,461.25
Gravel Fill cu.m. 23.00 80.00 1,840.00
d. Construction of CHB Fence w/ Concrete Post (0.3 x l.m. 110.00 20,000.00 2,200,000.00
0.3m) (wall ht. 2.2m. foundation 1 x 1 x 0.25m depth
@0.8m. 5 - 12mm BW) (100 mm Thk. CHB Plastered on
One Side
e Construction/ Restoration of Covered Walkway w/ Slab l.m. 65.00 10,000.00 650,000.00
on Fill (1.5m Width) and walk Guide Plant Box on Both
Side
f. Misc. Items (CWN, Welding Rods etc.) l.s. 1.00 4,601.00 4,601.00

Sub - Total for F1 (As Submitted) 3,143,763.90


F2. Materials
a. Landscaping and Drainage Improvement l.s. 1.00 20,000.00 20,000.00
b. Electrical System Improvement
Meralco Service Utility Lines and Accessories l.s. 1.00 5,000.00 5,000.00
c. Concreting of School Entrance and Parking
450.00 m²
Cement bags 428.00 250.00 107,000.00
Gravel cu.m. 45.00 1,587.58 71,441.10
Sand cu.m. 22.50 1,307.58 29,420.55
10mm dia. RSB kgs. 1452.30 37.50 54,461.25
d. Construction of CHB Fence w/ Concrete Post (0.3 x l.m. 110.00 20,000.00 2,200,000.00
0.3m) (wall ht. 2.2m. foundation 1 x 1 x 0.25m depth
@0.8m. 5 - 12mm BW) (100 mm Thk. CHB Plastered on
One Side
e Construction/ Restoration of Covered Walkway w/ Slab l.m. 65.00 10,000.00 650,000.00
on Fill (1.5m Width) and walk Guide Plant Box on Both
Side
f. Misc. Items (CWN, Welding Rods etc.) l.s. 1.00 4,601.00 4,601.00

Sub - Total for F2 (As Evaluated) 3,143,763.90


G1. Direct Unit Cost (E1 + F1) - As Submitted 4,156,689.66
G2. Direct Unit Cost (E2 + F2) - As Evaluated 4,156,689.66
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 498,802.76
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 498,802.76
I1. Contractor's Profit (CP) - As Submitted 8% of G1 332,535.17
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 332,535.17
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 249,401.38
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 249,401.38
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 5,237,428.97
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 5,237,428.97

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900(8) Structural Concrete (27.58 Mpa @ 28 days)


Unit of Measurement : m³
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 6 1.00 56.46 338.76
. - -
Sub - Total for A1 (As Submitted) 586.79
A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 6 1.00 56.46 338.76

Sub - Total for A2 (As Evaluated) 586.79


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 58.68

Sub - Total for B1 (As Submitted) 801.70


B2. Equipment

a. Concrete Vibrator 2 1.00 91.25 182.50


b. Pumpcrete 1 0.27 2,076.00 560.52
c. Minor Tools (10% of Labor Cost) 58.68

Sub - Total for B2 (As Evaluated) 801.70


C1. Total (A1 + B1) 1,388.49
C2. Total (A2 + B2) 1,388.49
D1. Output per our - As Submitted = 3.72 m³
D2. Output per our - As Evaluated = 3.72 m³
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 373.25
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 373.25
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F1 (As Submitted) 6,027.00


F2. Materials

a. Ready Mix, Class A, 28 days m³ 1.05 5,740.00 6,027.00

Sub - Total for F2 (As Evaluated) 6,027.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,400.25
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,400.25
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 768.03
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 768.03
I1. Contractor's Profit (CP) - As Submitted 8% of G1 512.02
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 512.02
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 384.01
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 384.01
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,064.31
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,064.31

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)a Reinforcing Steel (Deformed), Grade 40


Unit of Measurement : Kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A1 (As Submitted) 998.84


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A2 (As Evaluated) 998.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B1 (As Submitted) 385.51


B2. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B2 (As Evaluated) 385.51


C1. Total (A1 + B1) 1,384.35
C2. Total (A2 + B2) 1,384.35
D1. Output per our - As Submitted = 129.09 Kg
D2. Output per our - As Evaluated = 129.09 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 10.72
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 10.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reinforcing Steel Bars Deformed Grade 40 kg 1.000 37.50 37.50


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. c. Consumables (5% of Materials Cost) 1.94 1.94

Sub - Total for F1 (As Submitted) 40.64


F2. Materials

a. Reinforcing Steel Bars Deformed Grade 40 kg 1.000 37.50 37.50


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. c. Consumables (5% of Materials Cost) 1.94 1.94

Sub - Total for F2 (As Evaluated) 40.64


G1. Direct Unit Cost (E1 + F1) - As Submitted 51.36
G2. Direct Unit Cost (E2 + F2) - As Evaluated 51.36
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6.16
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.16
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.11
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.11
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.08
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.08
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 64.71
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 64.71

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1)b Reinforcing Steel (Deformed), Grade 60


Unit of Measurement : Kg
Output per hour : 129.094

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A1 (As Submitted) 998.84


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 3 1.00 73.29 219.87
c. Unskilled Laborer 12 1.00 56.46 677.52

Sub - Total for A2 (As Evaluated) 998.84


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B1 (As Submitted) 385.51


B2. Equipment

a. Bar Cutter 1 0.50 219.75 109.88


b. Bar Bender 1 0.50 351.50 175.75
c. Minor Tools (10% of Labor Cost) 99.88

Sub - Total for B2 (As Evaluated) 385.51


C1. Total (A1 + B1) 1,384.35
C2. Total (A2 + B2) 1,384.35
D1. Output per our - As Submitted = 129.09 Kg
D2. Output per our - As Evaluated = 129.09 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 10.72
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 10.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reinforcing Steel Bars Deformed Grade 60 kg 1.000 38.53 38.53


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99 1.99

Sub - Total for F1 (As Submitted) 41.72


F2. Materials

a. Reinforcing Steel Bars Deformed Grade 60 kg 1.000 38.53 38.53


b. GI Tie Wire #16 kg 0.015 80.00 1.20
c. Consumables (5% of Materials Cost) 1.99 1.99

Sub - Total for F2 (As Evaluated) 41.72


G1. Direct Unit Cost (E1 + F1) - As Submitted 52.44
G2. Direct Unit Cost (E2 + F2) - As Evaluated 52.44
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 6.29
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 6.29
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.20
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.20
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.15
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.15
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 66.07
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 66.07

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 903(2) Formworks & Falseworks


Unit of Measurement : m²
Output per hour : 4.500

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 4 1.00 73.29 293.16
c. Unskilled Laborer 6 1.00 56.46 338.76
Stripping
a. Construction Foreman 1 0.56 101.45 56.81
b. Unskilled Laborer 6 0.56 56.46 189.71
Sub - Total for A1 (As Submitted) 979.89
A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 4 1.00 73.29 293.16
c. Unskilled Laborer 6 1.00 56.46 338.76
Stripping
a. Construction Foreman 1 0.56 101.45 56.81
b. Unskilled Laborer 6 0.56 56.46 189.71
Sub - Total for A2 (As Evaluated) 979.89
Name and Capacity No of Unit/s No. of Day/s Daily R. Rate Amount (PhP)
B1.
Equipment
Area = 205.01 m²
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2pcs H-frames
4pcs diagonal cross braces
4pcs Horizontal cross braces
8pcs joint pins
b. Shoring Jack,3.8 m full extension 62 14.00 4.50 3,906.00
c. Adj. U-Head Jack, 0.60m 80 14.00 0.85 952.00
d. Adj. Base Jack, 0.60m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Not 558 14.00 0.15 1,171.80

Sub - Total for B1 (As Submitted) 19,024.60


B2. Equipment
Area = 205.01 m²
a. H-Frame 1.7 m x 1.2m, set 40 14.00 6.08 3,404.80
2pcs H-frames
4pcs diagonal cross braces
4pcs Horizontal cross braces
8pcs joint pins
b. Shoring Jack,3.8 m full extension 62 14.00 4.50 3,906.00
c. Adj. U-Head Jack, 0.60m 80 14.00 0.85 952.00
d. Adj. Base Jack, 0.60m 80 14.00 0.85 952.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00 2.50 2,170.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00 1.25 280.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00 1.75 784.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00 0.50 1,512.00
i. Tie Rod x 0.60m 278 14.00 1.00 3,892.00
j. Round Wing Not 558 14.00 0.15 1,171.80

Sub - Total for B2 (As Evaluated) 19,024.60


C1. Sub-Total for C1 (B1/Area) 92.80
C2. Sub-Total for C2 (B2/Area) 92.80
D1. Output per our - As Submitted = 4.50 m²
D2. Output per our - As Evaluated = 4.50 m²
E1. Direct Unit Cost (A1 ÷ D1) + C1 - As Submitted 310.55
E2. Direct Unit Cost (A2 ÷ D2) + C2 - As Submitted 310.55
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses pc. 0.347 1,450.00 100.63
b. Good Lumber - 3 Uses bd.ft. 4.727 60.00 94.54
d. Consumables (5% of Material Cost) 9.76

Sub - Total for F1 (As Submitted) 204.93


F2. Materials
a. 1.22m x 2.44m x 19mm thick Penolic Board - 5 uses pc. 0.347 1,450.00 100.63
b. Good Lumber - 3 Uses bd.ft. 4.727 60.00 94.54
d. Consumables (5% of Material Cost) 9.76

Sub - Total for F2 (As Evaluated) 204.93


G1. Direct Unit Cost (E1 + F1) - As Submitted 515.48
G2. Direct Unit Cost (E2 + F2) - As Evaluated 515.48
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 61.86
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 61.86
I1. Contractor's Profit (CP) - As Submitted 8% of G1 41.24
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 41.24
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 30.93
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 30.93
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 649.50
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 649.50
Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : L
Output per hour : 5.40

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A1 (As Submitted) 287.66


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 287.66


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B1 (As Submitted) 28.77


B2. Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B2 (As Evaluated) 28.77


C1. Total (A1 + B1) 316.43
C2. Total (A2 + B2) 316.43
D1. Output per our - As Submitted = 5.40 L
D2. Output per our - As Evaluated = 5.40 L
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 58.60
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 58.60
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Soil Poisoning L 1.00 255.00 255.00

Sub - Total for F1 (As Submitted) 255.00


F2. Materials

a. Soil Poisoning L 1.00 255.00 255.00

Sub - Total for F2 (As Evaluated) 255.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 313.60
G2. Direct Unit Cost (E2 + F2) - As Evaluated 313.60
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 37.63
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 37.63
I1. Contractor's Profit (CP) - As Submitted 8% of G1 25.09
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 25.09
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 18.82
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 18.82
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 395.13
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 395.13

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a1 CHB Non-Load Bearing (including Reinforcing Steel), 100mm
Unit of Measurement : m2
Output per hour : 3.825
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 417.41


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 417.41


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment
a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00
b. Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B1 (As Submitted) 213.74


B2. Equipment

a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00


b. Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B2 (As Evaluated) 213.74


C1. Total (A1 + B1) 631.15
C2. Total (A2 + B2) 631.15
D1. Output per our - As Submitted = 3.83 m2
D2. Output per our - As Evaluated = 3.83 m2
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 165.01
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 165.01
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. CHB Ordinary (101mm x 203mm x 406mm) pcs 13.00 15.00 195.00


b. Portland Cement bag 0.525 250.00 131.25
c. Sand cu.m 0.04 1,307.58 52.30
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F1 (As Submitted) 481.55


F2. Materials

a. CHB Ordinary (101mm x 203mm x 406mm) pcs 13.00 15.00 195.00


b. Portland Cement bag 0.525 250.00 131.25
c. Sand cu.m 0.04 1,307.58 52.30
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F2 (As Evaluated) 481.55


G1. Direct Unit Cost (E1 + F1) - As Submitted 646.56
G2. Direct Unit Cost (E2 + F2) - As Evaluated 646.56
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 77.59
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 77.59
I1. Contractor's Profit (CP) - As Submitted 8% of G1 51.72
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 51.72
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 38.79
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 38.79
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 814.67
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 814.67

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046(2)a2 CHB Non-Load Bearing (including Reinforcing Steel), 150mm
Unit of Measurement : m2
Output per hour : 3.18
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 417.41


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 417.41


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00


b. Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B1 (As Submitted) 213.74


B2. Equipment
a. One Bagger Mixer (4-6 ft³/min) 1 1.00 172.00 172.00
b. Minor Tools (10% of Labor Cost) 41.74

Sub - Total for B2 (As Evaluated) 213.74


C1. Total (A1 + B1) 631.15
C2. Total (A2 + B2) 631.15
D1. Output per our - As Submitted = 3.18 m2
D2. Output per our - As Evaluated = 3.18 m2
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 198.48
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 198.48
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. CHB Ordinary (150mm x 230mm x 406mm) pcs 13.00 18.00 234.00


b. Portland Cement bag 1.50 250.00 375.00
c. Sand cu.m 0.04 1,307.58 52.30
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.64 37.50 99.00
e. GI Tie Wire #16 kg 0.05 80.00 4.00

Sub - Total for F1 (As Submitted) 764.30


F2. Materials

a. CHB Ordinary (150mm x 230mm x 406mm) pcs 13.000 18.000 234.00


b. Portland Cement bag 1.500 250.000 375.00
c. Sand cu.m 0.04 1307.580 52.30
d. Reinforcing Steel Bars Deformed Grade 40 kg 2.640 37.500 99.00
e. GI Tie Wire #16 kg 0.050 80.000 4.00

Sub - Total for F2 (As Evaluated) 764.30


G1. Direct Unit Cost (E1 + F1) - As Submitted 962.78
G2. Direct Unit Cost (E2 + F2) - As Evaluated 962.78
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 115.53
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 115.53
I1. Contractor's Profit (CP) - As Submitted 8% of G1 77.02
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 77.02
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 57.77
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 57.77
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,213.10
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,213.10

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(4) Wooden Doors & Windows


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 208.00 101.45 21,101.60


b. Skilled Laborer 1 208.00 73.29 15,244.32
c. Unskilled Laborer 1 208.00 56.46 11,743.68

Sub - Total for A1 (As Submitted) 48,089.60


A2. Labor

a. Construction Foreman 1 208.00 101.45 21,101.60


b. Skilled Laborer 1 208.00 73.29 15,244.32
c. Unskilled Laborer 1 208.00 56.46 11,743.68

Sub - Total for A2 (As Evaluated) 48,089.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 4,808.96

Sub - Total for B1 (As Submitted) 4,808.96


B2. Equipment

a. Minor Tools (10% of Labor Cost) 4,808.96

Sub - Total for B2 (As Evaluated) 4,808.96


C1. Total (A1 + B1) 52,898.56
C2. Total (A2 + B2) 52,898.56
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 52,898.56
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 52,898.56
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Door Jamb (D-1) bd.ft. 335.000 100.00 33,500.00


b. Door Jamb (D-2) bd.ft. 98.400 100.00 9,840.00
c. Door Jamb (D-3) bd.ft. 34.160 100.00 3,416.00
d. Door Jamb (D-3a) bd.ft. 49.200 100.00 4,920.00
e. Door Jamb (BD-1) bd.ft. 68.80 100.00 6,880.00
f. Window Jamb (W-2) bd.ft. 404.00 100.00 40,400.00
g. Consumables (5% of Materials Cost) . 4,947.80

Sub - Total for F1 (As Submitted) 103,903.80


F2. Materials

a. Door Jamb (D-1) bd.ft. 335.000 100.00 33,500.00


b. Door Jamb (D-2) bd.ft. 98.400 100.00 9,840.00
c. Door Jamb (D-3) bd.ft. 34.160 100.00 3,416.00
d. Door Jamb (D-3a) bd.ft. 49.200 100.00 4,920.00
e. Door Jamb (BD-1) bd.ft. 68.800 100.00 6,880.00
f. Window Jamb (W-2) bd.ft. 404.000 100.00 40,400.00
g. Consumables (5% of Materials Cost) 4,947.80

Sub - Total for F2 (As Evaluated) 103,903.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 156,802.36
G2. Direct Unit Cost (E2 + F2) - As Evaluated 156,802.36
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 18,816.28
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 18,816.28
I1. Contractor's Profit (CP) - As Submitted 8% of G1 12,544.19
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 12,544.19
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 9,408.14
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 9,408.14
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 197,570.97
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 197,570.97

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)a Door (Flush)


Unit of Measurement : m²
Output per hour : 0.320

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 0.32 m²
D2. Output per our - As Evaluated = 0.32 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 794.75
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 794.75
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Flush hollow core door m² 1.000 700.00 700.00

Sub - Total for F1 (As Submitted) 700.00


F2. Materials

a. Flush hollow core door m² 1.000 700.00 700.00

Sub - Total for F2 (As Evaluated) 700.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,494.75
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,494.75
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 179.37
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 179.37
I1. Contractor's Profit (CP) - As Submitted 8% of G1 119.58
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 119.58
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 89.69
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 89.69
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,883.39
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,883.39

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Door (Wooden Panel)


Unit of Measurement : m²
Output per hour : 0.360

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A1 (As Submitted) 287.66


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 287.66


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B1 (As Submitted) 28.77


B2. Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B2 (As Evaluated) 28.77


C1. Total (A1 + B1) 316.43
C2. Total (A2 + B2) 316.43
D1. Output per our - As Submitted = 0.36 m²
D2. Output per our - As Evaluated = 0.36 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 878.96
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 878.96
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Wooden Panel Door m² 1.000 5,500.00 5,500.00

Sub - Total for F1 (As Submitted) 5,500.00


F2. Materials

a. Wooden Panel Door m² 1.000 5,500.00 5,500.00

Sub - Total for F2 (As Evaluated) 5,500.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,378.96
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,378.96
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 765.48
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 765.48
I1. Contractor's Profit (CP) - As Submitted 8% of G1 510.32
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 510.32
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 382.74
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 382.74
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,037.49
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,037.49

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(17) Carpentry and Joinery Works


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 56.00 101.45 5,681.20


b. Skilled Laborer 1 56.00 73.29 4,104.24
c. Unskilled Laborer 1 56.00 56.46 3,161.76

Sub - Total for A1 (As Submitted) 12,947.20


A2. Labor

a. Construction Foreman 1 56.00 101.45 5,681.20


b. Skilled Laborer 1 56.00 73.29 4,104.24
c. Unskilled Laborer 1 56.00 56.46 3,161.76

Sub - Total for A2 (As Evaluated) 12,947.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 1,294.72

Sub - Total for B1 (As Submitted) 1,294.72


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1,294.72

Sub - Total for B2 (As Evaluated) 1,294.72


C1. Total (A1 + B1) 14,241.92
C2. Total (A2 + B2) 14,241.92
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 14,241.92
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 14,241.92
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Blackboard Set 10.000 3,400.00 34,000.00

Sub - Total for F1 (As Submitted) 34,000.00


F2. Materials

a. Blackboard Set 10.000 3,400.00 34,000.00

Sub - Total for F2 (As Evaluated) 34,000.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 48,241.92
G2. Direct Unit Cost (E2 + F2) - As Evaluated 48,241.92
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 5,789.03
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 5,789.03
I1. Contractor's Profit (CP) - As Submitted 8% of G1 3,859.35
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 3,859.35
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 2,894.52
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 2,894.52
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 60,784.82
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 60,784.82

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006(4) Steel Louver Door


Unit of Measurement : m²
Output per hour : 0.260

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 120.87


B2. Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 120.87


C1. Total (A1 + B1) 352.07
C2. Total (A2 + B2) 352.07
D1. Output per our - As Submitted = 0.26 m²
D2. Output per our - As Evaluated = 0.26 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,354.12
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,354.12
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Steel Louver Door m² 1.000 5,500.00 5,500.00

Sub - Total for F1 (As Submitted) 5,500.00


F2. Materials

a. Steel Louver Door m² 1.000 5,500.00 5,500.00

Sub - Total for F2 (As Evaluated) 5,500.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 6,854.12
G2. Direct Unit Cost (E2 + F2) - As Evaluated 6,854.12
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 822.49
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 822.49
I1. Contractor's Profit (CP) - As Submitted 8% of G1 548.33
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 548.33
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 411.25
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 411.25
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 8,636.19
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 8,636.19

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(1) Residential Casement Steel Window


Unit of Measurement : m²
Output per hour : 0.180

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


b. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 120.87


B2. Equipment

a. Welding Machine (500) 1 0.25 391.00 97.75


b. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 120.87


C1. Total (A1 + B1) 352.07
C2. Total (A2 + B2) 352.07
D1. Output per our - As Submitted = 0.18 m²
D2. Output per our - As Evaluated = 0.18 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 1,955.94
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 1,955.94
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Steel Casement Window m² 1.000 1,900.00 1,900.00


b. Consumables (5% of Materials Cost) 95.00

Sub - Total for F1 (As Submitted) 1,995.00


F2. Materials

a. Steel Casement Window m² 1.000 1,900.00 1,900.00


95.00

Sub - Total for F2 (As Evaluated) 1,995.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,950.94
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,950.94
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 474.11
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 474.11
I1. Contractor's Profit (CP) - As Submitted 8% of G1 316.08
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 316.08
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 237.06
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 237.06
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,978.19
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,978.19

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005(6) Window Accessory


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Skilled Laborer 1 96.00 73.29 7,035.84
c. Unskilled Laborer 1 96.00 56.46 5,420.16

Sub - Total for A1 (As Submitted) 22,195.20


A2. Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Skilled Laborer 1 96.00 73.29 7,035.84
c. Unskilled Laborer 1 96.00 56.46 5,420.16

Sub - Total for A2 (As Evaluated) 22,195.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Welding Machine (500) 1 4.00 391.00 1,564.00


b. Minor Tools (10% of Labor Cost) 2,219.52

Sub - Total for B1 (As Submitted) 3,783.52


B2. Equipment

a. Welding Machine (500) 1 4.00 391.00 1,564.00


b. Minor Tools (10% of Labor Cost) 2,219.52

Sub - Total for B2 (As Evaluated) 3,783.52


C1. Total (A1 + B1) 25,978.72
C2. Total (A2 + B2) 25,978.72
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 25,978.72
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 25,978.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Window Grill
a. 12 mm x 12 mm Sq. Bar Kg 904.320 60.00 54,259.20
c. Consumables (3% of Materials Cost) 1,627.78

Sub - Total for F1 (As Submitted) 55,886.98


F2. Materials

Window Grill
a. 12 mm x 12 mm Sq. Bar Kg 904.320 60.00 54,259.20
c. Consumables (3% of Materials Cost) 1,627.78

Sub - Total for F2 (As Evaluated) 55,886.98


G1. Direct Unit Cost (E1 + F1) - As Submitted 81,865.70
G2. Direct Unit Cost (E2 + F2) - As Evaluated 81,865.70
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 9,823.88
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 9,823.88
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6,549.26
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6,549.26
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4,911.94
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4,911.94
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 103,150.78
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 103,150.78

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1009(1)a Jalousie Window (Glass)


Unit of Measurement : m²
Output per hour : 0.270

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 0.27 m²
D2. Output per our - As Evaluated = 0.27 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 941.93
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 941.93
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Jalousie Window (Glass, Inc. Jalousie Casing) m² 1.000 2,222.00 2,222.00


b. Consumables (3% of Materials Cost) 66.66

Sub - Total for F1 (As Submitted) 2,288.66


F2. Materials

a. Jalousie Window (Glass, Inc. Jalousie Casing) m² 1.000 2,222.00 2,222.00


b. Consumables (3% of Materials Cost) 66.66

Sub - Total for F2 (As Evaluated) 2,288.66


G1. Direct Unit Cost (E1 + F1) - As Submitted 3,230.59
G2. Direct Unit Cost (E2 + F2) - As Evaluated 3,230.59
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 387.67
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 387.67
I1. Contractor's Profit (CP) - As Submitted 8% of G1 258.45
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 258.45
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 193.84
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 193.84
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 4,070.54
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 4,070.54

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2) Finishing Hardware


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.

Sub - Total for A1 (As Submitted)


A2. Labor

a. Labor Cost for this items are to be considered/included in the installation of doors,windows, and other fab. Materials.

Sub - Total for A2 (As Evaluated)


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Sub - Total for B1 (As Submitted) -


B2. Equipment

Sub - Total for B2 (As Evaluated) -


C1. Total (A1 + B1) -
C2. Total (A2 + B2) -
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted -
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated -
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. door locks (schlage or equivalent) Set 33.00 510.00 16,830.00


b. hinge (50mm x 101mm) pc 132.00 70.00 9,240.00

Sub - Total for F1 (As Submitted) 26,070.00


F2. Materials

a. door locks (schlage or equivalent) Set 33.00 510.00 16,830.00


b. hinge (50mm x 101mm) pc 132.00 70.00 9,240.00

Sub - Total for F2 (As Evaluated) 26,070.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 26,070.00
G2. Direct Unit Cost (E2 + F2) - As Evaluated 26,070.00
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 3,128.40
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 3,128.40
I1. Contractor's Profit (CP) - As Submitted 8% of G1 2,085.60
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 2,085.60
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 1,564.20
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 1,564.20
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 32,848.20
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 32,848.20

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1051(6) Railing


Unit of Measurement : L.s.
Output per hour : 1.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 160.00 101.45 16,232.00


b. Skilled Laborer 2 160.00 73.29 23,452.80
c. Unskilled Laborer 4 160.00 56.46 36,134.40

Sub - Total for A1 (As Submitted) 75,819.20


A2. Labor

a. Construction Foreman 1 160.00 101.45 16,232.00


b. Skilled Laborer 2 160.00 73.29 23,452.80
c. Unskilled Laborer 4 160.00 56.46 36,134.40

Sub - Total for A2 (As Evaluated) 75,819.20


No. of
B1. Name and Capacity No of Unit/s Hourly Rate Amount (PhP)
Hour/s
Equipment

a. Welding Machine (500) 1 120.00 391.00 46,920.00


b. Cutting Outfit 1 40.00 45.45 1,818.00
c. Minor Tools (10% of Labor Cost) 7,581.92

Sub - Total for B1 (As Submitted) 56,319.92


B2. Equipment

a. Welding Machine (500) 1 120.00 391.00 46,920.00


b. Cutting Outfit 1 40.00 45.45 1,818.00
c. Minor Tools (10% of Labor Cost) 7,581.92

Sub - Total for B2 (As Evaluated) 56,319.92


C1. Total (A1 + B1) 132,139.12
C2. Total (A2 + B2) 132,139.12
D1. Output per our - As Submitted = 1 L.s.
D2. Output per our - As Evaluated = 1 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 132,139.12
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 132,139.12
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. 50 mm Ø G.I. Pipe (Stainless) pc. 15.00 2,480.00 37,200.00


b. G.I Pipes (50mm D) pc 22.00 1,500.00 33,000.00
c. 19 mm bar kg. 1,475.00 60.00 88,500.00
d. 12 mm dia. bar kg. 231.00 60.00 13,860.00
e. Welding Rod kg. 25.59 110.00 2,814.90
f. Consumables (5% of material cost) 8,768.75

Sub - Total for F1 (As Submitted) 184,143.65


F2. Materials

a. 50 mm Ø G.I. Pipe (Stainless) pc. 15.00 2,480.00 37,200.00


b. G.I Pipes (50mm D) pc 22.00 1,500.00 33,000.00
c. 19 mm bar kg. 1,475.00 60.00 88,500.00
d. 12 mm dia. bar kg. 231.00 60.00 13,860.00
e. Welding Rod kg. 25.59 110.00 2,814.90
f. Consumables (5% of material cost) 8,768.75

Sub - Total for F2 (As Evaluated) 184,143.65


G1. Direct Unit Cost (E1 + F1) - As Submitted 316,282.77
G2. Direct Unit Cost (E2 + F2) - As Evaluated 316,282.77
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 37,953.93
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 37,953.93
I1. Contractor's Profit (CP) - As Submitted 8% of G1 25,302.62
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 25,302.62
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 18,976.97
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 18,976.97
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 398,516.29
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 398,516.29

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1027(1) Cement Plaster Finish


Unit of Measurement : m²
Output per hour : 7.125

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A1 (As Submitted) 473.87


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A2 (As Evaluated) 473.87


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B1 (As Submitted) 47.39


B2. Equipment

a. Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B2 (As Evaluated) 47.39


C1. Total (A1 + B1) 521.26
C2. Total (A2 + B2) 521.26
D1. Output per our - As Submitted = 7.125 m²
D2. Output per our - As Evaluated = 7.125 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 73.16
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 73.16
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Portland Cement Bag 0.300 250.00 75.00


b. Sand m³ 0.027 1,307.58 35.30

Sub - Total for F1 (As Submitted) 110.30


F2. Materials

a. Portland Cement Bag 0.300 250.00 75.00


b. Sand m³ 0.027 1,307.58 35.30

Sub - Total for F2 (As Evaluated) 110.30


G1. Direct Unit Cost (E1 + F1) - As Submitted 183.46
G2. Direct Unit Cost (E2 + F2) - As Evaluated 183.46
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 22.02
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 22.02
I1. Contractor's Profit (CP) - As Submitted 8% of G1 14.68
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 14.68
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11.01
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11.01
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 231.16
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 231.16

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(1)a Cement Floor Finish (Plain)


Unit of Measurement : m²
Output per hour : 5.950

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A1 (As Submitted) 344.12


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 3 1.00 56.46 169.38

Sub - Total for A2 (As Evaluated) 344.12


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Power Throwel 1 1.00 310.00 310.00


b. Minor Tools (10% of Labor Cost) 34.41

Sub - Total for B1 (As Submitted) 344.41


B2. Equipment

a. Power Throwel 1 1.00 310.00 310.00


b. Minor Tools (10% of Labor Cost) 34.41

Sub - Total for B2 (As Evaluated) 344.41


C1. Total (A1 + B1) 688.53
C2. Total (A2 + B2) 688.53
D1. Output per our - As Submitted = 5.950 m²
D2. Output per our - As Evaluated = 5.950 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 115.72
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 115.72
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

Sub - Total for F1 (As Submitted) -


F2. Materials

Sub - Total for F2 (As Evaluated) -


G1. Direct Unit Cost (E1 + F1) - As Submitted 115.72
G2. Direct Unit Cost (E2 + F2) - As Evaluated 115.72
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 13.89
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 13.89
I1. Contractor's Profit (CP) - As Submitted 8% of G1 9.26
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 9.26
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 6.94
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 6.94
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 145.81
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 145.81

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)a1 Ceiling (4.5mm, Metal Frame, Fiber Cement Board)
Unit of Measurement : m²
Output per hour : 1.243

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A1 (As Submitted) 287.66


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 287.66


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B1 (As Submitted) 28.77


B2. Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B2 (As Evaluated) 28.77


C1. Total (A1 + B1) 316.43
C2. Total (A2 + B2) 316.43
D1. Output per our - As Submitted = 1.243 m²
D2. Output per our - As Evaluated = 1.243 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 254.57
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 254.57
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 4.5mm Fiber Cement Board pc 0.365 450.00 164.25


b. Metal Furring pc 1.131 130.00 147.03
c. Carrying Channels pc 0.357 150.00 53.55
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 20.00 120.00
f. Wall Angle pc 0.238 100.00 23.80
g. Rivets pc 14 1.50 21.00
h. 1" Metal Screw pc 4 3.00 12.00

Sub - Total for F1 (As Submitted) 621.63


F2. Materials

a. 4.5mm Fiber Cement Board pc 0.365 450.00 164.25


b. Metal Furring pc 1.131 130.00 147.03
c. Carrying Channels pc 0.357 150.00 53.55
d. Hanger Bars/Rod pc 1 80.00 80.00
e. Channel clip pc 6 20.00 120.00
f. Wall Angle pc 0.238 100.00 23.80
g. Rivets pc 14 1.50 21.00
h. 1" Metal Screw pc 4 3.00 12.00

Sub - Total for F2 (As Evaluated) 621.63


G1. Direct Unit Cost (E1 + F1) - As Submitted 876.20
G2. Direct Unit Cost (E2 + F2) - As Evaluated 876.20
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 105.14
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 105.14
I1. Contractor's Profit (CP) - As Submitted 8% of G1 70.10
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 70.10
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 52.57
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 52.57
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,104.01
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,104.01

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(11)a1 Fascia Board (19mm, Fiber Cement Board)


Unit of Measurement : Lm
Output per hour : 3.600

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 0.50 101.45 50.73


b. Skilled Laborer 1 0.50 73.29 36.65

Sub - Total for A1 (As Submitted) 87.37


A2. Labor

a. Construction Foreman 1 0.50 101.45 50.73


b. Skilled Laborer 1 0.50 73.29 36.65

Sub - Total for A2 (As Evaluated) 87.37


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 8.74

Sub - Total for B1 (As Submitted) 8.74


B2. Equipment

a. Minor Tools (10% of Labor Cost) 8.74

Sub - Total for B2 (As Evaluated) 8.74


C1. Total (A1 + B1) 96.11
C2. Total (A2 + B2) 96.11
D1. Output per our - As Submitted = 3.600 Lm
D2. Output per our - As Evaluated = 3.600 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 26.70
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 26.70
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 2-12 x 300mm Fiber Cement Board m 1.000 145.00 145.00


b. 1" Metal Screws pc 12.000 3.00 36.00
c. Consumables (5% of Materials Cost) 9.05

Sub - Total for F1 (As Submitted) 190.05


F2. Materials

a. 2-12 x 300mm Fiber Cement Board m 1.000 145.00 145.00


b. 1" Metal Screws m³ 12.000 3.00 36.00
c. Consumables (5% of Materials Cost) 9.05

Sub - Total for F2 (As Evaluated) 190.05


G1. Direct Unit Cost (E1 + F1) - As Submitted 216.75
G2. Direct Unit Cost (E2 + F2) - As Evaluated 216.75
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 26.01
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 26.01
I1. Contractor's Profit (CP) - As Submitted 8% of G1 17.34
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 17.34
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13.00
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13.00
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 273.10
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 273.10

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


Unit of Measurement : m²
Output per hour : 5.560

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A1 (As Submitted) 287.66


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 287.66


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B1 (As Submitted) 28.77


B2. Equipment

a. Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B2 (As Evaluated) 28.77


C1. Total (A1 + B1) 316.43
C2. Total (A2 + B2) 316.43
D1. Output per our - As Submitted = 5.560 m²
D2. Output per our - As Evaluated = 5.560 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 56.91
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 56.91
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Reflective Insulation, 10 mm thk m² 1.000 135.00 135.00


b. Consumable Materials (5% of Mat'l. Cost) 6.75

Sub - Total for F1 (As Submitted) 141.75


F2. Materials

a. Reflective Insulation, 10 mm thk m² 1.000 135.00 135.00


b. Consumable Materials (5% of Mat'l. Cost) 6.75

Sub - Total for F2 (As Evaluated) 141.75


G1. Direct Unit Cost (E1 + F1) - As Submitted 198.66
G2. Direct Unit Cost (E2 + F2) - As Evaluated 198.66
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 23.84
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 23.84
I1. Contractor's Profit (CP) - As Submitted 8% of G1 15.89
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 15.89
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11.92
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11.92
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 250.31
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 250.31

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(1) Glazed Tiles and Trims


Unit of Measurement : m²
Output per hour : 1.365

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 5 1.00 73.29 366.45
c. Unskilled Laborer 5 1.00 56.46 282.30

Sub - Total for A1 (As Submitted) 750.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 5 1.00 73.29 366.45
c. Unskilled Laborer 5 1.00 56.46 282.30

Sub - Total for A2 (As Evaluated) 750.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% Labor Cost) 75.02

Sub - Total for B1 (As Submitted) 75.02


B2. Equipment

a. Minor Tools (10% Labor Cost) 75.02

Sub - Total for B2 (As Evaluated) 75.02


C1. Total (A1 + B1) 825.22
C2. Total (A2 + B2) 825.22
D1. Output per our - As Submitted = 1.365 m²
D2. Output per our - As Evaluated = 1.365 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 604.56
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 604.56
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ceramic Glazed Tiles m² 1.05 750.00 787.50


c. Portland Cement bags 0.325 250.00 81.25
d. Sand m³ 0.026 1,307.58 34.00
e. Tile Grout bags 0.125 250.00 31.25
f. Tile Adhesive (25kg) bags 0.143 250.00 35.75
g. Consumables (3% of Material Cost) 29.09

Sub - Total for F1 (As Submitted) 998.84


F2. Materials

a. Ceramic Glazed Tiles m² 1.05 750.00 787.50


c. Portland Cement bags 0.325 250.00 81.25
d. Sand m³ 0.026 1,307.58 34.00
e. Tile Grout bags 0.125 250.00 31.25
f. Tile Adhesive (25kg) bags 0.143 250.00 35.75
g. Consumables (3% of Material Cost) 29.09

Sub - Total for F2 (As Evaluated) 998.84


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,603.40
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,603.40
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 192.41
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 192.41
I1. Contractor's Profit (CP) - As Submitted 8% of G1 128.27
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 128.27
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 96.20
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 96.20
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 2,020.28
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 2,020.28

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(2) Unlglazed Tiles


Unit of Measurement : m²
Output per hour : 1.950

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 5 1.00 73.29 366.45
c. Unskilled Laborer 5 1.00 56.46 282.30

Sub - Total for A1 (As Submitted) 750.20


A2. Labor

a. Construction Foreman 1 1 101.45 101.45


b. Skilled Laborer 5 1 73.29 366.45
c. Unskilled Laborer 5 1 56.46 282.30

Sub - Total for A2 (As Evaluated) 750.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% Labor Cost) 75.02

Sub - Total for B1 (As Submitted) 75.02


B2. Equipment

a. Minor Tools (10% Labor Cost) 75.02

Sub - Total for B2 (As Evaluated) 75.02


C1. Total (A1 + B1) 825.22
C2. Total (A2 + B2) 825.22
D1. Output per our - As Submitted = 1.95 m²
D2. Output per our - As Evaluated = 1.95 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 423.19
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 423.19
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ceramic Unglazed Tiles m² 1.05 350.00 367.50


b. Portland Cement bags 0.325 250.00 81.25
c. Sand m³ 0.026 1,307.58 34.00
d. Tile Grout bags 0.125 250.00 31.25
e. Consumable (3% of Materials Cost) 25.70

Sub - Total for F1 (As Submitted) 539.70


F2. Materials

a. Ceramic Unglazed Tiles m² 1.05 350.00 367.50


b. Portland Cement bags 0.325 250.00 81.25
c. Sand m³ 0.026 1,307.58 34.00
d. Tile Grout bags 0.125 250.00 31.25
e. Consumable (3% of Materials Cost) 25.70

Sub - Total for F2 (As Evaluated) 539.70


G1. Direct Unit Cost (E1 + F1) - As Submitted 962.89
G2. Direct Unit Cost (E2 + F2) - As Evaluated 962.89
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 115.55
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 115.55
I1. Contractor's Profit (CP) - As Submitted 8% of G1 77.03
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 77.03
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 57.77
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 57.77
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,213.24
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,213.24

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(1)a Water Proofing Cement Base


Unit of Measurement : m²
Output per hour : 1.875

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 1.88 m²
D2. Output per our - As Evaluated = 1.88 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 135.64
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 135.64
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Cement - Based Water Proofing m² 1.05 55.00 57.75

Sub - Total for F1 (As Submitted) 57.75


F2. Materials

a. Cement - Based Water Proofing m² 1.05 55.00 57.75

Sub - Total for F2 (As Submitted) 57.75


G1. Direct Unit Cost (E1 + F1) - As Submitted 193.39
G2. Direct Unit Cost (E2 + F2) - As Evaluated 193.39
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 23.21
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 23.21
I1. Contractor's Profit (CP) - As Submitted 8% of G1 15.47
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 15.47
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11.60
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11.60
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 243.67
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 243.67

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)a Painting Works (Masonry/Concrete)


Unit of Measurement : m²
Output per hour : 2.100

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 304.49


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 304.49


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B1 (As Submitted) 30.45


B2. Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B2 (As Evaluated) 30.45


C1. Total (A1 + B1) 334.94
C2. Total (A2 + B2) 334.94
D1. Output per our - As Submitted = 2.100 m²
D2. Output per our - As Evaluated = 2.100 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 159.49
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 159.49
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Concrete Neutralizer gal 0.02 540.00 10.80


b. Concrete Sealer/Primer gal 0.04 644.00 25.76
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats only) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.72

Sub - Total for F1 (As Submitted) 120.18


F2. Materials

a. Concrete Neutralizer gal 0.02 540.00 10.80


b. Concrete Sealer/Primer gal 0.04 644.00 25.76
c. Patching Compound gal 0.05 550.00 27.50
d. Semi Gloss Latex (two coats only) gal 0.08 630.00 50.40
e. Consumables (5% of Materials Cost) 5.72

Sub - Total for F2 (As Evaluated) 120.18


G1. Direct Unit Cost (E1 + F1) - As Submitted 279.68
G2. Direct Unit Cost (E2 + F2) - As Evaluated 279.68
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 33.56
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 33.56
I1. Contractor's Profit (CP) - As Submitted 8% of G1 22.37
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 22.37
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 16.78
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 16.78
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 352.39
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 352.39

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)b Painting Works (Wood Painting)


Unit of Measurement : m²
Output per hour : 1.890

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 304.49


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 304.49


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B1 (As Submitted) 30.45


B2. Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B2 (As Evaluated) 30.45


C1. Total (A1 + B1) 334.94
C2. Total (A2 + B2) 334.94
D1. Output per our - As Submitted = 1.890 m²
D2. Output per our - As Evaluated = 1.890 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 177.22
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 177.22
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Glazzing Putty gal 0.05 550.00 27.50


b. Flat Wall Enamel gal 0.04 600.00 24.00
c. Enamel Quick Dry gal 0.04 600.00 24.00
d. Paint Thinner gal 0.063 280.00 17.64
e. Consumables (5% of Materials Cost) 4.66

Sub - Total for F1 (As Submitted) 97.80


F2. Materials

a. Glazzing Putty gal 0.05 550.00 27.50


b. Flat Wall Enamel gal 0.04 600.00 24.00
c. Enamel Quick Dry gal 0.04 600.00 24.00
d. Paint Thinner gal 0.063 280.00 17.64
e. Consumables (5% of Materials Cost) 4.66

Sub - Total for F2 (As Evaluated) 97.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 275.01
G2. Direct Unit Cost (E2 + F2) - As Evaluated 275.01
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 33.00
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 33.00
I1. Contractor's Profit (CP) - As Submitted 8% of G1 22.00
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 22.00
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 16.50
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 16.50
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 346.52
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 346.52

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)c Painting Works (Steel)


Unit of Measurement : m²
Output per hour : 2.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 304.49


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 304.49


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B1 (As Submitted) 30.45


B2. Equipment

a. Minor Tools (10% of Labor Cost) 30.45

Sub - Total for B2 (As Evaluated) 30.45


C1. Total (A1 + B1) 334.94
C2. Total (A2 + B2) 334.94
D1. Output per our - As Submitted = Area = 2 m²
D2. Output per our - As Evaluated = Area = 2 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 167.47
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 167.47
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Flat Wall Enamel gal 0.10 600.00 60.00
c. Paint Thinner gal 0.063 280.00 17.64
d. Consumable Materials (5% Material Cost) 4.86 4.86

Sub - Total for F1 (As Submitted) 102.10


F2. Materials

a. Red Oxide Primer gal 0.04 490.00 19.60


b. Flat Wall Enamel gal 0.10 600.00 60.00
c. Paint Thinner gal 0.063 280.00 17.64
d. Consumable Materials (5% Material Cost) 4.86 4.86

Sub - Total for F2 (As Evaluated) 102.10


G1. Direct Unit Cost (E1 + F1) - As Submitted 269.57
G2. Direct Unit Cost (E2 + F2) - As Evaluated 269.57
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 32.35
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 32.35
I1. Contractor's Profit (CP) - As Submitted 8% of G1 21.57
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 21.57
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 16.17
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 16.17
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 339.66
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 339.66

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014(1)b1 Prepainted metal Sheet (Corrugated, Long Span, above 0.427 mm thk
Unit of Measurement : m²
Output per hour : 2.076

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A1 (As Submitted) 287.66


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 2 1.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 287.66


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B1 (As Submitted) 28.77


B2. Equipment

Minor Tools (10% of Labor Cost) 28.77

Sub - Total for B2 (As Evaluated) 28.77


C1. Total (A1 + B1) 316.43
C2. Total (A2 + B2) 316.43
D1. Output per our - As Submitted = Area = 2.076 m²
D2. Output per our - As Evaluated = Area = 2.076 m²
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 152.42
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 152.42
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54

Sub - Total for F1 (As Submitted) 430.54


F2. Materials

a. pre-painted metal roofing sheet ga. 26 long span m² 1.05 360.00 378.00
b. J-bolt with washers pcs. 10.00 4.00 40.00
c. Consumables (3% of Matl Cost) 12.54

Sub - Total for F2 (As Evaluated) 430.54


G1. Direct Unit Cost (E1 + F1) - As Submitted 582.96
G2. Direct Unit Cost (E2 + F2) - As Evaluated 582.96
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 69.96
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 69.96
I1. Contractor's Profit (CP) - As Submitted 8% of G1 46.64
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 46.64
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 34.98
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 34.98
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 734.53
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 734.53

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)a Structural Steel (Trusses)


Unit of Measurement : Kg
Output per hour : 85.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor
Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
b. Skilled Laborer 3 0.49 73.29 107.74
c. Unskilled Laborer 3 0.49 56.46 83.00

Sub - Total for A1 (As Submitted) 551.68


A2. Labor
Fabrication
a. Construction Foreman 1 1.00 101.45 101.45
b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 2 1.00 56.46 112.92
Erection
b. Skilled Laborer 3 0.49 73.29 107.74
c. Unskilled Laborer 3 0.49 56.46 83.00

Sub - Total for A2 (As Evaluated) 551.68


No. of
Name and Capacity No of Unit/s Hourly Rate Amount (PhP)
B1. Hour/s
Equipment

a. Welding Machine (300) 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
d. Minor Tools (10 % of Labor Cost) 108.88

Sub - Total for B1 (As Submitted) 1,197.68


B2. Equipment

a. Welding Machine (300) 1 0.75 371.00 278.25


b. Cutting Outfit 1 0.25 45.45 11.36
c. Truck Mounted Crane (20-25 mt) 1 0.49 1,631.00 799.19
d. Minor Tools (10 % of Labor Cost) 108.88

Sub - Total for B2 (As Evaluated) 1,197.68


C1. Total (A1 + B1) 1,749.37
C2. Total (A2 + B2) 1,749.37
D1. Output per our - As Submitted = 85.000 Kg
D2. Output per our - As Evaluated = 85.000 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 20.58
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 20.58
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Structural Steel Truss Kg 1.00 60.00 60.00


b. Acetylene Kg 0.011 65.00 0.72
c. Oxygen Kg 0.022 50.00 1.10
d. Welding Rod Kg 0.020 110.00 2.20
e. Consumables Materials (3% of Matl. Cost) 1.92

Sub - Total for F1 (As Submitted) 65.94


F2. Materials

a. Structural Steel Truss Kg 1.000 60.00 60.00


b. Acetylene Kg 0.011 65.00 0.72
c. Oxygen Kg 0.022 50.00 1.10
d. Welding Rod Kg 0.020 110.00 2.20
e. Consumables Materials (3% of Matl. Cost) 1.92

Sub - Total for F2 (As Evaluated) 65.94


G1. Direct Unit Cost (E1 + F1) - As Submitted 86.52
G2. Direct Unit Cost (E2 + F2) - As Evaluated 86.52
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 10.38
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 10.38
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.92
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.92
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 5.19
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 5.19
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 109.01
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 109.01

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)b Structural Steel (Purlins)


Unit of Measurement : Kg
Output per hour : 90.450
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A1 (As Submitted) 473.87


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 2 1.00 73.29 146.58
c. Unskilled Laborer 4 1.00 56.46 225.84

Sub - Total for A2 (As Evaluated) 473.87


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Welding Machine (300) 2 1.00 371.00 742.00


b. Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B1 (As Submitted) 789.39


B2. Equipment

a. Welding Machine (300) 2 1.00 371.00 742.00


b. Minor Tools (10% of Labor Cost) 47.39

Sub - Total for B2 (As Evaluated) 789.39


C1. Total (A1 + B1) 1,263.26
C2. Total (A2 + B2) 1,263.26
D1. Output per our - As Submitted = 90.45 Kg
D2. Output per our - As Evaluated = 90.45 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 13.97
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 13.97
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Structural Steel Purlins Kgs 1.05 60.00 63.00


b. Welding Rod Kgs 0.02 110.00 2.20
c. Consumables (5% of Materials Cost) 3.26

Sub - Total for F1 (As Submitted) 68.46


F2. Materials

a. Structural Steel Purlins Kgs 1.05 60.00 63.00


b. Welding Rod Kgs 0.02 110.00 2.20
c. Consumables (5% of Materials Cost) 3.26

Sub - Total for F2 (As Evaluated) 68.46


G1. Direct Unit Cost (E1 + F1) - As Submitted 82.43
G2. Direct Unit Cost (E2 + F2) - As Evaluated 82.43
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 9.89
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 9.89
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.59
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.59
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4.95
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4.95
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 103.86
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 103.86

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(6) Metal Structure Accessories (Steel Plates)


Unit of Measurement : Kg
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 12.995 Kg
D2. Output per our - As Evaluated = 12.995 Kg
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 19.57
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 19.57
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Steel Plates Kg 1.05 60.00 63.00


b. Consumables Materials (3% of Matl. Cost) 1.89

Sub - Total for F1 (As Submitted) 64.89


F2. Materials

a. Steel Plates kgs 1.05 60.00 63.00


b. Consumables Materials (3% of Matl. Cost) 1.89

Sub - Total for F2 (As Evaluated) 64.89


G1. Direct Unit Cost (E1 + F1) - As Submitted 84.46
G2. Direct Unit Cost (E2 + F2) - As Evaluated 84.46
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 10.14
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 10.14
I1. Contractor's Profit (CP) - As Submitted 8% of G1 6.76
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 6.76
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 5.07
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 5.07
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 106.42
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 106.42

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(7)b Metal Structure Accessories (Sagrods)


Unit of Measurement : Kgs
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 12.995 Kgs
D2. Output per our - As Evaluated = 12.995 Kgs
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 19.57
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 19.57
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Sagrod with nuts & Bolts kg 1.05 37.88 39.77

Sub - Total for F1 (As Submitted) 39.77


F2. Materials

a. Sagrod with nuts & Bolts kgs 1.05 37.88 39.77

Sub - Total for F2 (As Evaluated) 39.77


G1. Direct Unit Cost (E1 + F1) - As Submitted 59.34
G2. Direct Unit Cost (E2 + F2) - As Evaluated 59.34
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 7.12
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 7.12
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.75
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.75
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.56
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.56
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 74.77
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 74.77

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : Kgs
Output per hour : 12.995
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

a. Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 12.995 Kgs
D2. Output per our - As Evaluated = 12.995 Kgs
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 19.57
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 19.57
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. Cross Bracing kg 1.05 37.88 39.77


b. Consumables 1.19

Sub - Total for F1 (As Submitted) 40.97


F2. Materials

a. Cross Bracing kg 1.05 37.88 39.77


b. Consumables

Sub - Total for F2 (As Evaluated) 39.77


G1. Direct Unit Cost (E1 + F1) - As Submitted 60.54
G2. Direct Unit Cost (E2 + F2) - As Evaluated 59.34
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 7.26
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 7.12
I1. Contractor's Profit (CP) - As Submitted 8% of G1 4.84
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 4.75
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 3.63
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 3.63
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 76.28
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 76.28

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : ea.
Output per hour : 1.000
No. of
Designation No. of Person/s Hourly Rate Amount (PhP)
A1. Hour/s
Labor

a. Construction Foreman 1 0.15 101.45 15.22


b. Skilled Laborer 1 0.15 73.29 10.99
c. Unskilled Laborer 1 0.15 56.46 8.47

Sub - Total for A1 (As Submitted) 34.68


A2. Labor

a. Construction Foreman 1 0.15 101.45 15.22


b. Skilled Laborer 1 0.15 73.29 10.99
c. Unskilled Laborer 1 0.15 56.46 8.47

Sub - Total for A2 (As Evaluated) 34.68


B1. Name and Capacity No of Unit/s No. of Hourly Rate Amount (PhP)
Equipment

a. Minor Tools (10% of Labor Cost) 3.47

Sub - Total for B1 (As Submitted) 3.47


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3.47

Sub - Total for B2 (As Evaluated) 3.47


C1. Total (A1 + B1) 38.15
C2. Total (A2 + B2) 38.15
D1. Output per our - As Submitted = 1 ea.
D2. Output per our - As Evaluated = 1 ea.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 38.15
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 38.15
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials

a. 16mm Ø turn buckles Pc 1.00 200.00 200.00

Sub - Total for F1 (As Submitted) 200.00


F2. Materials

a. 16mm Ø turn buckles kgs 1.00 200.00 200.00

Sub - Total for F2 (As Evaluated) 200.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 238.15
G2. Direct Unit Cost (E2 + F2) - As Evaluated 238.15
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 28.58
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 28.58
I1. Contractor's Profit (CP) - As Submitted 8% of G1 19.05
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 19.05
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14.29
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14.29
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 300.07
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 300.07

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a1 Fabricated Metal Roofing Accessory (Ridge/Hip Rolls, Ga. 26)
Unit of Measurement : L.m.
Output per hour : 10.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 10.00 Lm
D2. Output per our - As Evaluated = 10.00 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 25.43
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 25.43
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted ridge roll, ga.24 (0.701mm) x 2.44mm m 1.05 165.00 173.25


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.05

Sub - Total for F1 (As Submitted) 207.80


F2. Materials

a. pre-painted ridge roll, ga.24 (0.701mm) x 2.44mm m 1.05 165.00 173.25


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.05

Sub - Total for F2 (As Evaluated) 207.80


G1. Direct Unit Cost (E1 + F1) - As Submitted 233.23
G2. Direct Unit Cost (E2 + F2) - As Evaluated 233.23
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 27.99
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 27.99
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.66
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.66
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 13.99
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 13.99
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 293.88
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 293.88

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)a2 Fabricated Metal Roofing Accessory (Flashing, Ga. 26)
Unit of Measurement : L.m.
Output per hour : 10.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 10.00 Lm
D2. Output per our - As Evaluated = 10.00 Lm
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 25.43
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 25.43
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted flashing, ga.24 (0.701mm) x 2.44mm m 1.05 168.00 176.40


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.15

Sub - Total for F1 (As Submitted) 211.05


F2. Materials

a. pre-painted flashing, ga.24 (0.701mm) x 2.44mm m 1.05 168.00 176.40


b. Blind Rivets pc 19.00 1.50 28.50
c. Consumables (3% of Materials Cost) 6.15

Sub - Total for F2 (As Evaluated) 211.05


G1. Direct Unit Cost (E1 + F1) - As Submitted 236.48
G2. Direct Unit Cost (E2 + F2) - As Evaluated 236.48
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 28.38
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 28.38
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18.92
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18.92
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14.19
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14.19
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 297.96
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 297.96

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)b1 Fabricated Metal Roofing Accessory (Gauge 24,Gutter)


Unit of Measurement : L.m.
Output per hour : 11.800

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A1 (As Submitted) 231.20


A2. Labor

a. Construction Foreman 1 1.00 101.45 101.45


b. Skilled Laborer 1 1.00 73.29 73.29
c. Unskilled Laborer 1 1.00 56.46 56.46

Sub - Total for A2 (As Evaluated) 231.20


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B1 (As Submitted) 23.12


B2. Equipment

Minor Tools (10% of Labor Cost) 23.12

Sub - Total for B2 (As Evaluated) 23.12


C1. Total (A1 + B1) 254.32
C2. Total (A2 + B2) 254.32
D1. Output per our - As Submitted = 11.80 L.m.
D2. Output per our - As Evaluated = 11.80 L.m.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 21.55
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 21.55
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. pre-painted gutter, ga.24 (0.701mm) x 2.44mm m 1.00 175.00 175.00


b. 12" x 1" Plain GI Strap pc 3.00 40.00 120.00
c. Blind Rivets pc 16.00 1.50 24.00
d. Consumables (3% of Materials Cost) 9.57

Sub - Total for F1 (As Submitted) 328.57


F2. Materials

a. pre-painted gutter, ga.24 (0.701mm) x 2.44mm m 1.00 175.00 175.00


b. 12" x 1" Plain GI Strap pc 3.00 40.00 120.00
c. Blind Rivets pc 16.00 1.50 24.00
d. Consumables (3% of Materials Cost) 9.57

Sub - Total for F2 (As Evaluated) 328.57


G1. Direct Unit Cost (E1 + F1) - As Submitted 350.12
G2. Direct Unit Cost (E2 + F2) - As Evaluated 350.12
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 42.01
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 42.01
I1. Contractor's Profit (CP) - As Submitted 8% of G1 28.01
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 28.01
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 21.01
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 21.01
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 441.15
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 441.15

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 64.00 101.45 6,492.80


b. Skilled Laborer 1 64.00 73.29 4,690.56
c. Unskilled Laborer 2 64.00 56.46 7,226.88

Sub - Total for A1 (As Submitted) 18,410.24


A2. Labor

a. Construction Foreman 1 64.00 101.45 6,492.80


b. Skilled Laborer 1 64.00 73.29 4,690.56
c. Unskilled Laborer 2 64.00 56.46 7,226.88

Sub - Total for A2 (As Evaluated) 18,410.24


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 1,841.02

Sub - Total for B1 (As Submitted) 1,841.02


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1,841.02

Sub - Total for B2 (As Evaluated) 1,841.02


C1. Total (A1 + B1) 20,251.26
C2. Total (A2 + B2) 20,251.26
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 20,251.26
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 20,251.26
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. PVC pipe, 150mm dia.x3m, S-1000 pcs 19.000 1,200.00 22,800.00


b. PVC pipe, 100mm dia.x3m, S-1000 pcs 12.000 700.00 8,400.00
c. PVC pipe, 75mm dia.x3m, S-1000 pcs 2.000 480.00 960.00
d. PVC, 50mm dia.x3m, S-1000 (Vent) pcs 14.000 270.00 3,780.00
e. Elbow, 100mm dia-90 deg. bend pcs 9.000 85.00 765.00
f. Elbow, 50mm dia-90 deg bend pcs 4.000 26.00 104.00
g. Wye, 100mm dia. pcs 6.000 173.00 1,038.00
h. Wye Reducer, 100mm dia.-75mm dia pcs 1.000 163.00 163.00
i. Wye Reducer, 100mm dia.-50mm dia. pcs 9.000 140.00 1,260.00
j. PVC Tee 100mm dia.x 100mm dia. pcs 4.000 130.00 520.00
k. PVC Tee 50mm dia.x50mm dia. pcs 11.000 40.00 440.00
l. PVC Tee Reducer, 75mm dia.x 50mm dia. pcs 1.000 75.00 75.00
m. Clean out with cover, 100mm dia. pcs 18.000 40.00 720.00
n. Clean out with cover, 75mm dia. pcs 1.000 25.00 25.00
o. PVC P-trap, 50mm dia. pcs 32.000 110.00 3,520.00
p. PVC Solvent Cement 400 cc can 7.000 155.00 1,085.00
q. Consumables (5% of Materials) Lot 1.000 2,282.75 2,282.75

Sub - Total for F1 (As Submitted) 47,937.75


F2. Materials

a. PVC pipe, 150mm dia.x3m, S-1000 pcs 19.000 1,200.00 22,800.00


b. PVC pipe, 100mm dia.x3m, S-1000 pcs 12.000 700.00 8,400.00
c. PVC pipe, 75mm dia.x3m, S-1000 pcs 2.000 480.00 960.00
d. PVC, 50mm dia.x3m, S-1000 (Vent) pcs 14.000 270.00 3,780.00
e. Elbow, 100mm dia-90 deg. bend pcs 9.000 85.00 765.00
f. Elbow, 50mm dia-90 deg bend pcs 4.000 26.00 104.00
g. Wye, 100mm dia. pcs 6.000 173.00 1,038.00
h. Wye Reducer, 100mm dia.-75mm dia pcs 1.000 163.00 163.00
i. Wye Reducer, 100mm dia.-50mm dia. pcs 9.000 140.00 1,260.00
j. PVC Tee 100mm dia.x 100mm dia. pcs 4.000 130.00 520.00
k. PVC Tee 50mm dia.x50mm dia. pcs 11.000 40.00 440.00
l. PVC Tee Reducer, 75mm dia.x 50mm dia. pcs 1.000 75.00 75.00
m. Clean out with cover, 100mm dia. pcs 18.000 40.00 720.00
n. Clean out with cover, 75mm dia. pcs 1.000 25.00 25.00
o. PVC P-trap, 50mm dia. pcs 32.000 110.00 3,520.00
p. PVC Solvent Cement 400 cc can 7.000 155.00 1,085.00
q. Consumables (5% of Materials) Lot 1.000 2,282.75 2,282.75

Sub - Total for F2 (As Evaluated) 47,937.75


G1. Direct Unit Cost (E1 + F1) - As Submitted 68,189.01
G2. Direct Unit Cost (E2 + F2) - As Evaluated 68,189.01
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 8,182.68
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 8,182.68
I1. Contractor's Profit (CP) - As Submitted 8% of G1 5,455.12
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 5,455.12
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 4,091.34
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 4,091.34
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 85,918.16
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 85,918.16

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(24) Cold Water lines


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 112.00 101.45 11,362.40


b. Skilled Laborer 1 112.00 73.29 8,208.48
c. Unskilled Laborer 2 112.00 56.46 12,647.04

Sub - Total for A1 (As Submitted) 32,217.92


A2. Labor

a. Construction Foreman 1 112.00 101.45 11,362.40


b. Skilled Laborer 1 112.00 73.29 8,208.48
c. Unskilled Laborer 2 112.00 56.46 12,647.04

Sub - Total for A2 (As Evaluated) 32,217.92


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 3,221.79

Sub - Total for B1 (As Submitted) 3,221.79


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3,221.79

Sub - Total for B2 (As Evaluated) 3,221.79


C1. Total (A1 + B1) 35,439.71
C2. Total (A2 + B2) 35,439.71
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 35,439.71
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 35,439.71
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. PPRC Pipe, 75mm dia. X 4m, PN 16 pcs 14.00 4,039.27 56,549.78


b. PPRC Pipe, 32mm dia. X 4m, PN 16 pcs 32.00 736.28 23,560.96
c. PPRC Pipe, 65mm dia. X 4m, PN 16 pcs 14.00 2,765.00 38,710.00
d. PPRC Pipe, 50mm dia. X 4m, PN 16 pcs 5.00 1,753.80 8,769.00
e. PP-R Coupling Reducer 32x25mm dia. pcs 2.00 15.80 31.60
f. PP-R Coupling Reducer 32x20mm dia. pcs 5.00 14.22 71.10
g. PP-R Elbow 25mm dia.-90 deg pcs 1.00 20.54 20.54
h. PP-R Elbow 20mm dia.- 90 deg pcs 4.00 12.64 50.56
i. PP-R Tee 20mm dia. pcs 5.00 14.80 74.00
j. PPR-Tee Reducer 32x20mm dia. pcs 2.00 32.52 65.04
k. PPR-Tee Reducer 25x20mm dia. pcs 2.00 26.86 53.72
k. Consumables (5% of Materials) 3,570.33

Sub - Total for F1 (As Submitted) 131,526.63


F2. Materials

a. PPRC Pipe, 75mm dia. X 4m, PN 16 pcs 14.000 4,039.27 56,549.78


b. PPRC Pipe, 32mm dia. X 4m, PN 16 pcs 32.000 736.28 23,560.96
c. PPRC Pipe, 65mm dia. X 4m, PN 16 pcs 14.000 2,765.00 38,710.00
d. PPRC Pipe, 50mm dia. X 4m, PN 16 pcs 5.000 1,753.80 8,769.00
e. PP-R Coupling Reducer 32x25mm dia. pcs 2.000 15.80 31.60
f. PP-R Coupling Reducer 32x20mm dia. pcs 5.000 14.22 71.10
g. PP-R Elbow 25mm dia.-90 deg pcs 1.000 20.54 20.54
h. PP-R Elbow 20mm dia.- 90 deg pcs 4.000 12.64 50.56
i. PP-R Tee 20mm dia. pcs 5.000 14.80 74.00
j. PPR-Tee Reducer 32x20mm dia. pcs 2.000 32.52 65.04
k. PPR-Tee Reducer 25x20mm dia. pcs 2.000 26.86 53.72
k. Consumables (5% of Materials) 3,570.33

Sub - Total for F2 (As Evaluated) 131,526.63


G1. Direct Unit Cost (E1 + F1) - As Submitted 166,966.34
G2. Direct Unit Cost (E2 + F2) - As Evaluated 166,966.34
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 20,035.96
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 20,035.96
I1. Contractor's Profit (CP) - As Submitted 8% of G1 13,357.31
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 13,357.31
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 10,017.98
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 10,017.98
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 210,377.59
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 210,377.59

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 72.00 101.45 7,304.40


b. Skilled Laborer 2 72.00 73.29 10,553.76
c. Unskilled Laborer 4 72.00 56.46 16,260.48

Sub - Total for A1 (As Submitted) 34,118.64


A2. Labor

a. Construction Foreman 1 72.00 101.45 7,304.40


b. Skilled Laborer 2 72.00 73.29 10,553.76
c. Unskilled Laborer 4 72.00 56.46 16,260.48

Sub - Total for A2 (As Evaluated) 34,118.64


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 3,411.86

Sub - Total for B1 (As Submitted) 3,411.86


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3,411.86

Sub - Total for B2 (As Evaluated) 3,411.86


C1. Total (A1 + B1) 37,530.50
C2. Total (A2 + B2) 37,530.50
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 37,530.50
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 37,530.50
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. PVC Drain Pipe, 100mm dia.x3m pcs 86.00 700.00 60,200.00


b. PVC Drain Pipe, 150mm dia.x3m pcs 10.00 1,975.25 19,752.50
c. Roof Drain (Dome-type strainer) pcs 26.00 500.00 13,000.00
d. PVC Sanitary Pipe, 75mm dia.x 3m, S-1000 pcs 4.00 480.00 1,920.00
e. Elbow, 75mm dia.-45 deg bend pcs 8.00 54.00 432.00
f. PVC solvent, 400cc cans 2.00 155.00 310.00
g. Consumables 5% 4,780.73

Sub - Total for F1 (As Submitted) 100,395.23


F2. Materials

a. PVC Drain Pipe, 100mm dia.x3m pcs 86.00 700.00 60,200.00


b. PVC Drain Pipe, 150mm dia.x3m pcs 10.00 1,975.25 19,752.50
c. Roof Drain (Dome-type strainer) pcs 26.00 500.00 13,000.00
d. PVC Sanitary Pipe, 75mm dia.x 3m, S-1000 pcs 4.00 480.00 1,920.00
e. Elbow, 75mm dia.-45 deg bend pcs 8.00 54.00 432.00
f. PVC solvent, 400cc cans 2.00 155.00 310.00
g. Consumables 5% 4,780.73

Sub - Total for F2 (As Evaluated) 100,395.23


G1. Direct Unit Cost (E1 + F1) - As Submitted 137,925.73
G2. Direct Unit Cost (E2 + F2) - As Evaluated 137,925.73
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 16,551.09
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 16,551.09
I1. Contractor's Profit (CP) - As Submitted 8% of G1 11,034.06
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11,034.06
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 8,275.54
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 8,275.54
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 173,786.42
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 173,786.42

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(4) Plumbing FIxtures


Unit of Measurement : L.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 160.00 101.45 16,232.00


b. Skilled Laborer 1 160.00 73.29 11,726.40
c. Unskilled Laborer 1 160.00 56.46 9,033.60

Sub - Total for A1 (As Submitted) 36,992.00


A2. Labor

a. Construction Foreman 1 160.00 101.45 16,232.00


b. Skilled Laborer 1 160.00 73.29 11,726.40
c. Unskilled Laborer 1 160.00 56.46 9,033.60

Sub - Total for A2 (As Evaluated) 36,992.00


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment
a. Minor Tools (10% of Labor Cost) 3,699.20

Sub - Total for B1 (As Submitted) 3,699.20


B2. Equipment

a. Minor Tools (10% of Labor Cost) 3,699.20

Sub - Total for B2 (As Evaluated) 3,699.20


C1. Total (A1 + B1) 40,691.20
C2. Total (A2 + B2) 40,691.20
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 40,691.20
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 40,691.20
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Water Closet complete w/ fittings & accs. sets 10.00 7,500.00 75,000.00
b. Urinal (trough) sets 2.00 4,600.00 9,200.00
c. Concrete Counter Sink (1 Faucet) sets 2.00 2,895.00 5,790.00
e. Concrete Counter Sink (3 Faucet) sets 4.00 6,028.00 24,112.00
f. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 4,600.00 9,200.00
g. Gate Valve, 32mm dia pcs 3.00 292.00 876.00
h. Gate Valve 20mm dia pcs 3.00 225.00 675.00
i. Gate Valve, 50mm dia pcs 2.00 980.00 1,960.00
j. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k. S.S. Floor Drain 4'x4'' pcs 19.00 250.00 4,750.00
l. Mirror m² 5.10 7,530.88 38,407.49
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 34.00 155.00 5,270.00
p. Consumables 5% 9,259.72

Sub - Total for F1 (As Submitted) 194,454.21


F2. Materials

a. Water Closet complete w/ fittings & accs. sets 10.00 7,500.00 75,000.00
b. Urinal (trough) sets 2.00 4,600.00 9,200.00
c. Concrete Counter Sink (1 Faucet) sets 2.00 2,895.00 5,790.00
e. Concrete Counter Sink (3 Faucet) sets 4.00 6,028.00 24,112.00
f. Wall Hung Lavatory, complete w/ fittings & accs. sets 2.00 4,600.00 9,200.00
g. Gate Valve, 32mm dia pcs 3.00 292.00 876.00
h. Gate Valve 20mm dia pcs 3.00 225.00 675.00
i. Gate Valve, 50mm dia pcs 2.00 980.00 1,960.00
j. Check Valve, 50mm dia. pcs 1.00 954.00 954.00
k. S.S. Floor Drain 4'x4'' pcs 19.00 250.00 4,750.00
l. Mirror m² 5.10 7,530.88 38,407.49
m. Handrail (PWD) sets 2.00 4,500.00 9,000.00
n. Faucet, Hose Bibb, Brass 12mm dia. pcs 34.00 155.00 5,270.00
p. Consumables 5% 9,259.72

Sub - Total for F2 (As Evaluated) 194,454.21


G1. Direct Unit Cost (E1 + F1) - As Submitted 235,145.41
G2. Direct Unit Cost (E2 + F2) - As Evaluated 235,145.41
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 28,217.45
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 28,217.45
I1. Contractor's Profit (CP) - As Submitted 8% of G1 18,811.63
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 18,811.63
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 14,108.72
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 14,108.72
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 296,283.22
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 296,283.22

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(11) Septic Vault (Concrete / CHB)


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 25.00 101.45 2,536.25


b. Skilled Laborer 4 25.00 73.29 7,329.00
c. Unskilled Laborer 6 25.00 56.46 8,469.00

Sub - Total for A1 (As Submitted) 18,334.25


A2. Labor

a. Construction Foreman 1 25.00 101.45 2,536.25


b. Skilled Laborer 4 25.00 73.29 7,329.00
c. Unskilled Laborer 6 25.00 56.46 8,469.00

Sub - Total for A2 (As Evaluated) 18,334.25


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 1,833.43

Sub - Total for B1 (As Submitted) 1,833.43


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1,833.43

Sub - Total for B2 (As Evaluated) 1,833.43


C1. Total (A1 + B1) 20,167.68
C2. Total (A2 + B2) 20,167.68
D1. Output per our - As Submitted = 1.000 L.s.
D2. Output per our - As Evaluated = 1.000 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 20,167.68
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 20,167.68
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 13.71 5,225.00 71,634.75


b. Reinforcement Steel Bars, Gr. 40 kgs 571.17 37.50 21,418.88
c. Plaster Finish m2 12.16 84.25 1,024.48
d. Cement - Based Water Proofing m2 170.00 55.00 9,350.00
e. 6" CHB m2 5.00 225.00 1,125.00
f. 4"CHB m2 2.50 187.50 468.75

Sub - Total for F1 (As Submitted) 105,021.86


F2. Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 13.71 5,225.00 71,634.75


b. Reinforcement Steel Bars, Gr. 40 kgs 571.17 37.50 21,418.88
c. Plaster Finish m2 12.16 84.25 1,024.48
d. Cement - Based Water Proofing m2 170.00 55.00 9,350.00
e. 6" CHB m2 5.00 225.00 1,125.00
f. 4"CHB m2 2.50 187.50 468.75

Sub - Total for F2 (As Evaluated) 105,021.86


G1. Direct Unit Cost (E1 + F1) - As Submitted 125,189.53
G2. Direct Unit Cost (E2 + F2) - As Evaluated 125,189.53
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 15,022.74
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 15,022.74
I1. Contractor's Profit (CP) - As Submitted 8% of G1 10,015.16
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 10,015.16
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 7,511.37
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 7,511.37
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 157,738.81
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 157,738.81

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(5)b Catch Basin (CHB)


Unit of Measurement : Ea
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 2.00 101.45 202.90


b. Skilled Laborer 1 2.00 73.29 146.58
c. Unskilled Laborer 1 2.00 56.46 112.92

Sub - Total for A1 (As Submitted) 462.40


A2. Labor

a. Construction Foreman 1 2.00 101.45 202.90


b. Skilled Laborer 1 2.00 73.29 146.58
c. Unskilled Laborer 1 2.00 56.46 112.92

Sub - Total for A2 (As Evaluated) 462.40


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 46.24

Sub - Total for B1 (As Submitted) 46.24


B2. Equipment

a. Minor Tools (10% of Labor Cost) 46.24

Sub - Total for B2 (As Evaluated) 46.24


C1. Total (A1 + B1) 508.64
C2. Total (A2 + B2) 508.64
D1. Output per our - As Submitted = 1.000 Ea
D2. Output per our - As Evaluated = 1.000 Ea
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 508.64
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 508.64
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 0.07 5,225.00 365.75


b. Reinforcing Steel Bars Deformed kgs 8.63 37.50 323.63
c. Grade 40
Masonry m2 0.80 187.50 150.00
d. Plaster Finish m2 1.76 110.30 194.14

Sub - Total for F1 (As Submitted) 1,033.51


F2. Materials

a. Ready mix Concrete 3000 Psi @ 28 days m3 0.070 5,225.00 365.75


b. Reinforcing Steel Bars Deformed Grade 40 kgs 8.630 37.50 323.63
c. Masonry m2 0.800 187.50 150.00
d. Plaster Finish m2 1.760 110.30 194.14

Sub - Total for F2 (As Evaluated) 1,033.51


G1. Direct Unit Cost (E1 + F1) - As Submitted 1,542.15
G2. Direct Unit Cost (E2 + F2) - As Evaluated 1,542.15
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 185.06
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 185.06
I1. Contractor's Profit (CP) - As Submitted 8% of G1 123.37
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 123.37
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 92.53
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 92.53
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,943.11
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,943.11

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in)
Unit of Measurement : L.s.
Output per hour : 1.000

No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor

a. Construction Foreman 1 54.00 101.45 5,478.30


b. Electrician 1 91.00 72.73 6,618.43
c. Unskilled Laborer 1 91.00 56.46 5,137.86

Sub - Total for A1 (As Submitted) 17,234.59


A2. Labor

a. Construction Foreman 1 54.00 101.45 5,478.30


b. Electrician 1 91.00 72.73 6,618.43
c. Unskilled Laborer 1 91.00 56.46 5,137.86

Sub - Total for A2 (As Evaluated) 17,234.59


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 1,723.46

Sub - Total for B1 (As Submitted) 1,723.46


B2. Equipment

Minor Tools (10% of Labor Cost) 1,723.46

Sub - Total for B2 (As Evaluated) 1,723.46


C1. Total (A1 + B1) 18,958.05
C2. Total (A2 + B2) 18,958.05
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 18,958.05
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 18,958.05
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 20mmØ PVC conduit length 465.00 98.00 45,570.00


b. 25mmØ PVC conduit length 4.00 125.00 500.00
c. 40mmØ RSC conduit length 4.00 1,069.50 4,278.00
c. 65mmØ RSC conduit length 6.00 2,233.35 13,400.10
c. 90mmØ RSC conduit length 4.00 3,580.46 14,321.84
c. 65mmØ RSC elbow pc 2.00 889.45 1,778.90
c. 90mmØ RSC elbow pc 2.00 2,348.15 4,696.30
d. 20mmØ PVC adpater pc 675.00 14.00 9,450.00
e. 25mmØ PVC adapter pc 4.00 17.00 68.00
f. 20mmØ locknut and bushing pc 675.00 10.00 6,750.00
g. 40mmØ RSC Elbow pc 4.00 289.80 1,159.20
. 25mmØ locknut and bushing pc 4.00 15.00 60.00
i. 20mmØ liquidtight flexible metal conduit m 3.00 20.00 60.00
j. 20mmØ connector pc 2.00 10.00 20.00
k. Utility box, deep type pc 115.00 35.00 4,025.00
l. junction box, deep type pc 155.00 32.00 4,960.00
m. 90mmØ entrance cap pc 1.00 304.00 304.00
n. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F1 (As Submitted) 113,801.34


F2. Materials

a. 20mmØ PVC conduit length 465.00 98.00 45,570.00


b. 25mmØ PVC conduit length 4.00 125.00 500.00
c. 40mmØ RSC conduit length 4.00 1,069.50 4,278.00
c. 40mmØ RSC conduit length 6.00 2,233.35 13,400.10
c. 40mmØ RSC conduit length 6.00 2,233.35 13,400.10
c. 40mmØ RSC conduit length 4.00 3,580.46 14,321.84
d. 20mmØ PVC adpater pc 675.00 14.00 9,450.00
e. 25mmØ PVC adapter pc 4.00 17.00 68.00
f. 20mmØ locknut and bushing pc 675.00 10.00 6,750.00
g. 40mmØ RSC Elbow pc 4.00 289.80 1,159.20
. 25mmØ locknut and bushing pc 4.00 15.00 60.00
i. 20mmØ liquidtight flexible metal conduit m 3.00 20.00 60.00
j. 20mmØ connector pc 2.00 10.00 20.00
k. Utility box, deep type pc 115.00 35.00 4,025.00
l. junction box, deep type pc 155.00 32.00 4,960.00
m. 40mmØ entrance cap pc 1.00 304.00 304.00
n. 16mmØx2.4m ground rod pc 2.00 1,200.00 2,400.00

Sub - Total for F2 (As Evaluated) 120,726.24


G1. Direct Unit Cost (E1 + F1) - As Submitted 132,759.39
G2. Direct Unit Cost (E2 + F2) - As Evaluated 139,684.29
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 15,931.13
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 16,762.11
I1. Contractor's Profit (CP) - As Submitted 8% of G1 10,620.75
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 11,174.74
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 7,965.56
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 7,965.56
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 167,276.83
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 167,276.83

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101(33) Wires and Wiring Devices


Unit of Measurement : L.s.
Output per hour : 1.000
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor
a. Construction Foreman 1 96.00 101.45 9,739.20
b. Electrician 1 96.00 72.73 6,982.08
c. Unskilled Laborer 1 96.00 56.46 5,420.16

Sub - Total for A1 (As Submitted) 22,141.44


A2. Labor
a. Construction Foreman 1 96.00 101.45 9,739.20
b. Electrician 1 96.00 72.73 6,982.08
c. Unskilled Laborer 1 96.00 56.46 5,420.16

Sub - Total for A2 (As Evaluated) 22,141.44


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 2,214.14

Sub - Total for B1 (As Submitted) 2,214.14


B2. Equipment

Minor Tools (10% of Labor Cost) 2,214.14

Sub - Total for B2 (As Evaluated) 2,214.14


C1. Total (A1 + B1) 24,355.58
C2. Total (A2 + B2) 24,355.58
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 24,355.58
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 24,355.58
F1. Name and Specification Unit Quantity Unit Cost Amount (PhP)
Materials
a. 3.5mm2 THHN wire,stranded m 2350.00 35.00 82,250.00
b. 5.5mm2 THHN wire,stranded m 18.00 45.00 810.00
c. 38.0mm2 THHN, wire, stranded m 54.00 292.60 15,800.40
d. 2.0mm2 TW wire, stranded m 264.00 22.00 5,808.00
e. 3.5mm2 TW wire, stranded m 1170.00 35.00 40,950.00
f. 5.5mm2 TW wire stranded m 21.00 45.00 945.00
g. 14.0mm2 TW wire stranded m 36.00 86.00 3,096.00
h. one gang switch set 16.00 95.00 1,520.00
i. two gang switch set 20.00 130.00 2,600.00
j. three way switch set 18.00 165.00 2,970.00
k. Duplex C.O. grounding type, 15A, 250V set 20.00 330.00 6,600.00
l. set 4.00 420.00 1,680.00
Duplex C.O. grounding type, 250 C, weatherproof
m.
n. KWHR meter set 1.00 2,200.00 2,200.00
o. Tape, bolt&nut, mica tube, terminal lugs, JB cover lot 1.00 3,000.00 3,000.00
clamps, screw and anchors
Sub - Total for F1 (As Submitted) 170,229.40
F2. Materials
a. 3.5mm2 THHN wire,stranded m 2350.00 35.00 82,250.00
b. 5.5mm2 THHN wire,stranded m 18.00 45.00 810.00
c. 38.0mm2 THHN, wire, stranded m 54.00 292.60 15,800.40
d. 2.0mm2 TW wire, stranded m 264.00 22.00 5,808.00
e. 3.5mm2 TW wire, stranded m 1170.00 35.00 40,950.00
f. 5.5mm2 TW wire stranded m 21.00 45.00 945.00
g. 14.0mm2 TW wire stranded m 36.00 86.00 3,096.00
h. one gang switch set 16.00 95.00 1,520.00
i. two gang switch set 20.00 130.00 2,600.00
j. three way switch set 18.00 165.00 2,970.00
k. Duplex C.O. grounding type, 15A, 250V set 20.00 330.00 6,600.00
l. set 4.00 420.00 1,680.00
Duplex C.O. grounding type, 250 C, weatherproof
m.
n. KWHR meter set 1.00 2,200.00 2,200.00
o. Tape, bolt&nut, mica tube, terminal lugs, JB cover lot 1.00 8,000.00 8,000.00

Sub - Total for F2 (As Evaluated) 175,229.40


G1. Direct Unit Cost (E1 + F1) - As Submitted 194,584.98
G2. Direct Unit Cost (E2 + F2) - As Evaluated 199,584.98
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 23,350.20
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 23,950.20
I1. Contractor's Profit (CP) - As Submitted 8% of G1 15,566.80
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 15,966.80
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 11,675.10
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 11,675.10
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 245,177.08
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 245,177.08

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102(1) Panel Board with Main Breaker


Unit of Measurement : L.s.
Output per hour : 1.000
No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor

a. Construction Foreman 1 24.00 101.45 2,434.80


b. Electrician 1 24.00 72.73 1,745.52
c. Unskilled Laborer 2 24.00 56.46 2,710.08

Sub - Total for A1 (As Submitted) 6,890.40


A2. Labor

a. Construction Foreman 1 24.00 101.45 2,434.80


b. Electrician 1 24.00 72.73 1,745.52
c. Unskilled Laborer 2 24.00 56.46 2,710.08

Sub - Total for A2 (As Evaluated) 6,890.40


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 689.04

Sub - Total for B1 (As Submitted) 689.04


B2. Equipment

Minor Tools (10% of Labor Cost) 689.04

Sub - Total for B2 (As Evaluated) 689.04


C1. Total (A1 + B1) 7,579.44
C2. Total (A2 + B2) 7,579.44
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 7,579.44
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 7,579.44
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. MDP set 1.00 37,602.50 37,602.50


Main: 500at, 600af, 3p, 240v, 42 KAIC
Br.: 1 - 60at, 100af, 2p, 240v
2 - 50at, 100af, 2p, 240v
1 - 400at, 400af, 3p, 240v

a. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p(lugs only)
Br.: 3 - 15at, 50af, 2p, 240v
8 - 20at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

a. LPB set 1.00 14,346.80 14,346.80


Main: 50at, 50af, 2p, 240v, 10KAIC 0.00
Br.: 3 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v
FPP set 1.00 46,597.20 46,597.20
Main:400AT,400AF,,240V, 22KAIC, 3p 0.00
Br.: 3 - 40at, 100af, 2p
1 - 40at, 100af, 3p
1 - 400at, 400af, 3p

Automatic Transfer Switch (ATS) set 1.00 128,000.00 128,000.00


Main:500AT, 600 AF, 3P, 240V, 42 KAIC
in NEMA 2r Closure

40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F1 (As Submitted) 244,155.30


F2. Materials

a. MDP set 1.00 37,602.50 37,602.50


Main: 500at, 600af, 3p, 240v, 42 KAIC
Br.: 1 - 60at, 100af, 2p, 240v
2 - 50at, 100af, 2p, 240v
1 - 400at, 400af, 3p, 240v

a. LPA set 1.00 14,008.80 14,008.80


Main: 60at, 2p(lugs only)
Br.: 3 - 15at, 50af, 2p, 240v
8 - 20at, 50af, 2p, 240v
1 - 30at, 50af, 2p, 240v

a. LPB set 1.00 14,346.80 14,346.80


Main: 50at, 50af, 2p, 240v, 10KAIC
Br.: 3 - 15at, 50af, 2p, 240v
7 - 20at, 50af, 2p, 240v

FPP set 1.00 46,597.20 46,597.20


Main:400AT,400AF,,240V, 22KAIC, 3p
Br.: 3 - 40at, 100af, 2p
1 - 40at, 100af, 3p
1 - 400at, 400af, 3p

Automatic Transfer Switch (ATS) set 1.00 128,000.00 128,000.00


Main:500AT, 600 AF, 3P, 240V, 42 KAIC
in NEMA 2r Closure

40at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
30at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00
20at, 50af, 2p, 240v ACB, in NEMA 3R enclosure set 1.00 1,200.00 1,200.00

Sub - Total for F2 (As Evaluated) 244,155.30


G1. Direct Unit Cost (E1 + F1) - As Submitted 251,734.74
G2. Direct Unit Cost (E2 + F2) - As Evaluated 251,734.74
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 30,208.17
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 30,208.17
I1. Contractor's Profit (CP) - As Submitted 8% of G1 20,138.7792
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 20,138.78
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 15,104.08
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 15,104.08
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 317,185.77
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 317,185.77

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103(1) Lighting Fixtures & Lamps


Unit of Measurement : L.s.
Output per hour : 1.000

No. of
Designation No. of Hour/s Hourly Rate Amount (PhP)
A1. Person/s
Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Electrician 1 96.00 72.73 6,982.08
c. Unskilled Laborer 2 96.00 56.46 10,840.32
.

Sub - Total for A1 (As Submitted) 27,561.60


A2. Labor

a. Construction Foreman 1 96.00 101.45 9,739.20


b. Electrician 1 96.00 72.73 6,982.08
c. Unskilled Laborer 2 96.00 56.46 10,840.32

Sub - Total for A2 (As Evaluated) 27,561.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

Minor Tools (10% of Labor Cost) 2,756.16

Sub - Total for B1 (As Submitted) 2,756.16


B2. Equipment

Minor Tools (10% of Labor Cost) 2,756.16

Sub - Total for B2 (As Evaluated) 2,756.16


C1. Total (A1 + B1) 30,317.76
C2. Total (A2 + B2) 30,317.76
D1. Output per our - As Submitted = 1 Ls
D2. Output per our - As Evaluated = 1 Ls
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 30,317.76
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 30,317.76
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. 2 x 36 watts FL fixture, box type set 60.00 1,180.00 70,800.00


b. 1 x 36 watts FL fixture box type. set 46.00 325.00 14,950.00
c. 1 - 18 watts CFL w/ medium base keyless type porcelain set 4.00 320.00 1,280.00
d. receptacle
Ceiling fan w/ control switch set 40.00 1,800.00 72,000.00
e. Exhaust fan w/ control switch set 12.00 1,400.00 16,800.00

Sub - Total for F1 (As Submitted) 175,830.00


F2. Materials

a. 2 x 36 watts FL fixture, box type set 60.00 1,180.00 70,800.00


b. 1 x 36 watts FL fixture box type. set 46.00 325.00 14,950.00
c. 1 - 18 watts CFL w/ medium base keyless type porcelain set 4.00 320.00 1,280.00
d. Ceiling fan w/ control switch set 40.00 1,800.00 72,000.00
e. Exhaust fan w/ control switch set 12.00 1,400.00 16,800.00

Sub - Total for F2 (As Evaluated) 175,830.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 206,147.76
G2. Direct Unit Cost (E2 + F2) - As Evaluated 206,147.76
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 24,737.73
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 24,737.73
I1. Contractor's Profit (CP) - As Submitted 8% of G1 16,491.82
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 16,491.82
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 12,368.87
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 12,368.87
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 259,746.18
K. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 259,746.18
Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(5) Fire Hose Cabinet Assembly


Unit of Measurement : Set
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 184.00 101.45 18,666.80


b. Skilled Laborer 2 184.00 73.29 26,970.72
c. Unskilled Laborer 4 184.00 56.46 41,554.56

Sub - Total for A1 (As Submitted) 87,192.08


A2. Labor

a. Construction Foreman 1 184.00 101.45 18,666.80


b. Skilled Laborer 2 184.00 73.29 26,970.72
c. Unskilled Laborer 4 184.00 56.46 41,554.56

Sub - Total for A2 (As Evaluated) 87,192.08


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 8,719.21

Sub - Total for B1 (As Submitted) 8,719.21


B2. Equipment

a. Minor Tools (10% of Labor Cost) 8,719.21

Sub - Total for B2 (As Evaluated) 8,719.21


C1. Total (A1 + B1) 95,911.29
C2. Total (A2 + B2) 95,911.29
D1. Output per our - As Submitted = 1.000 Set
D2. Output per our - As Evaluated = 1.000 Set
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 95,911.29
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 95,911.29
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. B.I. Pipe 50mm dia lm 23.00 708.00 16,284.00


b. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,628.40 1,628.40
c. Fire Hose Cabinet with Fire Extinguisher set 4.00 24,000.00 96,000.00
d. Fire Extinguisher, 10 lbs Capacity, Wall Mounted, HCFC 123 set 10.00 6,825.00 68,250.00
e. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Concrete m³ 33.02 5,740.00 189,534.80
h. Rebar , Gr40 kg 648.90 37.50 24,333.75
i. Plaster Finish m² 93.55 84.25 7,881.59
j. Cement Based Waterproofing bag 159.00 55.00 8,745.00
k. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
l. End-Suction Centrifugal Water Pump, TDH 10m, unit 2.00 29,800.00 59,600.00
1.5HP, 80GPM
m. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F1 (As Submitted) 894,057.54


F2. Materials

a. B.I. Pipe 50mm dia lm 23.00 708.00 16,284.00


b. Fittings (Elbow, Tee, Reducer, etc) l.s. 1.00 1,628.40 1,628.40
c. Fire Hose Cabinet with Fire Extinguisher set 4.00 24,000.00 96,000.00
d. Fire Extinguisher, 10 lbs Capacity, Wall Mounted, HCFC 123 set 10.00 6,825.00 68,250.00
e. Overhead Water Tank 2000 US Gal unit 2.00 167,000.00 334,000.00
f. FDC Siamese Twin: Two-Way unit 1.00 6,500.00 6,500.00
g. Concrete m³ 33.02 5,740.00 189,534.80
h. Rebar , Gr40 kg 648.90 37.50 24,333.75
i. Plaster Finish m² 93.55 84.25 7,881.59
j. Cement Based Waterproofing bag 159.00 55.00 8,745.00
k. .60 x .60 Manhole ea 2.00 21,000.00 42,000.00
l. End-Suction Centrifugal Water Pump, TDH 10m, unit 2.00 29,800.00 59,600.00
m. Booster Pump, TDH 25m, 3HP, 80GPM unit 1.00 39,300.00 39,300.00

Sub - Total for F2 (As Evaluated) 894,057.54


G1. Direct Unit Cost (E1 + F1) - As Submitted 989,968.83
G2. Direct Unit Cost (E2 + F2) - As Evaluated 989,968.83
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 118,796.26
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 118,796.26
I1. Contractor's Profit (CP) - As Submitted 8% of G1 79,197.51
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 79,197.51
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 59,398.13
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 59,398.13
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 1,247,360.73
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 1,247,360.73

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
Construction of Two (2) Storey Ten (10) Classroom Academic School Building at Tiaong East Elementary School,
Tiaong, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1208(1) Fire Alarm System


Unit of Measurement : L.s.
Output per hour : 1.000

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1.
Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborer 1 32.00 73.29 2,345.28

Sub - Total for A1 (As Submitted) 5,591.68


A2. Labor

a. Construction Foreman 1 32.00 101.45 3,246.40


b. Skilled Laborer 1 32.00 73.29 2,345.28

Sub - Total for A2 (As Evaluated) 5,591.68


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1.
Equipment

a. Minor Tools (10% of Labor Cost) 559.17

Sub - Total for B1 (As Submitted) 559.17


B2. Equipment

a. Minor Tools (10% of Labor Cost) 559.17

Sub - Total for B2 (As Evaluated) 559.17


C1. Total (A1 + B1) 6,150.85
C2. Total (A2 + B2) 6,150.85
D1. Output per our - As Submitted = 1.00 L.s.
D2. Output per our - As Evaluated = 1.00 L.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 6,150.85
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 6,150.85
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1.
Materials

a. Fire Alarm Control Panel set 1.00 18,850.00 18,850.00


b. Manual Pull Switch set 2.00 1,610.00 3,220.00
c. Bell, Vibrating Type set 2.00 1,400.00 2,800.00

Sub - Total for F1 (As Submitted) 24,870.00


F2. Materials

a. Fire Alarm Control Panel set 1.00 18,850.00 18,850.00


b. Manual Pull Switch set 2.00 1,610.00 3,220.00
c. Bell, Vibrating Type set 2.00 1,400.00 2,800.00

Sub - Total for F2 (As Evaluated) 24,870.00


G1. Direct Unit Cost (E1 + F1) - As Submitted 31,020.85
G2. Direct Unit Cost (E2 + F2) - As Evaluated 31,020.85
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 3,722.50
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 3,722.50
I1. Contractor's Profit (CP) - As Submitted 8% of G1 2,481.67
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 2,481.67
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 1,861.25
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 1,861.25
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 39,086.27
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 39,086.27

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1106(1) CCTV System


Unit of Measurement : l.s.
Output per hour : 1.00

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)


A1. Labor

a. Construction Foreman 1 16.00 101.45 1,623.20


b. Skilled Laborer 4 16.00 73.29 4,690.56
c. Unskilled Laborer 4 16.00 56.46 3,613.44

Sub - Total for A1 (As Submitted) 9,927.20


A2. Labor

a. Construction Foreman 1 16.00 101.45 1,623.20


b. Skilled Laborer 4 16.00 73.29 4,690.56
c. Unskilled Laborer 4 16.00 56.46 3,613.44

Sub - Total for A2 (As Evaluated) 9,927.20


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)
B1. Equipment

a. Minor Tools (10% of Labor Cost) 1 1.00 992.72 992.72

Sub - Total for B1 (As Submitted) 992.72


B2. Equipment

a. Minor Tools (10% of Labor Cost) 1 1.00 992.72 992.72

Sub - Total for B2 (As Evaluated) 992.72


C1. Total (A1 + B1) 10,919.92
C2. Total (A2 + B2) 10,919.92
D1. Output per our - As Submitted = 1.00 l.s.
D2. Output per our - As Evaluated = 1.00 l.s.
E1. Direct Unit Cost (C1 ÷ D1) - As Submitted 10,919.92
E2. Direct Unit Cost (C2 ÷ D2) - As Evaluated 10,919.92
Name and Specification Unit Quantity Unit Cost Amount (PhP)
F1. Materials

a. NVR 16 Channels unit 1.00 22,827.89 22,827.89


b. Indoor Camera IP 2.0Mp (Dome Type) unit 2.00 4,634.25 9,268.50
c. Camera IP 2.0Mp (Wall Type) unit 2.00 9,380.76 18,761.52
d. Switch Hub 24 ports unit 1.00 14,200.00 14,200.00
e. TV 32 inches unit 1.00 14,917.01 14,917.01
f. HDMI Cable 20 Meters unit 1.00 3,500.00 3,500.00
h. HDMI Switch 4 ports unit 1.00 11,000.00 11,000.00
i. 4TB Hard Disk unit 1.00 9,380.00 9,380.00
j. One Lot PVC Pipe and Cabling including fittings and lot 1.00 60,180.00 60,180.00
k. UTP Cable unit 4.00 7,008.24 28,032.96
l. Accs. Materials (Insulation) unit 1.00 12,000.00 12,000.00

Sub - Total for F1 (As Submitted) 204,067.88


F2. Materials

a. NVR 16 Channels unit 1.00 22,827.89 22,827.89


b. Indoor Camera IP 2.0Mp (Dome Type) unit 2.00 4,634.25 9,268.50
c. Camera IP 2.0Mp (Wall Type) unit 2.00 9,380.76 18,761.52
d. Switch Hub 24 ports unit 1.00 14,200.00 14,200.00
e. TV 32 inches unit 1.00 14,917.01 14,917.01
f. HDMI Cable 20 Meters unit 1.00 3,500.00 3,500.00
h. HDMI Switch 4 ports unit 1.00 11,000.00 11,000.00
i. 4TB Hard Disk unit 1.00 9,380.00 9,380.00
j. One Lot PVC Pipe and Cabling including fittings and support lot 1.00 60,180.00 60,180.00
k. UTP Cable unit 4.00 7,008.24 28,032.96
l. Accs. Materials (Insulation) unit 1.00 12,000.00 12,000.00

Sub - Total for F1 (As Evaluated) 204,067.88


G1. Direct Unit Cost (E1 + F1) - As Submitted 214,987.80
G2. Direct Unit Cost (E2 + F2) - As Evaluated 214,987.80
H1. Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Submitted 12% of G1 25,798.54
H2 Overhead, Contingencies & Miscellaneous (OCM) Expenses - As Evaluated 12% of G2 25,798.54
I1. Contractor's Profit (CP) - As Submitted 8% of G1 17,199.02
I2. Contractor's Profit (CP) - As Evaluated 8% of G2 17,199.02
J1. Value Added Tax (VAT) - As Submitted 5% of (G1 + H1 + I1) 12,899.27
J2. Value Added Tax (VAT) - As Evaluated 5% of (G2 + H2 + I2) 12,899.27
K1 Total Unit Cost - As Submitted (G1 + H1 + I1 + J1) 270,884.63
K2. Total Unit Cost - As Evaluated (G2 + H2 + I2 + J2) 270,884.63

Prepared by: Checked/Reviewed by:

CESAR ANTONIO P. JADER JUMEL B. REYES


Architect II Engineer II

You might also like