PROJECT : RIMA WATER TREATMENT PLANT (RWTP) WORK PACKAGE 3 AE

COMPANY : M/s. PETROLEUM DEVELOPMENT OMAN LLC

DESIGNER : M/s. SUSTAINABLE TECHNOLOGY LLC

CONTRACTOR : M/s. RIMA WATER TREATMENT PROJECTS LLC

SUB-CONTRACTOR : M/s. GULF DAM ENGINEERING SERVICES & CONTRACTING LLC


Request for Inspection (RFI) Register LAST UPDATED DATE & TIME : 11/9/2021 10:54

Total 24 Acceptable 9 Rejected 1 Open 14 Cancelled 0

INSPECTION SCHEDULE PREPARED BY INSPECTED BY


INSPECTION
Sl. No. RFI NO. Discipline Inspection/ TEST ACTIVITY LOCATION DRAWING NUMBER & Rev. No. RFI ISSUED DATE Closing RFI & Scan Copies BOQ Ref TYPE
STATUS
DATE TIME GULF DAM RWTP

1 C-GD-0001 Civil Inspection Request for Joint Survey of AE Dam Zone-1 OGL Survey Chainage: 0+000 to 0+997 AE Dam Zone-1 RWTP-DD-AE1000R03-210429-GA 25-05-2021 13 June 2021 8:30AM Ponnu Swamy Jageswer Acceptable 01-06-2021 scan completed 2.1.1 OGL

Inspection Request for Joint Survey of AE Dam Zone-2 and Zone-3 OGL Survey Chainage: 0+997 to AE Dam Zone-2 and
2 C-GD-0002 Civil RWTP-DD-AE1000R03-210429-GA 29-05-2021 30 May 2021 8:30AM Ponnu Swamy Jageswer Acceptable 01-06-2021 scan completed 2.1.1 OGL
2+167 Zone-3

3 C-GD-0003 Civil Inspection Request for Joint Survey of AE Dam Zone-4 OGL Survey Chainage 2+167 to 2+981 AE Dam Area Zone-4 RWTP-DD-AE1000R03-210429-GA 02-06-2021 3 June 2021 8:30AM Ponnu Swamy Jageswer Acceptable 06-07-2021 scan completed 2.1.1 OGL

4 C-GD-0004 Civil Inspection Request for Joint Survey of AE Dam Zone-5 OGL Survey Chainage 2+981 to 3+546 AE Dam Area Zone-5 RWTP-DD-AE1000R03-210429-GA 02-06-2021 3 June 2021 8:30AM Ponnu Swamy Jageswer Acceptable 06-07-2021 scan completed 2.1.1 OGL

5 C-GD-0005 Civil Inspection Request for Joint Survey of AE Dam Zone-6 OGL Survey Chainage 3+546 to 4+651 AE Dam Area Zone-6 RWTP-DD-AE1000R03-210429-GA 08-06-2021 10-06-2021 8:30AM Ponnu Swamy Jageswer Acceptable 02-08-2021 scan completed 2.1.1 OGL

6 C-GD-0006 Civil Inspection Request for Joint Survey of AE Dam Zone-8 OGL Survey Chainage 4+651 to 5+630 AE Dam Zone-8 RWTP-DD-AE1000R03-210429-GA 08-06-2021 10 June 2021 8:30AM Ponnu Swamy Jageswer Acceptable 02-08-2021 scan completed 2.1.1 OGL

Inspection request for Joint Survey of AE dam Zone(AE Dam Area Zone-1 Chainage 0+000 to 0+997 ) -
7 C-GD-0007 Civil 1 Rock Level Survey for prior to start rock cutting activity. Attached drawing and survey data sheet for AE Dam Zone-1 RWTP-DD-AE1000R03-210429-GA 19 June 2021 20 June 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
your reference.

Inspection request for Joint Survey of AE dam Zone 10 & 11 OGL Survey for prior to start top soil
8 C-GD-0008 Civil AE Dam Zone-10 & 11 RWTP-DD-AE1000R03-210429-GA 26 June 2021 27 June 2021 08:30 AM Sathiya Jageswer Acceptable 02-08-2021 scan completed 2.1.1 OGL
removal. Attached drawing and survey data sheet for your reference.

Inspection request for Joint Survey of AE Channel-C1 (CH 0+000 TO 2+016) OGL Survey for prior to
9 C-GD-0009 Civil AE Channel-C1 RWTP-DD-AE1000R03-210429-GA 29 June 2021 30 June 2021 08:30 AM Sathiya Jageswer Acceptable 02-08-2021 scan completed 2.3.1 OGL
start top soil removal. Attached drawing and survey data sheet for your reference.

Inspection request for Joint Survey of AE Dam area control points. Attached drawing and survey data
10 C-GD-0010 Civil AE Dam RWTP-DD-AE1000R03-210429-GA 14 July 2021 15 July 2021 08:30 AM Sathiya Jageswer Acceptable 02-08-2021 scan completed 2.1.1 control points
sheet for your reference.

Inspection request for Joint Survey of AE Dam area Zone-02 Rock Level Survey for prior to start rock
11 C-GD-0011 Civil AE Dam Zone-2 RWTP-DD-AE1000R03-210429-GA 26 July 2021 27 July 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
cutting activity Attached drawing and survey data sheet for your reference.

Inspection request for Joint Survey of AE Channel-C2 (CH 0+000 TO 849.09) OGL Survey for prior to
12 GD-RWTP-CIVIL-012 Civil AE Channel-C2 RWTP-DD-AE1000R03-210429-GA 28 July 2021 29 July 2021 08:30 AM Sathiya Jageswer Open 2.3.1 OGL
start top soil removal. Attached drawing and survey data sheet for your reference.

Inspection request for Joint Survey of AE Dam area Zone-03(CH 1+497 to CH 2+167) Rock Level
13 GD-RWTP-CIVIL-013 Civil AE Dam Zone-3 RWTP-DD-AE1000R03-210429-GA 29 July 2021 31 July 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
Survey for prior to start rock cutting activity Attached drawing and survey data sheet for your reference.

Inspection request for Joint Survey of AE Dam area Zone-04 (CH 2+167 to CH 2+981) Rock Level
14 GD-RWTP-CIVIL-014 Civil AE Dam Zone-4 RWTP-DD-AE1000R03-210429-GA 1 August 2021 2 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
Survey for prior to start rock cutting activity Attached drawing and survey data sheet for your reference.

RWTP-DD-AE1000R03-210429-GA &
Inspection request for Joint Survey of AE Channel-C3 (CH 0+000 TO 1+366.49) OGL Survey for prior
15 GD-RWTP-CIVIL-015 Civil AE Channel-C3 RWTP-DD-AE1003R02-210429-AE area-AE-C1-2-3-COO & 1 August 2021 2 August 2021 08:30 AM Sathiya Jageswer Open 2.3.1 OGL
to start top soil removal. Attached drawing and survey data sheet for your reference.
RWTP-DD-AE1005R01-210429-AE-C1 Profile-COO

RWTP-DD-AE1000R03-210429-GA &
Inspection request for Joint Survey of AE Channel-C1 (CH 0+000 TO 2+016) Rock Level Survey for
16 GD-RWTP-CIVIL-016 Civil AE Channel-C1 RWTP-DD-AE1003R02-210429-AE area-AE-C1-2-3-COO & 2 August 2021 3 August 2021 08:30 AM Sathiya Jageswer Open 2.3.2 Rock level survey
prior to start rock cutting activity Attached drawing and survey data sheet for your reference.
RWTP-DD-AE1005R01-210429-AE-C1 Profile-COO

Inspection request for Joint Survey of AE Dam area Zone-05 (2+981 to 3+546) Rock Level Survey for
17 GD-RWTP-CIVIL-017 Civil AE Dam Zone-5 RWTP-DD-AE1000R03-210429-GA 3 August 2021 4 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
prior to start rock cutting activity Attached drawing and survey data sheet for your reference.
INSPECTION SCHEDULE PREPARED BY INSPECTED BY
INSPECTION
Sl. No. RFI NO. Discipline Inspection/ TEST ACTIVITY LOCATION DRAWING NUMBER & Rev. No. RFI ISSUED DATE Closing RFI & Scan Copies BOQ Ref TYPE
STATUS
DATE TIME GULF DAM RWTP

Inspection request for Joint Survey of AE Dam area Zone-06 (3+546 to 4+651) Rock Level Survey for
18 GD-RWTP-CIVIL-018 Civil AE Dam Zone-6 RWTP-DD-AE1000R03-210429-GA 3 August 2021 4 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
prior to start rock cutting activity Attached drawing and survey data sheet for your reference.

RWTP-DD-AE1000R03-210429-GA &
Inspection request for Joint Survey of AE Channel-C2 (CH 0+000 TO 849.09) Rock Level Survey for
19 GD-RWTP-CIVIL-019 Civil AE Channel-C2 RWTP-DD-AE1003R02-210429-AE area-AE-C1-2-3-COO & 9 August 2021 10 August 2021 08:30 AM Sathiya Jageswer Open 2.3.2 Rock level survey
prior to start rock cutting activity Attached drawing and survey data sheet for your reference.
RWTP-DD-AE1006R01-210429-AE-C2-C3-profile-COO

Inspection request of soil sampling for backfilling material at stockpile-01(Qty-5000cum) RWTP-DD-BP1000R02-201229-BP-Location RWTP-DD-
20 GD-RWTP-CIVIL-020 Civil Borrow Pit-01 9 August 2021 10 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1 Sampling
Location: BORROW PIT RWTP-GD-BP-01 BP1001R01-210103-BP-SSA-Location

Inspection request for Joint Survey of Zone-01 (CH 0+000 to 0+250) AE Dam bottom level after 0.5%
21 GD-RWTP-CIVIL-021 Civil slope preparation and prior to start Structural backfilling activity Attached drawing and survey data AE Dam Zone-01 RWTP-DD-AE1000R03-210429-GA 18 August 2021 19 August 2021 08:30 AM Sathiya Jageswer Rejected 2.1.1.5 0.5% slope preparation
sheet for your reference.

Inspection request for Joint Survey of Zone-01 (CH 0+000 to 0+250) AE Dam bottom level after 0.5%
22 GD-RWTP-CIVIL-022 Civil slope preparation and prior to start Structural backfilling activity Attached drawing and survey data AE Dam Zone-01 RWTP-DD-AE1000R03-210429-GA 22 August 2021 23 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1.5 0.5% slope preparation
sheet for your reference.

Inspection request for Joint Survey of AE Dam area Zone-08 (4+651 to 5+630) Rock Level Survey for
23 GD-RWTP-CIVIL-023 Civil AE Dam Zone-8 RWTP-DD-AE1000R03-210429-GA 28 August 2021 29 August 2021 08:30 AM Sathiya Jageswer Open 2.1.1.3 & 2.1.1.4 Rock level survey
prior to start rock cutting activity Attached drawing and survey data sheet for your reference.