You are on page 1of 7

project -- behirawy primary and kindergart

owner ..
Timizing L*W*H orD Squaring

1 12.8
20.32 260.096
21.32
1 13.15 280.358
540.454
1 12.8
20.32
0.5 130.048
1 21.32
20.32
0.5 216.6112
346.6592
18.82
2 1
0.8 30.112
30.7
2 1
0.8 49.12
79.232

2 18.82
0.8 30.112
2 30.7
0.8 49.12
79.232
18.2
1 1.4
0.4 10.192
30.12
1 1.4
0.5 21.084
30.2
3 0.3
0.25 6.795
10.8
2 0.4
0.5 4.32
18.32
1 0.4
0.5 3.664
30.12
1 0.4
0.5 6.024
52.079
18.32
2 1
0.1 3.664
30.12
2 1
0.1 6.024

30.12
18.32
0.5 275.8992

2 30.12
0.8 48.192
18.32
2 0.8 29.312
1 30.12
11.15 335.838
7.15
1 10.8 77.22
490.562
18.32

3 0.3
0.25 4.122
11.15
4 0.3
0.25 3.345
10.8
3 0.3
0.25 2.43
30.12
2 0.3
0.25 4.518
14.415
6 18.32
0.3 32.976
11.15
8 0.3 26.76
6 10.8
0.3 19.44
4 30.12
0.3 36.144

115.32
school 1

Describtion
A.sub structure
1.Earth work and excavation
1.1.site clearance
clearing of the top soil up to adepth of
20cm withen 1m working space in m2

Total site clearane in m2


1.2 . Bulck excavation of ordinary soil up to a depth of 0.5m
and 1m working space for each side
m3

m3
Total bulck excavation in m3
1.3 Trench excavation
Trench excavation withen 0.25 m working space
and up to depth of 0.80m in m3

total trench excavation in m3


2. concrete work
2.1 5cm thick c-5 lean concrete laid under around
Trench excavation alonge short axise in m2

along longe axise


total lean concret laid under trench excavation
3. massonery work

in m3 for axis 1,3,7


in m3 for axis A,C,and E

in m3 for axis 3,4,5,6

in m3 for axis B and C

in m3 for axise 2

in m3 for axis D
Total massonery work in m3
3.1 . Fill selected material around trench massonery
a). Around trench massonery
in m3

m3
b). Total fill under harde core

m3 total fill selected matrials under harde core


4. 5 cm thick C-5 lean concrte laid under
a). Under trench foundation

m2 lean concret laid under massonery work

m2 lean concret laid under massonery work


b). Lean concret under hardcore
m2 lean concret laid under harde core

m2 lean concret
Total lean concret in m2
4.1 C-25 CONCRET WORK
a). For grad beam
m3 for axis 1,2,3

m3 for axis 4,5,6,7

m3 for axis A,B,C,D

m3 for axis B and E


Total grade beam concret in m3
5. formwork for grade beam
m2

m2

m2

m2

Total grade beam formwork in m2


project Behirawy primary and kindergarten school
owner addis ababa education bero
Timizing L*W*H orDSquaring Description
A. sub structure
1. Site clearance
1.1. site clearance up to adepth of 20cm
and 1.50 m working space
32.8
1 14.05 460.84 m2

460.84 Total site clearance in m2


1.2. bulck excavation
1.2.1 bulck excavation up to adepth of
1 32.8 0.68m withen 1.5m working space
14.05
0.68 313.3712 m2
313.3712 Total bulke excavation in m3

1.3 Trench excavation


1.3.1. Trench excavation withen 0.25m
working space and 0.8m depth

You might also like