The document outlines a project to construct a dining hall and kitchen building at Africa andent(B-1&2) primary school in Addis Ababa, Ethiopia. The contractor, Solomon Abiye Building Contractor, was hired for 6,043,489.40 birr to complete construction within 60 days. Work included site clearing, trench excavation, and masonry. The dining hall will cover 350 square meters and the kitchen 119.5 square meters, to serve both blocks of the primary school.
The document outlines a project to construct a dining hall and kitchen building at Africa andent(B-1&2) primary school in Addis Ababa, Ethiopia. The contractor, Solomon Abiye Building Contractor, was hired for 6,043,489.40 birr to complete construction within 60 days. Work included site clearing, trench excavation, and masonry. The dining hall will cover 350 square meters and the kitchen 119.5 square meters, to serve both blocks of the primary school.
The document outlines a project to construct a dining hall and kitchen building at Africa andent(B-1&2) primary school in Addis Ababa, Ethiopia. The contractor, Solomon Abiye Building Contractor, was hired for 6,043,489.40 birr to complete construction within 60 days. Work included site clearing, trench excavation, and masonry. The dining hall will cover 350 square meters and the kitchen 119.5 square meters, to serve both blocks of the primary school.
HALL AND KITCHEN BUILDING PROJECT ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project
PROJECT INFORMATION
Employer :- City Government of Addis Ababa Food Security and Productive safety Net Agency
Consultant :-PI CONSULTING ARCHITECTS ENGINEERS
Contractor:- SOLOMON ABIYE BUILDING CONTRACTOR
ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project
PROJECT INFORMATION
Contract Amount :- 6,043,489.40birr
Construction period :- 60 calendar days Contract Sign date :- NOVEMBER 1, 2020. Site Handover date :- :-11,11, 2020. Mobilization time :- 7 calendar days Commencement date :-. Actual Date of completion : - Total time extension days: Revised completion Date : ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project
SHORT DESCRIPTION OF THE PROJECT
The project is located Arada sub- city around atkilt tera post office The dinning hall building lays on 350 square meters and the kitchen building lay on 119.5 square meters .total area 512 including walk way and disable ramp The building will serve for dinning hall and kitchen purpose Both blocks (1&2) under the same construction stage ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project
PHISICAL STATUS OF THE PROJECT
Setting out is completed Site clearing is completed trench excavation is completed Masonry work is completed ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project Overview of the site before ARADA Sub-City for school feeding program Africa andent(B- 1&2) primary school dinning hall and kitchen building project Masonry work is completed