Contents
Introduction
1. Construction Industry

2. Domestic Construction Industry

3. Fundamentals of Management

HU, IoT, Construction Management, 2020


1. Construction Industry
1.1. General
 Construction: is a process of constructing something by
man for one purpose or another. It may be a road, bridge,
dam, dwelling place, an airport, commercial building,
etc.
 Construction types:
 Residential buildings;
 Institutional and commercial buildings;
 Specialized industrial construction; and
 Infrastructure and heavy construction.
 Construction Industry (CI) is an industry which is
involved in the planning, execution and evaluation of
all types of civil works.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.1. General
 Project: is some form of human activity that has a
beginning, a productive phase and an end, creating
something that did not exist before.
 Construction Project: is an investment of scarce
resources with a definite objective, time horizon and
geographical boundary.
 Construction projects are mostly constructed on the
ground and exposed fully to the local environment.
 A construction project has different scale and
complexities. It ranges from improvements to large
investments. But, every project is:
 An investment of resources, and
 A cause of irreversible change.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.1. General
 Common characteristics of construction projects:
 It has a specific starting and finishing time.
 It has usually geographical and sometimes
organizational boundary.
 It has clearly defined set of objectives.
 It entails the investment of scarce resources in the
expectation of future benefits.
 It may be planned, financed and implemented as a unit.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.2. Study of Construction
 Study of Construction mainly covers two themes:
1. Construction Technology: Relates to methods and techniques
used to place the physical materials and elements of
construction at the Job site.
2. Construction Management: Addresses how available
resources will be applied.
Money Manpower

Materials Machines

HU, IoT, Construction Management, 2020


1. Construction Industry
1.2. Study of Construction
 Many great construction projects mark
significant milestones in human history:

1. Great Pyramids;
2. Brooklyn Bridge;(suspension bridge,
Length=1.825km,
Width=25m, clearance=41m,
opening date=1883)

HU, IoT, Construction Management, 2020


3. Panama Canal
 The Panama Canal is a ship canal which joins the Caribbean Sea to the
Pacific ocean. One of the largest and most difficult engineering projects
ever undertaken, it had an enormous impact on shipping between the
two oceans, replacing the long and treacherous route via the Drake
Passage and Cape Horn at the southernmost tip of South America.
 A ship sailing from New York to San Francisco via the canal travels
9,500 km, well under half the 22,500 km route around Cape Horn.
 Although the concept of a canal near Panama dates back to the early
16th century, the first attempt to construct a canal began in 1880 under
French leadership. After this attempt failed and 21,900 workers died, the
project of building a canal was attempted and completed by the United
States in the early 1900s, with the canal opening in 1914.
 The building of the 77 km (48 mi) canal was plagued by problems,
including disease (particularly malaria and yellow fever) and landslides.
By the time the canal was completed, a total of 27,500 workmen are
estimated to have died in the French and American efforts.

HU, IoT, Construction Management, 2020


Panama Canal

HU, IoT, Construction Management, 2020



4. Channel Tunnel
The Channel Tunnel also known as the Chunnel, is a 50.5-kilometre
undersea rail tunnel linking England with northern France beneath the
English Channel.
 At its lowest point it is 75 m deep. The tunnel carries high-speed Eurostar
passenger trains.
 In 1996 the American Society of Civil Engineers identified the tunnel as
one of the Seven Wonders of the Modern World.
 Ideas for a cross-Channel fixed link existed as early as 1802. However, the
eventual successful project, organised by Eurotunnel, began construction in
1988 and opened in 1994.
 The design and construction was done by the ten construction companies in
the CTG/F-M group.
 Privately financed, the total investment costs at 1985 prices were £2600
million. At the 1994 completion actual costs were, in 1985 prices, £4650
million: an 80% cost overrun. At the peak of construction 15,000 people
were employed with daily expenditure over £3 million. Ten workers, eight
of them British, were killed during construction between 1987 and 1993,
most in the first few months of boring.
HU, IoT, Construction Management, 2020
Channel Tunnel

HU, IoT, Construction Management, 2020


Channel Tunnel

HU, IoT, Construction Management, 2020


1. Construction Industry
1.3. Construction Industry Category
 Construction Industry can be categorized into three major
sectors:
i. Transport and Communication Sector - Road, Railway,
Airway, and Telecommunication related physical works;
ii. Water and Energy Works – Hydropower development,
transmission lines, wind power, irrigation projects; and
iii. Buildings and Other Physical Infrastructures.
Infrastructures
 CI is among the leading industry in producing
employment and contribute to the over all national
development.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.3. Construction Industry Category

Transportation Infrastructure
The Construction Energy supply
Industry

Urban development Water supply


HU, IoT, Construction Management, 2020
1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:
 Requires big capital investment thus is highly affected by
the economy of the nation.
 Consumes much of the national budget in developing
countries like Ethiopia.
World Total 3.41 Trillion $ 1. US $819 B (8.2%)
Asia 1,113 Billion $ 2. Japan $618 B (13.9%)
Europe 1,017 Billion $ 3. Germany $253 B (11.4%)
North America 885 Billion $ 4. China $181 B (17.0%)
Latin America 241 Billion $ 5. UK $109 B (7.7%)
Middle East 101 Billion $ Ethiopia $ 402 M(59.8%)
Africa 56 Billion $
HU, IoT, Construction Management, 2020
1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:
A. Nature of production: mainly on site.
 Changing supply-chain relationship and production site.
 Exposed to inclement(bad) weather condition.
 Seasonal disruption.
 Health and safety concerns.

B. Nature of product
 Large, heavy, durable, expensive, heterogeneous, and
immobile.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.4. Construction Industry Attributes
1.4.1 Nature of Construction Industry:
C. Demand for the product
 Demand is usually driven by ‘other’ goods and services;
not controlled by industry,
 In the majority of cases, clients define requirements
before the industry provides it,
 Time lags between demand and supply is long.
D. The Workforce
 The industry is, by its very nature, an overwhelmingly
domestic and labor-intensive industry despite the
advancement in modern technologies.
 Construction is a team output and requires motivated and
skilled workers.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:
 Fragmented industry;

Sequential process

Need Design Bid Build

Client A/E Client Contractor

Fragmented project participants

HU, IoT, Construction Management, 2020


1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:
 Long production cycle;

HU, IoT, Construction Management, 2020


1. Construction Industry
1.4. Construction Industry Attributes
1.4.2 Uniqueness of Construction Industry:
 Large uncertainty;
 Transient(short-lived) organization nature;
 Unpredictable work load; and
 Subject to environmental impact.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.5. Roles of Construction Industry
 Construction Industry is the most important enabler for
social, economic and political development of countries.
 It provides the basis upon which other sectors can grow
by constructing the physical facilities required for the
production and distribution of goods and services.
 Specifically this fact is true for least developing countries
like Ethiopia because projects are:
 Inter-sectoral;
 Source of employment; and
 Demands huge capital budget.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.6. Construction Project Lifecycle
 The project life cycle of a construction project may be viewed as a
process through which a project is implemented from cradle to grave.

Definition of project
objectives and scope

Fulfillment
Conceptual plan or
of useful life
preliminary design

Acceptance of facility Plans and specifications

Completion of
construction
HU, IoT, Construction Management, 2020
1. Construction Industry
1.7. Stakeholders of Construction sector
 Stakeholders of Construction sector:
 Construction Industry involves many people, organization, agencies,
ministries, designers, contractors, project managers, equipment
suppliers, material suppliers, testing Laboratories, etc.

Architect

Subs Owner

Contractor Suppliers

Engineer Vendors

Public
HU, IoT, Construction Management, 2020
THANK YOU!

HU, IoT, Construction Management, 2020


1. Construction Industry
1.7. Stakeholders of Construction sector
 Contractual stakeholders:
 Employer/Client,
 Consultant/Engineer, and
 Contractor.
 Non-contractual stakeholders:
 Public agencies: Statutory Agencies (EEPCo, AAWSA,
Fire Authority), Public authorities and Municipalities
(land and building permit),
 Suppliers, and
 End users etc.

HU, IoT, Construction Management, 2020


1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.1 Employer/client
 Employer/Client is the initiator and owner of the project (it
can be public or private client).
 The client is the most important party who is active from
inception to completion and event to post-occupancy
maintenance.
 Duties of the client encompass the following:
 Availability and cost of land,
 Location & accessibility
 Required Infrastructure
 Legal constraints
 Current & future development
 Soil characteristics of land
 Site preparation (right of way)
 Permits

HU, IoT, Construction Management, 2020


1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.2 Consultant
 The main role of the consultant is to interpret the client’s
project requirement into a specific design and possibly the
supervision.
 The consultants’ team shall:
 Ascertain, interpret and formulate the client’s requirement into an
understandable project.
 Design the project to much requirements and constraints (imposed by
statutory obligations, technical feasibility, environmental factors, site
conditions, cost, etc)
 Assess client’s cost limit to decide on materials & the like.
 Prepare contract documents.
 Supervise the project and constantly inform the client on the progress
 Approve payments
 Resolve contractual disputes
 Issue provisional and final acceptance certification
1. Construction Industry
1.7. Stakeholders of Construction Sector
1.7.3 Contractor
 These are groups established mainly as commercial
companies, that contract to construct development projects.
 Responsibility of contractors:
 Carry out a full site investigation prior to submission of tender,
 Submit tender,
 Plan, Program, Control the construction process.
 Notify the consultant about delays, discrepancies,
 Effect all payments to his employees, suppliers, subcontractors,
 Rectify all defects on completion of works, etc
 Provide post occupancy repair and maintenance if required.
1. Construction Industry
1.8. Resources for Construction Industry
 The following resources are vital that make up an integral
components for construction industry:
 Human Resources (Labor or Workmen);
 Financial Resources ( Fund);
 Information Resources;
 Physical Resources ( Materials, Equipment and Other
Assets); and
 Services and Management.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 Previous monarchies had contributed to the development of
construction in Ethiopia.
 Historic chronicles of the 17th and 18th centuries showed
that there were a number of small roads, palaces and
river improvement works.
 Among the Emperors Atse Fasil, Atse Tewodros and Atse
Menilik were noted for their major contributions.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 Modern construction however had started during the reign
of Emperor Menilik II (The road from Addis Ababa to
Asmara).
Asmara
 Italy during its invasion (1936-1941)
1936-1941 had also contributed
to the development of the construction industry. It had
constructed about 6000km of roads.
 After Italian invasion, the first Ministry called “Ministry
of Communication and Public Works’’
Works was established
during the Imperial regime.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.1. Domestic Construction Industry: Historical Aspect
 The construction development can be reviewed into six
distinct periods based on the historical paradigm shifts in
the construction industry in Ethiopia:
i. Pre 1968: Foreign Companies dominated construction Industry.
ii. 1968-1982: Emergence of Small scale Domestic construction
companies,
iii. 1982-1987: Parastatal companies dominated Construction
Industry,
iv. 1987-1991: Fragmentation between Design services &
Construction works,
v. 1991-2001: Parastatal Domination legally abolished, and re-
emergence of private construction companies,
vi. 2001- to date: Integration and Capacity Building.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 Current status of the construction industry is
distinguished by:
 Lack of clear developmental objectives for the industry;
 Inadequate co-ordination of planning between the industry and
infrastructure programs in the various sectors of the economy;
 Heavy dependence on foreign resources such as materials,
equipment and expertise, which continue to be supplied to a
major extent by foreign consultants and contractors;
 Transport bottlenecks to the distribution of construction
materials and equipment;
 Inadequate relevant local construction regulations and
standards;

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 Current status of the construction industry is distinguished
by:
 Control of the construction sector by small-to-medium sized firms
and parastatal construction enterprises operating at low levels of
capacity and with inadequate working capital;
 Inadequate and ineffective organizations representing the interests
of contractors, consultants and engineers;
 Inadequate numbers of suitably qualified and experienced
personnel, at all levels: engineers, technicians, mechanics, operators
and foremen etc.;
 Inadequate consideration given to the use of local resources
(including community participation in labor-based works);
 Little consideration given to the concept or cost of maintenance as a
component of investment costs.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.2. Current Status of Local Construction Industry
 The general state of the domestic construction industry
in Ethiopia is characterized by the following five major
deficiencies:
 An inadequate capital base;
 Old and limited numbers of equipment;
 Low levels of equipment availability and utilization;
 Deficiencies in technical, managerial, financial and
entrepreneurial skills; and
 Insufficient and ineffective use of labor-based construction
and maintenance technology.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.3. Challenges of Domestic Construction Industry
 Some of the major challenges faced in the Ethiopian
construction industry are:
 Lack of equipment and material;
 Obstacles posed by government regulations;
 Scarcity of finance;
 Big projects off-limits to domestic firms;
 Inefficient custom and clearance;
 Lack of skilled labor; and
 Construction project delays:- Delays are endemic to
construction projects in Ethiopia.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 The Road Sector Development Plan (RSDP) has been
implemented over a period of thirteen years and in three
separate phases, as follows:
 RSDP I – Period from July 1997 to June 2002 (5 year plan);
 RSDP II – Period July 2002 to June 2007 (5 year plan); and
 RSDP III – Period July 2007 to June 2010 (3 year plan).

Phases of the Program Financial (in Million % Physical ( in km) %


ETB)

Budget Disb. Plan Acco.


RSDP I (Five Years ) 9812.9 7284.5 74 8908 8709 98
RSDP II (Five Years) 15985.8 18112.8 113 8486 12006 142
RSDP III (Three Years) 34643.9 34957.8 101 20686 19250 93
Total RSDP (Thirteen
Years
HU, IoT, )
Construction Management, 2020 60442.6 60355.1 100 38080 39965 105
2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 RSDP IV is prepared as part of Governments’ overall
Growth and Transformation Plan.
 Implementation of RSDP IV is major strategic pillar of the
Growth and Transformation Plan.
 RSDP IV consists of:
 Rehabilitation of 728Km of trunk roads;
 Upgrading of 5,023Km of trunk and link roads;
 Construction of 4,331Km of new link roads;
 Heavy maintenance of 4,700Km of paved and gravel roads; and
 Routine maintenance of 84,649Km of road network.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.1 Road Construction
 The program also consists of the following regional and
Wereda road components through Universal Road Access
Program, URAP.
 Construction of 11,212Km of new rural roads through
the RRAs; and
 Construction of 71,523Km of Wereda roads through the
Wereda road offices.
 Cost Estimate:
 The total cost of implementing RSDP IV is estimated to
be ETB 125,276.7 million.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
 Ethiopian Railway Corporation, ERC is presently
managing a 5,000Km proposed National Railway Network
study and the Addis Ababa Light Rail Transit (AALRT)
Project.
A. Addis Ababa Light Rail transit Project (AA LRT):
 The 1st Phase of the LRT project comprises an East-West
line from Ayat to Torhailoch (17.35Km) and a North-
South line from Menelik II Sq. to Kality (16.90 Km).
 The Total Length of Phase I will be 34.25Km.
 Cost: USD 3 milion per Kilometre.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
A. Addis Ababa Light Rail transit Project (AA LRT):

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
B. Federal Railway Projects
 Ethiopia has launched the construction of a 5,000Km
railway complex which aims to link the capital, Addis
Ababa, to various regions of the country.
 According to the GTP 2,000Km of the total will be
constructed in the next five years.
 The first phase of construction will be the construction of
five railway tracks, which will create job opportunities for
over 300,000 citizens nationwide, and will cost the nation
an estimated 6 billion Birr (US$336 million) annually.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
Project B. Federal
Route Railway Projects Via Distance
Phase (Km)
Phase I Route 1 Addis Ababa (Sebeta)_Mojo_Awash_Dire Dewa_ Djibouti 656

Part of Route 3 Addis Ababa(Sebeta)_Ejaji_Seka_Bedele 366


Part of Route 6 Weldia_Mile_Djibouti_Railway 256
Part of Route 5 Awash_Kombolcha_Mekele 556.2
Phase II Route 4 Ejaji_Nekemt_Asossa_Kurmuk 460
Route 2 Mojo_Shashemene_Konso_Woyito_ Konso_ Moyale 905
Route 7 Wereta_Azezo_Metema 244
Part of Route 5 Mekele_Shire 201.2
Part of Route 6 Fnoteselam_Bahirdar_Wereta_Weldia 461
Route 8 Adama_Indeto_Gasera 248
Extension Extension to Sudan Via Boma (not part of the project) 115
HU, IoT, Construction Management, 2020
2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.2 Railway Construction
B. Federal Railway Projects

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
 Ethiopia has a vast hydropower potential, which is
estimated to be about 45,000 MW.
 Even though Ethiopia considers itself the Powerhouse of
Africa, so far very little percentage (less than 5%) of the
vast potential has been harnessed.
 In 2009 less than 10% of Ethiopians had access to
electricity and the country was plagued by power outages.

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
Name Installed Commissi Basin Contractor Financing Cost
Capacity oning
Fincha 134 MW 1973 Fincha (Blue Nile)
Gilgel Gibe I 180 MW 2004 Omo river Salini (bid) World Bank $331m
Tekeze 300 MW 2009 Tekeze (Atbara) Sinohydro Chinese $365m
Corporation (bid)
Beles 460 MW 2010 Lake Tana (Blue Salini (no bid) Ethiopian
Nile) government
Gilgel Gibe II 420 MW 2010 Omo River (no dam, Salini (no bid) Italy and EIB Euro 370m
fed by GG I)
Gilgel Gibe III 1870 MW 2012-13 Omo river Salini (no bid) Italy Euro 1.55bn
Fincha Amerti 100 MW 2013 Fincha (Blue nile) China (CGGC) Exim Bank of $276m
Nesse (FAN) China
Halele 440 MW 2014 Omo river Sinohydro FairFund? Euro 470m
Worabese Corporation
Gilgel Gibe IV 2000 MW 2014 Tributary of the Omo Sinohydro Chinese $1.9bn
River Corporation
Chemoga Yeda 278 MW 2013 tributary of the Blue Sinohydro Chinese $555m
Nile, near Debre Corporation
Markos
Genale Dawa 256 MW Awarded between Oromo and Chineese (CGGC) Chinese $408m
HU, IoT, Construction Management, 2020
III in 2009 Somali state
2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.3 Hydropower Development
Possible interconnection with neighboring countries

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
 EEPCo has decided to use wind power for the several
advantages that it posses:
 Being renewable;
 Being reliable and affordable;
 Being complementary to hydropower plants: rainy season
– low wind; dry season – high wind potential; and
 combining wind and hydro adds value to the hydro plant,
i.e. longer operation time, also at the end of dry season
(water saving through wind).

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
S. No. Name of the project Electric power Year of
generation capacity in completion
MW

1 Ashengoda Wind Power Project 120 (€210 million ) 2012

2 Adama Wind Power Project 51 ($117 million) 2011

3 Adama II Wind Power Project 51 2013


4 Assela Wind Power Project 100 2013
5 Ayisha Wind Power Project 300 2012
6 Debre Birhan Wind Power Project 400 2013
7 Messobo Wind Power Project 42 2012

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.4 Wind Power Development
Four major search areas for wind power

HU, IoT, Construction Management, 2020


2. Domestic Construction Industry
2.4. Recent Trends and Future Prospects
2.4.5 Irrigation Projects
2.4.6 Housing development projects
2.4.7 University Capacity Building Projects, UCBP
2.4.8 Sugar Factory Projects
2.4.9 Fertilizer Factory Projects

HU, IoT, Construction Management, 2020


Thank you!

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.1. Management: Definition
 A means of achieving political, economic, and social
objectives.
 A means of integrating resources (materials, finance,
human resources, information, etc.,) in order to achieve
organizational objectives efficiently and effectively.
 A means of getting things done through people in order to
achieve objectives.
 A process of establishing vision, mission, values,
objectives, goals, and strategies and communicating these,
and guiding and empowering others to accomplish them.
 A process of planning, organizing, directing and
controlling of organizational activities in order to achieve
objectives.
3. Fundamentals of Management
3.2. Management Functions

 Management is a set of goal-directed,


interrelated and interdependent activities, aimed
at accomplishing organizational goals in an
efficient and effective manner.
 Generally, management functions encompass:
planning, organizing, leading and controlling.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
Management Function inputs and outputs
Management sets direction

Planning
Performance
Resources
•Attain goals
•Human
•Products
•Financial Controlling Organizing
•Services
•Raw Materials
•Efficiency
•Technological
•Effectiveness
•Information
Leading
Inputs Outputs

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
 Planning: devising a systematic approach for attaining
the goals of the organization.
 Organizing: determining how activities and resources are
grouped and the composition of work groups and the way
in which work and activities are to be coordinated.
 Leading: guiding, leading and overseeing of employees
to achieve organizational goals.
 Controlling: establishing performance standards and
comparing results and expectations to make appropriate
changes.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions

Planning
Planning Organizing
Organizing

Management
Management
Functions
Functions

Controlling
Controlling Leading
Leading

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.1 Planning
 Management starts with planning. Without a plan
organizations will never succeed. If they do, it will have been
by luck or chance and is not repeatable. Plan, will help us in:
 What to accomplish (goals);
 When to accomplish the goals;
 What resources to use;
 Who should accomplish what;
 Where to accomplish; and
 What methods to use.
 Assess all possible scenarios including the best and worst and
what actions to take.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.2 Organizing
 Organizing refers to the process of designing jobs and
departments and determining authority relationships in
organizations.
 Organizing:
 Permits people to work together in order to achieve goals;
 Helps to achieve synergy;
 Avoid duplication of resources;
 Establish authority; and
 And facilitate communication.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.2 Organizing
 Some issues in organizing include:
 Specialization (division of labor);
 Grouping jobs into departments and structuring
(functional, product, customer, geographic, matrix);
 Determining authority relationships (span of control,
chain of command);
 Delegation of authority; and
 Centralization and decentralization.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.3 Leading
 Influencing, inspiring and empowering employees to
work towards the leaders vision.
 Leading involves:
 Building successful groups and teams in organizations;
 Motivating people;
 Communication; and
 Developing organizational change.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
 The process of measuring performance, comparing it
with the objectives, and making any necessary
adjustments.
 The purpose of control include:
 Adapting to changes;
 Minimizing consequences of errors;
 Helping the organization cope with complexities; and
 Improving efficiency(working productively with
minimum wastage ).

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
A. Control Purpose
 The control function, in turn, has four basic purposes.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.2. Management Functions
3.2.4 Controlling
B. Control Process

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.3. Levels of Management
Manager: Definition
 The people looking beyond
themselves and exercising formal
authority over the activities and
performance of other people in
pursuit of organizational goals.
 Someone whose primary
responsibility is to carry out the
management process.
 Someone who plans and makes
decisions, organizes, leads, and
controls human, financial,
physical, and information
resources.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.3. Levels of Management
A. Top Managers
 The relatively small group of executives who manage the
organization’s overall goals, strategy, and operating
policies.
B. Middle Managers
 Largest group of managers in organizations who are
primarily responsible for implementing the policies and
plans of top managers. They supervise and coordinate the
activities of lower-level managers.
C. First-Line Managers
 Managers who supervise and coordinate the activities of
operating employees.
HU, IoT, Construction Management, 2020
3. Fundamentals of Management
3.3. Levels of Management
Levels of Management

Top managers

Middle managers

First-line managers
g

n
e
in

ns

er
tio
nc

ce
et

th
tio

ra
na

ur
k

O
ar

ra

ist
so
Fi
M

pe

in
re

dm
O

an

Areas of Management A
um
H

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.3. Levels of Management
Make decision about the overall
direction and performance of the
Top Level organization

Translate the over all direction


Middle Level and performance into specific
objectives and plans

Implement directions and


Lower Level plans through production
and delivery of services

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.4. Managerial skills
 Conceptual skills: the capacity to think in the abstract
and to see the organization as a complete unit and to
integrate and give direction to its diverse activities so that
objectives are achieved.
 Interpersonal skills: the ability to communicate with,
understand and motivate both individuals and groups.
 Technical skills: skills necessary to accomplish or
understand the specific kind of work being done in an
organization.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.4. Managerial skills
Conceptual Skills
Intellectual ability to process information and make accurate
decision about the work, group, and the job

Interpersonal Skills
Management Skills
Communication , conflict resolution, leading

Technical Skills
Knowledge and ability to accomplish the specialized activities of the
work group
Top Level Middle Level Lower Level
HU, IoT, Construction Management, 2020
3. Fundamentals of Management
3.5. Construction Management
 The management of construction is an enterprise that
involves many people with diverse interests, talents and
backgrounds. The owner, design professional and
contractor comprise the primary triad of parties,
 However, others such as subcontractors, material
suppliers, bankers, insurance and bonding companies,
attorneys and public agency officials, are vital elements
of the project team whose interrelated roles must be
coordinated to assure a successful project.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.5. Construction Management
 The function of project management for construction
include:
 Specification of project objectives and plans including
delineation of scope, budgeting, scheduling, setting
performance requirements, and selecting project participants.
 Maximization of efficient resource utilization through
procurement of labor, materials and equipment according to
the prescribed schedule and plan.
 Implementation of various operations through proper
coordination and control of planning, design, estimating,
contracting and construction in the entire process.
 Development of effective communications and mechanisms
for resolving conflicts among the various participants.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.6. Organization Management
A. Organization
 A consciously coordinated social unit, composed of two or
more people influencing each other that functions on a
relatively continuous basis to achieve a common goal or set of
goals.
 It is a structured process in which people interact and
influence each other in order to achieve objectives.
B. Components of Organization
 People,
 Influence ,
 Goals or Purpose,
 Structure, and
 Technology.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.6. Organization Management
C. Organization Environment
Macro or Far Environment

Near or Operating
Environment Economic
Technological
Factors
Factors Partners
Customers

Clients ORGANIZATION

Suppliers Political
Social Competitors Factors
Factors

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.7. Organizational Structure
 Organizational structures can fall into either mechanistic
or organic forms.
 Mechanistic organizations are rather rigid in that they
comprise distinctly delineated jobs, clearly defined
hierarchical structure and are driven primarily by top-
down command and control. Mechanistic organizations
are tall structures, consisting of hierarchies with several
layers of management levels.
 Organic structures are is relatively flexible. They are
structurally decentralized, empowering employees at all
levels of the organization to take personal responsibility
for the processes and activities in which they are engaged.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.7. Organizational Structure
 Organizational design is creating an appropriate
organizational structure that will enable the organization
to accomplish its goals.
 The organization can choose from among functional,
divisional or matrix designs, whichever is appropriate.
 It is the process of arranging, allocating work authority
and resources to achieve organization goals.
 It involves:
 Identifying tasks to be performed;
 Allocating the tasks among members; and
 Integrating efforts to achieve its objectives.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.7. Organizational Structure
Key Concepts
 Span of Management Control: The number of
subordinates reporting directly to a given manger;
 Chain of Command: The plan that specifies who reports
to whom in an organization, such reporting lines are
prominent features of organization chart;
 Coordination: The integration of the activities of the
separates parts of an organization to accomplish
organizational goals; and
 Downsizing: A version of organizational restructuring
which results in decreasing the size of the organization
and often results in a flatter organizational structure.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.7. Organization Structure
3.7.1. Functional Organization
 In a functional organization, tasks or jobs of similar
nature are grouped together and structured as a unit.
Each unit is staffed by functional specialists.
 Structuring the organization along the functional lines
facilitates good coordination and makes supervision of
the unit easy for managers as they only need to be
familiar with a narrow set of skills.
General Manager

Marketing Mgr. Production Mgr. Finance Mgr. HRM Mgr.

HU, IoT, Construction Management, 2020


3. Fundamentals of Management
3.7. Organization Structure
3.7.2. Divisional Organization
 Divisional structures are grouped according to workflow
and structures are made up of independent strategic
organizational units.
 The workflow can be broken into product lines,
geographic regions, etc.

GM (Head Quarter)
(A.A)

DGM (Awasa) DGM (Mekelle) DGM (Bahir Dar)


Dar DGM (Jimma)
HU, IoT, Construction Management, 2020
3. Fundamentals of Management
3.7. Organization Structure
3.7.3. Matrix Organization
 In matrix organization, individuals are made responsible
both to their line manager and the project manager
involved.
 The matrix concept facilitates working on concurrent
projects by creating a dual chain of command, the
project (program, systems, or product) manager and the
functional manager.
 Matrix structures utilize functional and divisional chains
of command simultaneously in the same part of the
organization, commonly for one-of-a-kind projects.
3. Fundamentals of Management
3.7. Organization Structure
3.7.3. Matrix Organization

Head Quarter

Material
Human
Production Finance Marketing &
Resource
Procurement

Marketing HR
Project A Production Finance Materials
Grp Grp
Manager Grp Grp Grp

Production Finance Marketing Materials


Project B HR
Grp Grp Grp Grp
Manager Grp

HU, IoT, Construction Management, 2020


Assignment
 Write short note on nature of construction industry of
Ethiopia. What are the challenges of Ethiopian
construction industry and annual budget and percentage
of employment
 Write at least 10 grade one local contractors and
consultants, their capital, year of establishment, number
of projects they win annually etc.
 Write the top ten world contractors and consultants and
their capital
 Write the foreign contractors(At least 6) that are
working currently in Ethiopia, the type of project they
are engaged in.

HU, IoT, Construction Management, 2020


THANK YOU!