Professional Documents
Culture Documents
00 Weir
00 Weir
Component
3.3 Hydrology
3.3.1 Available water for the project site
3.3.2 Flood discharge
3.6 Inlet
Fig. 1
1.50x3+0.50x 3 = 6m 146.3 m
The effective crest width (Be) is related to the actual crest width (B) between
abutments and / or piers by following equation:
Be = B - 2 (n Kp + Ka) H1
where n is number of piers
Kp is pier contraction coefficient
Ka is abutment contraction coefficient
H1 is energy head in m
Effective width for scouring sluice are taken at 80%.
Main 2/60
for rounded abutments where r > 0.5 H1 0
Water level for each discharge are calculated at several water depth (see table
2), and result are shown in below table.
Main 3/60
3.5 Stability analysis for weir
The external forces acting on the weir body include dead weight, hydrostatic
pressure, sedimentation pressure, uplift, seismic force.
(1) Condition
Unit weight of concrete 2.20 t/m3
Unit weight of soil 1.95 t/m3
Cohesion 0 t/m2
Coefficient of sediment earth pressure 0.5
Coefficient of uplift 1.0
Friction coefficient 0.7
Seismic coefficient 0.1
P
P'
Pe P P'
W
P P
0
U
Main 4/60
U
P' shows that hydraulic pressure acting on weir when flow type is submerged.
Pe
W, F
P
P
0
U
1) Flood condition
Force Moment
Item
Vertical Horizontal
Dead load -96.71 - -490.60 -
Hydraulic pressure -35.46 24.07 -128.61 104.91
Uplift pressure 83.47 - 402.89 -
Sediment pressure - 1.04 - 7.00
Seismic force - - - -
Total -48.70 25.11 -216.32 111.91
Total (without uplift) -132.17 25.11 -619.21 111.91
3) Normal condition
Force Moment
Item
Main 5/60
Item
Vertical Horizontal
Dead load -96.71 - -490.60 -
Hydraulic pressure -6.45 22.78 -29.04 77.90
Uplift pressure 47.99 - 227.86 -
Sediment pressure - 1.04 - 7.00
Seismic force - - - -
Total -55.17 23.82 -291.78 84.90
Total (without uplift) -103.16 23.82 -519.64 84.90
1) Analysis on overturning
The eccentric distance must be satisfied following condition.
e = |ΣM / ΣV - l/2|
e =< l / 6 (normal), l / 3 (earthquake)
Where e is eccentric distance (m)
l is length of the base (m)
Case Remarks
1-1 1-2 2-1 2-2 3-1 3-2
ΣM -104.41 -507.30 -125.67 -353.53 -206.88 -434.74
ΣV -48.70 -132.17 -55.17 -103.16 -55.17 -103.16
l 10.20 10.20 10.20 10.20 10.20 10.20
l/2 5.10 5.10 5.10 5.10 5.10 5.10
e= |ΣM / ΣV - l/2| 2.96 1.26 2.82 1.67 1.35 0.89
l/6 1.70 1.70 1.70 1.70 1.70 1.70
l/3 3.40 3.40 3.40 3.40 3.40 3.40
e =< l / 6 Ok Ok
e =< l / 3 Ok Ok Ok Ok
2) Analysis on sliding
The following condition must be satisfied against sliding.
Main 6/60
SL = (ΣV / ΣH) x f > 1.5(normal), 1.2(earthquake)
Where f is coefficient of friction against ground
Case Remarks
1-1 1-2 2-1 2-2 3-1 2-2
ΣV 48.70 132.17 55.17 103.16 55.17 103.16
ΣH 25.11 25.11 43.18 43.18 23.82 23.82
f= 0.7 0.70 0.70 0.70 0.70 0.70 0.70
ΣV / ΣH 1.94 5.26 1.28 2.39 2.32 4.33
(ΣV / ΣH) x f 1.36 3.68 0.89 1.67 1.62 3.03
SL 1.5 OK OK
1.2 OK OK check OK
3) Analysis on settlement
The compressive strength at the bottom is obtained from the formula and it must
be within the bearing capacity of the foundation.
p = ΣV / l (1+ 6e / l )
Where p is compressive strength caused at the both end of the bottom (t/m 2)
Case Remarks
1-1 1-2 2-1 2-2 3-1 3-2
ΣV -48.70 -132.17 -55.17 -103.16 -55.17 -103.16
l 10.20 10.20 10.20 10.20 10.20 10.20
e 2.96 1.26 2.82 1.67 1.35 0.89
(1+6e/l) 2.74 1.74 2.66 1.98 1.79 1.52
(1-6e/l) -0.74 0.26 -0.66 0.02 0.21 0.48
p= ΣV / A (1+ 6e / l ) -13.08 -22.58 -14.39 -20.07 -9.70 -15.38
Item Remarks
a 1 KP-6, table 2.5, p13
b 0.5 KP-6, table 2.5, p13
c 0.00 Result of soil investigation
r 1.95 Result of soil investigation
z 2.00
Main 7/60
B 10.20
Nc 16.0 KP-6, figure 2.3, p14
Nq 6.0 KP-6, figure 2.3, p14
Nr 4.5 KP-6, figure 2.3, p14
qu 68.15 from above formula
1/3 qu 22.72 safety factor is 3.0
1/2 qu 34.08 safety factor is 2.0
Case Remarks
1-1 1-2 2-1 2-2 3-1 3-2
p= ΣV / A (1+ 6e / l ) 13.08 22.58 14.39 20.07 9.70 15.38
1/3 qu 22.72 22.72 22.72 22.72 22.72 22.72
1/2 qu 34.08 34.08 34.08 34.08 34.08 34.08
1/3 qu > P OK OK
1/2 qu > P OK OK OK OK
Main 8/60
3.5.2 Correction of trapezoidal section
Y / hd = 1 / k ( X / hd )n
where X and Y are coordinates of the down stream face
hd is the design head over the crest
K and n value are parameters
slope of upstream face K n
vertical 2.000 1.850
1 to 0.33 1.936 1.836
1 to 0.67 1.939 1.810
1 to 1.00 1.873 1.776
H1 hd
0.119 X1.776 = 1.873 hd0.776Y
hd x
Intersection point
(X1,Y1)
1:m
r=0.45h
1:1.00 d y R =3.45 m
(2) Bucket
Main 9/60
Radius of bucket are defined t be from 1/2 to 1/3 of the weir height. (refer to
Engineering Manual for Irrigation and Drainage)
Therefore
Radius = 6.9 / 2 = 3.45 m
6.9 / 3 = 2.30 m
The minimum allowable bucket radius (Rmin) is given in figure 4.22 (Kp-02) as
function of dH/hc and Rmin/hc.
hc = (q2 /g) 1/3
where hc is critical water depth (m)
q is discharge per unit width (m3/s/m)
g is acceleration of gravity (m/s2)
Therefore
hc = (132/9.8)1/3
= 2.58
Therefore
dH / hc 3.4 / 2.58
= 1.3178 when dH/hc=1.32, Rmin/hc is found 1.55 from fig.
Therefore
Rmin = 1.55 x 2.58
3.999 (m)
3.5.3 Apron
Therefore
Lj = 5 x( 1 + 4.77 )
= 28.85 m
The baffle-block type is used for this project. Therefore the length L of the basin
can be found from
Lj= 2 yu { ( 1 + 8 Fru2 )0.5 -1} (The USBR type IV, Froude number between 2.5 to 4.5)
where yu is water depth at start of jum 1.18 see annex 4
Fru is froude number 3.19
Therefore minimum length of down stream apron is,
Lj= 19.064 m
2) Thickness
Main 10/60
The thickness of the stilling basin flow is calculated as follows.
dx > S x (Px - Wx ) / r
dx is thickness of floor at x (m)
Px is uplift pressure at point x (kg / m 2)
Wx is water depth at point x (m)
r is unit density of material (kg / m 3)
S is safety factor
1.5 for normal condition
1.25 for extreme condition
I II III
The minimum thickness at the section of I-I and II-II are found from above
formula (detailed calculation for Px is shown in annex 4)
Condition Section S Px Wx r dx
Normal I 1.5 5.3 1 2.2 2.93
II 4.1 1 2.2 2.11
III 3 1 2.2 1.36
Flood I 1.25 8.7 4.7 2.2 2.27
II 7.6 4.7 2.2 1.65
III 6.5 4.7 2.2 1.02
The minimum thickness I section 2.93 m
II section 2.11 m
III section 1.36 m
Bligh's method
L > C dH
where L is length of creep length measured along the foundation face of weir (m)
C is coefficient mention above
dH is maximum head difference at upstream and downstream sides (m)
Main 11/60
Lane's method
L' > C' dH
where L' is length of weighted creep length
L'= Σ lv + 1/3 Σ lh
lv is creep length of vertical direction (inclination of more than 45 degrees)
lh is creep length of horizontal direction (inclination below 45 degree)
C' is coefficient which varies by the type of ground
dH is maximum difference between water heads (m)
Main 12/60
Table 1 Coefficient for Bligh's method and for Lane's method
Foundation Bligh's Lan's
Silty sand or clay 18 8.50
Fine sand 15 7.00
Medium sand - 6.00
Coarse sand 12 5.00
Gravel - 4.00
Coarse gravel - 3.50
Sandy gravel 9 -
Cobble stone with gravel - 3.00
Rock with Cobblestone and gravel - 2.50
Rock with gravel and sand 4 to 6 -
Soft clay - 3.00
Medium clay - 2.00
heavy clay - 1.80
Hard clay - 1.60
Result of calculation are shown in below table, and detail are attached annex 3.
3.5.5 Riprap
(1) Length of riprap (by Brigh's formula)
Length of riprap are found by following Brigh's formula.
L= Lb - la
Lb = 0.67 C ( Ha q f)0.5
Where L is riprap length (m)
Lb is total length of protection including length of apron
Ha is height from above water level of downstream side to weir
crest in dry season (m)
q is flow per unit width of design flood discharge (m3/sec/m)
q= 1950m3/s / 150 m = 13
f is safety factor, 1.0 in case of fixed weir, 1.5 in case of movable weir
C is Bligh's coefficient
Therefore
Lb = 0.67 x 13.5 x ( 3.4 x 13 x 1.0) ^0.5
= 60 m
L= 60 - 20 = 40 m
Main 13/60
The velocity (v1) at the start of the jump are found from:
V1 = (2g (1/2 H1) +Z )0.5
where V1 is velocity at start of jump (m/s)
g is acceleration of gravity (m/s2)
H1 is energy head above crest (m)
Z is drop height (m)
The formula for the conjugate depth in a hydraulic jump:
y2 / yu = 1/2 ((1+8Fr2)-1)0.5 in which Fr = V1 / (gyu)0.5
where y2 is water depth above end sill (m)
yu is water depth at start of jump (m)
Fr is Froude number
V1 is velocity at start of jump (m/s)
g is acceleration of gravity (m/s2)
EL1
H1 H2
Z+0.5H1 EL3
EL2
Z y2 y3
y1 V1
Each value for different return period are shown below table. (detailed
calculation are shown in Annex 4)
Therefore flow type are type B which dose not occur lowering of bedlevel.
Main 14/60
3) Size of riprap block
The size of block is desirable to satisfy the formula below.
W > 3.75 A v2 / 2g
Where W is weight of each block (t)
A is area of collision with flowing water (m 2)
v is velocity at which flowing water collides with block (m/s)
g is acceleration of gravity (m/s2)
Main 15/60
4) Height of end shill
The height of endshill are found from figure. 4.18 (kp-2).
n/y1 =1/2 are found
here n is height of endsill (m)
y1 is water depth at start of jump (m)
Therefore
n = 1.18 x 1/2 = 0.59 m
Main 16/60
(2) Stability analysis of scouring sluice
1) Load condition
Loads acting on the scouring sluice are assumed as follows.
P4 P4 P4 P4
1/2H
P2
FP2
P1 H
FW
P2' 1/2H
W FP2'
P3
P2'
FP2'
3) Structural analysis
- Scouring Sluice
- Operating bridge
Main 17/60
3.6 Inlet
Main 18/60
(2) Flow discharge
1) Intake velocity
With entrance velocity of 1.0 to 2.0 m/s which are normal design values, it may
be expected that grains of 0.01 to 0.04m can enter.
Main 19/60
energy energy Water Bottom
No Discharge Distance item V2/2g W.L. Remarks
loss E.L. depth E.L.
Main 20/60
B is width of sediment trap (m)
This gives
LB = Q / w
The fall velocity w for grain size 0.07m is 0.004m/s from figure 7.4 (KP-2).
Therefore
LB = 25.11 / 0.004 = 6,278 m2
Because of L / B > 8, L and B are found as below.
L= 270 m
B = 23.25 m
Then L / B = 11.613 > 8
L x B = 6,278 m2
hn =2.700 m
Main 21/60
V = K x R2/3 x I1/2
Here R = A / S = 15.07 / ( 23.25 + 0.65 x 2 ) = 0.61 m
k = 25 (because of sedimentation, value for natural canal is assumed)
Then
2.0 = 25 x 0.652/3 x I251/2 Then I = (1.5 / 25 x 0.652/3 )2
= ###
(minimum slop ness for flushing)
Velocity should remain below the critical velocity. Therefore this flow must be
confirmed whether critical flow or not.
Fr = V / ( g x h )0.5 = 0.7924 < 1 OK
Although, it is necessary to confirm type of flow, when coefficient is K=40.
Q = A V = A x K x R2/3 x I1/2
Here Area ( A ) is 23.25 m x 0.594 m = 13.811 m2
K is 40
R is 13.811 / ( 23.250 + 0.594 x 2 ) = 0.565
I is 0.006394
Therefore
V = 40 x 0.565 ^(2/3) x 0.006394 ^(1/2) = 2.186 m/s
Q = 2.186 x 13.811 = 30.191 m3/s
Then
Fr = V / ( g x h )0.5 = 0.906 < 1 OK
2.700 m 2.700 m
ia = 0.000022
0.350 m 0.350 m
ib = 0.006394 1.720 m
270 m 23.25 m
h1 = 0.35 m
V = 0.35 x 270.00 x 23.25 + 0.5 x (0.006394 - 0.000022 ) x 270.00 x 270.00 x 23.25
= 7597 m3 > ,OK 7,593 m3 (necessity volume)
Main 22/60
The retaining wall is divided into 2 parts and is constructed for protection of
transition and dike as follows.
5m 5m
Riprap Apron Apron Riprap
The upstream edge of protection should be the upper end compared both. (see above fig.)
The downstream edge of protection should be the lower end compared both.
Dimension (m)
H1 H2 H3 B0 B1 B2 B3 B4 Remarks
No1 9.600 1.000 2.000 6.000 2.000 1.000 3.000 0.300
No2 1.000 1.000 1.000 9.000 3.300 1.000 2.000 0.400
No3 11.000 1.000 1.000 9.000 3.000 1.000 3.000 0.400
No4 12.000 1.000 1.000 9.000 3.000 1.000 4.000 0.400
B4
H1
B1 B2 B3
H2 H3
B0
2) Load condition
Main 23/60
Force acting on the retaining wall are shown in below figure.
Case (q')
Case 1(q)
1/2 H
1/2 H
Main 24/60
Ground water level:
Height of ground water is considered as 1/2 of difference between normal
water level and top of wall.
Live load :
Live load for No.2 and No. 4 are considered because of inspection road. 0.5
t/m2 are considered for inspection vehicle. Loading place are considered two
case shown in above figure q1 and q2.
Passive earth pressure
Passive earth pressure is not considered for this case.
Back filling
Type Sand from soil investigation report page ***
Unit weight 1.8 m /s 3
Friction angle 30 o
cohesion 0 t/m2
Foundation
Type Sand from soil investigation report page ****
N value N = 30
Bearing capacity 30 t/m2 see Annex 7
friction factor 0.6 t/m2
Main 25/60
case 1
case 2
case 3
II III
I I
II III
As result, size and interval of reinforcement bar for tension are as follows.
size interval As As' Remarks
No 1 1
2
3
1
No 2 1
2
3
No 3 1
2
3
No 4 1
2
2
3
3
Main 26/60
3.7.3 Flood dike
(1) Freeboard
For creating extra safety, 0.25 m above the elevation of the abutments of the
weir is taken as freeboard.
5m Safety factor =
1:2.0 1:2.5
Main 27/60
Main 28/60
Main 29/60
Main 30/60
head-loss (= 0.80)
Main 31/60
Main 32/60
oth. (see above fig.)
Main 33/60
Annex 1 (34/60)
The head-discharge equation for a short crest weir with rectangulear contraol section reads.
Discharge is depend on crest type such as cylinder type and ogee type. Therefore discharge
is found according to the crest type as follows.
556987790.xlsannex 1
Annex 1 (35/60)
1.60
1.50
f(x) = 0.181605257446127 ln(x) + 1.18791559586172
1.40
1.30
1.20
Co
1.10
1.00
0.90
0.80
0.70
0 1 2 3 4ratio H1/r
5 6
p/ H 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.5
C1 0.77 0.83 0.87 0.89 0.92 0.93 0.94 0.96 0.97 0.97 0.99
1.05
1.00
f(x) = 0.085071307415435 ln(x) + 0.970399424615561
0.95
0.90
C1
0.85
0.80
0.75
0.70
0 0.2 0.4 0.6
p/H0.8 1 1.2 1.4 1.6
556987790.xlsannex 1
C
0.85
0.80
Annex 1 (36/60)
0.75
0.70
0 0.2 0.4 0.6
p/H0.8 1 1.2 1.4 1.6
556987790.xlsannex 1
Annex 1 (37/60)
p/ H 0.16 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1 1.2 1.3 1.4 1.5
(1:1) 1.040 1.036 1.026 1.018 1.012 1.008 1.006 1.003 1.000 0.998 0.997 0.996 0.995 0.993 0.992
(1:0.67) 1.028 1.027 1.022 1.019 1.017 1.014 1.012 1.009 1.008 1.007 1.006 1.005 1.003 1.002 1.000
(1:0.33) 1.010 1.009 1.008 1.007 1.006 1.005 1.005 1.004 1.003 1.003 1.002 1.002 1.001 1.001 1.000
1.050
1.040
f(x) = − 0.021774219194115 ln(x) + 0.999044261639584
1.030
f(x) = − 0.012561588786755 ln(x) + 1.00676675070815
1.020
1.010
f(x) = − 0.004440428140449 ln(x) + 1.00244031816344
C2
1.000
0.990
0.980
0.970
0.960
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6
p/H
H2/H1 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 0.95
f 1.00 1.00 0.99 0.97 0.95 0.93 0.87 0.77 0.55 0.35
1.20
1.00
f(x) = − 4.53250036057 x⁴ + 6.12687444562 x³ − 2.7932652553 x² + 0.3383290507 x + 1
0.80
0.60
f
0.40
0.20
0.00
0 0.1 0.2 0.3 0.4H2/H1
0.5 0.6 0.7 0.8 0.9 1
556987790.xlsannex 1
Annex 2(38/60)
Annex 2
Dead Load 10.20
2.00 2.00 2.25 3.95
2.50 2.50
1 2 3
1.90 4 5 1.90
0.10 6 0.10
1.00 7 8 9 10 2.00
2.90 11 12 1.90
38/60 556987790.xlsannex 2
Annex 2(39/60)
0.29
### 14.55
3.19 2.90 1 1'
2' 2 13.90 0.65
5 6 7
2.50 10' 2.50
8.40 8 8.40 9.05
9
1.90
3 4
5.90 10
4.00
39/60 556987790.xlsannex 2
Annex 2(40/60)
### 13.90
2
2.50 3.40
8.40 10.50 8.40 8.40
3
1.00
5.90 1
4 4.00
5.00
40/60 556987790.xlsannex 2
Annex 2(41/60)
1 2 3 4 5 6 7
10 11
9 6.60 12 8.21
8 6.81 8.36 13 14
7.95 9.67 9.45
8.10 Coefficient for uplift : 1.00
41/60 556987790.xlsannex 2
Annex 2(42/60)
1 2 3 4 5 6 7
10 11
9 3.15 12 4.50
8 3.51 4.75 13 14
4.73 6.04 5.68
4.99 Coefficient for uplift : 1.00
42/60 556987790.xlsannex 2
Annex 2(43/60)
2.50 2.50
5.90
Seismic force
2.00 2.00 2.25 3.95
2.50 2.50
1 2 3
1.90 4 5 1.90
0.10 6 0.10
1.00 7 8 9 10 2.00
2.90 11 12 1.90
43/60 556987790.xlsannex 2
Annex 2(44/60)
44/60 556987790.xlsannex 2
Annex 3 (45/60)
Annex 3
Sub project Spon
Condition
Crest elevation 13.9 m
Flood Upstream Water level 17.0 m
Down stream Water level 14.2 m
Normal Upstream Water level 13.9 m
Down stream Water level 10.5 m
17.0 m
8.6
13.9 m H1 = 2.9 m
5.5
14.2 m 1.00 0.75
H2 = 3.4 m
1
10.5 m
3.0
4 5 1.0
1.0 2 3
2.0 1.5 4.0
11
6 7
2.0 10 1.0 1.5
1.9 1.5
12 13
2' 8 9
1.5 0.9 2.1 1.2 1.5 0.9 2.1 18.5 0.75 0.75
556987790.xlsAnnex 3
Annex 3 (46/60)
Bligh's ,method and Lane's method
H1<H2 Therefore Normal condition 3.4 m (maximum different head)
(1) Without sheet pile (3) Calculation sheet for creep length
No. Length Vertical Horizontal 1/3 Horizontal Total length Total length Creep length
(1) (2)
I II III IV I III + IV (1)Without sheet pile (2)With sheet pile
1 0.00 0.00 0.00 0.00 0.00 0.00
2 3.00 3.00 3.00 3.00 Lane's method Lane's method
3 1.50 1.50 0.50 4.50 3.50 L > C' x dh L > C' x dh
4 1.35 1.35 5.85 4.85 L= 24.79 L= 28.79
5 2.10 2.10 0.70 7.95 5.55 C' x dh = 20.40 C' x dh = 20.40
6 2.33 2.33 10.28 7.88 C' = 6 C' = 6
7 1.50 1.50 0.50 11.78 8.38 Therefore Ok Therefore Ok
8 2.10 2.10 13.88 10.48
9 2.10 2.10 0.70 15.98 11.18 Brigh's method Brigh's method
10 1.50 1.50 17.48 12.68 S > C x dH S > C x dH
11 18.53 18.53 6.18 36.01 18.86 S= 42.44 S= 46.44
12 1.68 1.68 37.69 20.54 C x dh = 45.90 C x dh = 45.90
13 0.75 0.75 0.25 38.44 20.79 C= 13.5 C= 13.5
14 4.00 4.00 0.00 42.44 24.79 Therefore Not Ok Therefore Ok
total 42.44 15.96 26.48 8.83
556987790.xlsAnnex 3
Annex 3 (47/60)
12 1.68 1.68 41.69 24.54
13 0.75 0.75 0.25 42.44 24.79
14 4.00 4.00 0.00 46.44 28.79
total 46.44 19.96 26.48 8.83
556987790.xlsAnnex 3
Annex 4 (48/60)
Condition
17.0 m Crest elevation 13.9 m
8.6 Flood Upstream Water level 17.0 m
Down stream Water level 14.2 m
Normal Upstream Water level 13.9 m
Down stream Water level 10.5 m
13.9 m H1 = 2.9 m
5.5
14.2 m 1.00 0.75
H2 = 3.4 m
1 10.5 m
14
3.0
4 5 1.0
1.0 2 3
2.0 1.5 4.0
11
6 7 10'
2.0 10 1.0 1.5
1.9 1.5
12 13
2' 8 9
9.3
1.5 0.9 2.1 1.2 1.5 0.9 2.1 18.5 0.75 0.75
Uplift pressure No Length(m) Normal Flood
Px = Hx - Lx / L dH Hx Px Hx Px
1 0 0.00 2.5 2.5 5.6 5.6
2 3.00 3.00 5.5 5.3 8.6 8.4
3 5.50 8.50 5.5 4.9 8.6 8.1
4 1.35 9.85 4.5 3.8 7.6 7.0
5 2.10 11.95 4.5 3.6 7.6 6.9
6 2.33 14.28 6.5 5.5 9.6 8.7
7 1.50 15.78 6.5 5.3 9.6 8.6
8 2.10 17.88 8.4 7.1 11.5 10.4
9 2.10 19.98 8.4 6.9 11.5 10.3
10 1.50 21.48 6.9 5.3 10.0 8.7
10' 9.26 30.74 6.4 4.1 9.5 7.6
11 9.26 40.01 5.9 3.0 9.0 6.5
12 1.68 41.68 7.4 4.3 10.5 7.9
13 0.75 42.43 7.4 4.3 10.5 7.9
14 4.00 46.43 3.4 0.0 6.5 3.7
46.43
556987790.xlsAnnex 4
Annex 5 (49/60)
from non-
y3 3.88 4.16 4.49 4.75 5.15 uniform
calculation
EL1
H1
hc
Z+0.5H1 EL2
Z y2 H2
y1 V1
49/60 556987790.xlsAnnex 5
Annex 6 (50/60)
Result
energy energy Water Bottom
No Discharge Distance item V2/2g W.L. Remarks
loss E.L. depth E.L.
m3/s m (m) (m) (m) (m) (m) (m)
1 3.476 inflow ### 0.000 691.150 2.350 46.300
0.062
2 3.476 pier ### 0.123 49.215 1.615 47.600
641.837
3 3.476 10 friction and curvature 49.251 0.141 49.110 1.510 47.600
0.007
4 3.476 15 gradual increase 49.244 0.143 49.101 1.501 47.600
0.161
5 3.476 drop 49.083 0.029 49.054 1.464 47.590
0.006
6 3.476 150 friction 49.077 0.007 49.070 3.070 46.000
0.003
556987790.xlsAnnex 6
Annex 6 (51/60)
7 3.476 beginning point for can 49.074 0.004 49.070 4.170 44.900
total 642.076
556987790.xlsAnnex 6
Annex 6 (52/60)
556987790.xlsAnnex 6
Annex 6 (53/60)
Assumption
687.500 m dh3' = 0.227 m
Therefore
dh2 = 3.476 ^2/(2*9.8) x (1/ ( 0.920 ^2 x 3.750 ^2 x 0.788 ^2 ) - 1 / ( 5.000 ^ 2 x 1.015 ^ 2 )
= 0.059 m retry dh3' = 0.227 m
Therefore
W.L.3= 690.906 m
A3 = B3 x h3 = 5.000 x 0.956 = 4.780 m/s
P3 = B3 + h3 x 2 = 5.000 + 0.956 x 2 = 6.912 m/s
R3 = A3 / P3 = 4.780 / 6.912 = 0.692 m/s
V3 = Q / (B3 x h3) = 3.48 / ( 0.956 x 5.000 ) = 0.727 m/s
V3 /2g = 0.727 ^2/(2 x 9.8)
2
= 0.027 m
690.894 m dhe = dhe W.L.5 where hge is loss due to gradual increase inflow area (m)
h4= 690.837 m he is loss due to dradual increase (transition)
V4 0.944 m V5 hf is loss due to friction of transition
689.950 m h5 = 0.887 m fge is head loss coefficient for gradual increase 0.4 from fig. 3.2.99
689.950 m fse is head loss coefficient due to abrupt increase 0.64 from table 3.2.17
B4 = 5.000 m B5= 11.300 m Assumption
L= 15.000 m dh5' = 0.057 m
Therefore
V5 = Q / (B5 x h5) = 3.48 / ( 0.887 x 11.300 ) = 0.347 m/s
V /2g = 0.347 ^2/(2 x 9.8) =
5
2
0.006 m
5.000 m 11.300 m A5 = B5 x h5 = 11.300 x 0.887 = 10.023 m2
P5 = B5 + h5 x 2 = 11.30 + 0.887 x 2 = 13.074 m
R5 = A5 / P5 = 10.023 / 13.074 = 0.767 m
Vm = (V4 + V5) /2 ( 0.736 + 0.347 ) / 2 = 0.542 m/s
Rm = (R4 + R5 )/2 ( 0.685 + 0.767 ) / 2 = 0.384 m
Therefore
dh5 = 0.400 x 0.640 x 0.028 + ( 0.015 x 0.542 / 0.384 ^(2/3)) ^ 2 x 15.000
556987790.xlsAnnex 6
Annex 6 (55/60)
556987790.xlsAnnex 6
Annex 6 (56/60)
556987790.xlsAnnex 6
Annex 6 (58/60)
556987790.xlsAnnex 6
annex 0 (59/60)
2) Empirical formula
L = 20 Q0.5
where
L is length of sedimentation ditches (m)
Q is design discharge in sedimentation ditches (m3/s)
Therefore
annex 0 (60/60)
L = 70.866 m
W W'
L1 L2 L3
37 m 183 m 4m
Volume of sedimentation
Volume of suspended material of the water flowing through the trap :
0.05 %
Grain size for settling :
0.07 m
Flushing interval :
1 per a week
Therefore necessity volume Q is as below.
Q= 12.56 x 0.00050 x 7 x 24 x 3600 / 1 = 3,797 m3