11th Floor Accomplishment as of 8/9/21

Units 1st Coat 2nd Coat Flood test Remarks


Unit A
Service Kitchen Flood Test Passed
Maids Flood Test Passed
Gourmet Flood Test Passed
Powder Room Flood Test Passed
T&B 2 Flood Test Passed
T&B 3 Flood Test Passed
Master Flood Test Passed

Unit B
Master Flood Test Passed
Powder Flood Test Passed
T&B 2 Flood Test Passed
Kitchen Flood Test Passed
Maids Flood Test Passed
Utility Flood Test Passed

Unit C
Master Flood Test Passed
T&B 2 Flood Test Passed
T&B 3 Flood Test Passed
Powder Flood Test Passed
Service Kitchen Flood Test Passed
Maids Flood Test Passed
Gourmet Flood Test Passed
Lanai Flood Test Passed

Unit D
Service Kitchen Flood Test Passed
Maids Flood Test Passed
Gourmet Flood Test Passed
Powder Flood Test Passed
T&B 2 Flood Test Passed
T&B 3 Flood Test Passed
Master Flood Test Passed

Unit E
Master Flood Test Passed
Kitchenette Flood Test Passed
T&B 2 Flood Test Passed
T&B 3 Flood Test Passed
T&B 4 Flood Test Passed
Maids Flood Test Passed
Powder Flood Test Passed
Service Kitchen Flood Test Passed
Gourmet Flood Test Passed
Lanai Flood Test Passed
omplishment as of 8/9/21
Remarks

Flood Test Passed


Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed

Flood Test Passed


Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed

Flood Test Passed


Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed

Flood Test Passed


Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed

Flood Test Passed


Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Flood Test Passed
Concrete Solution Re-entry August 23, 2021

Name Position Re-entry


Panida, Gilbert Applicator Re-entry
Dela Rosa, Roel Safety officer Re-entry
Du-ag, Mark Angelo Applicator Re-entry
14th Floor Accomplishment as of 9/11/21
Units Waterplug 1st Coat 2nd Coat Flood test Remarks
Unit A
Service Kitchen clearing of the area
Maids FLOOD TEST PASSED
Gourmet FLOOD TEST PASSED
Powder Room FLOOD TEST PASSED
T&B 2 FLOOD TEST PASSED
T&B 3 watered / for floodtest inspection today
Master clogged stubout

Unit B
Master wet surface (baha)/latance
Powder FLOOD TEST PASSED
T&B 2 ready for application
Kitchen ready for application/wet surface
Maids wet surface/ verify clogged stubout
Utility wet surface/laitance

Unit C
Master laitance/slab self leveling
T&B 2 2nd coat
T&B 3 Flashing resto./waterline leak
Powder ready for application
Service Kitchen Laitance
Maids ready for application
Gourmet PL
Lanai for surface prep

Unit D
Service Kitchen Laitance/Zocalo (ongoing works)
Maids 2nd coat / underslab restoration/masonry work
Gourmet laitance
Powder ready for floodtesting
T&B 2 laitance/wet surface (baha)
T&B 3 ready for floodtesting
Master laitance

Unit E
Master PL
Kitchenette ready for inspection of surface prep
T&B 2 1st coat with blockout
T&B 3 2nd coat / underslab restoration
T&B 4 2nd coat / underslab restoration
Maids for surface prep
Powder wet surface (flooded)
Service Kitchen surface prep inspection
Gourmet surface prep inspection
Lanai for surface prep
14th Floor Accomplishment as of 9/11/21
Units Waterplug 1st Coat 2nd Coat Flood test
Unit A
Service Kitchen clear
Maids FLOO
Gourmet FLOO
Powder Room FLOO
T&B 2 FLOO
FT 5 T&B 3 watered / for fl
FTI 1 Master clo
to be watered 6
PL/sp 26 Unit B
38 Master wet surf
Powder FLOO
T&B 2 ready
Kitchen ready for ap
Maids wet surface/
Utility wet s

Unit C
Master laitance
T&B 2
T&B 3 Flashing r
Powder ready
Service Kitchen
Maids ready
Gourmet
Lanai for

Unit D
Service Kitchen Laitance/Zo
Maids 2nd coat / undersla
Gourmet
Powder ready
T&B 2 laitance/
T&B 3 ready
Master

Unit E
Master
Kitchenette ready for ins
T&B 2 1st co
T&B 3 2nd coat / u
T&B 4 2nd coat / u
Maids for
Powder wet su
Service Kitchen surface
Gourmet surface
Lanai for
ment as of 9/11/21
Flood test Remarks

clearing of the area


FLOOD TEST PASSED
FLOOD TEST PASSED
FLOOD TEST PASSED
FLOOD TEST PASSED
watered / for floodtest inspection today
clogged stubout

wet surface (baha)/latance


FLOOD TEST PASSED
ready for application
ready for application/wet surface
wet surface/ verify clogged stubout
wet surface/laitance

laitance/slab self leveling


2nd coat
Flashing resto./waterline leak
ready for application
Laitance
ready for application
PL
for surface prep

Laitance/Zocalo (ongoing works)


2nd coat / underslab restoration/masonry work
laitance
ready for floodtesting
laitance/wet surface (baha)
ready for floodtesting
laitance

PL
ready for inspection of surface prep
1st coat with blockout
2nd coat / underslab restoration
2nd coat / underslab restoration
for surface prep
wet surface (flooded)
surface prep inspection
surface prep inspection
for surface prep
16th Floor Accomplishment as of 9/9/21
Units Waterplug Epoxy 1st Coat 2nd Coat
Unit A
Service Kitchen
Maids
Gourmet
Powder Room
T&B 2
T&B 3
Master

Unit B
Master
Powder
T&B 2
Kitchen
Maids
Utility

Unit C
Master
T&B 2
T&B 3
Powder
Service Kitchen
Maids
Gourmet
Lanai

Unit D
Service Kitchen
Maids
Gourmet
Powder
T&B 2
T&B 3
Master

Unit E
Master
Kitchenette
T&B 2
T&B 3
T&B 4
Maids
Powder
Service Kitchen
Gourmet
Lanai
plishment as of 9/9/21
Flood test Remarks
Units
MDC BALANCE Unit A
FLOOD TEST PASSED Service Kitchen
MDC BALANCE Maids
MDC BALANCE Gourmet
FLOOD TEST PASSED Powder Room
re-water/water was removed by MDC worker T&B 2
MDC BALANCE T&B 3
Master

MDC BALANCE Unit B


FLOOD TEST PASSED Master
FLOOD TEST PASSED Powder
MDC BALANCE T&B 2
FLOOD TEST PASSED Kitchen
MDC BALANCE Maids
Utility

Unit C
watered/toppings provided w/o proper floodtest insp. Master
FLOOD TEST PASSED T&B 2
FLOOD TEST PASSED T&B 3
MDC BALANCE Powder
FLOOD TEST PASSED Service Kitchen
MDC BALANCE Maids
MDC BALANCE Gourmet
Lanai

Unit D
2nd coat / to be watered today Service Kitchen
MDC BALANCE Maids
FLOOD TEST PASSED Gourmet
wet surface Powder
FLOOD TEST PASSED T&B 2
MDC BALANCE T&B 3
Master

MDC BALANCE Unit E


MDC BALANCE Master
MDC BALANCE Kitchenette
wet surface T&B 2
MDC BALANCE T&B 3
FLOOD TEST PASSED T&B 4
MDC BALANCE Maids
MDC BALANCE Powder
MDC BALANCE Service Kitchen
Gourmet
Lanai
T&B 4
Maids
Powder
Service Kitchen
MDC BALANCE Gourmet
Lanai
16th Floor Accomplishment as of 9/9/21
Units Waterplug Epoxy 1st Coat 2nd Coat Flood test
Unit A
Service Kitchen
Maids
Gourmet
Powder Room
T&B 2
T&B 3 re-water
Master

Unit B
Master
Powder
T&B 2
Kitchen
Maids
Utility

Unit C
Master
T&B 2 watered/top
T&B 3
Powder
Service Kitchen
Maids
Gourmet
Lanai

Unit D
Service Kitchen
Maids 2
Gourmet
Powder
T&B 2
T&B 3
Master

Unit E
Master
Kitchenette
T&B 2
T&B 3
T&B 4
Maids
Powder
Service Kitchen
Gourmet
Lanai
T&B 4
Maids
Powder
Service Kitchen
Gourmet
Lanai
/21
test Remarks

MDC BALANCE
FLOOD TEST PASSED
MDC BALANCE
MDC BALANCE
FLOOD TEST PASSED
re-water/water was removed by MDC worker
MDC BALANCE

MDC BALANCE
FLOOD TEST PASSED
FLOOD TEST PASSED
MDC BALANCE
FLOOD TEST PASSED
MDC BALANCE

watered/toppings provided w/o proper floodtest insp.


FLOOD TEST PASSED
FLOOD TEST PASSED
MDC BALANCE
FLOOD TEST PASSED
MDC BALANCE
MDC BALANCE

2nd coat / to be watered today


MDC BALANCE
FLOOD TEST PASSED
wet surface
FLOOD TEST PASSED
MDC BALANCE

MDC BALANCE
MDC BALANCE
MDC BALANCE
wet surface
MDC BALANCE
FLOOD TEST PASSED
MDC BALANCE
MDC BALANCE
MDC BALANCE
MDC BALANCE
MDC BALANCE
FLOOD TEST PASSED
MDC BALANCE
MDC BALANCE
MDC BALANCE
MDC BALANCE
22nd Floor Unit A Accomplishment as of 9/9/21
Units Waterplug Epoxy 1st Coat 2nd Coat Flood test
Unit A
Master
Maids
Powder Room
T&B 2
T&B 3
Service Kitchen
Gourmet
Lanai

22nd Floor Unit B Accomplishment as of 9/9/21


Units Waterplug Epoxy 1st Coat 2nd Coat Flood test
Unit A
Master
Maids
Powder Room
T&B 2
T&B 3
Service Kitchen
Gourmet
Lanai
ent as of 9/9/21
Remarks Units Waterplug Epoxy
Unit A
bathtub area 1st coat
Master
FLOOD TEST PASSED
Maids
FLOOD TEST PASSED Powder Room
FLOOD TEST PASSED T&B 2
FLOOD TEST PASSED T&B 3
wet surface/flushing Service Kitchen
1st coat
Gourmet
ready for application
Lanai

ent as of 9/9/21
Remarks Units Waterplug Epoxy
Unit A
bathtub area 1st coat Master
ready for application Maids
watered/for floodtest inspection on 09/13/21 Powder Room
watered/for floodtest inspection on 09/13/22 T&B 2
watered/for floodtest inspection on 09/13/23 T&B 3
ready for application Service Kitchen
ready for application Gourmet
ready for application Lanai
22nd Floor Unit A Accomplishment as of 9/9/21
Waterplug Epoxy 1st Coat 2nd Coat Flood test Remarks

bathtub area 1st coat


FLOOD TEST PASSED
FLOOD TEST PASSED
FLOOD TEST PASSED
FLOOD TEST PASSED
n wet surface/flushing
1st coat
ready for application

22nd Floor Unit B Accomplishment as of 9/9/21


Waterplug Epoxy 1st Coat 2nd Coat Flood test Remarks

bathtub area 1st coat


ready for application
watered/for floodtest inspection on 09/13/21
watered/for floodtest inspection on 09/13/22
watered/for floodtest inspection on 09/13/23
ready for application
ready for application
ready for application
marks

area 1st coat


TEST PASSED
TEST PASSED
TEST PASSED
TEST PASSED
ace/flushing
st coat
r application

Remarks

b area 1st coat


or application
est inspection on 09/13/21
est inspection on 09/13/22
est inspection on 09/13/23
or application
or application
or application
23rd Floor Unit A Accomplishment as of 8/27/21
Units Waterplug Epoxy 1st Coat 2nd Coat Flood test
Unit A
Master
Maids
Powder Room
T&B 2
T&B 3
Service Kitchen
Gourmet
Lanai

23rd Floor Unit B Accomplishment as of 8/25/21


Units Waterplug Epoxy 1st Coat 2nd Coat Flood test
Unit A
Master
Maids
Powder Room
T&B 2
T&B 3
Service Kitchen
Gourmet
Lanai
nt as of 8/27/21
Remarks Units Waterplug Epo
Unit A
done surface prep inspection Master
done surface prep inspection Maids
done surface prep inspection/no 1 meter ref. Powder Room
done surface prep inspection T&B 2
done surface prep inspection T&B 3
done surface prep inspection Service Kitchen
done surface prep inspection Gourmet
done surface prep inspection Lanai

nt as of 8/25/21
Remarks Units Waterplug Epo
Unit A
no handover Master
no handover Maids
no handover Powder Room
no handover T&B 2
no handover T&B 3
no handover Service Kitchen
no handover Gourmet
no handover Lanai
23rd Floor Unit A Accomplishment as of 8/27/21
Waterplug Epoxy 1st Coat 2nd Coat Flood test Remarks

done surface prep inspecti


done surface prep inspecti
m done surface prep inspection/no 1
done surface prep inspecti
done surface prep inspecti
en done surface prep inspecti
done surface prep inspecti
done surface prep inspecti

23rd Floor Unit B Accomplishment as of 8/25/21


Waterplug Epoxy 1st Coat 2nd Coat Flood test Remarks

no handover
no handover
m no handover
no handover
no handover
en no handover
no handover
no handover
Remarks

one surface prep inspection


one surface prep inspection
ace prep inspection/no 1 meter ref.
one surface prep inspection
one surface prep inspection
one surface prep inspection
one surface prep inspection
one surface prep inspection

Remarks

no handover
no handover
no handover
no handover
no handover
no handover
no handover
no handover
Monitoring

EPOXY INJECTIO
Activity
August 5, 2021 August 6, 2021 August 7, 2022

Patching Half day Half day Whole day


Injection

Manpower Qty

P.I.C. 1
QA/QC 1
Applicators 3

Materials Delivered August 5, 2021


Item Qty
Metal Box 1
Full body harness 2
Consol 1119 LV 20 sets
Patching compound 10 kgs.
Aluminum Tube 1 kg
Electrical Plier 1 pc.
Flat Screw 1 pc.
Grease Gun 2 pc.
Chemical Hose 6 m.
Hose Clamp 10 pcs
Perla Soap 1 pc.
Padlock 1 pc.
Lacquer Thinner 1 gal.
Waste Rage 2 kgs.
Putty Knife 4 pcs.

Materials Delivered August 7, 2021


Item Qty
Patching Compound 1 bag (20 kgs.)
EPOXY INJECTION
Schedule
August 8, 2022 August 9, 2023 August 10, 2021 August 11, 2021 August 12, 2021

Whole day Half day


waterproofing work stop safety violation

violations
1. harness
2. faceshield
August 12, 2021 August 13, 2022

DONE