GUTLINE

Gutline Commissioning Manual Ball Fill 50% BM1 Automatic Ball


1
Fills 50% SAG
Maintenance & Inspection
Secuences Manual Fill W/ Maxibags Operation 50%MB1 Pulp Test
Day -1 0 1 2 3 4 5 6 7 8 9
Equipments Sequences S-1 Vendor Requirements
tph 800 1100
Molino SAG 1 25% 50%
Molino Bolas 1 25% 50%
Molino Bolas 2
Correas Pebbles
Chancado Pebbles
BHC1, Bomba 11
BHC2, Bomba 12
Flotación Rougher Fila 1
Remolienda HIG 1
Remolienda HIG 2
BHC7
BHC8
Flotación 1era Limpieza Fila 1
Flotación 1era Limpieza Fila 2
Flotación Scavenger Fila 1
Flotación Scavenger Fila 2
Flotación 2da Limpieza
Cal Prepare & Fill Loop
Floculante Prepare
Colector Primario Instale BIN
Colector Secundario
Espumante Instale BIN
Espesador de Concentrado Cu-Mo Full in Water
Espesador Concentrado Cu
Holding Tank 601 Full in Water Gutline
Espesador de Relaves 281 Full in Water
Espesador de Relaves 283
Tranque Relaves Available
Lineas de Agua Principales Full in Water
Piscinas (Proceso / Transferencia) Full in Water
RO - Train 1 Commissioning Commissioned
RO - Train 2 Commissioning Commissioned
RO - Train 3 Commissioning Commissioned
RO - Train 4 Commissioning Commissioned
RO - Train 5 Commissioning
Pump Station #1 Port Commissioned
Pump Station #2 (Salfa) Commissioned
Pump Station #3 (Salfa) Commissioned
Pump Station #4 (Salfa) Commissioned
Pump Station #5 (Salfa) Commissioned

First Concentrate at Holding Tank 1st Intent

Preparation to Operation (reagent, water, balls fill)


Operation with ore, Load Comm secuences
Stop to do maintenance inspection & vendor requirements activities
GUTLINE
Manual Ball Fill 100% MB 1 Operation Maintenance & Initial Fills
Manual Fill W/ Maxibags 100% MB1 + 50% SAG 1 Pulp Test Inspection HIG Mill 1
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
S-2 Vendor Requirements
Water Run Power Calibration
1500 1500 Fill Isolate Circuit

75% 100%

to 30% 30% 40% 50%

Prepare & Fill Loop


Prepare
Instale BIN

Instale BIN
Full in Water

Full in Water Gutline


Full in Water

Available
Full in Water
Full in Water
Commissioned
Commissioned
Commissioned
Commissioned
In Progress
Commissioned
Commissioned
Commissioned
Commissioned
Commissioned

Probably Most Probably


al Fills Manual Ball Fill 50% BM2 Automatic Ball Fills 100% SAG 2 Maintenance & Manual Ball Fill 100% MB 2
Mill 1 Manual Fill W/ Maxibags Operation 50%MB2 Pulp Test Inspection Manual Fill W/ Maxibags
25 26 27 28 29 30 31 32 33 34 35 36 37
ower Calibration S-3 Vendor Requirements
olate Circuit 1500 1500
75% 100%

25% 50% 50%

Prepare Full Pebbles Loop

60% se deja a 30% se deja a 30% Prueba 30% Prueba 40%

Prepare & Fill Loop Prepare & Fill Loop


Prepare Prepare
Instale BIN Instale BIN

Instale BIN Instale BIN


Full in Water Full in Water

Full in Water Full in Water

Available Available
Full in Water Full in Water
Full in Water Full in Water
Commissioned Commissioned
Commissioned Commissioned
Commissioned Commissioned
Commissioned Commissioned

Commissioned Commissioned
Commissioned Commissioned
Commissioned Commissioned
Commissioned Commissioned
Commissioned Commissioned
Manual Ball Fill 100% MB 2 Operation Maintenance & Inspection 30
Manual Fill W/ Maxibags 100% MB2 + 100% SAG 1 Pulp Test
38 39 40 41 42 43 44 45 46 47 49 51 53 55
S-4 Sec
Vendor Requirements
2220 2220 2000 3000 3170 3170

100%

Prepare Full Pebbles Loop

Prueba 50% Prueba 60%

Prepare & Fill Loop


Prepare
Instale BIN

Instale BIN
Full in Water

Full in Water

Available
Full in Water
Full in Water
Commissioned
Commissioned
Commissioned
Commissioned

Commissioned
Commissioned
Commissioned
Commissioned
Commissioned
30 Deys Pulp Test Maintenance & Inspection
57 59 61 63 65 67 69 71 73 75 77 79 80 81 82 83 84 85 86
Secuencia 5-6 (30 días)
Vendor Requirements
3170 3170 3170 3170 3170 3170 3170 3170 3170 3170 3170 3170