PROPOSAL FOR DRAWING DESIGN , DEA & CONSTRUCTION OF

CIVILWORK OF PROPOSED THREE STORIED STORE BUILDING

Project Title : 03 storied store building.


Ref. no. : DES/AD.&F/A.F.L/V-03/FP-12
Client Name : Amazing Fashions ltd.

Project Address : Gazipur,Bangladesh.

Proposal submission date : 27th Oct 2021


Proposal submitted by : Md Rimon Miah
General Manager
Detailed Engineering Solution (DES)

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Date: 27th Oct 2021.

To
Managing Director
Amazing fashions Ltd.
Gazipur ,Bangladesh

Sub : Proposal for Drawing design, DEA and civil construction work of proposed
three storied RCC building

Dear Sir,

Detailed Engineering Solution (DES) has resources to undertake both small and large projects
in civil infrastructure, commercial, industrial and building sectors with an experienced team
of principals overseeing project quality and delivery. We are involved in structural design &
construction of several multi-storied RCC as well as steel structures around Dhaka and
outside of Dhaka, with engineering assessment of Existing Reinforced concrete structure,
multi-storied steel structure.

We have the experience and resources to undertake seismic evaluations of buildings


.including seismic building assessments in RMG sectors for various clients. We are involved
in the design and construction management of seismic upgrades to deficient buildings to
improve their earthquake strength.

We are pleased to offer a proposal for subjective jobs.

______________
Md Rimon Miah
General Manager
Detailed Engineering Solution (DES)
Mobile-01323724807, 01719078931.

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Financial Offer for drawing design:
Sl Scope of work Particular of Total Rate per(sft) Total Cost
N building Volume(Sft) (Tk)
o
01 1)Architectural drawing
2) Structural design.
3) Electrical design. Three storied
Store N/A N/A 1,80,000/-
4) Plumbing design building.
5) BOQ

Total(tk) 1,80,000/-

In word (BDT): One Lac Eighty Thousand Taka Only.

Note-01: This Amount is fixed up without considering all types of VAT & Taxes.

Note-02: Site Supervision: Per visit BDT 10,000.

Mode of payment for design & drawing


Payment Schedule: Fee will be payable by the client in installments are as follows:
i. 50% advances with confirm work order.
ii. 50% of total amount will be paid after submission of full drawing

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Financial Offer for DEA:
Sl Scope of work Particular Total Rate Total Cost
N of building Volume(Sft per(sft (Tk)
o ) )

01 As-built drawings check & prepare As per


BNBC standard (Architectural & Structural).
02 Structural analysis & design by computer
Three
modeling (ETABS/ Staad Pro.)) following the
storied
guideline of BNBC-2020. N/A N/A 1,20,000/-
store
03 Preparation of assessment report based on
building
detail analysis and testing of materials.
04 Preparation of floor live load plan

Total(tk) 1,20,000/-

In word (BDT): One Lac Twenty Thousand Taka Only


Note-01: This Amount is fixed up without considering all types of VAT & Taxes.

Mode of payment for DEA


Payment Schedule: Fee will be payable by the client in installments are as follows:
i. 50% advances with confirm work order.
ii. 50% of total amount will be paid after submission of DEA

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Financial Offer for materials of civil work:

Material cost for civil works:


Unit Amount
Sl/No Description Volume Unit
Rate (BDT)
Cement
for RCC work (1:1.5:3) 750 bag 450 337,500
for RCC work (1:2:4) 1720 bag 450 774,000
for Plain concrete (1:2:4) 55 bag 450 24,750
1
For Brick work (1:4) 550 bag 450 247,500
For Inner plaster (1:4) 3/4" thick 202.5 bag 450 91,125
For outer plaster (1:4) 1/2" thick 85 bag 450 38,250
For celling plaster (1:4) 100 bag 450 45,000
Sylhet Sand
2 for RCC work (1:1.5:3) 1400 cft 65 91,000
for RCC work (1:2:4) 2150 cft 65 139,750
Local Sand
for RCC work (1:1.5:3) 0 cft 65 0
for RCC work (1:2:4) 2150 cft 65 139,750
3
Stone chips as CA
for RCC work (1:1.5:3) 2770 cft 205 567,850
for RCC work (1:2:4) 8600 cft 205 1,763,000
Brick Chips as CA in plain concrete
4
for Plain concrete work (1:2:4) 270 cft 85 22,950
Brick work
5
Inner & outer wall 109056 nos 10 1,090,560
Reinforcement
6 420 Mpa deformed bar for all RCC work
78216 kg 72 5,631,552
Sub Total 11,004,537
Contractor profit 15% 16,50,680
Total Amount 1,26,55,217

In word: One Core Twenty Six Lac Fifty Five Thousand Two Hundred Seventeen Taka Only.

Note-01: This Amount is fixed up without considering all types of VAT & Taxes.

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Financial Offer for labor cost of civil work:

Labor cost for civil works


Sl/No Description Area Unit Unit Rate Amount (BDT)
Base to top
(Below GB,Ground floor, 1st floor &
1 2nd floor) 3185*4=12740 sft 235 29,93,900
Total 29,93,900

In word: Twenty Nine Lac Ninety Three Thousand Nine Hundred Taka Only.

Note-01: This Amount is fixed up without considering all types of VAT & Taxes.

Mode of payment for labor cost of civil works:


Payment Schedule: Fee will be payable by the client in installments are as follows:
iii. 20% advances with confirm work order. (Total job amount)
iv. 20% of total amount will be paid after completion of grade beam..
v. 20% total amount will be paid after completion ground floor roof slab
vi. 20% total amount will be paid after completion 1st floor roof slab
vii. 15% total amount will be paid after completion 2nd floor roof slab
viii. Final 5% of total amount will be paid after completion of full work.

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607
Conditions:
 The client arranges electricity, water, and labor shed, if necessary.
 Final bill should be paid within seven working days after submitted of bill.
 In case of any additional work other than above mention then payment will be paid by client
to contractor at market rate after both party negotiations.
 The quoted price is Excluding VAT&AIT.
 This offer is valid up to one month.
 Amount will be varied according to area of final working drawing

Proposal Validity:
This proposal is valid for 30 days from the date of issuance.

Thanks & Best regards

_______________
Md Rimon Miah
General Manager
Detailed Engineering Solution (DES)
Mobile: 01323724807, 01719078931

DETAILED ENGINEERING SOLUTION (DES)


House-424 (Ground floor), Road no-30, Mohakhali New DOHS, Dhaka-1206
Email: info.desbangladesh@gmail.com; Mobile:+8801743681607

You might also like