Signatures: Owner _____________, Surveyor _____________, Building Inspector _____________, Date _____________
Check Stages:
2. After completing excavation and before starting brick work:
3. On completion of boundary wall at DPC level
4. On construction of main building at DPC level
5. Before pouring roof slab of porch and ground floor
6. On raising of first floor structure 3 feet above roof of ground floor
7. Before pouring roof slab of 1st floor
8. On making UGWT, Septic Tank, OHWT and Ramp
9. On final completion before occupation at the time of getting sewer / water connection