PERHITUNGAN VOLUME

PROGRAM :
KEGIATAN :
PEKERJAAN :
LOKASI :
TAHUN :

NO LINGKUP PEKERJAAN BESERTA GAMBAR SKETSA URAIAN PERHITUNGAN VOLUME DAN PEKERJAAN VOLUME

I PEKERJAAN PONDASI
1. Pek. galian tanah biasa sedalam 2 m 139.332 m3
Luas penampang = 1.7 x 1
= 1.7 m2
Volume = 1.7 x 81.96
= 139.332 m3

2. Pek. urugan pasir tebal 5 cm 40.98 m3


Luas penampang = 0.5 x 1
= 0.5 m2
Volume = 0.5 x 81.96
= 40.98 m3
3. Pek. Astamping/batu kosong
Panjang rencana pondasi : Luas penampang = 0.2 x 1 16.392 m3
Area horizontal = 17.8 + 17 = 34.8 = 0.2 m2
Area vertikal = 23.58 + 15.28 + 8.3 = 47.16 Volume = 0.2 x 81.96
Panjang Total Pondasi = 81.96 = 16.392 m3
4. Pek.Pasang batu kali spesi 1 Pc : 4 Ps 79.911 m3
Luas penampang = 1/2 x 0.3 + 1 x 1.5
= 0.975 m2
Volume = 0.975 x 81.96
= 79.911 m3
5. Urugan tanah kembali
Luas penampang = 2 x 1/4 x 0.35 x 1.5 36.882 m3
= 0.45 m2
Volume = 0.45 x 81.96
= 36.882 m3
II PEKERJAAN BETON BERTULANG
1 Pekerjaan Sloof Uk 15x30 1. Bekesting sloof
Bentang L 4,17 m
1. Ukuran = 15x30 Lebar sloof = 0.15
2. Bahan = beton bertulang Tinggi Sloof = 0.3
3. Beton = k 200 Panjang sloof = 4.17
4. Tulang = U24 (polos) Jumlag sloof = 2
Utama = 4 Ø 10
sengkang = Ø8-150
5. selimu = 2.5 cm Luasan Bekesting = 2x 0.3 x 4.17 x 2
= 2.502 m2

Bentang L 4,17 m = 4.17 x 2 = 8.34 m Bentang L 3,5 m


Bentang L 3,50 m = 3.5 x 3 = 10.5 m Lebar sloof = 0.15
Bentang L 2,70 m = 2.7 x 21 = 56.7 m Tinggi Sloof = 0.3
Bentang L 2,99 m = 2.99 x 2 = 5.98 m Panjang sloof = 3.5
Bentang L 5 m = 5 x 1 = 5 m Jumlag sloof = 3
Bentang L 2 m = 2 x 6 = 12 m
Bentang L 2,55 m = 2.55 x 2 = 5.1 m
Bentang L 1,71 m = 1.71 x 4 = 6.84 m Luasan Bekesting = 2x 0.3 x 3.5 x 3
Bentang L 1,85 m = 1.85 x 1 = 1.85 m = 2.1 m2
Bentang L 1,20 m = 1.2 x 4 = 4.8 m
Total panjang sloof = 117.11 m Bentang L 2,7 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 2.7
Jumlag sloof = 21

Luasan Bekesting = 2x 0.3 x 2.7 x 21


= 1.62 m2

Bentang L 2,99 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 2.99
Jumlag sloof = 2

Luasan Bekesting = 2x 0.3 x 2.99 x 2


= 1.794 m2

Bentang L 5 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 5
Jumlag sloof = 1

Luasan Bekesting = 2x 0.3 x 5x 1


= 3 m2

Bentang L 2 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 2
Jumlag sloof = 6
Luasan Bekesting = 2x 0.3 x 2x 6
= 1.2 m2

Bentang L 1,71 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 1.77
Jumlag sloof = 4

Luasan Bekesting = 2x 0.3 x 2x 4


= 1.2 m2

Bentang L 1,85 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 1.85
Jumlag sloof = 1

Luasan Bekesting = 2x 0.3 x 2x 1


= 1.2 m2

Bentang L 2,55 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 2.55
Jumlag sloof = 2

Luasan Bekesting = 2x 0.3 x 2x 2


= 1.2 m2

Bentang L 1,20 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 1.2
Jumlag sloof = 4

Luasan Bekesting = 2x 0.3 x 2x 4


= 1.2 m2

2. Pembesian
Bentang L 4,17 m
Lebar sloof = 0.15
Tinggi Sloof = 0.3
Panjang sloof = 4.17
Jumlag sloof = 2

a. Tulangan pokok (Ø 10 mm)


Diameter Tulangan = 10 mm
Panjang besi perbatang = 12 m
Beat besi perbstang = 7.38 Kg
berat besi per-1 m = 0.62 Kg
Jumlah tulangan pokok = 5 bh
Overlap untuk sambunga= 0.4 m

Panjang 1 bh tulangan Pokok = 0.4 + 4.17 + 0.4


= 4.97 kg
Panjang total tulangan pokok = 5x 4.97
= 24.85 m
Volume tulangan = 24.85 x 0.62
= 15.407
Total volume tulangan = 15.407 x 2
= 30.814