F1 FTB-1/WF-1
No. of F1 = 12 Total Length ≈ 32.7 m
Thickness = 350 mm Cross-Sec. Area = 0.25(0.40)
Cross-Sec. Area = 1.9 × 1.9 = 0.100 m2
= 3.61 m2 Volume ≈ 32.7 × 0.10 × 1.10
Volume = 12 × 0.35 × 3.61 × 1.10 ≈ 3.597 m3
= 16.678 m3
FTB-2
F2 Total Length ≈ 5.89 m
No. of F2 = 3 Cross-Sec. Area = 0.25(0.40)
Thickness = 300 mm = 0.100 m2
Cross-Sec. Area = 3.2 × 1.2 Volume ≈ 5.89 × 0.10 × 1.10
= 3.82 m2 ≈ 0.648 m3
Volume = 3 × 0.3 × 3.82 × 1.10
= 3.782 m3 WF-2
Total Length ≈ 18.955 m
Cross-Sec. Area = (1/2)(0.30+0.60)(0.15)
= 0.068 m2
Volume ≈ 18.955 × 0.068 × 1.10
≈ 1.418 m3
BEAMS
2B-1 2CB-1
𝑆−3 2 𝑆−5 7 𝑆−3 2
Sheet No. ; & Sheet No. ; Sheet No. ;
10 | 21 𝑆−3 12 | 21 𝑆−5 10 | 21 𝑆−3
C2
𝑆−4 2
Sheet No. ;
11 | 21 𝑆−4
No. of C2 =6
Total Length = 8750 mm
Area = 0.30 × 0.30
= 0.090 m2
Volume = 0.09 × 8.75 × 6 × 1.05
= 4.961 m3
SLABS CONCRETE WATER TANK
𝑆−6 5 6
Sheet No. ; ,
13 | 21 𝑆−6 𝑆−6
GROUND FLOOR
Floor Area = 10.4 × 8.4
Volume = Total Volume – Volume of Hollow
= 87.360 m2
Volume = (3.8 × 1.45 × 1.5) – (3.4 × 1.05 × 1.15) × 1.05
Area Embedded by Columns
Volume = 3.954 m3
= 0.35 × 0.35 ×12
= 1.470 m2
Area Embedded Walls
= 6.723 m2
Thickness = 100 mm
Volume of Concrete
= (87.36-1.47-6.723)×0.10×1.10
= 8.708 m3
SECOND FLOOR
Floor Area = 87.36 – (3.55 × 2.215)
= 79.497 m2
Area Embedded by Columns
= 0.35 × 0.35 ×12
= 1.470 m2
Area Embedded by Beams
= 15.235
Thickness = 125 mm
Volume of Concrete
= (79.497-1.47-15.235)× 0.125 × 1.05
= 8.241 m3
INTERIOR STAIR Total Volume = 0.468 + 0.068(20)(1.05)
Volume of Landing = 2.215 × 1.15 × 0.175 × 1.05 = 0.668 m3
= 0.468 m3
Volume per Step = ½ (0.3)(0.175)(0.983) +
0.125√0.32 + 0.1752 (0.983)
= 0.068 m3
POWER HOUSE
𝐴−7
Sheet No. 7 | 21
SLAB
Floor Area = 2.7 × 3
= 8.100 m2
Thickness = 150 mm [Assumed]
Volume of Concrete = 8.1 × 0.15 × 1.10
= 1.337 m3
ROOF DECK
Floor Area = 3.5 × 3
= 10.500 m2
Thickness = 150 mm [Assumed]
Volume of Concrete = 10.5 × 0.15 × 1.05
= 1.654 m3
EXTERIOR STAIR
Using Class AA
Cement = 115.516 × 10.460
= 1208.297
≈ 1209 bags of Cement
Sand = 115.516 × 0.420
= 48.517 m3 of Sand
Gravel = 115.516 × 0.840
= 97.033 m3 of Gravel