24-Jun-21

DAILY ACTIVITY AT PT. DAYASA ARIA PRIMA


PT. MEGA ENERGY INDONESIA
Duration Picture
No Description MN Area Jumlah Start (Date) Progress (%) Name User F/P Name MP Clasification Work Problem/ Finding Remark
(day) Before After
Kausar Inspector

Lutfi Helper

1 Membuat dan memasang tray cable WTP 1 24-Jun-21 1 100% Sugiyanto Done

Kausar Inspector

Lutfi Helper

Membuat tiang lampu pemerangan


2 WTP 1 24-Jun-21 1 100% Sugiyanto Done
WTP

Sandy Corrective

Agung Corrective

Marsito Helper

Pulling cable 3x70mm untuk power


3 SP2,3 1 24-Jun-21 1 100% Rizal Done
motor compressor 110 kW

Sandy Corrective

Marsito Helper

Workshop
4 Install motor untuk pompa solar 1 24-Jun-21 1 100% Rizal Done
Mekanik
Afandi Corrective

Cek kebocoran jalur instalasi


kompresor di area dryer, coater,
5 PM3 6 24-Jun-21 1 100% Rizal Done
calender, pope reel, rewinder,
double cutter

Sandy Corrective

Agung Corrective

Marsito Helper

Connect power for motor of


6 SP2,3 1 24-Jun-21 1 100% Rizal Done
compressor 110kW

Andaz Inspector

Afandi Inspector

7 Inspeksi panel M6A7 PM2 1 24-Jun-21 1 100% Rizal Done

Marsito Helper

Agung Corrective

Mengambil Air Drayer dari


8 SP2,3 1 24-Jun-21 1 100% Rizal Done
Warehouse induk ke SP 2 3
Huda Helper

Replace contactor of balling press


9 Weight Bridge 1 24-Jun-21 1 100% Rizal Done
machine

Huda Helper

Connect control remote and


10 Deinking 1 24-Jun-21 1 80% Rizal Continue
running test riject pump

Huda Helper

11 Check water level control PM2&3 PM2,3 1 24-Jun-21 1 80% Rizal Continue

Andaz Inspector
Afandi Inspector

Check air bellow, flapper, limit


12 switch and instrument area press PM2,3 1 24-Jun-21 1 80% Rizal Continue
wire PM2&3

Subagiyo Inspector
Saifudin Inspector

Install support and display


13 New Deinknig 1 24-Jun-21 1 80% Rizal Continue
flowmeter 1080
Makhmudi Inspector

Putra Agung Inspector

14 Trial motor M1-23 New Deinknig 1 24-Jun-21 1 100% Yosef Done

Roikhan Inspector

Sarijo Inspector

15 Install flowmeter flowmeter FT1027 New Deinknig 1 24-Jun-21 1 100% Yosef Done

Roikhan Inspector

Sarijo Inspector

Install suport transmiter steam


16 New Deinknig 1 24-Jun-21 1 100% Yosef Done
input PT 1069

Roikhan Inspector
Sarijo Inspector

Pasang scafolding untuk install


17 New Deinknig 1 24-Jun-21 1 100% Yosef Done
Flowmeter FT-1080

Makhmudi Inspector
Putra Agung Inspector

Recheck DCS Relay


18 (P1-07, A1-04, P1-03, M1-04, P1-04, New Deinknig 6 24-Jun-21 1 100% Yosef Done
M1-05)
Makhmudi Inspector
Putra Agung Inspector

Replace DCS Relay


19 New Deinknig 4 24-Jun-21 1 100% Yosef Done
(P1-05, M1-06, P1-12, ,M1-21)

Makhmudi Inspector
Putra Agung Inspector

Replace DCS Timer


(M1-15 ,M1-16, M1-17, M1-18, M1-
20 New Deinknig 11 24-Jun-21 1 100% Yosef Done
35, M1-19, M1-20, P1-66, M1-07,
M1-48, M1-09d)

Makhmudi Inspector
Putra Agung Inspector
Subagiyo Inspector
Saifudin Inspector

21 Trial belt press 1 dan 2 New Deinknig 2 24-Jun-21 1 100% Yosef Done

Subagiyo Inspector
Saifudin Inspector

Check connection of power motor


22 New Deinknig 1 24-Jun-21 1 100% Yosef Done
pulper
Subagiyo Inspector
Saifudin Inspector

Pulling power and signal cable from


23 old flowmeter 1027 to new New Deinknig 1 24-Jun-21 1 100% Yosef Done
flowmeter 1027

Note : ABSEN
99000014 Tendda Artha K Corrective Sakit

PREPARED BY

ADMIN OFFICER SUPERVISOR SITE MANAGER

Moh Harianto ____________________ Dimas Fahmigafur